Unit 7 AssignmentProject Progress Report
Charles W. Jansen, IIKaplan University
IT499-01 Bachelors Capstone in Information TechnologyInstructor: Allison Selby
June 27, 2012
Project Client (fictitious)
Patch Productions1066 Big Picture BlvdNaples, FL 34104(239) 555-1066
Current company profileCompany Produces:• Video Games• Commercials• DocumentariesVideo Restoration & Transfer Service• 70mm• 35mm• 16mm• 8mm
• Currently employs several hundred people
• Will add over one hundred new hires
Project Progress ReportAs of June 27, 2012The progress report for the Patch Production
Network Upgrade will show how the project is proceeding.
Progress will show:What changes have been made.What tasks have been completed.What milestones have been met.What tasks remain.The original timeline and an updated timeline.
Project Goal Add new department for developing theatrical film production offices. Chuckamania Productions will install network equipment in the building. Equipment will include:
Routers Switches Wiring Closet New IP addressing scheme
Servers, computers and printers will be provided by separate firms. IPS and Firewall services will be provided by Corero Network Security
Project ImpactThe project is progressing and when finished
will provide Patch Productions personnel a secure environment for developing a motion picture division.
The network will have the necessary bandwidth to carry the high volume of network traffic.
The router and switch configuration will automatically manage the network traffic providing priority ratings to different types of traffic.
Congestion at peak operation will be avoided because of the bandwidth available.
Tasks CompletedTask Milestone Status SD ECD AFDCreate Project Charter Complete 5/21/2012 5/25/2012 5/25/2012Deliver Project Charter u Complete 5/28/2012 5/28/2012 5/28/2012Perform Network Inspection Complete 5/29/2012 5/30/2012 5/30/2012Gather Information Complete 5/29/2012 5/30/2012 5/30/2012Network Analysis Complete 6/4/2012 6/5/2012 6/5/2012Deliver Network Analysyis Report u Complete 6/7/2012 6/7/2012 6/6/2012Create Specifications Complete 6/8/2012 6/14/2012 6/14/2012Deliver Implementation Plan u Complete 6/12/2012 6/12/2012 6/12/2012Deliver Specification Report u Complete 6/15/2012 6/15/2012 6/15/2012Order Equipment Complete 6/15/2012 6/15/2012 6/15/2012Create Configuration Complete 6/18/2012 6/21/2012 6/21/2012Deliver Configuration u Complete 6/22/2012 6/22/2012 6/22/2012Receive Equipment Complete 6/22/2012 6/22/2012 6/22/2012Lab Configuration and Testing 80% Complete 6/25/2012 6/29/2012
Deliver Lab Certification uTo be completed 7/2/2012 7/2/2012
Configuration AdjustmentsTo be completed 7/5/2012 7/6/2012
Installation and TestingTo be completed 7/9/2012 7/12/2012
Deliver (handover) Installed Network u
To be completed 7/13/2012 7/13/2012
Assemble and Edit DocumentationTo be completed 7/16/2012 7/20/2012
Deliver Documentation uTo be completed 7/23/2012 7/23/2012
Closeout ProjectTo be completed 7/24/2012 7/24/2012
As of EOD 6/28/2012
KeySD is Start DateECD is Estimated Completion DateAFD is Actual Completion Date
Changes ImplementedChange Order One
Reduced meeting timesReassigned project team member Gloria
Howard Brought in new project team member Raiko
Nakamura at less hours netChange Order Two
Eliminated 4 Cisco Catalyst WS-C3750X-48T-L switches
Replaced with 4 Cisco Catalyst C2960 S-48TS-L switches
Milestones MetDelivered the Project Charter on timeDelivered the Network Analysis report on
timeDelivered the Implementation PlanDelivered the Specification report on timeDelivered the Configuration report on time
Old Timeline
Updated Timeline
Review of ProgressThe project is on schedule for completion by
the planned date.Changes have been made and spelled out in
previous MS PowerPoint presentation and those changes will not affect the success of the project.
Milestones have been met as scheduled.The network will meet or exceed network
users needs.
Outstanding Items to CompleteLab configuration 20% remainingDeliver lab certification uConfiguration adjustmentsInstallation of network equipment and testingHandover installed network upgrade uAssemble and edit documentationDeliver documentation uCloseout project
QuestionsAddress questions to Chuck Jansen II [email protected]