Project Management Orientation Program Project Planning & Scheduling Basics
Sadhanandavel R
Dheenadayalan S
4251
0011 0010 1010 1101 0001 0100 1011
Projects happen in two ways:
a)Planned and then executed or b) Executed, stopped, planned
and then executed.
4251
0011 0010 1010 1101 0001 0100 1011• Develop Project Management Plan
• Define the Scope and Create the WBS
• Sequence the activities, Estimate the duration and Create the
Schedule
• Identify the Risks and Plan the Responses
• Estimate the Costs
• Plan the Human Resources, Purchases
• Plan the Communication
Planning
4251
0011 0010 1010 1101 0001 0100 1011• Describes the Project Management Processes used by the Project
Team
• If the processes differ from Organization’s standards, the details of
Project Specific Processes
• Project Team Structure
• Roles and Responsibilities of Project Team
• Communication needs – Status Reports, Review Meetings,
Escalation Matrix
PLANNING > Project Management Plan
4251
0011 0010 1010 1101 0001 0100 1011• Defines the Project Life Cycle
• Describes management of:
• Risk – Risk Dimensions, Approach to Risk Management
• Change Control – Change Control Process
• Configuration – Details of version control mechanisms
• Quality – Project Metrics; Quality Audits
PLANNING > Project Management Plan
4251
0011 0010 1010 1101 0001 0100 1011• Integrates all the plans in one place
• Subsidiary plans are developed separately also
• PMP is different from Schedule
• Some plans include Earned Value Management
PLANNING > Project Management Plan
4251
0011 0010 1010 1101 0001 0100 1011• Product Scope – The functions and features of the product
• Project Scope – The work associated in the delivery of the product
of the project with specified
• Methods for defining scope vary from industry to industry
• In Software, product scope is defined in SRS and Project Scope is
defined in Project Plan, WBS
• Document Assumptions/Constraints
Planning > Scope Definition
4251
0011 0010 1010 1101 0001 0100 1011• Define the Deliverables of the Project – SRS, Project Plan, Design
Specs, Test Plans, Test Cases, User Documents, Tested Product
etc.
• Define the related work - Deployment on Client Servers, User
Training, Online Support etc.
• Document the Assumptions/Constraints
Planning > Scope Definition > Project Scope
4251
0011 0010 1010 1101 0001 0100 1011• Define the Functional and Non-functional requirements – Use
Cases, Screen Shots, Process Flow Charts etc
• Define the Technical Requirements – Deployment Architecture,
Technology used, License, Bandwidth requirements, Disaster
Recovery Plan etc.
• A separate Technical Requirements Document may be prepared
• Document the assumptions, constraints
Planning > Scope Definition > Product Scope
4251
0011 0010 1010 1101 0001 0100 1011
“Assumptions are important sources for Risk Identification!”
4251
0011 0010 1010 1101 0001 0100 1011• Represents the scope of the project into smaller, manageable
hierarchy of components
• Enables allocation of resources and assignment of responsibilities at
granular levels
• Improves the accuracy of Cost Estimation
• Improves the Cost, Performance Measurement & Control
Planning > Work Breakdown Structure
4251
0011 0010 1010 1101 0001 0100 1011
Planning > Work Breakdown Structure
4251
0011 0010 1010 1101 0001 0100 1011• Start at the project goal, and keep breaking down activities until you
get to the smallest task
• Involve the team for identifying the tasks or
• The Sub team approach (agree on level 1 activities, then have sub
teams tackle each activity in detail; then check for duplication and
missed tasks)
Planning > WBS > Top-down Approach
4251
0011 0010 1010 1101 0001 0100 1011• Agree on the top level activities using the top-down approach
• Then break into teams and brainstorm all the activities you think are
within that overall activity
• Organize the activities, and check for missed tasks and
redundancies
Planning > WBS > Bottom-up Approach
4251
0011 0010 1010 1101 0001 0100 1011
The top-down approach is more effective for generating a detailed WBS
4251
0011 0010 1010 1101 0001 0100 1011• The levels of hierarchy varies from project to project
• The division of levels can be based on Product Features (e.g. User
Module), Process (e.g. Requirements)
• The lowest level of the WBS contains items for which the cost can
be tracked
• The items at the lowest level are called Work Packages or Terminal
Elements
Planning > WBS > Levels of Hierarchy
4251
0011 0010 1010 1101 0001 0100 1011• Do not make it too detailed – Results Micro-Management
• Do not make it less detailed too – Tasks too large to manage
• 8/80 Rule – Thumb Rule says Work Package should be more than 8
and less than 80 hours in duration
• Consider appropriate milestones as Control points as well as for
Status Reporting
• Maintain Standard WBS for the organization based on project types
Planning > WBS > Points To Ponder
4251
0011 0010 1010 1101 0001 0100 1011• Decomposition – The process of arriving at components for WBS;
Division of project scope into manageable components/activities to
the level of work packages
• Rolling Wave Planning – The process of defining the tasks at a
higher level (due to lack of information) and elaborating them later
based on the clarification of details
Planning > WBS > Terminology
4251
0011 0010 1010 1101 0001 0100 1011• Develop the list of project activities (WBS/Activity List)
• Sequence the list of project activities
• Determine the relationships between activities
• Estimate the resource requirements for each activity
• Estimate the duration for each activity
• Determine the project duration (start and completion dates)
Scheduling > Steps Involved
4251
0011 0010 1010 1101 0001 0100 1011
Scheduling > Activity Sequencing
4251
0011 0010 1010 1101 0001 0100 1011
The resource related dependencies and constraints should not be considered for sequencing the activities
4251
0011 0010 1010 1101 0001 0100 1011• Identifying the relationships between activities involves the
sequencing plus dependencies between tasks
• There are 4 types of scheduling dependencies
Scheduling > Activity Relationships
Finish to Start
Start to Start Finish to Finish
Start to Finish
4251
0011 0010 1010 1101 0001 0100 1011• Two widely used diagramming techniques
• Bar / Gantt Charts
• Schedule and progress graphically depicted on a single chart
• Simple and most used scheduling diagram
• Good for Status Reporting
• Network Diagrams
• Identifies activities that control the project length
• Clearly shows the task dependencies
• Shows available float for non-critical activities
Scheduling > Schedule Diagrams
4251
0011 0010 1010 1101 0001 0100 1011
Scheduling > Gantt Charts
Status Date
Tasks
Plan
Progress
4251
0011 0010 1010 1101 0001 0100 1011• Two types of network diagramming techniques
• Arrow Diagramming Method
• Precedence Diagramming Method
Scheduling > Network Diagrams
AB
C
D
EF
C E
FA
B D
4251
0011 0010 1010 1101 0001 0100 1011• Precedence Diagramming Method (PDM)
• Boxes/Nodes represent the activities
• Arrows connect the boxes, show the dependencies
• Also called Activity On Node (AON) method
• PDM uses all the four dependencies (F-S,F-F,S-S,S-F)
• The dependency – Start to Finish – is seldom used
Scheduling > Network Diagrams
C E
FA
B D
4251
0011 0010 1010 1101 0001 0100 1011• Arrow Diagramming Method (ADM)
• Arrows represent activities
• Arrows connect the nodes for showing dependencies
• Also called Activity on Arrow (AOA) method
• Uses only Finish to Start dependency
• Uses Dummy activities to show logical relationships
Scheduling > Network Diagrams
AB
C
D
EF
4251
0011 0010 1010 1101 0001 0100 1011• Estimate the resource requirement for each activity
• The information from previous projects will be helpful
• The dependency between tasks should be considered for estimating
the resources
Scheduling > Resource Estimation
4251
0011 0010 1010 1101 0001 0100 1011• People who are familiar with the work can estimate better
• Organizational Process Assets (Historical Info, Productivity Data etc.)
will be helpful as a reference
• Estimation will be more accurate if it is obtained from more than one
source and averaged
• Consider the availability of a resource for a task. If the resource is
available only 50%, the task will take twice the duration
Scheduling > Duration Estimation
4251
0011 0010 1010 1101 0001 0100 1011• Two estimating methods : PERT and CPM
• Three time estimates
• Optimistic (O) No risk impacts considered
• Pessimistic (P) Some amount of risk impacts considered
• Most Likely (M) All risk impacts considered
• PERT uses the distribution’s mean to determine individual activity
duration (P + 4M + O) / 6
• CPM uses only one time estimate – Most Likely estimate
Scheduling > Duration Estimation
4251
0011 0010 1010 1101 0001 0100 1011• A Milestone is an event specifically designated to represent
some meaningful or specified goal that shows progress
• Good Reference for Management Reporting
• Types of Milestones
• Key Milestones – Phase Gates
• Schedule Milestones – Any significant event in the schedule
Scheduling > Milestones
4251
0011 0010 1010 1101 0001 0100 1011• Lead – A lead in dependency that allows acceleration of successor
activity
• Lag – A lag in dependency directs a delay in the successor activity
Scheduling > Leads & Lags
-5
B
Lag – 3 days delay after A Lead – D accelerated for 5 days
+3
A
C
4251
0011 0010 1010 1101 0001 0100 1011• The path in a project with the longest duration. The duration of the
Critical Path is earliest completion date for the project
• Critical Path Method (CPM)
• Forward Pass calculates Early Start and Early Finish dates
• Backward Pass calculates Late Start and Late Finish dates
Scheduling > Critical Path
4251
0011 0010 1010 1101 0001 0100 1011• Early Start (ES)- The earliest date a task can start
• Early Finish (EF)- The earliest date a task can be completed
• Late Start (LS)- The latest date a task can start without delaying the
projects end date
• Late Finish (LF)- The latest date a task can finish without delaying
the projects end date
Scheduling > Early & Late Dates
A 2ES EF
ES EF
LS LF
LS LF
4251
0011 0010 1010 1101 0001 0100 1011Calculation of Early & Late Dates
•Early Start = EF predecessor + 1
•Early Finish = ES + duration - 1
•Late Start = LF - duration + 1
•Late Finish = LS successor - 1
Scheduling > Early & Late Dates
4251
0011 0010 1010 1101 0001 0100 1011Forward pass calculates an activity’s early dates
•ES start + duration – 1 = EF
•Purpose of forward pass is to find the Critical Path
Backward pass calculates an activity’s late dates
•LF – duration + 1 = LS
•Purpose of the Backward Pass is to find the slack/float
Scheduling > Forward/Backward Pass
10 A 14
15 5 19
ES EF
LS LF
4251
0011 0010 1010 1101 0001 0100 1011The amount of time an activity can be delayed or lengthened. Also
called slack.
•Total float - The amount of time an activity can be delayed without
extending the overall project completion time. TF = LS – ES or TF = LF –
EF
•Free Float - The amount of time that an activity can be delayed without
delaying the start or occurrence of any other activity in the schedule
Scheduling > Float
4251
0011 0010 1010 1101 0001 0100 1011
My Sample Project
Scheduling > Sample Project
Tasks Duration Start End Predecessor
12 days 6-Oct-08 21-Oct-08
Task A 1 day 6-Oct-08 6-Oct-08
Task B 3 days 7-Oct-08 9-Oct-08 A
Task C 2 days 7-Oct-08 8-Oct-08 A
Task D 5 days 10-Oct-08 16-Oct-08 B,C
Task E 3 days 9-Oct-08 13-Oct-08 C
Task F 3 days 17-Oct-08 21-Oct-08 D,E
4251
0011 0010 1010 1101 0001 0100 1011
My Sample Project
Method
ES of task with no predecessor = 1
EF of task with one predecessor = EF of predecessor + 1
EF of task with multiple predecessors = Max (EF of predecessors) +
1
EF = ES + Task Duration – 1
Critical Path = A-B-D-F
Scheduling > Forward Pass
2 3
C 2
4 6
E 3
10 12
F 3
1 1
A 1
2 4
B 3
5 9
D 5
4251
0011 0010 1010 1101 0001 0100 1011
My Sample Project
•LF of the last task = EF of the last task
•LS = LF - Duration +1
Scheduling > Backward Pass
2 3
C 2
4 6
E 3
10 12
F 3
1 1
A 1
2 4
B 3
5 9
D 5
LS
1210
LF
ES EF
4251
0011 0010 1010 1101 0001 0100 1011
My Sample Project
LF of a predecessor = Min (LS of all successors) - 1
Scheduling > Backward Pass
9743
1 1
A 1
2 4
B 3
5 9
D 5
2 3
C 2
4 6
E 3
10 12
F 310 12
9542
11
4251
0011 0010 1010 1101 0001 0100 1011
Scheduling > Calculating Float
A
B
C D
E F
Early StartEarly
Finish Late Start Late Finish Free Slack Total Slack
Task A 1 1 1 1 0 0
Task B 2 4 2 4 0 0
Task C 2 3 3 4 0 1
Task D 5 9 5 9 0 0
Task E 4 6 7 9 3 3
Task F 10 12 10 12 0 0
Total Float = LS – ES or LF – EF
Free float = ES (Earliest successor) - EF – 1
or
Free float = Min (ES of successors) – ES - Duration
My Sample Project
4251
0011 0010 1010 1101 0001 0100 1011
Questions…?