Project Performance Reporting
1
Gary Mainwaring
![Page 2: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/2.jpg)
Project Performance Reporting - v1 - 01Mar16 2
Agenda
• Process
• Dependencies
• Reporting – Examples
• Lessons to Share
![Page 3: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/3.jpg)
Project Performance Reporting - v1 - 01Mar16 3
PMC Process Map
![Page 4: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/4.jpg)
Project Performance Reporting - v1 - 01Mar16 4
Proposal Execution
Project Start (KPIs)
Project Closedown
Baseline
Planning Planning Monitoring & Control
Project Performance Reporting
PMC Timeline
![Page 5: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/5.jpg)
Project Performance Reporting - v1 - 01Mar16 5
PPR & GoPM
Organisation
Corporate
Governance
Project
Management
GoPM
![Page 6: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/6.jpg)
Project Performance Reporting - v1 - 01Mar16 6
Basic Elements of PPR
• Baseline against which to measure progress
• Method(s) to measure progress
• Forecast of future performance
![Page 7: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/7.jpg)
Project Performance Reporting - v1 - 01Mar16 7
Content of PPR
• Based on project constraints (cost, time,
performance, risk, resources) and other factors such
as customer performance
• Standard report format / template essential
![Page 8: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/8.jpg)
Project Performance Reporting - v1 - 01Mar16 8
Cadence
• Important to ensure cadence is maintained for reporting
periods (e.g. monthly)
• Need owner to ensure cadence is maintained
• Reports should be based on common baselines (e.g.
cost, schedule) to ensure coherent picture is presented
• Be aware of currency of data / changes to baselines as
progress is reported through the reporting hierarchy
• Focus should be on adding value / generating
information, not ‘processing data’
• Dependent on key stakeholders (e.g. PMs, Functions) to
provide source data – requires extensive stakeholder /
relationship management
![Page 9: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/9.jpg)
Project Performance Reporting - v1 - 01Mar16 9
Reporting Hierarchy
LEVEL
1
LEVEL 2
LEVEL 3
LEVEL 4
LEVEL 5
L O W
MED
HIGH
Portfolio Status Reporting
Customers: Executive Mgmnt & Sponsors
Programme Status Reporting
Customers: Programme Mgr, Key Senior
Stakeholders
Project Status Reporting
Customers: Project Mgr, Project Team, Key
Stakeholders
Functional Intermediate Reporting
Customers: Functional Mgrs, Project
Team Leads
Working Level Reporting
Customers: Supervisors, Team
Members
LEVEL OF DETAIL
![Page 10: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/10.jpg)
Project Performance Reporting - v1 - 01Mar16 10
Toolsets
• Reduce level of ‘manual data manipulation’ by
automating report generation
• Generate ‘glue ware’ (using e.g. Visual Basic, Excel
Macros) to integrate disparate toolsets
• Use shared data repositories to reduce duplication
of ‘data pots’ around the business – single
database with ability to generate ‘views’ of
relevant information
![Page 11: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/11.jpg)
Project Performance Reporting - v1 - 01Mar16 11
Project Overview
![Page 12: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/12.jpg)
Project Performance Reporting - v1 - 01Mar16 12
Changes to Baseline
![Page 13: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/13.jpg)
Project Performance Reporting - v1 - 01Mar16 13
Project Roadmap
![Page 14: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/14.jpg)
Project Performance Reporting - v1 - 01Mar16 14
-30 / 30 / 60
![Page 15: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/15.jpg)
Project Performance Reporting - v1 - 01Mar16 15
Milestones
![Page 16: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/16.jpg)
Project Performance Reporting - v1 - 01Mar16 16
Risks
![Page 17: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/17.jpg)
Project Performance Reporting - v1 - 01Mar16 17
Issues / Actions
![Page 18: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/18.jpg)
Project Performance Reporting - v1 - 01Mar16 18
Spend
![Page 19: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/19.jpg)
Project Performance Reporting - v1 - 01Mar16 19
EV
![Page 20: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/20.jpg)
Project Performance Reporting - v1 - 01Mar16 20
EV
No concerns regarding meeting
forecast ‘Go Live’ date
Looking at opportunities to
recover potential cost increase
(due to rework as a result of loss
of development environments)
![Page 21: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/21.jpg)
Project Performance Reporting - v1 - 01Mar16 21
Resources
![Page 22: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/22.jpg)
Project Performance Reporting - v1 - 01Mar16 22
Summary Status
• Amber or Green Project?
• Subjective or Objective status?
![Page 23: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/23.jpg)
Project Performance Reporting - v1 - 01Mar16 23
Lessons to Share
Presenting:
• Communication primarily one way – be sure of
information presented
• Keep it simple
• No surprises
• Chair the meeting – avoid going down rabbit holes
• Be careful about use of traffic light status (objective
/ subjective status)
• Recycle slides (appending as necessary) as you go
up the reporting chain
![Page 24: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/24.jpg)
Project Performance Reporting - v1 - 01Mar16 24
Lessons to Share
Performance:
• Don’t dwell in the past, focus on forecasting future
performance and risks / issues that would prevent
project success
• Analyse trend information to help forecast future
performance
• Integrated toolsets helps realise efficiencies and
data integrity when generating reporting artefacts
• Don’t just generate information, spend quality time
analysing the information
![Page 25: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/25.jpg)
Project Performance Reporting - v1 - 01Mar16 25
Lessons to Share
Governance:
• Maintain the cadence of the monthly (e.g.) reporting cycle
• Use reporting templates
• Don’t tolerate deviations from standard templates unless approved
• Need governance to maintain standards
Personal Development:
• Ensure those involved in generating information fo reporting understand who reviews it and how they use it to make decisions
![Page 26: Project Performance Reporting](https://reader031.fdocuments.us/reader031/viewer/2022022201/58a083d91a28ab19098b754f/html5/thumbnails/26.jpg)
Questions?