Project Pegasus · 2019-10-24 · Construction Works: 21 st October to 04 th November Project...

1
Construction Works: 21 st October to 04 th November Project Pegasus Issue #21 18 th October 2019 SRM Special Projects Site Team offices are located within the Inn’s former Treasury Office, with access from the South Terrace where ‘Reception Entrance’ signage can be found on the hoarding to assist. Please press the bell to attract attention. Site working hours will be from: 8.00am – 6.00pm Monday – Friday 9.00am – 2.00pm Saturday Project Manager: John Walker SRM Special Projects E: [email protected] T: 07866 783710 Contact Us Soft strip / Demolition to all floors internally Demolition of existing Mansard and Flat roof structures Press mouldings to be taken of the existing Hall cornice detailing Careful removal of the Hall ceiling Asbestos removal; site wide Forming new structural openings and installing temporary works supports on all floors Demolition of the external bin hoist on the North Elevation Enabling works for the crane on the South terrace and required hoarding alterations Internal scaffold crash deck within library to facilitate roof demolition Demolition of existing slab and adjacent walls to facilitate the formation of a new lift pit in the north façade lightwell Removal of the Hall’s Mansard Roof Enabling Groundworks for the Mobile Crane

Transcript of Project Pegasus · 2019-10-24 · Construction Works: 21 st October to 04 th November Project...

Page 1: Project Pegasus · 2019-10-24 · Construction Works: 21 st October to 04 th November Project Pegasus Issue #21 18th October 2019 SRM Special Projects Site Team offices are located

Construction Works: 21st October to 04th November

Project Pegasus

Issue #2118thOctober 2019

SRM Special Projects Site Team offices

are located within the Inn’s former

Treasury Office, with access from the

South Terrace where ‘Reception

Entrance’ signage can be found on the

hoarding to assist. Please press the bell

to attract attention.

Site working hours will be from:

8.00am – 6.00pm Monday – Friday

9.00am – 2.00pm Saturday

Project Manager: John Walker

SRM Special Projects

E: [email protected]

T: 07866 783710

Contact Us

• Soft strip / Demolition to all floors internally

• Demolition of existing Mansard and Flat roof structures

• Press mouldings to be taken of the existing Hall cornice

detailing

• Careful removal of the Hall ceiling

• Asbestos removal; site wide

• Forming new structural openings and installing temporary

works supports on all floors

• Demolition of the external bin hoist on the North Elevation

• Enabling works for the crane on the South terrace and

required hoarding alterations

• Internal scaffold crash deck within library to facilitate roof

demolition

• Demolition of existing slab and adjacent walls to facilitate

the formation of a new lift pit in the north façade lightwell

Removal of the Hall’s Mansard Roof

Enabling Groundworks for the Mobile Crane