Project Pegasus · 2019-10-24 · Construction Works: 21 st October to 04 th November Project...
Transcript of Project Pegasus · 2019-10-24 · Construction Works: 21 st October to 04 th November Project...
Construction Works: 21st October to 04th November
Project Pegasus
Issue #2118thOctober 2019
SRM Special Projects Site Team offices
are located within the Inn’s former
Treasury Office, with access from the
South Terrace where ‘Reception
Entrance’ signage can be found on the
hoarding to assist. Please press the bell
to attract attention.
Site working hours will be from:
8.00am – 6.00pm Monday – Friday
9.00am – 2.00pm Saturday
Project Manager: John Walker
SRM Special Projects
T: 07866 783710
Contact Us
• Soft strip / Demolition to all floors internally
• Demolition of existing Mansard and Flat roof structures
• Press mouldings to be taken of the existing Hall cornice
detailing
• Careful removal of the Hall ceiling
• Asbestos removal; site wide
• Forming new structural openings and installing temporary
works supports on all floors
• Demolition of the external bin hoist on the North Elevation
• Enabling works for the crane on the South terrace and
required hoarding alterations
• Internal scaffold crash deck within library to facilitate roof
demolition
• Demolition of existing slab and adjacent walls to facilitate
the formation of a new lift pit in the north façade lightwell
Removal of the Hall’s Mansard Roof
Enabling Groundworks for the Mobile Crane