PROJECT OVERVIEW The Austin Public Works Urban Trails Program is reviewing La Loma Trail as part of the 2016 Mobility Bond. The project is located between Airport Blvd and US 183, and would extend through the East Boggy Creek Greenbelt area. There are no design or construction funds allocated for La Loma Trail, but having a plan ready allows the City to move forward, if funding is identified. Project Website: AustinTexas.gov/LaLomaTrail La Loma Trail Project Map /ATXPUBLICWORKS @ AUSTINTEXASGOV @AUSTINMOBILITY

Transcript of PROJECT OVERVIEW - Austin, Texas · 2020. 2. 20. · PROJECT BACKGROUND Project Overview • City...

Page 1: PROJECT OVERVIEW - Austin, Texas · 2020. 2. 20. · PROJECT BACKGROUND Project Overview • City staff are developing a Preliminary Engineering Report to identify a recommended route

PROJECT OVERVIEW

The Austin Public Works Urban Trails Program is reviewing La Loma Trail as part of the 2016 Mobility Bond. The project is located between Airport Blvd and US 183, and would extend through the East Boggy Creek Greenbelt area.

There are no design or construction funds allocated for La Loma Trail, but having a plan ready allows the City to move forward, if funding is identified.

Project Website: AustinTexas.gov/LaLomaTrail

La Loma Trail Project Map

/ATXPUBLICWORKS@AUSTINTEXASGOV@AUSTINMOBILITY

Page 2: PROJECT OVERVIEW - Austin, Texas · 2020. 2. 20. · PROJECT BACKGROUND Project Overview • City staff are developing a Preliminary Engineering Report to identify a recommended route

PROJECT BACKGROUND

Project Overview• City staff are developing a Preliminary Engineering Report to identify a recommended

route and project considerations like environmental concerns, wildlife, nearby property ownership and more

• No design or construction funds are currently allocated for this project, but having a plan ready allows the City to move forward quickly, if funding is identified

Project Timeline

FALL 2017 SPRING 2018 FALL 2018 SPRING/ SUMMER 2019 FALL 2019

• Final Environmental Report completed

• City and Capital Metro partners finalize railroad/trail crossing options

• Final draft Preliminary Engineering Report reviewed by interdepartmental City staff

• Second public meeting held

• Preliminary Engineering Report completed

• Preliminary Engineering Report process begins

• First public meeting held

Page 3: PROJECT OVERVIEW - Austin, Texas · 2020. 2. 20. · PROJECT BACKGROUND Project Overview • City staff are developing a Preliminary Engineering Report to identify a recommended route

PROJECT BACKGROUND

Existing Conditions & Considerations

• Railroad crossing

• Tannehill Creek

• Railcar storage

• Existing beaten path

Page 4: PROJECT OVERVIEW - Austin, Texas · 2020. 2. 20. · PROJECT BACKGROUND Project Overview • City staff are developing a Preliminary Engineering Report to identify a recommended route

RECOMMENDATIONS

Preferred Route Alternatives - Alternative 1: Sara Dr to Southern

Walnut Creek Trail

- Alternative 2: Brookswood Ave to Jain Ln

- Alternative 3: Prock Ln to Southern Walnut Creek Trail

Recommended Trail Features• 10-12 ft wide concrete trail

• ADA accessible

• Safer connections through neighborhood and to Eastside Memorial High School and Southern Walnut Creek Trail

Additional Connections• Recommended project expansions

(depending on future funding availability)

Page 5: PROJECT OVERVIEW - Austin, Texas · 2020. 2. 20. · PROJECT BACKGROUND Project Overview • City staff are developing a Preliminary Engineering Report to identify a recommended route

ALTERNATIVE 1

About Alternative 1:

• Route currently used by Eastside Memorial High School students

• Connects to Southern Walnut Creek Trail

• Majority of trail within City

of Austin property

Existing Conditions: Current student route

Sara Dr to Southern Walnut Creek Trail

183

Spri

ngda

le R

dLegendPreferred Route

Additional Connections

Existing Trail: Southern Walnut Creek Trail

Page 6: PROJECT OVERVIEW - Austin, Texas · 2020. 2. 20. · PROJECT BACKGROUND Project Overview • City staff are developing a Preliminary Engineering Report to identify a recommended route

ALTERNATIVE 2

About Alternative 2:

• Connects neighborhoods on

both sides of Austin Area

Terminal Railroad tracks

• Least environmental impact

• Farther from Eastside

Memorial High School

Existing Conditions: Jain Ln railroad tracks

Brookswood Ave to Jain Ln

183

Spri

ngda

le R

dLegendPreferred Route

Existing Trail: Southern Walnut Creek Trail