MAINTENANCE AND PROTECTION OF SWITCHYARD An Industry oriented Project submitted to Jawaharlal Nehru Technological University, Hyderabad In partial fulfillment for the award of B.Tech Degree in Electrical And Electronics Engineering SUBMITTED BY K.SRINIVAS ( 08871A0221 ) M.GOUTHAM ( 08871A0231 ) T.VIDHYADAR ( 08871A0258 ) S.SAI CHAND ( 08871A0250 ) Under The Guidance Of Sri. B. PRABHAKAR (SUPTD-EM) N.T.P.C, Ramagundam.

Transcript of Project Original

Page 1: Project Original

MAINTENANCE AND PROTECTION OF SWITCHYARD

An Industry oriented Project submitted to

Jawaharlal Nehru Technological University, Hyderabad

In partial fulfillment for the award of B.Tech Degree in

Electrical And Electronics Engineering

SUBMITTED BY

K.SRINIVAS ( 08871A0221 )

M.GOUTHAM ( 08871A0231 )

T.VIDHYADAR ( 08871A0258 )

S.SAI CHAND ( 08871A0250 )

Under The Guidance Of

Sri. B. PRABHAKAR (SUPTD-EM) N.T.P.C, Ramagundam.

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING

RAMAPPA ENGINEERING COLLEGE

(Accredited by NBA and Affiliated to JNTU, Hyderabad)

Hunter Road, Warangal-506001

Page 2: Project Original

CERTIFICATE

This is certifying that the project entitled MAINTENANCE AND PROTECTION OF

SWITCHYARD submitted by K.Srinivas, Ht.no:08871A0221, M.Goutham,

Ht.no:08871A0231, T.Vidhyadar,Ht.no:08871A0258,S.Saichand, Ht.no:08871A0250, for the

partial fulfillment of the requirements of ELECTRICAL AND ELECTRONICS

ENGINEERING Degree of RAMAPPA ENGINEERING COLLEGE embodies the work done

by them under my supervision.

PROJECT GUIDE : EXPLICATOR:(Sri. B. PRABHAKAR ) ( Sri.K.RAJAMALLAIAH )SUPTD-EM Asst EngN.T.P.C, RAMAGUNDAM N.T.P.C, RAMAGUNDAM

Page 3: Project Original

JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY

Hyderabad 500 072

C E R T I F I C A T E

This is to certify that the dissertation titled “MAINTENANCE AND PROTECTION OF

SWITCHYARD ” is being submitted by K.SRINIVAS (08871A0221),M.GOUTHAM

(08871A0231), T.VIDHYADAR (08871A0258), S.SAICHAND (08871A0250) in partial

fulfillment for the award of the degree of BACHELOR OF TECHNOLOGY IN

ELECTRICAL & ELECTRONICS ENGINEERING of RAMAPPA ENGINEERING

COLLEGE, HUNTER ROAD WARANGAL is a record of bonafide work carried out by them

under my guidance and supervision.

Mr. K.RAM MOHAN REDDY Ms.FARHEEN SULTANA HOD INTERNAL GUIDEAssociate professor, B.Tech,Department of EEE, Department of EEE,Ramappa Engineering College, Ramappa Engineering College,WARANGAL WARANGAL

Mrs.M.PRASANTHIProject Co-ordinator

Page 4: Project Original

ACKNOWLEDGEMENT

I hereby acknowledge with heartfelt thanks and gratitude to several gentlemen who have

devoted their valuable time for completion of our project work.

Particularly we are very much indebted to the Sri B. V. Subramanyam DGM (EM), who

has given fullest cooperation for fulfilling this project work in time.

My heartfelt thanks to Sri.B.PRABHAKAR Superintendent (EM) and Sri.

K.RAJAMALLAIAH Assistant Engineer (E.M) who has rich experience in this field and given

me valuable suggestions in competing the project work.

We are also thankful to the management of our organization M/S N.T.P.C. Ramagundam

Division (RSTPS) for their cooperation in completing this project work.

By

K. Srinivas

M. Goutham

T. Vidhyadar

S. Saichand

Page 5: Project Original

ABSTRACT

This is project is about the maintenance and protection of “ SWITCHYARD” in the

Power Plant for Economic Transmission of power to various load centers by using protective

devices like Circuit Breakers, Isolators ,Earth Switch, Bus-Bar, Surge & lightening Arresters,

Current Transformers, Capacitive Voltage Transformers and Wave Traps etc.

Equipments used under Switchyard:

1.Circuit Breakers

2.Isolators

3.Earth Switch

4.Bus-Bars

5.Surge and Lightening arresters

6.Current Transformers

7.Capacitive Voltage Transformers

8.Wave Traps

9.Control Relay Panels

10.Event Logger

11.Master Clock

12.Disturbance Recorder

13.Fault Locator

14.Indicating and Recording Instrument

15.Arcing Horns

Page 6: Project Original

TABLE OF CONTENTS

S.NO. Description Page

Nos.

1 ABOUT RSTPS 400 KV SWITCH YARD

2 SWITCHYARD OPERATION ACTIVITIES

3 SWITCHYARD EQUIPMENT

4 SWITCHYARD CONTROL ROOM EQUIPMENT

5 RELAYS & PROTECTION SCHEMES

6 SWITCHYARD EMERGENCIES AND PLAN OF ACTION

7 DE ENERGISATION AND ISOLATION OF SWITCHYARD

EQUIPMENT

8 NORMALISATION & CHARGING OF LINES &

TRANSFORMERS

9 BLACKOUT OF STATION AND BLACKSTART

PROCEDURES

Page 7: Project Original

1.ABOUT RSTPS 400 KV SWITCH YARD

400 KV Switchyard of Ramagundam Super Thermal Power Station is the most vital switching

station in the southern Grid 2600 MW of Bulk Power generated by three 200 MW Units and

four 500 MW Units of NTPC Ramagundam is evacuated for supplying to the southern states.

Switchyard consists of four 400 KV busbar systems fed by 7 Nos. of generator feeders, 10 Nos

of 400 KV feeders, 3 Nos of 220 KV feeders and two nos. of 132 Kv feeders as shown in the

single line diagram of 400 Kv switch yard.

In addition to the above, four nos. of Tie Transformers, five nos. of Auto Transformers and two

nos. of Shunt Reactors are provided as shown in the switchyard line diagram.

1.1. 400 KV TRANSMISSION LINES

1. Ramagundam Nagarjunasagar Circuit 1 Double Circuit lines

(267 Km length)2. Ramagundam Nagarjunasagar Circuit 2

3. Ramagundam Hyderabad Circuit 1 Independent lines

(189 Km length)

(189 Km length)

(189 Km length)

4. Ramagundam Hyderabad Circuit 2

5 Ramagundam Hyderabad Circuit 3

6 Ramagundam Hyderabad Circuit

7. Ramagundam Khammam Circuit 1 Single line (202 Km length)

8. Ramagundam Chandrapur Circuit 1 HVDC back to back intergrid

connecting double circuit lines

(180 Km length)9. Ramagundam Chandrapur Circuit 2

Ramagundam Ditchpally 1 (189 Km length)

Page 8: Project Original

1.2. 220 KV TRANSMISSION LINES

1. NTPC AP Transco line 1 Through 400 Kv/220KV 250MVA

A.T # 3 & 42. NTPC AP Transco line 2

3. NTPC AP Transco line 3 Through 400 KV/220KV

250MVA A.T # 5

1.3. 132 KV TRANSMISSION LINES

1. NTPC AP Transco line 1 Through 400 Kv/132KV 200MVA

A.T # 1 & 22. NTPC AP Transco line 2

1.4. AUTO TRANSFORMERS

Five Auto Transformers with on Load Tap Changers are provided to interconnect the 400 Kv

system of NTPC and 220/132 Kv system of AP Transco, Malyalapally sub station situated 1.8

Km away from the RSTPS switchyard.

1

.

400/132 Kv 200 MVA (TELK make) 2 Nos

2

.

400/220 Kv 250 MVA (TELK make) 2 Nos

3

.

400/220 Kv 315 MVA (Crompton Greevs Ltd.

make)

1 Nos

Page 9: Project Original

1.5 TIE TRANSFORMER

Four nos. of Tie Transformers are provided for feeding power to station auxiliaries like Cooling

water & Raw water pumps, Coal Handling & water treatment Plants, Ash & Fuel Handling

pumps, Cooling towers and lighting requirements of station & colony.

1.6 SHUNT REACTORS

Long lines when lightly loaded, the receiving end voltage raises, due to ferranti effect. Shunt

Reactors produce lagging MVAR there by control the receiving end voltages during lightly

loaded conditions. Shunt reactors also limit the short circuit fault levels. Therefore, Shunt

reactors are provided on both the ends of Nagarjuna Sagar lines 1 & 2, the length of these lines

being about 267 km.

Bus bar Arrangement:

a) Single Bus bar Arrangement

This has only single bus bar to which all lines/Transformers/Generators, etc. are connected. In

the event of the fault on the bus entire bus has to be deenergised and a major outage occurs. 

Page 10: Project Original

b) Single Sectionalized Bus bar Scheme

In this, main bus is divided into two sections with a circuit breaker. One complete

section can be taken out for maintenance or for breakdown works without distribution

continuity of other section.

   c) Main & transfer bus bar scheme

With this arrangement, any line breaker (one at a time) requiring maintenance can be

transferred to transfer bus. The feeder protection thus gets transferred to trip bus couple

breaker. On fault occurrence or maintenance, entire bus becomes de-energised.

Page 11: Project Original

c)  Double Bus arrangement: -

Flexibility of transferring any line to any of the buses. On fault occurrence or maintenance

only one bus becomes dead, while other bus remains in service.

Page 12: Project Original

d) Double bus and transfer bus arrangement:-

Combination of main and transfer bus and double bus arrangement.

e) One and half breaker scheme

In Ramagundam we use one and half Breaker scheme with 3 current transformer method

The following layout gives the single line diagram of 400KV switch yard:

Page 13: Project Original

2. SWITCHYARD OPERATION ACTIVITIES

Page 14: Project Original

As mentioned else where, RSTPS switchyard is handling bulk power and its operation and

Maintenance has become critical. Any ambiguity in the operation of the switchyard may lead to

such disasters like grid failure, station outages crippling not only the normal life of people but

also the very economy of the country. Even in less serious situations such as cascade tripping of

Auto Transformers due to unplanned over loading has caused under utilization of our generating

capacity many times. The operation of switchyard calls for a very alert staff that shall have to

sense the abnormalities in time and prompt to concern timely to enable normalcy of the system.

The following are some of the identified activities of 400 KV switchyard operations.

1. Identifying of faulty equipment, safe isolation of equipment without disturbing other

system as much as possible, raising job cards, arranging shutdowns, trial charging

and normalization of 400 KV SWYD. And 132KV Swyd, associated equipment like

CBs, Isolators, Ats, TTS, Shunt Reactors, ACDBs, DCDBs, Battery Plant, Charges

PLCC equipment, Swyd. Compressors and lighting.

2. Daily inspection of indoor/outdoor swyd equipment, checking of oil leakages,

temperatures and any other abnormalities like sparks etc. SF6 gas pressures,

compressed air pressures, running period of compressors, availability status of

mulsifier system, swyd. And station P.A. system and PLCC communication system

etc. monitoring of physical conditions of swyd equipment.

3. Analyzing and locating of fault leading to feeder/Transformer trip, reporting

emergencies to the higher authorities, coordinating with other agencies like AP

Transco/Genco, PGCIL in clearing faults and normalization of system.

4. Close monitoring of grid parameters, coordinating with IOCC, SRLDC, OS (SR), OS

(ED), LDC (APSEB), Shift charge Engineer & Desk Engineers for smooth operation

of grid system, timely action to ensure continuity of power supply.

Page 15: Project Original

5. Quick arrangement of startup power supply in case of grid failures, station outages.

6. Continuous monitoring of system parameters like voltage, frequency, line and

Transformer, loading unit generations, MVAR and MW net exports etc. recording

and corrective action where the abnormality found.

7. Preparing of daily power generation / export/import energy reports, exchanging data

with IOCC, OS (ED), OS (SR), collection of generation details from other power

projects and storing.

8. Assisting the shift incharge in transmitting the flash report, availability report, unit

trip/synchronization messages, shutdown messages, generation back down messages,

modification of availability declarations, feed back to shift in charge, the deviation if

any in total generation with respect to the declaration.

3. SWITCHYARD EQUIPMENT

To perform switchyard operation activities perfectly, operation staff should have good

knowledge about the equipment provided in switchyard as well as in control room. They should

be familiar with the control system adopted here and a good understanding about the procedures

to be followed during the emergencies, outage requirements and charging. Brief description

about switchyard equipment is given below.

3.1 CIRCUIT BREAKER

It is an automatic device capable of making and breaking an Electrical Circuit under normal and

abnormal conditions such as short circuits. SF6 is the arc quenching media for all the 400 KV

and 220 KV breakers installed in the switchyard. Pneumatic operating system is provided in

Page 16: Project Original

AEG, ABB and NGEF make breakers and Hydraulic operating system is provided in BHEL

make breakers. 132KV breakers provided in 132 KV lines are of Minimum oil type operating

on spring charge mechanism.

3.2 ISOLATORS

Isolator is an off load device provided in conjunction with circuit breaker to disconnect the

equipment or the section, which is to be isolated from all other live parts. The isolators

provided in the switchyard are of central break type. The operation of Isolators can be done

from control room (remote) or local. Motorized operation for opening & closing of Isolator is

provided, however Isolators can also be opened & closed manually in the even of non-

availability of motorized operation.

Page 17: Project Original

3.3 EARTH SWITCH

Earth switch is mounted on the isolator base on the line side or breaker side depending upon the

position of the isolator. The earth switch usually comprises of a vertical break switch arm with

the contact, which engages with the isolator contact on the line side. Earth switch is required to

discharge the trapped charges on the line or equipment (under shut own) to earth for maintaining

safety. Earth switch can be operated only from local either by electrical operation or manually.

Page 18: Project Original

3.4 BUSBAR

Busbar is an Aluminium tube of 4” IPS having wall thickness of 0.4”, where all incoming and

outgoing feeders are connected in a schematic way to enable smooth operation and Maintenance

of equipment without any interruption to the system. At RSTPS one and half breaker scheme is

provided for 200 MW generator feeders and 400 KV outgoing lines, Two-breaker scheme is

provided for 500 MW generator feeders.

3.5 SURGE / LIGHTING ARRESTERS

Surge Arresters are provided to ground the over voltage surges caused by switching and lighting

surges. Surge Arresters provide leakage path to the ground whenever the system voltage rises

above the specified value. They are equipped with surge monitors, which measure the leakage

currents and a counter to record the number of surges taken place.

Page 19: Project Original

3.6 CURRENT TRANSFORMER (CT)

Current Transformers are provided to step down the current to low values suitable for

measuring protection and control instruments. Current Transformers also isolate measuring and

protective devices from high system voltage. CTs in the switchyard consist of five secondary are

for main 1&2 protection and core 3 is for measuring instruments.

3.7 CAPACITIVE VOLTAGE TRANSFORMER (CVT)

CVTs step-down the system voltage to sufficiently lo w value (110 V) for measuring,

protection and synchronizing circuits. CVT has a H.F. terminal point for receiving &

transmitting the high frequency signals for carrier protection and communication.

1. Dome

2. Nitrogen filling valve

3. Primary terminal

4. Collar

5. Porcelain insulator

6. Primary conductor with insulation

7. Adaptor cylinder

8. Secondary cores

9. Base

10. Oil drain plug

Page 20: Project Original

3.8. WAVE TRAP

Wave Trap is a parallel resonant circuit tuned to the carrier frequency connected in series with

the line conductor at each end of the protected transmission line section. Wave trap offers high

impedance path for high frequency signals and low impedance path for power frequency

current. This keeps carrier signal confined to the protected line section and does not allow the

carrier signals to flow into the neighboring sections.

1. Oil level indicator (optional)

2. Expansion device3. Capacitor units4. Insulating oil5. Porcelain insulator6. Sealing7. Electromagnetic

unit8. Low voltage

terminals box/ HF terminal

9. Series inductance10. Medium voltage

transformer11. Damping circuit

against ferroresonance

effects

123

4

5

7

89

11

6

10

C1

Page 21: Project Original

4. SWITCH YARD CONTROL ROOM EQUIPMENT

The control room is the place where the conditions of the system are monitored, controls

initiated and operations are integrated. Control room consists of the following equipment.

4.1 CONTROL PANELS

XC=1/2ΠFC30KHZ TO 500KHZ

IMPEDENCE 75 OHMS

WAVE TRAPXL=2ΠFL

LMU

PLCC

POWER FREQ -50 KHZLINE

LA

Page 22: Project Original

Corridor type flat control panels are provided in U shape with doors at both the end panels.

Between the front and rear panels, there is adequate space for inspection of interior wiring. The

controlling knobs are provided on front panel for opening & closing of breakers and isolators.

The close/open position of the breakers / isolators / earth switches is indicated through lamps or

semaphore indicators. The relative position of each equipment is shown in the mimic single line

diagram that is painted on front side of the control panels. The indicating instruments (MW,

MVAR, voltage, current etc.) and annunciation windows are provided on the top of front panel

for monitoring of the equipment. Breaker monitoring and protective relays such as LBB, Auto

reclosure, check synchronization, Trip circuit monitoring, Annunciation relays and energy

meters are mounted on the rear side of the panel.

4.2 RELAY PANELS

Relay panels are of cubicle type, flat independent boxes with a door at backside. All the

protective relay units related to one bay are divided into two groups viz. Main 1 protection, stub

protection, O/V protection and their auxiliary & trip relays as group 1 and Main 2 protection,

U/v protection and their auxiliary & trip relays as group 2 relays. Group 1 & group 2 relays are

mounted on front side of two separate panels side by side. Fault locator and disturbance

recorder of the corresponding bay mounted on front side of the third panel. A separate glass

door is provided front side of all the panels to cover the relays from dust.

4.3 EVENT LOGGER

Even Logger recognizes the changes in signal-input states, plus time data allocation for

sequential recording of events. It displays the events in a time sequential of 1/ sec, such as

opening/closing of breaker poles, Isolator poles, E/S etc. pressure high/low of air, SF6, N2 Oil

etc. Alarm Appeared/reset of all protection / trip relays, it also displays the status of equipment,

in service/ out of service in a regular period say 8 hrs. This is one of the important diagnostic

equipment available to operation staff to understand the type of emergency in a flick of a

second.

Page 23: Project Original

4.4 MASTER CLOCK

One maser clock (make Keltron) is provide in switchyard control room to synchronize the

timings of all the Event loggers, DAS (Data Acquisition system of units), Disturbance

Recorders, clocks provided in control rooms, etc., to maintain a uniform time, so that the

sequence of events can be recorded and analyzed to know the cause of disturbance.

4.5 GENERATION DATA ACQUISITION AND MONITORING SYSTEM (GDAMS)

At large switchyard control rooms like RSTPS it is essential to record and continuously monitor

the parameters of the Generation & transmission system. NTPC is the largest power utility of

the country generating power from 20 thermal/ gas power stations at various places of the

country. Many more power stations are ye to come. To manage all these power stations

efficiently and effectively NTPC has established an operational services control room at

corporate office in New Delhi, where generation data from all the stations is to be monitored

continuously. To facilitate the above function, Generation Data acquisition and Monitoring

system is provide at all NTPC switchyard control rooms. CMC Ltd. has supplied the necessary

software on

Micro Soft Windows NT environment and installed the PC based GDAMS network in Server

Client configuration. GDAMS scans automatically the real time measurements like load on

units, load flows on feeders. Bus voltage, grid frequency, MVR loads, etc. for every second

through RTUs and record it. The Acquired data is linked up to OS control room though satellite

communication channel. The types of data displays available in GDAMS are given below.

Page 24: Project Original

TYPES OF DISPLAYS

1 Alpha Numeric Display Displays direct of measured parameter along

with name of the parameter in a tabular form

2 Mimic Diagram Display In this Display the single line diagram of the

circuit with position of the breakers along with

real time power flow is indicated.

3 Graphical Display This displays the graph of quantities

4 Threshold Display In threshold blackout Display the threshold

(border) values of quantity are Displayed.

5 Alarm Displays Alarms are Displayed to draw the attention of

operator.

6 Trend display In this display the trend of the quantity real time

values in a specified time blocks are shown

The data Acquisition by GDAMS is more vital in analyzing the faults, forecasting the local

trends, impact of the line and unit outages, estimation of variations in frequency and voltages in

different seasons, generating reports etc.

Page 25: Project Original

4.6 DISTURBANCE RECORDER

All 400 KV lines connected to this switchyard are provide by the Disturbance Recorders (D/R),

D/R is a PC based or Microprocessor based on line monitoring equipment D/R is the most vital

diagnostic equipment in analysis of post fault trappings.

4.7 FAULT LOCATOR

When a line tripped on fault, the Fault Locator provided in the Relay panel indicates the

approximate distance of the fault location so that Maintenance group easily tract the fault and

clear it. When F.L. indicates zero or very less distance, operation staff should assume that the

fault is in the switchyard equipment, and check for all equipment connected to the concerned

bay, which was tripped on fault.

4.8 INDICATING & RECORDING INSTRUMENT

The following measuring instruments were providing on control panels of all bays.

a) At the top of the control panel.

1. Ammeters in three phases.

2. Volt (KV) meters in three phase

3. Reactive power (MVAR) meter

4. Watt (MW) meter

5. Winding Temperature indicating meter (for only Transformer bays)

6. Tap position indicating meter (do)

b) Rear side of the each bay control panel

1. Main energy meter (export)

2. Check Energy meter (do)

Page 26: Project Original

3. Main energy meter (import)

4. Check Energy meter (do)

4.9 PLCC ( power line carrier communication )

In order to achieve fast clearance and correct discrimination for faults in 400 KV transmission

network, it is necessary to signal between the points at which protection relays are connected.

PLCC is high frequency signal transmission along with actual overhead power line. IT is

robust and therefore reliable, constituting a low loss transmission path that is fully controlled by

the power authority. PLCC is required for the following cases.

a) Inter tripping

b) Permissive tripping

c) Blocking

d) Telemetry

e) Telephone

4.10. 220 V DCDB & BATTERY PLANT

220 VDC supply is required mainly for the following applications.

a) Control supply for 400, 220, 132, 33 KV breakers, and associated equipment.

b) Control supply for relaying and protection circuits.

c) Annunciation & indication circuits.

d) Emergency lighting.

5. RELAYS AND PROTECTION SCHEMES

Page 27: Project Original

5.1 CAUSES OF FAULTS

Every power system element is subjected to a fault or a short circuit. The cause of fault is any

of the following.

1. Healthy insulation in the equipment subjected to either transient over voltages of small

time duration due to switching and lighting strokes, direct or indirect.

2. Aging of insulation.

3. An external object, such as a tree branch, bird, kite, rodent etc. spanning either two

power conductors or a power conductor and ground.

5.2. EFFECTS OF FAULTS

1. Equipment is likely damage due to over heating and sudden mechanical force

developed.

2. Arcing faults invariably are a fire hazard and damage the equipment.

3. A frequency drop may lead instability among interconnected system.

4. Unsymmetrical faults result in voltage imbalance and negative sequence currents,

which lead to overheating.

5.3 PROTECTIVE RELAYS

A relay detects the faulty element in the integrated power system and removes it, with the help

of the circuit breaker, from the remaining healthy system as quickly as possible to avoid damage

and maintain security or reliability of supply in the healthy system. The quality of relaying

depends on its sensitivity, selectivity, speed and reliability. Varieties of protection relays are

provided to protect EHV lines and Transformers. A brief Description is given below about the

relays used for protection of Transformers and lines connected to switchyard.

5.4 OVER CURRENT RELAY

Page 28: Project Original

There are basically three types of OC relays

1. Instantaneous OC relay :

As the name signifies instantaneous OC relay operates without any intentional time delay as

and when the input current exceeds the pickup value or the plug setting.

2. Definite time OC relay (DTOC Relay)

The DTOC Relay has two settings; the first one is the pick value in amperes (plug setting.).

Another setting is the constant or definite operating time of the relay. The relay delivers trip

output only when the current exceeds the pickup value and that after a specified time delay.

3. Inverse Definite Minimum Time OC Relay (IDMT OC Relay)

The operating time of IDMT relay is inversely proportional to the square o the relay input

current (plug setting) and the travel time of the disk to close the NO contacts. The travel time of

the disk to close the NO contact can be changed by moving the backstop of the relay (Time

multiplier setting).

5.5 DIRECTIONAL RELAYS

Conventional over current relays are non-directional, which means the relay operates on current

magnitude and not on its direction or phase shift. The Directional over current relay comprises

two elements, a directional element and OC relay element. The OC element is inhibited for

operating until the directional element has operated. The directional element is a watt metric

device, which measures the direction of power flow.

5.6 EARTH FAULT RELAY

Page 29: Project Original

Earth fault relay is a sensitive protection against earth faults, which responds only to residual

current of the system, since a residual component that exists only when fault current flow to

earth. The residual component is extracted by connecting the line CTs in parallel.

5.7 DIFFERENTIAL PROTECTION:

The differential relay checks the difference between the input and output currents for any power

system element, either in amplitude or in phase or both, to determine whether the state of the

power system is healthy or faulty. In the event of a substantial difference, the element is

assumed to be faulty and trip the concerned breakers.

5.8 PILOT WIRE PROTECTION:

Pilot wire protection scheme can be used for protection of transmission lines of 220 KV and

below voltages. Similar current Transformers at each end of the protected zone are

interconnected through pilot wires. Current transmitted through the zone causes secondary

current to circulate round the pilot circuit without producing any current flow in relay. A fault

within the protected zone will cause secondary current flow in to protection relay.

Page 30: Project Original

5.9 PHASE COMPARISON RELAY

The basic principle of the phase comparison relay is to check the phase difference of current at

both ends of the protected line. The carrier channel is used to convey the phase angle of the

current at one relaying point to another for comparison with the phase angle of the current at

that point.

5.10 DISTANCE RELAY

Distance relay is of the high speed class can provide both primary and back up facilities in a

single scheme. Distance relay operate only for faults occurring between the relay location and

the selected reach point, thus giving discrimination for faults that may occur between different

line sections. The basic principle is comparing of the fault current ‘seen’ by the relay with

voltage at the relaying point; by comparing these two quantities sit is possible to determine

whether the impedance of the line up to the point of the fault is greater than or less than the

predetermined reach point independence.

For EHV, line where fast fault clearance and high reliability vital ‘full scheme of

distance relays are provided. Full distance scheme uses six measuring units per zone, three for

phase faults and three for earth faults. All 18 measuring units in three zones operate

independently to protect the line and provide backup to the adjacent lines.

Page 31: Project Original

5.11 POWER SWING BLOCKING

Power swings are variations in power flow which occur when the voltage of generators at

different points of the power system slip relative to ach other to cater changes of load magnitude

and direction or as a result of faults and their subsequent clearance. In the case of a transient

power swing, it is important that the Distance relay should not trip and should allow the power

system to return to a stable condition. For this reason Distance, protection scheme has an

optional power swing-blocking feature.

6. SWITCHYARD EMERGENCIES AND PLAN OF ACTION

6.1 CONDITION MONITORING

The abnormalities in equipment or system are continuously monitored by the relays,

pressure/level switches etc. and initiate a trip / alarm followed by an annunciation. The Alarm

alerts the operator and annunciation flashes give the first information of the type of breakdown.

Event logger provides the sequence of events taken place along with time. This does allow

some assessment in relation to failure of equipment. Basing on this information operator has to

start quick remedial action.

6.2 BREAKDOWN ANALYSIS

The details break down analysis can be done after checking the relays, protections operated at

relay panels. Disturbance recorder provides the voltage and current graph with respect to time

of pre and post incident of fault conditions. D/R also provide the sequence of protections

operated.

6.3 ANNUNCIATIONS AND ALARM SCHEME

Page 32: Project Original

Annunciation and alarm scheme is provided to call attention of the operation staff against any

abnormality in the switchyard equipment and control system, so the quick preventive measures

can be initiated. The annunciation flashes along with an alarm on the control panel until it is

acknowledged. The annunciation is reset only after normalization of the system. The operation

staff upon receiving an alarm has to comprehend the nature of the problem to take appropriate

steps at the earliest, thus saving the equipment system from failing further. The various

annunciations are provided for 400 KV lines and Auto Transformers at RSTPS switchyard

control room are shown in the following tables.

A) CIRCUIT BREAKER CONDITION MONITORING ANNUNCIATIONS

1. C.B. AUTO TRIP

This annunciations appears whenever circuit breaker trips on a protection or on intertrip signal

(Other than manual trip)

PLAN OF ACTION

1. Confirm the opening of the other end breaker if it is a line feeder or opening of the LT

side breaker if it is a Transformer.

2. Check for the protective Relay operations if any.

3. Check for the event logger and D/R printouts for various relay operations and events

taken place.

4. If CB auto trip indication appears during the closing operation of the breaker, check

for closing interlocks.

5. Reset the CB auto trip indication by giving the trip impulse with the breaker close/open

handle at control panel.

2. CB POLE DISCREPANCY TRIP

Page 33: Project Original

All the three poles of a circuit breaker must open or close at a time when a trip or close

command initiated. If one of the pole fails or delayed to open or close within a specified (0.02

secs) time, circuit breaker trips immediately followed by C.B. pole discrepancy alarm.

PLAN OF ACTION

1 Check the flag indication for operation of pole discrepancy relay (62x) in relay

panel.

2 Confirm from local, the opening of all the three poles of breaker. If not

immediate action to be taken to open the poles.

3 Breaker tripped on pole discrepancy protection shall be charged only after

checking and rectifying the problem.

3. LBB PROTECTION OPERATED

This annunciation appears when the master trip relay (86) operates in

response to a fault but the concerned circuit breaker fails to trip. Local Breaker Breakup

relay (50Z) acts and initiates the bus bar protection of the respective bus, which trips all

other circuit breakers connected to the bus.

PLAN OF ACTION

Page 34: Project Original

1 Check for the protection relay, which caused operation of Group A/B trip relays.

2 Check for the bus bar protection trip relay (96) for Main/tie breaker whichever

LBB has operated.

3 Check for physical opening of breakers for which LBB relay operated.

4 Inform Maintenance group for attending the problem.

5 Restore the normalcy through the other breaker (Tie breaker) in case of Main

breaker failed to trip and vice versa.

4. TRIP COILS 1/2 CKT. FAULTY

All the circuit breakers are provided with two trip coils to facilitate breaking operation

reliability. This annunciation appears whenever either of the trip circuit gets open circuited. As

the failure of one of the trip circuit reduces the reliability of the tripping operation of the breaker

in the vent of fault.

PLAN OF ACTION

1 Check for operation of relays 195AR, 195BR/195AY, 195BY/195AB, 195BB

Or combination of these relays and identify fault is in T.C. 1 and respective pole.

2 Check for operation of relays 295AR, 295BR/295AY, 295BY 295AB, 295BB or

combination of these relays and identify fault is in TC. 2 and respective pole.

3 This annunciation appears in case of operation lockout, failure of DC or actual

failure of trip coil. Verify the actual cause.

4 In case of failure of both the trip coils of the breaker, the breaker shall be

isolated from the system by making the load flow zero and opening of both sides

of isolators of breaker.

5 Inform to the Maintenance staff for attending the problem.

Page 35: Project Original

5. C.B. SF6 DENSITY LOW/ AIR PRESSURE LOW

This annunciation appears whenever SF6 gas pressure/ Air pressure falls below the specified

value.

PLAN OF ACTION

1 Check the SF6 pressure / Air pressure locally, and asses the rate of leakage.

2 If the rate of leakage is high, after obtaining necessary clearance trip and isolate

the breaker as early as possible. Otherwise the breaker may go into lockout

state, which is to be avoided as much as possible.

3 If leakage rate is low inform Maintenance group for attending the problem.

6. CB OPERATION LOCKOUT

This annunciation appears whenever either air pressure (oil pressure in case of hydraulic

operated breakers) or SF6 gas pressure falls below specified values. In operation lockout state

circuit breaker will not operate. This feature is very much required to prevent the breaker

operation in adverse conditions of operating system and/or arc quenching media (SF6 gas).

The settings for this annunciation are given below for reference.

AIR / OIL PRESSURE SF6 PRESSURE

AGEG MAKE (pneumatic oprn) <30.0 bar <6.5 bar

Page 36: Project Original

ABB “”” <23.0 bar <6.5 bar

NGEF “” <31.5 bar <6.5 bar

BHEL (hydraulic oprn) <253 bar <6.0 bar

PLAN OF ACTION

A) FOR PNEUMATIC OPERATED BREAKER

1 Check for the air pressure and SF6 gas pressure locally.

2 Identify the problem. If heavy leakage is observed in SF6 gas/ AIR system, then

sough permission from IOCC for isolates the breaker from connecting bus.

3 Isolate the breaker by opening the both the side isolators after making the load flow

zero.

4 If leakage is minute, Inform Maintenance staff to attend the problem. After

normalizing SF6/Air parameters the reset alarm.

B) FOR HYDRAULIC OPERATED BREAKERS

1 Check for the loss of oil/N2 gas pressure /SF6 gas pressure locally and also AC

supply to the pump.

2 Conform the running of the pump if oil pressure is low.

3 Identify the problem. If leakage is observed in SF6 gas line, sought permission from

Page 37: Project Original

IOCC to isolate the breaker.

4 If leakage is minute, inform the Maintenance staff to attend the problem. After

normalizing SF6/Oil parameters rest the alarm.

B.ALARMS RELATED TO TRANSMISSION LINE FEEDER PROTECTION

1. MAIN 1/2 PROTECTION OPERATED

Two main protection relays are providing for the protection of each EHV transmission line

against phase to phase and phase to earth faults. Two distance relays or combination of one

distance relay and one phase comparison relay are provided as main protection relays in each

line. Main 1/2 operated alarm appears when one of the main protection relays operates.

PLAN OF ACTION

1 Check the operation of protection relays.

2 Check the phase and the zone of operation.

3 Confirm the breaker tripping at both ends.

4 Collect the other end relay operations and fault locator reading and correlate with the

relay operations this end.

5 Take the prints of D/R And E/L prints and analyze the cause of tripping.

6 Check the Auto reclosures switch position and confirm from D/R and E/L the auto

reclosure operation. In case the auto reclosure operation taken place, do not attempt

to change the line until Maintenance group gives clearance.

7 In case the Auto reclosure switch is in non-auto position or line tripped other than

Page 38: Project Original

line fault, an attempt may be made to test charge the line.

2. OVER VOLTAGE PROTECTION OPERATED (86 O/V)

Over voltage relay operate when the line voltage rises above a specified value. Instantaneous

and definite time over voltage relay is provided for each line. If the voltage exceeds 40% of the

rated voltage (400 kv) instantaneous relay picks up and trip the line. If voltage exceeds 10% of

rated value for duration of more than 5 sec. the time delay relay picks up and trip the line.

PLAN OF ACTION

1 Check whether time delayed or instantaneous element has picked up.

2 Confirm the relay operations/ breaker tripping at the other end.

3 Check the D/R and voltage recorder printouts.

4 Check the CVT physically for any damage of equipment.

5 Find out there is any system disturbance at other end.

6 Line is to be charged only after testing CVT secondary voltages and obtaining

clearance from Maintenance group.

3. MAIN /12 PROTECTION UNHEALTHY (97XY)

This alarm appears when one of the main protections becomes unhealthy due to D.C. supply

failure for relay unit or some in built problem in the relay.

PLAN OF ACTION

1 Identify the faulty relay

Page 39: Project Original

2 Check for the DC fail indication

3 Inform to Maintenance staff for rectification

4. INTERTRIP SIGNAL RECEIVED (PERMISSIVE INTERTRIPPING 85XY)

In carrier aided distance schemes carrier signal is used in connection with distance relays to

speed up fault clearance, falling in delayed zone 2, from

both ends. The delay inherent in the second zone may be overcome by transmitting an intertrip

signal to the relay at the remote terminal via a carrier channel, transmission being initiated by

local zone 1 relay operation. The intertrip signal thereby allows simultaneous and fast tripping

at both ends of the line and also permits application of auto reclosure schemes

PLAN OF ACTION

1 Confirm the breakers tripping at both ends.

2 Collect the other end relay operations and analyse the fault

3 After getting the clearance from the other end operator and IOCC charge the line.

5. GROUP 1/2 PROTECTION OPERATED (95CA/95CB)

The protection scheme provided for the bay equipment are divided into two groups and

connected separately to two trip relays. Operation of any protection relay will operate the trip

relay connected to that group. The operation of any one of the two trip relays initiates the above

annunciation.

PLAN OF ACTION

1 Check for protection relays in the group operated.

Page 40: Project Original

2 Confirm the breaker opening at both the ends.

6. AUTO RECLOSURE LOCKOUT (186 A/B)

Auto reclosure feature is provided to ensure availability of feeder during transient faults. In the

event of a feeder fault, protection relay detect the fault and trips the line. Auto reclosure relay

operate and close the breaker after a specified time (0.5m sec). If the fault is still persisting, the

breaker trips again on protection relay operation. Auto reclosure relay locks out on its own after

one reclosure effect.

PLAN OF ACTION

1 Collect the other end relay and breaker operation and correlate with the operations of

this end.

2 Do not charge the line until Maintenance clearance obtained.

7. FAULT LOCATOR FAULTY (CS57)

This alarm appears whenever power supply unit of fault locator fails (power switch off position

etc) or some in built problem in the unit arises.

PLAN OF ACTION

1 Check for DC supply fuse for F/L

2 Check the selector switch in/out

3 Check the 50VDC supply system

Page 41: Project Original

4 Check whether MCB in panel supply modules of EIT 21/21 is off.

5 Witch on the panel if it is off. If it trips again inform Maintenance staff.

8. DISTURBANCE RECORDER FAULTY (DRX) / 86B CIRCUIT FAULTY

This alarm appears whenever power supply unit of D/R fails (power switch off position etc.) Or

some in built problem in the unit arises.

PLAN OF ACTION

1 Check for the DC supervision relay flag indication.

2 Inform Maintenance group to attend.

9. REACTOR TROUBLE (30 L/M/O/R/G/H/J/K)

Reactor trouble Annunciation indicates the unhealthiness of the reactor or NGR (Neutral

Grounding reactor) Generally neutral point of a reactor is grounded through a reactor. This

annunciation appears when one or more of the following events taken place.

1. Reactor Buchholz alarm

2. Reactor wdg. Temp. High alarm

3. Reactor oil temp. High alarm

4. Reactor oil level low alarm

5. NGR Buchholz alarm

6. NGR wdg. Temp. High alarm

Page 42: Project Original

7. NGR oil temp. High alarm

8. NGR oil level low alarm

PLAN OF ACTION

1 Check for the protection relay operations of the reactor and identify the fault.

2 Check physically reactor and its NGR (Neutral grounding reactor) observe any oil

spillage in the surroundings, oil leakages, gas accumulation in buchholz relay.

3 If any abnormality observed take permission from IOCC and trip the line.

4 Inform to Maintenance group to attend the problem.

C. ALARMS RELATED TO TRANSFORMER PROTECTIONS

1. TRANSFORMER COOLER TROUBLE

Cooler trouble alarm appears when one or more of the following conditions.

1. Failure of cooler supply

2. Cooling fan failure

3. Cooling pump failure

PLAN OF ACTION

1 Check for the cooling fans and pumps operation.

2 In case of a group of fans or pumps not in service check their overload relay

operation and reset.

3 Check for availability of two sources of power supply

2. TRANSFORMER BUCHHOLZ ALARM/ TRIP

Page 43: Project Original

Buchholz relay is a gas-operated relay. When a slight or incipient fault occurs in the

Transformer, the gas generated will collect in the top of the buchholz relay. A pre set volume of

gas collection in the relay causes the buchholz annunciation / trip contacts to operate.

PLAN OF ACTION

1 Confirm the flag indication for the operation of the relay

2 Check for the gas accumulation in Buchholz relay

3 If gas collection is found, Transformer shall be hand tripped

3. TRANSFORMER WDG. TEMP/OIL TEMP. HIGH

This alarm appears when the wdg. Temp/oil temp of the Transformer goes

beyond the set value.

PLAN OF ACTION

1 Confirm from local the actual winding/ oil Temperature

2 Confirm the running of all the cooling fans and oil pumps

3 If the fans and pumps are not running, start them in manual mode. In case not

possible to start inform Maintenance group.

4 Request IOCC and LDC to reduce the local on Transform

4. TRANSFORMER OIL LEVEL LOW

Page 44: Project Original

The magnetic oil level gauge fitted on the main conservator initiates annunciation / trip in the

event of the oil level falling below the preset levels due to any reason.

PLAN OF ACTION

1 Confirm from the local the actual level of oil.

2 Check for any heavy leakage of oil from the Transformer if found then take

immediate action to trip the Transformer

3 Inform Maintenance group to attend the problem

5. TRANSFORMER OVER LOADED

The load (current) on Transformer exceeds its rated (or set) value for more than a specified time,

then Transformer over loaded annunciation appears.

PLAN OF ACTION

1 Check the current readings of the Transformer, in case the current is more than the

set value, request LDC to reduce load.

2 Check the system voltage and frequency. Also check voltage and frequency

recorders for any sudden change.

3 Request IOCC to coordinate with SREB and AP LDC to bring the system

parameters with in the limits.

6. PRESSURE RELIEF DEVICE OPERATED

Pressure release device allows for the rapid release of excessive pressure that may be generated

in the event of a serious fault in the Transformer. A bright colour coded Mechanical indicator

pin in the cover moves with the valve disc during operation of PRD and is held in position by an

Page 45: Project Original

in the pin bushing. This pin is clearly visible from the ground level indicating that the device is

operated.

PLAN OF ACTION

1 Check for any other protection relays operated to identify the problem.

2 Check for both LT and HT side breaker tripping. If any one of the breaker in service

hand trip the same.

3 Check for any gas accumulation in Buchholz relay

4 Transformer may be charged only after thorough investigation for the reason of PRD

operation and obtaining clearance from Maintenance group.

7. DE-ENERGISATION AND ISOLATION OF SWITCHYARD EQUIPMENT

De energisation of equipment isolation from live parts, normalization of the equipment after

completion of Maintenance jobs trail charging and taking in to service are the important day-to-

day operation activities.

7.1 IMPORTANCE OF SAFETY IN SWITCHYARD OPERATION

Isolation and charging of high voltage equipment have great potential for hazardous occurrences

and need to consider safety at each juncture. Safety in electrical system concerns three

different areas; protection of life, protection of equipment, protection of uninterrupted

productive output. The protection of human life is paramount. Equipment can be replaced lost

production can be made up. However, human life can never be recovered nor human sufferings

compensated. Therefore, only qualified and authorised persons shall be allowed to operate

switchyard equipment.

7.2 GENERAL PRECAUTIONS

Page 46: Project Original

a) All apparatus should be legibly marked for every identification. These makings

should not be placed on removable part.

b) There must be checks and cross checks to confirm that you are at right apparatus for

the particular operation.

c) NO part of the body should touch any part of the equipment under charging during

isolation or normalization.

d) Proper illumination should be there to avoid poor visibility in any part.

e) All control knobs and indicative lamps should be in working condition.

f) Operation staff for their own safety should use the personal protective equipment

like safety shoe, hand gloves etc. at work.

g) Always put DANGER TAGS after isolating the equipment and remove the danger

ages after and normalization of the equipment.

h) Operation staff they must understand operations to be done and be completely

familiar with every details of his part of operation.

i) Should not start a switching sequence until it is correct in every respect.

j) Once begum the switching sequence keeps total attention on what is doing, ignoring

distractions, until the job is completed. If attention is diverted to another tasks while

executing a switching operation, then should not continue the operation before

carefully checking what has already been done.

7.3 DE- ENERGIZATION & ISOLATION OF EQUIPMENT

De energisation and Isolation of equipment required during the following situations.

1. When carrying out preventive or breakdown Maintenance it is essential to isolate

reliably the equipment or section on which the work is to be done, from all other live

parts on the installation in order to ensure complete safety of working staff.

2. When some abnormality observed in a section of the system, t The faulty section should

be isolated from the main system to safe guard the rest of the system.

Page 47: Project Original

3. When the equipment found defective while in service, isolation of defective equipment

or section is necessary to stop further damage to that equipment or surrounding

equipment.

7.4 PLANNING OF SHUTDOWN PF EQUIPMENT

If it is a planned shutdown, to attend a preventive or break down Maintenance job, the

problem will be discussed in daily planning meeting in the presence of operation and

Maintenance representatives and the shutdown schedule of equipment will be planned.

If it is an emergency shutdown, Maintenance and operation HOD’s discuss the emergency

and decide the plan of shutdown of the equipment.

If the required shutdown is going to affect the power flow in the tie lines connected to

PGCIL substations, then shutdown concurrence must be obtained from IOCC. For the line

belongs to AP Transco, shutdown concurrence must be obtained from LDC.

7.5 REQUESTS FOR PERMIT TO WORK (PTW)

The concerned authorized area Maintenance Engineer requests for a permit to work (PTA)

on the shutdown-planned equipment in a specified form to the authorized operation engineer

of the location. Operation Engineer takes the responsibility of de energizing and isolating

the equipment for which shutdown is required with the help of the controllers and operators.

7.6 PRE REQUISITES BEFORE DE ENERGISAITON

a) Take clearance from the shift in charge for de energisation of the equipment.

b) Inform the Maintenance group before de energisation.

c) If the de energisation is for a tie line or auto Transformer inform the other end substation

operator and take clearance.

Page 48: Project Original

d) Check the line loads and ensure that the shutdown of the equipment, should not

make over loading the other lines or Transformers.

e) Identify the correct bay and concerned main and tie breakers to be tripped for de

energisation of the line/ Transformer.

f) Keep the Auto Recloser switches of the main and tie breakers in N.A. position.

g) Give announcement in swyd. PA system, the name and the number of the breaker,

which is going to hand, trip to aware the personnel working in swyd.

h) Give announcement in station PA system, the name of the line or Transformer that is

going to hand trip, to alert the unit desk operation engineers to face any abnormality

arises during line de energisation.

i) Inform orally to the other end substation shift in charge regarding the de energisation of

line/Transformer and hold him on line.

7.7 PROCEDURE OF DE ENERGISATION

A) DE ENERGISATION OF 400 KV TRANSMISSION LINES

1. Hand trip Main/ Tie breaker whichever bay is to be energized. Subsequently trip the

other breaker if the bay equipment is not under PTW.

2. Confirm from the other end operator on telephone that the breaker at their end

tripped on intertrip signal.

B) DE ENERGISATION OF 220 KV/132 KV LINES

1. Hand trip the main breaker of the line to be de energized if the line is connected to

main bus or the transfer bay breaker if the line is connected to transfer bus.

2. Confirm from the other end operator on telephone that the breaker at their end tripped on

intertrip signal.

Page 49: Project Original

C. DE-ENERGISATION OF 400 KV/220KV AUTO TRANSFORMERS

1. Hand trip Main/ Tie breaker (400 KV SIDE) whichever bay is to be de energized.

Subsequently trip the other breaker also if the bay equipment is not under PTW.

2. Hand trip line breaker (220 KV side) and inform the other end shift in charge on phone

that the Transformer is de energized and ensure that the other end breaker tripped on

intertrip signal.

D. DE ENERGISATION OF 400KV/132 KV AUTO TRANSFORMERS

1. Hand trip Main/ Tie breaker (400 KV SIDE) whichever bay is to be de

energized. Subsequently trip the other breaker also if the bay equipment is not

under PTW.

2. Hand trip the LT breaker (220 KV SIDE) of the Transformer is on main bus or hand

trip the transfer bus breaker if the Transformer is on transfer bay. Inform the other end

operator on telephone that the Transformer is de energized.

7.8 POST DE ENERGISATION CHECKS

1. Check for any window annunciation or alarms appeared.

2. Check for the breaker open events in event logger.

3. Check for the semaphore indication of breakers in open position.

4. Check the breaker on/off indication lamp and ensure the breaker is in off position.

5. Check for the fall of flags in three phase of the trip relay.

7.9 ISOLATION OF 400 KV TRANSMISSION LINE BAY

1. Physically check at breaker for open indications in 3 poles and ensure that the

breaker is absolutely in open position.

Page 50: Project Original

2. Open the 400 KV side (HT) isolator from remote or local mode.

3. Open the 220kv/132kv side (LT) isolator either from remote or from local position.

4. Ensure physically all the three poles of isolators opened.

5. Close the 400 kv side isolator earth switch and 220 kv/132 kv side earth switches and

lock them.

6. Keep the danger tags at breakers on/off handle giving the details of the permit

being issued.

7. Note down on the permit card the isolations done along with the precautions to be taken

further by the recipient at time of work carrying the work and issue the permit card to

the applicant.

8 . NORMALIZATION AND CHARGING OF LINES AND TRANSFORMERS

For normalizing and charging the transmission lines and Transformers, certain preconditions

are required to be met so as to safely normalize and charge the feeder or Transformer. As the

transmission lines in 400 KV net work are so long and Transformer s are of large capacities,

certain conditions like enough capacity of the system to absorb the line MVAR to be ensured.

Safety of personnel to be ensured. While synchronizing the feeder, enough precautions to be

taken to ensure that the grid system is compatible and within limits so that there should not be

power swings owing to a synchronism.

8.1 COMMON INSTRUCTIONS FOR CHARGING THE LINE AND

TRANSFORMERS

Page 51: Project Original

a) Lines or Transformers shall be charged always from the strong source end, where there

is a facility to absorb reactive power and synchronization shall be done from the other

end in normal conditions.

b) Generally, voltage at charging end bus shall be kept below 400 kv before charging of the

line.

c) When a line or a Transformer is charging after completion of Maintenance works trips

on a fault, second attempt shall not be made until it is thoroughly investigated and

reasons for tripping should be established.

d) If the frequency and voltage are not in synchronism limits. Line / Transformer shall not

synchronies to Grid. A synchronous inter connection may lead to unwarranted power

swings that may cause not only grid disturbances but also accidents SRLDC shall

coordinate with SEBs to bring the parameters within the limits.

8.2 CHECKS BEFORE NORMALIZATION

a) Ensure that all permits issued on Line equipment / the authorised area Maintenance

engineer canceled Transformer. Also, ensure that any NBFC issued to the other end

substation was returned back in writing.

b) Check physically the work area for removal of men and Material.

c) Take clearance from IOCC, if the line is connected to PGCIL substations or from

LDC, if the line is connected to AP Transco substations and take clearance from shift

in charge.

d) Ensure that all switchyard equipment associated with the line or Transformer under

shutdown is in operating condition.

e) Check for SF6 gas and air/ oil pressure of main/ tiebreakers.

f) Ensure that the Local / Remote switches of the Main/ Tie breakers are kept on

remote position.

g) Check physically for the removal of all the temporary earthlings done at the work

site.

h) Check physically for the healthiness of line shunt reactor or the Transformer going to

be charged.

Page 52: Project Original

i) Ensure that all relay flags are reset.

j) Check that no window indication is persisting and ensure that annunciation lamp test

OK.

k) Ensure that disturbance recorder, fault recorder, and event logger are in service.

l) Check the communication book for remarks if any on the equipment associated to

the shutdown bay. Remarks if any found take written clearance for charging the bay

form the concerned area Maintenance engineer.

m) Return back the NBFC obtained from the other end substation through written

message and take clearance in writing for charging the line.

8.3 NORMALIZATION OF A TRANSMISSION LINE BAY EQUIPOTENT

a) Open the earth switch of the line isolator. Also open the earth switches of

main and tie bay isolators if any closed position.

b) Close the line isolator of the line under shut down.

c) Close the Bus 1 / Bus 2 connecting isolators in main bay, if permits are not pending

on the concerned bay equipment.

d) Close the tie bay isolators I the permits are not pending on Tie bay equipment.

e) Close the shunt reactor isolator if shunt reactor available for the line and it is in

isolated condition.

f) If isolators are closed in remote mode, check physically to confirm all the three poles

closed properly.

8.4 CHARGING OF TRANSMISSION LINES

In case of IOCC instructed to charge the line from this end and to synchronize from the remote

substation.

a) Inform IOCC that the line is ready for charging and take the final clearance for charging

the line.

Page 53: Project Original

b) Inform orally to the other end substation operator that the line is ready for charging and

hold him on line.

c) Give announcement in swyd PA system regarding line charging to aware the

Maintenance group any body working in swyd.

d) Give announcement in station PA system for alerting the unit desk operation engineers

to face abnormality if any arises during process of line charging.

e) Keep heck synchronizing selector switch in bypass position (switch available in control

panel no.12) and plugin the synchroscope into the concerned breaker synchronizing

socket Keep the synchroscope in on mode.

f) Close main/ tiebreaker which ever bay is made ready for charging the line (dead line

charging). Subsequently close the other breaker also If the bay equipment not under

permit.

g) Inform the remote end operator on telephone that the line is charged and give clearance

for synchronizing to the grid.

8.5 SYNCHRONIZING THE LINE AFTER CHARGING AT REMOTE END

In case, IOCC instructed to charge the line at remote end and synchronize the line this end.

a) Inform IOCC that the line is ready for synchronizing and take the final clearance for

synchronizing and take the final clearance for synchronizing the line.

b) Ensure that check synchronizing selector switch is on position and plug in synchronic

scope into the concerned breaker-synchronizing socket. Make synchroscope on and

checkt for syncro in limit indication. If it is not in limits inform to IOCC which

parameter (Voltage/ frequency) is not matching and request them to coordinate in

bringing the voltage/ frequency within limits i.e. 0.4% in respect of frequency and 10%

in respect of voltage.

Page 54: Project Original

c) Once again, ascertain that the voltage and the frequency are within synchronizing limits.

d) Inform orally to the other end substation operator that the line is going to be

synchronized and let him hold on line.

e) Give announcement in switchyard PA system regarding closing of the beaker to aware

the persons any body working in switchyard.

f) Given announcement in station PA system regarding line charging to alert the unit desk

operation engineers to face any abnormality if arises during the process of line charging.

g) Close Main/ tiebreaker whichever bay is made ready for charging the line. Subsequently

close the other breaker also if the bay equipment not under permits.

8.6 NORMALIZATION OF TRANSFORMER BAY EQUIPMENT

a) Inspect the Transformer physically and check the following.

1. Conservator oil level of main tank and OLTC is maintained

2. Breather silica gel colour is blue.

3. Check for heavy oil leaks if any from tank, radiator, pipes and bushings.

4. Check the availability of cooler supply and healthiness of fans and pumps

by running in manual mode.

5. Note down the WTI and OTI readings, confirm they are working.

6. Check the cleanliness of Transformer & surround area.

7. Check any removal of HT/LT connections and fuses in marshaling box.

8. Check the emulsifier system operation.

b) Open the earth switches of the 400 KV Bus side Isolator (HT) and 220 kv line side

isolator (LT): Also open the earth switches of main and tie-bay isolators if any found in close

position.

c) Check for any portable earthlings on bay equipment. If found any, request Maintenance

staff to remove the same.

d) Close 220 kv side isolators and 400 kv side main and tie bay isolators provided the

permits are not pending.

Page 55: Project Original

e) If isolators are closed in remote mode, check physically to confirm all the three poles

closed properly.

8.7 CHARGING OF TRANSFORMER FEEDER

In case, AP Transco requested to change the 220 KV line from this end and to synchronize at

their substation.

a) Inform LDC that the 220 KV line is ready for charging and take the final

clearance for charging the line.

b) Inform orally to the AP Transco substation Engineer that Auto Transformer is going

to be charged at our end.

c) Give announcement in swyd & station PA system regarding charging of

Transformer.

d) Keep check synchronizing selector switch in by pass position and plug in the

synchroscope into concerned breaker synchronizing socket. Keep the synchroscope

in on mode.

e) Close Main/ Tie breaker which ever bay is made ready for charging the Transformer.

Subsequently close the other breaker also if the bay equipment not under permits.

f) Inform to the AP Transco Engineer on telephone that 20 kv line is going to charge

and hold him on line.

g) Keep Auto recolor switch in NLA mode. Close the line breaker of the feeder to be

charged.

h) Inform AP TRANSCO ENGINEER that feeder is charged and check for voltage at

their end. Give clearance to synchronize the feeder at their end.

8.8 SYNCHRONIZING THE TRANSFORMER FEEDER

In case, AP LDC requested to charge the Transformer feeder at remote end and synchronize

at this end.

Page 56: Project Original

a) Give clearance to AP Transco Engineer to charge the 220 Kv line at their end.

b) After getting information from AP Transco Engineer regarding the closing of 220

KV line breaker at their end, check for the line voltage at control panel meter and

confirm.

c) Keep check synchronizing selector switch in bypass position and plugin the

sysnchroscope into the concerned Auto Transformer breaker-synchronizing socket.

Keep the synchroscope in on mode.

d) Close Main/ Tie breaker which ever bay is made ready for charging the Auto

Transformer. Subsequently close the other breaker also if the bay equipment is not

under permit.

e) Auto Transformer is in idle charge condition. Check the current in three phases to

ascertain the healthiness of the Transformer.

f) Normalize the check-synchronizing switch from by pass position.

g) Inform the AP Transco Engineer on telephone that 220 KV line is going to

synchronies and hold him on line.

h) Keep the check synchronizing selector switch in on position and plugin the

synchroscope into the concerned line breaker-synchronizing socket. Make the

syncrhoscope on.

i) Ascertain that the voltage and the frequency are within synchronizing limits.

j) Give announcement in switchyard & station PA system regarding closing of breaker

k) Close the 220 kv line breaker (LT breaker of Auto Transformer).

l) Inform to AP Transco S/S & APLDC that the line is synchronized.

9 . BLACKOUT OF STATION AND BLACK START PROCEDURES

Despite of all precautions and protective measures, the integrity of the power system is

occasionally at risk owing to human error, malfunction of equipment, lack of complete

information, and natural disasters. The emergency like grid failure/ partial grid failure may

lead to total loss of power supply in the region / station, which is called the blackout

condition.

Page 57: Project Original

In case of total Blackout of station / region due to grid failure or partial grid failure,

operation staff are responsible.

1. To analyse and locate the fault leading to the situation

2. To inform all the authorities and units about the problem.

3. To arrange startup power at the earliest to bring back the units.

9.1 PLAN OF ACTION DURING STAITON BLACKOUT

1. See and ensure DC lighting has come in auto.

2. Have a broad lock on the panel, see whether any unit has survived on house load

and / or any line feeding on house load has survived.

3. Inform shift charge engineer and all units about the status on emergency PA

system through group call.

4. Specifically inform shift charge engineer, Sr. supdt. (Operation) DGM (O), DGM

(EM), AGM (O&M), and GM (R) about grid failure.

5. Check and not down the relays operated, ascertain the reasons of cause leading to

grid failure also whether it is from station side or switchyard side or substation

side.

6. See that all outgoing feeder breakers have opened out, if not, open them

manually.

7. Normal sources of startup power are Chandrapur HVDC S/S and Nagarjuna

sagar Hydro power station (AP GENCO). Find out how much startup power can

be made available.

8. Inform shift charge engineer about the amount of startup power available and

quantum thereof. This I necessary to decide further course of action regarding

bringing back the units.

9. As per recommendations of IOCC/LDC, Hyderabad startup power is to be

availed through respective feeder.

Page 58: Project Original

9.2 BLACK START FACILITIES AT RSTPS

In general at least one of the 400 KV Chandrapur Ramagundam HVDC back-to-back lines is

always in service. With the consent of SRLDC, startup power supply can be taken immediately

from Western region by passing HVDC back to back like at Chandrapur.

In case of startup power not available form CHANDRAPUR S/S due to outage of equipment or

any other, reason the following alternate arrangements to be made.

9.3 ACTIVITIES AFTER OBTAINING STARTUP POWER

a) Close 400 KV breakers pertaining to above set feeder and thus charge 400 kV buses

1 or 2

b) Charge 400/33 kV Tie Transformer 1 or 2 or 3.

c) Charge 33 kV bus 1 and / r 2 and / or 3.

d) Depending on the quantum of power available and units to be brought on bar; seek

shift charge engineer instructions regarding charging of CW Transformers, WTP

Transformers, Station Transformers and act accordingly.

e) Charge switchyard service Transformers and extend supply to switchyard MCC and

lighting panel

f) After normal supply is resumed, switch off DC lights.

g) Due to lack of power, battery chargers had tripped and the ENTIRE D Batteries

supplied load.

h) Check the condition of batteries and accordingly keep the chargers in service.

i) See that air compressor, providing compressed air for breaker operations, have

started and developing adequate pressure.

j) Now situation is normal. Once units are ready for synchronization seek

instructions from IOCC and LDC, accordingly take lines in service and

synchronize the units.