Project Oorja - Investor Presentation 30 Jul 09aceanalyser.com/Analyst Meet/132778_20090731.pdf ·...
Transcript of Project Oorja - Investor Presentation 30 Jul 09aceanalyser.com/Analyst Meet/132778_20090731.pdf ·...
Lanco InfratechInvestor Presentation
July 2009
2
Disclaimer
No representation or warranty, express or implied, is made as to, and no reliance should be placed on, the fairness, accuracy, completeness or correctness of the information or opinions contained in this presentation. Such information and opinions are in all events not current after the date of this presentation. Certain statements made in this presentation may not be based on historical information or facts and may be "forward looking statements" based on the currently held beliefs and assumptions of the management of the Company, which are expressed in good faith and in their opinion reasonable, including those relating to the Company's general business plans and strategy, its future financial condition and growth prospects and future developments in its industry and its competitive and regulatory environment. Forward-looking statements involve known and unknown risks, uncertainties and other factors, which may cause the actual results, financial condition, performance or achievements of the Company or industry results to differ materially from the results, financial condition, performance or achievements expressed or implied by such forward-looking statements, including future changes or developments in the Company's business, its competitive environment and political, economic, legal and social conditions. Further, past performance is not necessarily indicative of future results. Given these risks, uncertainties and other factors, viewers of this presentation are cautioned not to place undue reliance on these forward-looking statements. The Company disclaims any obligation to update these forward-looking statements to reflect future events or developments.
This presentation is for general information purposes only, without regard to any specific objectives, financial situations or informational needs of any particular person. This presentation does not constitute an offer or invitation to purchase or subscribe for any securities of the Company by any person in any jurisdiction, including India and the United States. No part of it should form the basis of or be relied upon in connection with any investment decision or any contract or commitment to purchase or subscribe for any securities. The Company may alter, modify or otherwise change in any manner the content of this presentation, without obligation to notify any person of such change or changes. This presentation may not be copied or disseminated in any manner.
3
Agenda
1 Company Overview
2 Power Business
3 Construction and EPC Business
4 Infrastructure Business
5 Property Development Business
6 Key Financials
7 Experienced Management Team
4
Agenda
1 Company Overview
2 Power Business
3 Construction and EPC Business
4 Infrastructure Business
5 Property Development Business
6 Key Financials
7 Experienced Management Team
5
32
350
690
1,292
-
500
1,000
1,500
FY06 FY07 FY08 FY09
(US$
mm
)Lanco Infratech – A Leading Integrated Infrastructure Player
Construction & EPC Power Infrastructure Property Development
• Executed projects worth US$1.3bn over last 3 years (FY07 - FY09)
• Order book of US$2.2bn
• 5 plants with approx. 511 MW capacity under operation
• 9 plants with approx. 3,913 MW capacity under construction
• 2 plants with approx. 3,960 MW capacity under development
• Largest private player in power trading with 12.4% market share
• Developing approx. 163 km of National Highways in Karnataka
• Bidding for constructing and operating Airports, Metro Rail Transport Systems and renovation, modernization & operation of roads, ports and redevelopment projects
• 4mm sq ft under development in Hyderabad, India
• Developing Lanco Hills, mixed used space of high rise residential structures, IT SEZ office space, shopping malls and hotels
Division of Lanco Infratech
Special Purpose Vehicles
Note:
1 This presentation assumes an exchange rate of US$ / INR =47
2 Financial year ending March 31
3 mm indicates million
Revenues EBITDA PAT
4
98
149189
-
50
100
150
200
FY06 FY07 FY08 FY09
(US$
mm
)
4
40
6075
-
25
50
75
100
FY06 FY07 FY08 FY09
(US$
mm
)
6
Pan India Presence
Chitradurga Kondapalli - I
Aban power
Amarkantak – I & IIAmarkantak – III & IV
Kondapalli - II
Udupi
Teesta
Lanco Uttaranchal
Anpara
Babandh
Lanco Hills
Plants under construction
Plants under development
Plants under operation
Plants under construction
Plants under operation
Plants under construction
Plants under operation
Property development
Road development
Vamshi - I
Vamshi - IIVamshi Industrial
Lanco Green
81 km Bangalore – Hoskote – Mudbagal82 km Neelamangla – Devihalli Tamil Nadu Wind
Coal Based
Hydro
Gas
Wind
Registered office
Administrative office
Hyderabad
Gurgaon
Coal mine
7
Strong Push to Drive Infrastructure Growth
Infrastructure spending (2007-2012)
Source: UNDP, Human Development Indicators, 2007/08
In the XIth five year plan (2007-2012), the Government targets to add 78,700 MW of generating capacity
Government is targeting investment of >US$400 billion during 2007-2012
Commentary
• Recent election mandate provides a stable coalition government which may focus on infrastructure
• Positive regulatory reforms remain a key driver of growth
• Power, airports and ports are likely to be the fastest growth sectors in the foreseeable future
Per capita consumption of electricity
Total - US$437bn
Demand / supply gap for power
774
579625
666 689632 691739
591548
-
200
400
600
800
1,000
FY05 FY06 FY07 FY08 FY09
(bn
kwh)
0%
3%
6%
9%
12%
Requirement Availability Deficit
18.4
14.2
7.4 6.4
2.3 1.7 0.6 1.2
-
5
10
15
20
Canada US Germany Russia Brazil China India Developingcountries
(Tho
usan
d kw
h/ye
ar)
Source: Planning commission (XIth five year plan) Source: Central Electricity Authority (“CEA”)
0
40
80
120
160
Power
Roads
and B
ridge
sTele
com
Railway
sIrri
gatio
nWater
/ san
itatio
n
Ports
Airport
sStorag
e
Gas
(US$
bn)
Central Govt. State Govt. Private sector
157
79 68 65 5551
199 6 5
8
Agenda
1 Company Overview
2 Power Business
3 Construction and EPC Business
4 Infrastructure Business
5 Property Development Business
6 Key Financials
7 Experienced Management Team
9
18
3584
131
238
408582
631
1,000
1950
19601970
1980
1990
2001
20042006
2012
No. of Units
Projected 2012 peak Energy Deficit Power Deficit (2009)
Per Capita Consumption Growth (Units)Planned Vs. Installed Capacity – Xth Plan (MW)
(0.9)%
(2.0)%
(3.2)%
(3.6)%
(4.8)%
(6.2)%
(7.6)%
(10.0)%
(13.0)%
(15.9)%
(22.1)%
(23.7)%
(24.3)%
OR
C H
R J
WB
KN
T N
A P
M P
KL
P N
UP
M H
GJ
(1.5)%
(2.6)%
(1.1)%
(3.2)%
(6.0)%
(7.9)%
(6.8)%
(17.2)%
(11.8)%
(10.6)%
(20.9)%
(21.4)%
(9.8)%
Peak Deficit States Energy Deficit
58% growth in XIth Plan
Source: CEA
Source: Ministry of Power Source: CEA
Power Deficit Scenario
4,481
2,691
6,676
3,553
5,951
7,33012,790
1,1801,3008,7424,495
1,231
700
1,170
0
10,000
20,000
30,000
Hydro Hydro Thermal Thermal Nuclear Nuclear
(MW
)
Central sector State sector Private sector(Planned) (Installed) (Planned) (Installed) (Planned) (Installed)
Source: CEA
(9.7) (9.3)(5.0)
1.63.5
(5.8)
(0.7)
3.7
(4.4)
(10.4)
(4.5)
15.0
2.7
15.816.0
(15.0)(10.0)(5.0)0.05.0
10.015.020.0
North India West India South India East India North-EastIndia
Winter Peak Monsoon Peak Summer Peak
10
Presence Across Value Chain De-risking the Business
Fuel (Coal mining) Construction and EPC Generation and O&M Trading
• Captive coal mine allocated by Govt. of India to Lanco and five others
• Coal to be used for portion of needs of the Orissa based 2,640 MW Babandh power plant
• 5 completed projects with capacity of 514MW and 3,913MW projects under development
• Strong engineering capability and resources spanning feasibility studies, front-end design and complete detail design with over 10 years of experience in design and development of Power Projects
• Handles global suppliers selection and sourcing of diverse materials like high-pressure fabricated equipment, skids, electrical and instrumentation systems
• 5 operating projects with capacity of 511MW and 7,873 MW projects under implementation
• Generation activities include conventional and non-conventional sources of energy like coal, hydro and wind
• Largest private sector player in Indian power trading market with approx. 12% market share
• Covers all the five regions of India by covering 32 utilities from 19 States
• Traded 2,841mm units in year ended March 31, 2009
• Bought 5% stake in the Indian Energy Exchange floated by Financial Technologies Ltd and Power Trading Corporation
Transmission and Distribution
• Strategy includes possible expansion into transmission and distribution
Integrated presence across value chain capturing value addition across the businesses
11
Focused on Power Sector with a Pan-India presence
Location of power plants
Fuel diversification of power plants1
Note:1 After installation of all current projects including projects under development
Regional split of power plants1
One of the early private sector entrants in the field of power generation with first plant set up in 2000
Chitradurga
Aban
Kondapalli - I
Kondapalli - II
Vamshi Hydro - I
Tamil Nadu Wind
Amarkantak – I & II
Amarkantak – III & IV
Vamshi Hydro - II
Vamshi Industrial
Lanco Green
Udupi
Teesta
Lanco Uttaranchal
Anpara
Babandh
Plants under operation
Plants under construction
Plants under development
Central22.9%
North17.2%
South22.4%
East37.5%
Wind0.1%
Domestic coal
68.7%Imported coal
12.1%
Gas10.2%
Hydro8.9%
Capacity (MW)
511
3,913
3,960
Total 8,384
12
Mature Power Projects Provide Visibility into Earnings
Projected capacity addition
FY10• Amarkantak I & II• Vamshi Industrial • Kondapalli II• Udupi I
FY11• Budhil• Udupi II• Anpara
FY12
• Uttaranchal I
FY13
• Amarkantak III• Babandh (2
units)• Teesta• Uttaranchal II
FY14
• Babandh (2 units)
• Amarkantak IV
Lanco is expected to increase its power generation capacity significantly in next 2 years
1,994.5 MW
3,772 MW
3,848 MW
6,404MW
8,384 MW
511 MW
Current• Kondapalli I• Aban• Chitradurga• Tamil Nadu
Wind• Vamshi
Hydro
13
Project Status UpdateProjects under operation
Plant Fuel Capacity
(MW) Total cost (US$mm)
Kondapalli I Gas 368 241
Aban Gas 120 93
Chitradurga Wind 3 3
Tamil Nadu Wind Wind 10 10
Vamshi Hydro Hydro 10 12
Total 511 359
Projects under construction
Plant Fuel
Govt. approval
status
Financial closure status
Capacity (MW)
Budgeted cost
(US$mm) PPA
(Years) Estimated completion Current status
Amarkantak I Coal 300 275 25 Q2 FY101 Synchronization with grid completed
Vamshi Industrial Hydro 10 12 35 Q2 FY10 / Q3 FY10 EOT Crane commissioned
Amarkantak II Coal 300 285 25 Q3 FY10 Turbine, generator erection currently under progress; Hydro testing to happen soon
Udupi I & II Imported Coal 1,0152 923 25 Q3 FY10 / Q1 FY11 Turbine, generator erection currently under progress
Kondpalli II Gas 366 253 Merchant Q2 FY10 / Q4 FY103 Gas turbine generator placed on the foundation
Lanco Green Hydro 70 89 35 Q2 FY11 Pressure shaft excavation complete
Anpara Coal 1,200 729 29 Q4 FY11 Boiler erection under progress
Lanco Uttaranchal I & II Hydro 152 221 Merchant Q4 FY12 / Q4 FY13 Expected financial closure in FY10
Teesta Hydro 500 638 35 Q4 FY13 Construction commenced in May 2007 and currently in progress
Total 3,913 3,425
Projects under development Babandh Coal (Partly Owned) 2,640 3,370 Part PPA Q4 FY13 / Q1FY14 MOU signed for 1,320 MW and land acquisition in
progress
Amarkantak III & IV Coal 1,320 1,685 Part PPA Q4 FY13 / Q1FY14 MOU signed with Govt. of Chattisgarh; Environmental clearances obtained
Total 3,960 5,055
Note: 1 Currently under litigation
2 1,200 MW upon receipt of approval 3 Q2 FY10 is for open cycle and Q4 FY10 is for combined cycle
14
Agenda
1 Company Overview
2 Power Business
3 Construction and EPC Business
4 Infrastructure Business
5 Property Development Business
6 Key Financials
7 Experienced Management Team
15
In-house EPC Reduces Execution Risk/ Enhances Margins
Revenue contribution1 (FY09) FY09 EBIT margin comparison with other businessesEBIT contribution (FY09)
In-house EPC enables Lanco to complete projects on an accelerated basis
US$1.3bn US$166mm
13.4%11.8%
5.8%
0%
4%
8%
12%
16%
EPC Power PropertyDevelopment
Capability to take up more projects
• Approx. 114 km Veeranam water supply transmission pipeline constructed along with JV Partner, Punchak in Tamil Nadu
• Balance of Plant of approx. 368 MW LANCO Kondapalli Power Project in Andhra Pradesh
• Balance of approx. 120 MW Aban Power Project in Tamil Nadu• 825 bed Asvini Hospital for Indian Navy at Colaba, Mumbai• Four laning of National Highway 31 in West Bengal• Construction of 1st phase of 100 bed hospital, college and hostel
complex etc., at National Institute of Unani Medicine, Bangalore• Construction of Railway Offices at Koparkhairane Railway Station
List of projects executed
• Lanco undertakes the EPC business of its planned projects and profits earned during the construction period can be injected into new projects in the form of equity contribution
• The business model also enables the company to quote more aggressive tariffs in the competitive bidding process thereby increasing the likelihood of getting new projects while maintaining acceptable profit margins
Note:
1 Before elimination of inter segment revenues
Pow er39.1%
Property Development
2.3%
Others0.3%
Construction and EPC
58.3%
Property Development
1.0%
Pow er36.7%
Construction and EPC
62.3%
16
Agenda
1 Company Overview
2 Power Business
3 Construction and EPC Business
4 Infrastructure Business
5 Property Development Business
6 Key Financials
7 Experienced Management Team
17
Leveraging Construction Expertise to Build Infrastructure Business
• Awarded two National highway projects in Karnataka
– Approx. 81 km stretch connecting Bangalore – Hoskote –Mudbagal
– Approx. 82 km stretch connecting Neelamangla – Devihalli
• Budgeted project cost of US$288mm
• Concession periods of 20 years and 25 years respectively during which toll will be collected
• Construction under progress and expected to be completed by Q1FY11
Lanco has moved into selective infrastructure projects to leverage its EPC experience
18
Agenda
1 Company Overview
2 Power Business
3 Construction and EPC Business
4 Infrastructure Business
5 Property Development Business
6 Key Financials
7 Experienced Management Team
19
Property Development - An Opportunistic PlayLanco Hills is the group’s foray into property development, located in Hyderabad, spread over 100 acres and comprises residential space, office space, IT SEZ, shopping mall and two hotels with US$292mm of capital expenditure already incurred
Lanco Hills
Residential • Developing 12 residential towers with construction on 6 towers in first phase • Construction in progress with possession of apartments to commence in Q4 2010
Office space• Office complex with built-up area of 0.5 mm sq ft• Constructing SEZ space with completion target of 2012• Constructing office space with completion target of 2010
Shopping mall • Plans to build a 2.5mm sq ft of a shopping mall • Construction will be in phases
Hotels • Tied up with Grand Hyatt for a 400 room, 5 star deluxe hotel
20
Agenda
1 Company Overview
2 Power Business
3 Construction and EPC Business
4 Infrastructure Business
5 Property Development Business
6 Key Financials
7 Experienced Management Team
21
32
350
690
1,292
-
300
600
900
1,200
1,500
FY06 FY07 FY08 FY09
(US
$mm
)
4
40
60
75
-
25
50
75
100
FY06 FY07 FY08 FY09
(US
$mm
)
4
98
149
189
-
50
100
150
200
FY06 FY07 FY08 FY09
(US
$mm
)
Steady Growth History
Revenues EBITDA
PAT
Source: Company filings
Power projects capex and debt overview (As of March 31, 2009)
1,619
1,609
1,1811,806
0
1,000
2,000
3,000
4,000
Capex Debt
(US
$mm
)
Incurred Remaining
3,425
2,790
22
Agenda
1 Company Overview
2 Power Business
3 Construction and EPC Business
4 Infrastructure Business
5 Property Development Business
6 Key Financials
7 Experienced Management Team
23
Experienced Management Team
L Madhusudhan RaoExecutive Chairman
• M. Tech; MS (Wayne Univ)
• Joined Lanco in 1989
• Guided the company through its crucial stages of growth and mergers
G Bhaskara RaoExecutive Vice Chairman
• ME (Machine Design), B.E. (Production) from IISc
• 25 years of experience in construction industry in project planning and implementation
G Venkatesh BabuManaging Director
• Chartered Accountant and Cost Accountant
• 15 years of experience in Commercial Banking, Corporate Advisory,Mergers & Acquisitions, Project Finance and Equity Capital Markets
J Suresh KumarChief Financial Officer
• Chartered Accountant
• Over 14 years of experience in the financial services sector including M&A, corporate restructuring and fund raising
• Previously employed with JM Morgan Stanley
P Panduranga RaoDirector and Chief Executive Officer, Lanco Kondapalli
• Chartered Accountant and Company Secretary
• 28 years of experience from diverse industries across companies
K Raja GopalChief Executive Officer and Director, Lanco Amarkantak
• ME, MBA (Marketing)
• 22 years of experience in project development and various functional disciplines of manufacturing and power industries
Pochendar ShenigarapuChief Executive Officer, Lanco Hills
• Post graduation in Environment Engineering, B.E. (Civil)
• Previous work experience with IVRCL, Hyderabad Metropolitan Water Supply & Sewerage Board and CPWD
• 26 years of experience
Prasad KandimallaDirector & Chief Executive Officer –Renewable Energy, Carbon Assets
• Masters Degree and Specialisation in Energy & Systems
• Experience in financial services, IT, Management Consultancy spanning several countries
SC ManochaCEO - EPC
• Mech. Engineer & Mgmt Graduate
• 35 years experience in Reliance Energy, Maithon Power, Utility Powertech, L&T, BHEL and ISGEC John Thomson
Pradeep LenkaChief Executive Officer-Thermal, Lanco Infratech Ltd
• ME, 30 years of experience in power projects as OEM and also as IPP developer
• Executed more than 15 projects in BHEL
S M RoyCEO - Construction Division
• Mechanical engineer and post graduation degree in Business management from XLRI Jamshedpur
• 40 years of experience
24
Thank You