Project :M/s SRS Real Infrastructure Ltd., Group …nromoef.gov.in/SMPR/12012016/26.pdfProject:M/s...

23
Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008 Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected] 1 PURPOSE OF THE REPORT As per the “Sub Para (ii)” of “Para 10” of EIA Notification 2006, it is stated that “It shall be mandatory for the project management to submit half-yearly compliance reports in respect of the stipulated prior environmental clearance terms and conditions in hard and soft copies to the regulatory authority concerned, on 1st June and 1st December of each calendar year” and as per compliance of condition mentioned in Environment Clearance Letter (i.e. Part B General Condition, point number XVII), Six monthly compliance reports should be submitted to the Regulatory Authority of Central and State Government. It is mandatory to submit a Six Monthly Compliance Report to show the status & compliance of all the Conditions mentioned in Environment clearance Letter, along with monitoring of various Environmental Parameters (as per CPCB Norms). The regulatory authorities in this case are MoEF & CC, Delhi, MoEF & CC, Chandigarh and HSPCB, Panchkula. Various scheduled Site Visits were conducted by a team of Experts to Monitor Pollution related parameters as defined by CPCB / HSPCB. Samples for water and soil were also collected for further analysis. Based on the Specific and General Conditions mentioned in the EC Letter, a Compliance Report was prepared by the Vardan Enviro Net on behalf of Project Proponent; details of which are present in Chapter “Compliance Report”. This report is supposed to submit after every six month as per the conditions stipulated in Environment Clearance Order. The Environmental assessment has been carried out to verify: 1) That the proposed project has not any adverse effect on the project site as well as its surrounding. 2) That there is compliance with the conditions stipulated in the Environmental Clearance Letter. 3) That the Project proponent is implementing the environmental safeguards in true spirit. 4) The non conformity in the project with respect to the environmental implication of the project. 5) That the project proponent is implementing the environmental pollution mitigative measures as suggested in approved Form-1 and Form 1A, Environmental Management Plan and Building Plan. 1

Transcript of Project :M/s SRS Real Infrastructure Ltd., Group …nromoef.gov.in/SMPR/12012016/26.pdfProject:M/s...

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

1

PURPOSE OF THE REPORT

As per the “Sub Para (ii)” of “Para 10” of EIA Notification 2006, it is stated that “It shall be

mandatory for the project management to submit half-yearly compliance reports in respect of the

stipulated prior environmental clearance terms and conditions in hard and soft copies to the

regulatory authority concerned, on 1st June and 1st December of each calendar year” and as per

compliance of condition mentioned in Environment Clearance Letter (i.e. Part B General

Condition, point number XVII), Six monthly compliance reports should be submitted to the

Regulatory Authority of Central and State Government.

It is mandatory to submit a Six Monthly Compliance Report to show the status & compliance of

all the Conditions mentioned in Environment clearance Letter, along with monitoring of various

Environmental Parameters (as per CPCB Norms).

The regulatory authorities in this case are MoEF & CC, Delhi, MoEF & CC, Chandigarh and

HSPCB, Panchkula. Various scheduled Site Visits were conducted by a team of Experts to

Monitor Pollution related parameters as defined by CPCB / HSPCB. Samples for water and soil

were also collected for further analysis.

Based on the Specific and General Conditions mentioned in the EC Letter, a Compliance Report

was prepared by the Vardan Enviro Net on behalf of Project Proponent; details of which are

present in Chapter – “Compliance Report”.

This report is supposed to submit after every six month as per the conditions stipulated in

Environment Clearance Order. The Environmental assessment has been carried out to verify:

1) That the proposed project has not any adverse effect on the project site as well as its

surrounding.

2) That there is compliance with the conditions stipulated in the Environmental Clearance

Letter.

3) That the Project proponent is implementing the environmental safeguards in true spirit.

4) The non conformity in the project with respect to the environmental implication of the

project.

5) That the project proponent is implementing the environmental pollution mitigative

measures as suggested in approved Form-1 and Form – 1A, Environmental Management

Plan and Building Plan.

1

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

2

1.1 Methodology for Preparation of Report is as follows:

1) Study of EC Letter & Related Documents,

2) Site Visits by a Team of Experts,

3) Monitoring of Environment Parameters, viz. Ambient Air, Water, Noise, Soil & DG Sets,

4) Analysis of Samples collected during Monitoring,

5) Interpretation of Monitoring Results,

6) Preparation of Semi Annual Environmental Compliance Report. 1.2 Generic Structure of Report:

1) Purpose of the Report, explaining the need of a Compliance Report and Methodology

Adopted for preparation of Report. .

2) Compliance Report, explaining the entire General & specific conditions in the EC Letter

and providing details w.r.t. each condition/ guideline.

3) Monitoring Reports & Analysis, showing the level of emission within the project site for

various Environment Parameters.

4) Photographs showing status of the project and site.

5) Supporting Documents related mandatory for the project.

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

3

ADHERENCE TO SPECIFIC AND GENERAL CONDITIONS

2.1 Introduction

M/s SRP Builders Ltd. has proposed a group housing project at Sector-05, Palwal, Faridabad (HR)..

The Project has been recommended by State Expert Appraisal Committee (SEAC). This

Project has obtained its Environmental Clearance from State Environment Impact

Assessment Authority (SEIAA) with the EC No.21-614/2007/IA III dated 1/10/2008. But

now the name of the Builder has been changed From SRP Builders to SRS Real

Infrastructure, under the provision of the State Environment Assessment Authority of

Haryana (SEIAA), with reference no. of SEIAA/HR/2014/675. dated

PART A – SPECIFIC CONDITIONS

I. Construction Phase

S. No. Conditions of Environmental Clearance Status of Compliance

1) Vehicles hired for construction activities should be operated only during non-peak hours.

Agreed.

2) All the top soil excavated during construction activities should be stored for use in horticulture/landscape development within project site.

All the excavated topsoil has been used for landscape development within the project site.

3) Ready mixed concrete shall be used in building construction.

Agreed. We have used RMC in building construction

4) Water demand during construction phase should be reduced by uses of premix concrete, curing agent and other best practices.

Agreed and complied with.

5) Permission to draw and use ground water for construction work shall be obtained from competent authority prior to construction /operation of the project.

Noted and agreed

6) Fixtures for Shower, toilets, flushing and drinking should be of low flow either by use of aerators or pressure reducing devices or sensor based control.

Noted and we will do the same.

7) Use of glass may be reduced upto 40% to reduce the electricity consumption and load on air conditioning .If necessary use high quality double glass with special reflective coating in windows.

We are using the high quality glass with special reflective coating in windows, which will help in low electricity consumption.

8) Roof must meet prescribed requirements as per energy conservation building code by using appropriate thermal insulation material to

Agreed. We have been meeting the prescriptive requirements as per ECBC norms by using

2

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

4

fulfill requirements.. appropriate thermal insulation material. 9) Opaque wall should meet prescribed

requirements as per energy conservation building code which is proposed to be mandatory for all air conditioned spaces while it is desirable for non air conditioned spaces by use of appropriate thermal insulation to fulfill the requirement.

Agreed. We are following ECBC norms for air-conditioned

and non-air conditioned spaces.

10) Storm water control and its reuse should be as per Central Ground Water Board and BIS standards for various applications.

We have been following the CGWB norms for storm water management.

11) All required sanitary and hygienic measures including portable toilets and septic tanks etc.for labour should be in place before starting construction activities and to be maintained throughout the construction phase.

Agreed and complied with. All the necessary facility are given to the workers.

12) Soil and ground water samples will be tested to ascertain that there is no threat to ground water quality by leaching of heavy metals and other toxic contaminants.

Quality of soil samples is being tested regularly. There is no leaching of heavy metals/toxic contaminants into the ground water due to project. Soil test reports are enclosed as Annexure-2

13) A first aid room will be provided at the project site both during construction and operation phase of the project.

A first aid room is proposed at the project site for the workers during the construction phase. The same will be provided in the operational phase too.

14) Adequate drinking water and sanitary facilities should be provided for construction workers at the site.. The safe disposal of waste water and solid wastes generated during the construction phase should be ensured.

Agreed. Adequate drinking water and sanitary facilities have been provided for construction workers. Safe disposal of waste water and solid waste from construction activities has been ensured

15) Disposal of muck including excavated material during the construction phase should not create any adverse effect on the neighboring communities and be disposed off taking the necessary precautions for general safety and health aspects of people.

Agreed. No adverse impact has been observed on the neighboring communities as muck including excavated material has been backfilled during construction with necessary precautions for general public health and safety

16) Diesel power generating sets used during construction phase should be of ‘’enclosed type’ to prevent noise and should conform to rules made under Environment (Protection) Act 1986,prescribed for Air and noise emission standards.

Agreed. We are using low sulphur diesel and all the DG sets are enclosed to prevent noise and conform to rules under Environment (Protection) Act 1986, prescribing Noise and Air emission standards. The Ambient Air and Noise Monitoring report is enclosed as Annexure - 2

17) Ambient noise levels should conform to standards both during day and night when measured at boundary wall of the premises.Incremental pollution load on the ambient air and noise quality should be closely monitored during construction phase.

Agreed. Ambient noise levels conform to the stipulated standards both during day and night time.

18) The construction agencies shall use flyash based material product as per the notification 0f 14.9.1999 and as amended on 27.08.2003.

Complied with

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

5

19) Vehicles hired for brining construction material at the site should be in good condition and should have valid “Pollution under check”(PUC) certificate and to conform to applicable air and noise emission standard and should be operated only during non peaking hour.

All the vehicles hired for bringing construction material at site are in good condition and checked for “pollution under control”(PUC) certificate.

20) Construction spoils, including bituminous materials and other hazardous materials must not be allowed to contamination watercourses and the dump site for such materials must be secured so that they should not leach into groundwater.

Construction spoils is being stored in a dedicated area duly bounded to avoid contamination to the environment in proximity. Storage area is covered by insulated lining to prevent contamination from hazardous materials like fuel of DG sets.

21) Any hazardous waste generated during construction phase should be disposed off as per applicable rules and norms with necessary approval of the State Pollution Control Board.

Hazardous material is being disposed as per norms.

22) Under the provision of Environment (Protection) Act 1986 legal action shall be initiated against the project proponent if it was found that the construction of the project had started without obtaining environmental clearance.

Construction activities for the project were initiated after the receipt of Environmental Clearance. EC letter is being enclosed as Annexure-.3

23) The diesel required for operating DG set shall be stored in underground tanks and if required clearance from the Chief controller of explosives shall be taken.

We will do the same.

24) The approval of competent authority shall be obtained for structural safety of the buildings due to earthquake, adequacy of fire fighting equipments etc. as per National Building Code including protection measures from lightening etc. If any forest land is involved in the proposed site, clearance under The Forest Conservation Act shall be taken from the competent Authority.

Agreed. We have designed the building as per NBC norms and taken utmost care for structural safety, fire fighting, lightening, etc

25) Regular supervision of the above and other measures for monitoring should be in place all through the construction phase so as to avoid disturbance to the surroundings.

We have been supervising the compliance of all conditions stipulated in the EC letter to ensure no/minimal disturbance to the surroundings.

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

6

II. Operation Phase

S. No

Conditions of Environmental Clearance Status of Compliance

i. Diesel power generating sets proposed as source of backup power for lifts, common area illumination and for domestic use should be of "enclosed type" and conform to rules made under The Environment (Protection) Act 1986. The location of DG Sets may be decided in consultation with State Pollution Control Board.

Agreed.

DG sets are enclosed type and conform to the rules made under the Environment (Protection) Act, 1986.

ii. Ambient noise levels should be controlled to ensure that it does not exceed the prescribed standards both within and at the boundary of the proposed complex.

Agreed.

Ambient noise levels have been/will be maintained as per prescribed standards.

iii. Weep holes in the compound walls shall be provided to ensure natural drainage of rainwater in the catchment area during the monsoon period.

Agreed.

iv. The STP shall be installed for group housing project for the treatment of sewage generated to the prescribed standards including odour and treated effluent will be re-cycled to the maximum extent possible. In case treated effluent is to be discharged separately during monsoon period consent of State Pollution Control Board shall be taken.

Agreed. STP of adequate capacity and efficiency will be provided to meet the prescribed standards for Sewerage treatment. Treated water will be used for gardening and DG cooling, etc.

v. Separation of gray and black water should be done by the use of duel plumbing line. Treatment of 100% gray water by decentralized treatment should be done.

Yes, we will use duel plumbing for the separation of grey and black wate.

vi. For disinfection of waste water ultra violet radiation shall be used in place of chlorination.

Agreed. For disinfection of water, we are using UV technology.

vii. Rainwater harvesting and ground water recharging shall be practiced. Oil & Grease trap shall be provided to remove oil and grease from the surface run off and suspended matter shall be removed in a settling tank before its utilization for rainwater harvesting.

We are practicing rain water harvesting for surface and roof run-off. Oil & Grease trap has been provided in the RWH pits and suspended matter is removed in the settling tank.

viii. The solid waste generated should be properly collected & segregated. Wet garbage should be sent for composting and dry/inert solid waste should be disposed off to approved sites for land filling after recovering recyclable material.

Agreed. Solid waste is being collected and segregated. We are following the practice prescribed under CPHEEO Manual for MSW.

ix. The open spaces inside the plot should be preferably landscaped and covered with vegetation of indigenous variety. Green belt of adequate width and density will be provided all around the periphery of the plot suitably with local species to

Agreed.

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

7

S. No

Conditions of Environmental Clearance Status of Compliance

reduce noise and dust level.

x. The ground water levels and its quality should be monitored regularly in consultation with Central Ground Water Authority.

Noted and we are/will doing/do the same.

xi. A Report on the energy conservation measures should be prepared incorporating details about building materials & technology, R & U Factors etc and submitted to the Ministry in three months time.

Agreed. Energy conservation report has been submitted to MoEF.

xii. The values of R & U for the building envelope should meet the requirements of the hot & humid climatic location. Details of the building envelope should be worked out and furnished in three months time.

The R & U values for the building envelope are meeting the requirements of hot & humid climatic locations. Details have been submitted earlier.

xiii. Energy conservation measures like installation of CFLs/TFLs for lighting the areas outside the building should be integral part of the project design and should be in place before project commissioning. Used CFLs & FLs should be properly collected and disposed of/sent for re-cycling as per the prevailing rules/outlines of the regulatory authority to avoid Mercury contamination. Use of solar panels may be done to the extent possible.

We are using CFLs/TFLs for lighting of common areas. Solar energy has been utilized for water heating and lighting purposes.

xiv. The buildings should have adequate distance between them to allow movement of fresh air and passage of light to the residential premises

We have ensured proper ventilation and daylight in the building as per NBC norms.

xv. Adequate measures should be taken to prevent odour problem from solid waste processing plant as also from the STP.

Agreed.

PART B – GENERAL CONDITIONS

S. No.

Conditions of Environmental Clearance Status of Compliance

i. The environmental safeguards contained in the documents should be implemented in letter and spirit.

Agreed.

ii. Provision should be made for the supply of kerosene or cooking gas and pressure cooker to the labourers during construction phase.

Yes we are doing the same.

iii. Six monthly monitoring reports should be submitted to the Ministry and its Regional Office.

We are/will regularly submit six monthly compliance reports with lab reports to Ministry and its Regional Office.

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

8

S. No.

Conditions of Environmental Clearance Status of Compliance

iv. Officials from the Regional Office of MOEF, Chandigarh who would be monitoring the implementation of environmental safeguards should be given full cooperation, facilities and documents/data by the project proponents during their inspection. A complete set of all the documents submitted to MoEF should be forwarded to the CCF, Regional office of MOEF, Chandigarh.

Agreed. We extend full cooperation to the Regional Office of MoEF during site inspection. Complete set of documents have been submitted to CCF, Regional office of MoEF, Chandigarh.

v. In the case of any change(s) in the scope of the project, the project would require a fresh appraisal by this Ministry.

Agreed.

vi. The Ministry reserves the right to modify/add additional environmental safeguard measures subsequently, if found necessary. Environment Clearance granted will be revoked if it is found that false information has been given for approval of the project.

Noted and agreed.

vii. Necessary permission shall be obtained from the State Fire Department for providing fire safety measures before allotment of premises for residential purpose in the township.

We have obtained all the due clearances (including Fire NOC) as applicable.

viii. These stipulations would be enforced among others under the provisions of the Water (Prevention and Control of Pollution) Act, 1974, the Air (Prevention and control of Pollution) act 1981, the Environment (Protection) Act, 1986 and the Public Liability (Insurance) Act, 1991.

Noted and agreed

ix. The project proponent shall enter in to MOU with all buyers of the property to ensure operation and maintenance of the STP and other assets of the township.

Noted and agreed.

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

9

DETAILS OF ENVIRONMENTAL MONITORING

3.0 Monitoring Snapshot

This report is prepared for the period of April 2015 to September 2015 as per EC

conditions. Post Environmental Clearance Monitoring was carried out during September

2015. The samples were analyzed at MoEF & CC and NABL approved Environmental

laboratory named Vardan Enviro Lab, Gurgaon. Following environmental components

has been monitored and analyzed.

1. Ambient Air Quality

2. Noise Quality

3. Water Quality

4. Soil Quality

3.1 AMBIENT AIR QUALITY MONITORING

3.1.1 Ambient Air Quality Monitoring Stations

Ambient air quality monitoring has been carried out at three locations, to assess the

ambient air quality of the project site. This will enable to have a comparative analytical

understanding about air quality and the changes in the air environment in the study

area with respect to the condition prevailing. The locations of the ambient air quality

monitoring stations are given in Table 3.1.

Table 3.1 Details of Ambient Air Quality Monitoring Stations

S. No. Location Location Name/ Description

Present Land use

1. AAQ1 Near Main Gate Residential

2. AAQ2 Centre of the Project Residential

3. AAQ3 Near Back Side Residential

3

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

10

AAQ-1: Near Main Gate

The sampler was placed near main gate of building and was free from any obstructions.

Surroundings of the sampling site represent residential environmental setting.

AAQ-2: Centre of the Project

The sampler was placed near Centre of the Project building and was free from any

obstructions. Surroundings of the sampling site represent residential environmental

setting.

AAQ-3: Near Back Side

The sampler was placed near back side of building and was free from any obstructions.

Surroundings of the sampling site represent residential environmental setting.

3.1.2 Ambient Air Quality Monitoring Methodology

Monitoring was conducted in respect of the following parameters:

Particulate Matter 2.5 (PM 2.5)

Particulate Matter 10 (PM 10)

Sulphur Dioxide (SO2)

Oxides of Nitrogen (NOx)

Carbon Monoxide (CO)

The duration of sampling of PM 2.5, PM10, SO2 and NOx were 8 hourly continuous

monitoring this is to allow a comparison with the National Ambient Air Quality

Standards.

The air samples were analyzed as per standard methods specified by Central Pollution

Control Board (CPCB) and IS: 5182. The techniques used for ambient air quality

monitoring and minimum detectable levels are given in Table 3.2.

Fine Particulate Sampler instruments have been used for monitoring Particulate Matter

2.5 (PM2.5 i.e. <2.5 microns), and Respirable Dust Sampler was used for sampling

Respirable fraction (<10 microns), gaseous pollutants like SO2, and NOx. Bladder and

Aspirator bags were used for collection Carbon monoxide samples. Gas Chromatography

techniques have been used for the estimation of CO.

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

11

Table 3.2 Techniques used for Ambient Air Quality Monitoring

S. No. Parameter Technique Technical Protocol

1 Particulate Matter 2.5 Fine Particulate Sampler, Gravimetric

Method

As Per CPCB

Guidelines.

2 Particulate Matter 10 Respirable Dust Sampler, with cyclone

separator, Gravimetric Method IS-5182 (Part-23)

3 Sulphur dioxide Modified West and Gaeke IS-5182 (Part- II)

4 Oxides of Nitrogen Jacob & Hochheiser IS-5182 (Part-VI)

5 Carbon Monoxide Gas Chromatography IS-5182 (Part-X)

3.1.3 Ambient Air Quality Monitoring Results

The detailed on-site monitoring results of PM 2.5, PM 10, SO2, NOx and CO are presented in

Table 3.3.

Table 3.3 Ambient Air Quality Monitoring Results

AAQ1 AAQ2 AAQ3 NAAQS*

Particulate Matter (PM2.5) 46.32 42.81 41.48 60

Particulate Matter(PM10) 88.62 80.25 78.36 100

Nitrogen Dioxide(NO2) 35.21 31.96

32.49 80

Sulphur Dioxide(SO2) 14.89 14.95 14.23 80

Carbon Monoxide(CO) 0.79 0.85 0.86 4

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

12

Figure 3.1 Location-wise Variation of Ambient Air Quality

Figure 3.2 Location-wise Variation of CO in Ambient Air Quality

0

10

20

30

40

50

60

70

80

90

100

AAQ1 AAQ2 AAQ3 LIMITS

(PM2.5) 46.32 42.81 41.48 60

(PM10) 88.62 80.25 78.36 100

(NO2) 35.21 31.96 32.49 80

(SO2) 14.89 14.95 14.23 80

0

0.5

1

1.5

2

2.5

3

3.5

4

AAQ1 AAQ2 AAQ3 LIMITS

(CO) 0.79 0.85 0.86 4

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

13

3.1.4 Discussion on Ambient Air Quality in the Study Area

PM10 and PM 2.5 levels at the project site are within the permissible limit of 100 μg/m3 and

60 μg/m3 respectively (for residential, rural and other areas as stipulated in the National

Ambient Air Quality Standards). SO2, NOx and CO was observed within the corresponding

stipulated limits (Limit for SO2 and NOx: 80 g/m3 and limit for CO: 4.0 mg/m3) at all

monitoring locations. Station wise variation of ambient air quality parameters has been

pictorially shown in Figure 3.1 and Figure 3.2.

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

14

3.2 AMBIENT NOISE MONITORING

3.2.1 Ambient Noise Monitoring Locations

The main objective of noise monitoring in the study area is to assess the present ambient

noise levels in near front gate due to various construction allied activities and increased

vehicular movement. A preliminary reconnaissance survey has been undertaken to

identify the major noise generating sources in the area. Ambient noise monitoring was

conducted at 3 locations at project site as given in Table 3.4.

Table 3.4 Details of Ambient Noise Monitoring Stations

S. No. Location Code Location Name/ Description Present Land use

1. N1 Near Main Gate Residential

2. N2 Centre of the Project Residential

3. N3 Near Backside of the Project Residential

3.2.2 Methodology of Noise Monitoring

Noise levels were measured using sound level meter. Noise level monitoring was carried

out continuously for 24-hours with one hour interval starting at 06:00 hrs to 06:00 hrs

next day. The noise levels were monitored on working days only. During each hour Leq

were directly computed by the instrument based on the sound pressure levels.

Monitoring was carried out at ‘A’ response and fast mode.

3.2.3 Ambient Noise Monitoring Results

The location wise ambient noise monitoring results is summarized in Table 3.5. The

location-wise variation of noise levels are graphically presented in Figure 3.3.

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

15

Table 3.5 Ambient Noise Monitoring Results

Location Code

N1 N2 N3

Day Time Night

Time Day Time Night Time Day Time Night Time

Lmax 63.50 51.60 61.60 50.80 62.40 51.20

Lmin 44.60 38.20 44.80 38.60 44.50 38.90

Leq 53.82 43.69 52.23 43.44 53.62 42.17

CPCB Limits in

dB(A) Leq

( Residential

area)

55.00 45.00 55.00 45.00 55.00 45.00

Figure 3.3 Location-wise Variation of Ambient Noise Levels

0

10

20

30

40

50

60

70

Day Time Night Time Day Time Night Time Day Time Night Time

N1 N2 N3

Lmax 63.5 51.6 61.6 50.8 62.4 51.2

Lmin 44.6 38.2 44.8 38.6 44.5 38.9

Leq 53.82 43.69 52.23 43.44 53.62 42.17

Limits 55 45 55 45 55 45

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

16

3.2.4 Discussion on Ambient Noise Levels in the Study Area

Day Time Noise Levels (Lday):

The day time noise level at all the locations were found to within limits prescribed for

residential area i.e. 55 dB (A).

Night Time Noise Levels (Lnight):

The night time noise level at all the locations were found to within limit prescribed for

residential area i.e. 45 dB (A).

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

17

3.3 Drinking WATER QUALITY MONITORING

3.3.1 Drinking Water Quality Monitoring Locations

Keeping in view the importance of water as an important source of drinking water to the

local population, sample of Drinking water was collected from the project site for the

assessment of impacts of the project on the drinking water quality.

Water sample was collected from the project site. The sample was analyzed for various

parameters to compare with the standards for drinking water as per IS: 10500 for ground

water sources. The details of water sampling locations are given in Table 3.6.

Table3.6 Details of Water Quality Monitoring Station

S. No. Location Code Location Name/ Description

1. DW 1

Near Project Site

3.3.2 Methodology of Drinking water Quality Monitoring

Sampling of drinking water was carried out on September 2015. Samples were collected

as grab sample and sampling forms are filled in as per the sampling plan. The preservative

sample were properly added to preserve as per standard operating procedures (SOP) and

stored immediately in ice boxes, which were ensured for appropriate temperatures.

Sample for chemical analysis was collected in polyethylene carboys. Sample collected for

metal content were acidified to <2 pH with 1 ml HNO3. A sample for bacteriological

analysis was collected in sterilized glass bottles.

Soon after the completion of sampling, chain of custody sheets for the samples are filled in

and then they were transported by road to Vardan Enviro Lab, Gurgaon for further

analysis. Proper care was taken during packing and transportation of samples. All the

samples reached the central laboratory within the holding times for different parameters.

After ensuring the same the samples were forwarded immediately for analysis.

The samples were analyzed as per the standard procedures specified in 'Standard

Methods for the Examination of Water and Wastewater' published by American Public

Health Association (APHA) and CPCB. The analytical techniques and the test methods

adopted for testing of drinking water are given in Table 3.7.

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

18

3.3.3 Drinking Water Quality Monitoring Results

The detailed water quality monitoring results are presented in Table 3.7.

Table 3.7 Drinking water Quality Monitoring Result

S.

No. Parameter Test-Method Result Unit

Limits of IS:10500 -

2012

Desirabl

e limit

(Max.)

Permissible

limit in the

Absence of

Alternate

Source

(Max.)

1. pH (at 25 0C) APHA 22nd Edition, 4500-H+

B

7.13 -- 6.5 to 8.5 No Relaxation

2. Colour APHA 22nd Edition, 2120 B BDL (DL 5Hazen) Hazen 5 15

3. Turbidity APHA 22nd Edition, 2130 B BDL (DL 1 NTU) NTU 1 5

4. Odour APHA 22nd Edition, 2150 B Agreeable -- Agreeable Agreeable

5. Taste APHA 22nd Edition, 2160 B Agreeable -- Agreeable Agreeable

6. Total Hardness as CaCO3 APHA 22nd Edition, 2340 C 61.35 mg/l 200 600

7. Calcium as Ca APHA 22nd Edition, 3500 Ca

B

14.98 mg/l 75 200

8. Alkalinity as CaCO3 APHA 22nd Edition, 2320 B 44.38

mg/l 200 600

9. Chloride as Cl APHA 22nd Edition, 4500-Cl-

B

22.96

mg/l 250 1000

10. Cyanide as CN APHA 22nd Edition, 4500

CN- D

BDL(DL 0.02

mg/l)

mg/l 0.05 No Relaxation

11. Magnesium as Mg APHA 22nd Edition, 2340 B 5.82 mg/l 30 100

12. Total Dissolved Solids APHA 22nd Edition, 2540 C 90.44 mg/l 500 2000

13. Sulphate as SO4 APHA 22nd Edition, 4500 E 4.98 mg/l 200 400

14. Fluoride as F APHA 22nd Edition, 4500-F- D 0.23 mg/l 1.0 1.5

15. Nitrate as NO3 IS 3025 (P-34) 1988 0.83 mg/l 45 No Relaxation

16. Iron as Fe APHA 22nd Edition, 3500-Fe

B

0.12 mg/l 0.3 No relaxation

17. Aluminium as Al APHA 22nd Edition, 3111 B BDL(DL 0.03

mg/l)

mg/l 0.03 0.2

18. Boron APHA 22nd Edition, 4500B C BDL(DL 0.1 mg/l) mg/l 0.5 1

19. Hexa Chromium as Cr+6 APHA 22nd Edition, 3111 B BDL(DL 0.01

mg/l)

mg/l 0.05 No Relaxation

20. Phenolic Compounds APHA 22nd Edition, 5530 C BDL(DL 0.001

mg/l)

mg/l 0.001 0.002

21. Mineral Oil Clause 6 of IS:3025(Part 39) BDL(DL

0.01mg/l)

mg/l 0.5 No Relaxation

22. Anionic Detergents as MBAS APHA 22nd Edition, 5540 C BDL(DL 0.02

mg/l)

mg/l 0.2 1.0

23. Zinc as Zn APHA 22nd Edition, 3111 B BDL(DL 0.02

mg/l)

mg/l 5 15

24. Copper as Cu APHA 22nd Edition, 3111 B BDL(DL 0.02

mg/l)

mg/l 0.05 1.5

25. Manganese as Mn APHA 22nd Edition, 3111 B BDL(DL 0.10

mg/l)

mg/l 0.1 0.3

26. Cadmium as Cd APHA 22nd Edition, 3111 B BDL(DL

0.001mg/l)

mg/l 0.003 No Relaxation

27. Lead as Pb APHA 22nd Edition, 3111 B BDL(DL0.01mg

/l)

mg/l 0.01 No Relaxation

28. Selenium as Se APHA 22nd Edition, 3111 B BDL(DL 0.01

mg/l)

mg/l 0.01 No Relaxation

29. Arsenic as As APHA 22nd Edition, 3111 B BDL(DL 0.01

mg/l)

mg/l 0.01 No Relaxation

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

19

30. Mercury as Hg APHA 22nd Edition, 3111 B BDL (DL 0.001

mg/l)

mg/l 0.001 No Relaxation

31. Total Coliform IS 1622,1981(Reaffirmed

2003)

Absent MPN/100ml - 10.00

32. E. Coli IS 1622,1981(Reaffirmed

2003)

Absent MPN/100ml Absent Absent

3.3.4 Discussion on water Quality in the Study Area

The water quality in the project area is observed to neutral in nature with total alkalinity

reaching up to 44.38 mg/L against desirable limit of 200 mg/L, however, alkalinity is less

than the permissible limit of 600 mg/L. Total dissolved solids in the ground water is 90.44

mg/L which is lower than prescribed limit of 500 mg/L. However, remaining parameters

are within the CPCB prescribed limits. Arsenic and mercury which are considered to be

the very risky contaminants were found within the permissible limit too. The

microbiological contaminants (E. Coli and Total Coli form) are absent in water sample

taken from the project site.

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

20

3.4 SOIL MONITORING

3.4.1 Soil Monitoring Locations

The objective of the soil monitoring is to identify the impacts of ongoing project

activities on soil quality and also predict impacts, which have arisen due to execution of

various constructions allied activities. Accordingly, a study of assessment of the soil

quality has been carried out

To assess impacts of ongoing project activities on the soil in the area, the physico-

chemical characteristics of soils were examined by obtaining soil samples from selected

points and analysis of the same. Single sample of soil was collected from the project site

for studying soil characteristics, the location of which is listed in Table 3.8.

Table 3.8 Details of Soil Quality Monitoring Location

S. No. Location Code

Location Name/ Description

1. S1

Project Site

3.4.2 Methodology of Soil Monitoring

The sampling has been done in line with IS: 2720 & Methods of Soil Analysis, Part-1, 2nd

edition, 1986 of American Society for Agronomy and Soil Science Society of America. The

homogenized samples were analyzed for physical and chemical characteristics (physical,

chemical and heavy metal concentrations). The soil samples were collected in the month

of September 2015.

The samples have been analyzed as per the established scientific methods for physico-

chemical parameters. The heavy metals have been analyzed by using Atomic Absorption

Spectro-photometer.

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

21

3.4.3 Soil Monitoring Results

Single sample of soil is collected from the site to check the quality of soil of the study

area .The physico-chemical characteristics of the soil, as obtained from the analysis of

the soil sample, are presented in Table 3.9.

Table 3.9 Physico-Chemical Characteristics of Soil in the Study Area

3.4.4 Discussion on Soil Characteristics in the Study Area

The soil in study area is characterized by moderate organic content. The soil quality in

the project area has not been affected by the project activities.

S. No. Parameter Protocol Result Unit

1. pH (at 25 0C) IS : 2720 (P-26,1987) 7.32 --

2. Conductivity IS:14767-2000 Reaffirmed 2006 0.51 mS/cm

3. Soil Texture USDA Method, 1968 Silty --

4. Color USDA Method, 1968 Yellowish brown --

5. Water holding capacity USDA Method, 1968 26.35 %

6. Bulk density USDA Method, 1968 1.52 gm/cc

7. Chloride as Cl USDA Method, 1968 25.99 mg/100gm

8. Calcium as Ca USDA Method, 1968 9.65 mg/100gm

9. Sodium as Na USDA Method, 1968 11.30 mg/100gm

10. Potassium as K USDA Method, 1968 82.34 kg/hec.

11. Organic Matter IS:2720 (P-22, 1972) 0.57 %

12. Magnesium as Mg USDA Method, 1968 7.38 mg/100gm

13. Available Nitrogen as N IS:14684, 1999 239.54 kg./hec.

14. Available Phosphorus USDA, APHA-4500PC 31.33 kg./hec.

15. Zinc as Zn APHA-3030D, APHA-3111B 3.85 mg/100gm

16. Manganese as Mn APHA-3030D, APHA-3111B 4.96 mg/100gm

17. Chromium as Cr APHA-3030D, APHA-3111B 0.52 mg/100gm

18. Lead as Pb APHA-3030D, APHA-3111B 0.93 mg/100gm

19. Cadmium as Cd APHA-3030D, APHA-3111B 1.33 mg/100gm

20. Copper as Cu APHA-3030D, APHA-3111B 2.26 mg/100gm

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

22

Project Site

Project :M/s SRS Real Infrastructure Ltd., Group Housing Project, East End Heights Sector-5, Palwal, Faridabad (HR). EC No. 21-614/2007/IA III Dated 1/10/2008

Vardan Enviro Net, D-142, SushantLok-lll, Golf Course Road, Sector 57, Gurgaon E-mail: [email protected], [email protected]

23

Ambient air and noise monitoring