    Mapping of Construction Project Life Cycle and PMBOK

    Project

    DeliverySystem,

    Contract

    System

    The Brief, Identification

    of alternatives, SiteInvestigation, Public

    Input, Code Analysis,

    Preliminary Cost

    Estimate, Financial

    Feasibility Analysis,

    Funding, Site Selection

    and Land Acquition

    Schematic

    Design

    Detail

    Design

    Legal/Contract

    Issue, Planning &Scheduling,

    Budgeting and Cost

    System, Organizing

    of Worksite,

    Subkontraktor,

    Project Organization

    Project

    Monitoring &Control, Safety

    Management,

    Material

    Management,

    Documentation

    and

    Communication

    Project Charter

    Scope Management

    Procurement

    Management

    Scope Management

    Time Management

    Cost Management

    HR Management

    Risk Management

    Earn Value

    Performance

    Report

    PMBOK

    Side

  • 8/14/2019 Project Monitoring.ppt

    3/24

    3

    P appingKnowledge Area &

    ProcessesInitiating Planning Executing

    Monitoring &Controlling

    Closing

    4. Project IntegrationManagement

    4.1 Develop ProjectCharter

    4.2 Develop Project Management Plan4,3 Direct & Manage ProjectExecution

    4.4 Monitor & ControlProject Work

    4.5 Perform IntegratedChange Control

    4.6 CloseProject orPhase

    5. Project ScopeManagement

    5.1 Collect Requirements5.2 Define Scope

    5.3 Create WBS

    5.4 Verify Scope

    5.5 Control Scope

    6.Project TimeManagement

    6.1 Define Activities

    6.2 Sequence Activities

    6.3 Estimate Activity Resources

    6.4 Estimate Activity Duration

    6.5 Develop Schedule

    6.6 Control Schedule

    7. Project CostManagement

    7.1 Estimate Costs

    7.2 Determine Budget7.3 Control Cost

    8. Project QualityManagement

    8.1 Plan Quality 8.2 Perform Quality Assurance8.3 Perform QualityControl

    9. Project HRManagement

    9.1 Develop HR Planning

    9.2 Acquire Project Team

    9.3 Develop Project Team

    9.4 Manage Project Team

    10. ProjectCommunication Mgt

    10.1 IdentifyStakeholder

    10.2 Plan Communication

    10.3 Distribute Information

    10.4 Manage StakeholderExpectation

    10.5 ReportPerformance

    11. Project RiskManagement

    11.1 Plan Risk Management11.2 Identify Risk

    11.3 Perform Qualitative Risk Analysis

    11.4 Perform Quantitative Risk Analysis

    11.5 Plan Risk Responses

    11.6 Monitor andControl Risk

    12. ProjectProcurement Mgt.

    12.1 Plan Procurement 12.2 Conduct Procurement12.3 AdministerProcurement

    12.4 CloseProcurement

    3

  • 8/14/2019 Project Monitoring.ppt

    4/24

    Overview V.3.0 4

    Pengendalian Waktu danBiaya Proyek

    Copyright 2009 - ESH

  • 8/14/2019 Project Monitoring.ppt

    5/24

    5

    Biaya Proyek

    Biaya Proyek merupakan total biaya yangdiperlukan untk menyelesaikan proyek

    Biaya Proyek disusun dari biaya-biaya aktifitas

    proyek

    Menyusun biaya proyek Determine Budget

    Menghitung biaya aktifitas proyek Estimate

    Cost

  • 8/14/2019 Project Monitoring.ppt

    6/24

    6

    Pembuatan Budget Proyek (Cost Baseline)

    Estimasi Biaya PerAktifitas

    Menyusun Total

    Biaya Proyek

  • 8/14/2019 Project Monitoring.ppt

    7/24

    7

    Teknik Determine Budget

    Metode Analogous

    Metoda Parametrik

    Metoda Bottom Up, dengan menggabungkan

    biaya per aktivitas (Estimate Cost). TeknikEstimate Cost didasarkan atas sumber daya(resource based) : Tentukan Sumberdaya aktifitas (resource)

    Material, Tenaga Kerja, Peralatan, dll Hitung biaya sumberdayanya

    Hitung biaya aktifitasnya

  • 8/14/2019 Project Monitoring.ppt

    8/24

    8

    Membuat Schedule Barchart

    Buat Network Planning

    Hitung Earliest Time dan Latest Time denganCPM (Critical Path Method)

    Buat Barchart dengan Start-Finish Aktifitasmenggunakan Earliest Time

  • 8/14/2019 Project Monitoring.ppt

    9/24

    9

    Cost Baseline

    Suatu budget proyek yang didistribusikan selamamasa proyek sesuai schedule yang sudah dibuat

  • 8/14/2019 Project Monitoring.ppt

    10/24

    10

    Cost Baseline (Sample)

  • 8/14/2019 Project Monitoring.ppt

    11/24

    11

    Forward calculation

    Backward calculation

    A10

    2 hari

    A20

    3 hari

    A40

    4 hari

    A30

    1 hari

    A50

    2 hari

    A60

    5 hari

    1 2

    3 6

    3 5 6 6

    7 8

    9 13

    9

    7 9 13

    8 8

    3 6 7 8

    5 7

    1 2

    8

    84

    2

    Network Planning (Perhitungan Jalur Kritis)

  • 8/14/2019 Project Monitoring.ppt

    12/24

    12

    BAR CHART

    ACTIVITY PRE DEC ES OR TIME

    (DAY)

    D E P E N D E N C Y

    , LAGS

    R E S . R E Q .

    P E R D A Y

    R E S .

    C O S T

    TOTAL

    C O S T

    1 2 3 4 5 6 7 8 9 10 11 12 13

    A10 - 2 F S , 0 4 50 400 200 200

    A20 A10 3 F S , 0 2 50 300 100 100 100

    A30 A20 1 F S , 0 2 50 100 100

    A40 A10 4 F S , 0 3 50 600 150 150 150 150

    A50 A40 2 F S , 0 1 50 100 50 50

    A60 A30, A50 5 F S , 0 2 50 500 100 100 100 100 10

    2000 200 200 250 250 250 250 50 50 100 100 100 100 1

    CUM.EX 200 400 650 900 1150 1400 1450 1500 1600 1700 1800 1900 20

    R E . R E Q 4 4 5 5 5 5 1 1 2 2 2 2

  • 8/14/2019 Project Monitoring.ppt

    13/24

    13

    Cost Baseline (Sample)

  • 8/14/2019 Project Monitoring.ppt

    14/24

    14

    The earned value technique in its various forms is acommonly used method of performance measurement

    It integrates project scope, cost, and schedulemeasures to help the project management team assessproject performance

    The EVM methodology integrates scope, schedule, and

    resources, to objectively measure projectperformance and progress

    Earn Value Measurement (EVM)

    14

  • 8/14/2019 Project Monitoring.ppt

    15/24

    15

    EVM Parameters

    PLAN ACTUAL

    PV(Planned value)

    EV(Earn Value)

    AC(Actual Cost)

    Planned Valuethe authorized budget assigned to the schedule work to

    be accomplished for a schedule activity or work breakdown structurecomponent

    Earn Valueis the value of work performed expressed in terms of theapproved budget assigned to that work for a schedule activity or workbreakdown structure component

    Actual Costis the total cost actually incurred and recorded inaccomplishing work performed for a schedule activity or workbreakdown structure component

    15

  • 8/14/2019 Project Monitoring.ppt

    16/24

    16

    VARIANCE INDICATOR :

    Cost Variance (CV) = EV-AC Schedule Variance (SV) = EV-PV

    INDEX INDICATOR :

    Cost Performance Index (CPI) = EV/AC Schedule Performance Index (SPI) = EV/PV

    CV0 :?, CPI1 :?SV0 :? , SPI1 :?

    EVM Indicators

    16

  • 8/14/2019 Project Monitoring.ppt

    17/24

    17

    S-Curve

    Planned Value

    CumulativeValue

    Time

    Actual Cost

    Earned Value

    Cost Variance

    Schedule Variance

    Budget at

    Completion

    (BAC)

    Data Date

    17

  • 8/14/2019 Project Monitoring.ppt

    18/24

    18

    Sample case:

    A A A A A

    B B B B

    C

    D

    C C

    D

    E

    Period

    S Curve

    AccumulativeCost (Schedule)

    1 2 3 4 5

    $ 10

    Development 5 modules: A, B, C, D, E

    Modules will be produced per period

    Cost per module = $ 10

    $ 20 $ 30 $ 40 $ 50

    EVM Calculation (1/3)

    18

  • 8/14/2019 Project Monitoring.ppt

    19/24

    19

    EVM Calculation (2/3) Condition case 1:

    AccumulativeCost (Sched)

    A A A

    B B

    C

    Period

    PV

    1 2 3 4 5$ 10

    In 3 rd period: $ 40 isexpended

    Module completion:A=100%, B= 100%, C= 100%,

    D=100%, E=50%

    $ 20 $ 30 $ 40 $ 50

    Cost (Act)

    Value(performed)

    $ 10 $ 20 $ 40

    $ 10 $ 20 $ 45

    AC

    PV

    EV

    D

    E

    EV

    AC

    19

  • 8/14/2019 Project Monitoring.ppt

    20/24

    20

    EVM Calculation (3/3)

    Condition case 2:

    AccumulativeCost (Sched)

    A A A

    B B

    C

    Period

    1 2 3 4 5

    $ 10

    In 3 rd period: $ 30 isexpended

    Module completion:A=100%, B= 100%, C= 50%,

    D=0%, E=0%

    $ 20 $ 30 $ 40 $ 50

    Cost (Act)

    Value(performed)

    $ 10 $ 20 $ 30

    $ 10 $ 20 $ 25

    AC

    PV

    EV

    EV

    AC

    20

  • 8/14/2019 Project Monitoring.ppt

    21/24

    Overview V.3.0 21

    Project Forecasting

  • 8/14/2019 Project Monitoring.ppt

    22/24

    22

    Project Forecasting

    Parameter untuk melakukan project ForecastingEstimate At Completion (EAC)

    EAC : meramalkan berapa total biaya proyek

    pada saat akhir proyek untuk kondisi statusproject tertentu (saat ini)

  • 8/14/2019 Project Monitoring.ppt

    23/24

    23

    S-Curve

    Planned Value

    Cumulat

    iveValue

    Time

    Actual Cost

    Earned Value

    Cost Variance

    Schedule Variance

    Budget at

    Completion

    (BAC)

    Data Date

    23

  • 8/14/2019 Project Monitoring.ppt

    24/24

    24

    Alternative 1 :EAC = Actual + Remaining Budget = AC + (BAC EV)Use when current variances are thought to be atypical of the future

    Alternative 2 :EAC = Actual + Remaining Budget/CPI = AC + (BAC EV) / CPIUse when current variances are thought to be typical of the future

    Alternative 3 :EAC = Actual + Remaining/CPI/SPIWorst case scenario

    Alternative 4:EAC = BAC / CPI

    Used when if no variances from the BAC have occurred orwill continue at the same rate of spending

    Alternative 5:EAC = Actual + New Estimate for Remaining Budget = AC + ETCUse when original estimate was fundamentally flawed

    Estimate at Completion (EAC)

    24