Project Mgt and Life Cycle

29
 Project Management and Life Cycle

Transcript of Project Mgt and Life Cycle

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 1/29

 

Project Management

and Life Cycle

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 2/29

The Two End Points in a Project

Inspiration

Operation

A miracle occurs

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 3/29

Some consider planning to be

miraculous

• Why do planning?

 – Time constraints

 – Budget constraints

 – Personnel constraints – Physical Constraints

 – Flight Constraints

 – Any and all of above

• Provides structure to “think the problem through”

increasing likelihood of project success

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 4/29

Purpose of Project Management• Ensure meeting the project objectives within the

allocated schedule & budget

 – Communication

 – Meetings

 – Reviews

 – Authorization

 – Record Keeping

 – Monitoring (testing)

 – Interface Control

• Not for assigning blame (usually)

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 5/29

Example Management FlowACES Program

Team Lead

Science Lead Payload Lead Business Lead

GroundSoftware

DataAnalysis

Results

Procurement

Accounting

SciencePayload

Flight Segment

InterfaceControl

MissionOps

SpacecraftIntegration

FlightSoftware

Integration &Testing

InterfaceControl

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 6/29

The Project Life Cycle

• Phases that all projects go through from inceptionto completion

DESIGN

DEVELOPMENT

FABRICATION

INTEGRATION

TESTING

OPERATION

PDR

CDR

FRR

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 7/29

The Design Phase

• “Paper” study of all issues including the following: 

 – Define Objectives

 –

Understand Constraints – Identify all subsystems & interfaces

 – Design hardware

 – Identify parts, costs & availability

 – Determine personnel needs

 – Establish schedule

 – Develop plan to achieve objectives

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 8/29

Preliminary Design Review (PDR)

• Organized by the ACES Program

• Results from your design phase

Should show that you have “thought theproblem through” 

• Include written report and oral presentation

PDR reviews will occur on Feb. 27, 2003• More on PDR next week

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 9/29

The Development Phase

• Detailed in-depth study including

 – Test hardware concepts by prototyping

 – Finalize designs

 – Purchase long lead items (identified at PDR) – Establish interface controls

 – Complete fabrication plan

 –

Finish integration & test plans – Complete operations & data analysis plans

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 10/29

Critical Design Review

(CDR)

• Organized by the ACES Program

• Results from your development phase

Determines whether you are ready to beginbuilding your payload

• Include written report and oral presentation

Precise date should be identified during PDR

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 11/29

Payload Construction Phases

• Parts procurement

• Fabrication

 – Construct subsystems, test, fix, retest

• Integration

 – Assemble subsystems, test, fix, retest

Testing – Payload qualification testing, fix, retest

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 12/29

Flight Readiness Review

(FRR)

• Organized by the ACES Program

• Results from your construction phase

 – Particularly qualification testing

• Determines whether you are ready to

participate in launch operations

Include written report and oral presentation• FRR will occur on May 1, 2003

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 13/29

Operations & Analysis

• Interface with launch team

• Prepare payload for launch

Monitor during flight• Collect & analyze data

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 14/29

Program Schedule Constraint

Design 1/21 – 2/26

PDR 2/27

Development 2/28 – 3/26

CDR 3/27 (flexible)

Construction, Integration,

Testing

3/28 – 4/30

FRR 5/1

Operations 5/18 – 5/22

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 15/29

Other Project Constraints

• Budget Constraint

 – $500 per team

• Personnel Constraint

 –

3 members per team• Physical Constraint

 – Weight 1 kilogram

 – 10 cm x 10 cm x 10 cm or “Coke can” size 

• Flight Constraints – Shock, Thermal, Duration, Altitude

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 16/29

LSU 01/18/2005 Project Life Cycle 16

The Project Phases

All projects complete roughly the same phases from inceptionto completion

OPERATION

DESIGN PDR

DEVELOPMENT CDR

FABRICATION

INTEGRATION

TESTINGFRR

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 17/29

LSU 01/18/2005 Project Life Cycle 17

The Design Phase

• Little to no hardware testing or prototyping

• Define science goals and objectives

• System level design (subject of Lecture 3)

 –

System requirements derived from goals and objectives – Identify major subsystems and interfaces

• Concept hardware and software design – Derived from system requirements and constraints

 – Identify parts, costs & availability

• Establish tasks, schedule, resource needs and plans forremaining phases of life-cycle

• Develop preliminary risk assessment & management plan

• Phase terminates with Preliminary Design Review (PDR)

“Paper” study of all issues to establish major concepts and plans  

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 18/29

LSU 01/18/2005 Project Life Cycle 18

The Development Phase - 1

• Test concepts by prototyping

 – Not building flight hardware

 – Used to gain information necessary to refine or

finalize a design

 – Applies to structure, electronics, sensors and

software

• Finalize hardware & software design

 –

Complete system design – Define interfaces and develop appropriate Interface

Control Documents (ICD)

 – Complete detailed design

Design

Prototype

Test

Complete

Design

Detailed in-depth study when all design components are finalized

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 19/29

LSU 01/18/2005 Project Life Cycle 19

The Development Phase - 2

Purchase long lead items (identified at PDR)• Finalize plans for pre-flight phases

 – Fabrication, integration, calibration and testing

 – Tasks, schedule, procedures, resource needs, costs

• Update risk assessment & management plan

 – Preliminary plan should already be in use for tracking and

mitigating risks during development

Develop preliminary mission operations & dataanalysis plan

• Phase terminate with Critical Design Review (CDR)

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 20/29

LSU 01/18/2005 Project Life Cycle 20

The Fabrication Phase

Training

Integration

Thermal Test

QA / QC Assembly

Order Parts

Inspect/Test

• Parts procurement

 – Test that parts satisfy flight

requirements before assembly

• Assemble hardware & software subsystems – Training may be required for particular assemblies

 – Fabricate component with qualified parts

 – If part fails initial inspection and testing, return to

assembly for rework / fixing

 – If part fails thermal testing return to assembly for

rework / fixing

• Once complete move to integration

Implement construction of flight components

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 21/29

LSU 01/18/2005 Project Life Cycle 21

The Integration Phase

• Make sure all parts fit together, if not

then rework

• Make sure power system is delivering

proper voltage and current

• Connect electronics and sensors

• Install software and run

• Fix issues before proceeding to system

testing

Fit Check

System

Testing

Integrate Fix

Test

Subassemblies are put together to make the finalpackage

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 22/29

LSU 01/18/2005 Project Life Cycle 22

The System Testing Phase

Payload flight certification

Functional

Test

FRR

Fix

Calibration

Thermal Test

Pressure Test

Shock Test

Check

Calibration

• Integrated payload must first be fully functional

• Calibration values are determined

 – Sensors, ADC gain, timing

• Payload must function correctly during

thermal, pressure & shock testing – If not, fix and begin again

 – If OK, then validate calibrations

• Test and test data must be documented

• Proceed to Flight Readiness Review 

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 23/29

LSU 01/18/2005 Project Life Cycle 23

Mission Operations & Data Analysis

(MO&DA)

• Mission Operations plan includes the following

 – Sequence of operations to prepare payload for vehicle integration

 – Sequence of operations to prepare payload for launch

 – Flight profile requirements

 – Operations, commanding, contingencies during flight

 – Recovery handling and operations

• Data Analysis plan describes what happens to the flight

data – Flight data handling, processing and analysis sequence

 – Specify data required from vehicle

Operate payload during flight & obtain scienceresults

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 24/29

LSU 01/18/2005 Project Life Cycle 24

Process Flow During Life Cycle

• Effort focus changes as a function of phase – Design can be highly theoretical involving simulations and

calculations

 – Development involves “experiments” and testing concepts to gaininformation necessary for the design

 – Fabrication, Integration, and System testing requires skilledtechnical help to realize the design in hardware and software

 – MO&DA requires “scientists” to direct the proper use of thepayload and to turn the data into science results

• Resource needs and costs changes as a function of phase

 – Design requires no hardware and few personnel

 – Development costs increase a bit with some prototyping

 – Major cost in personnel and hardware is in fabrication, integrationand testing

 – MO&DA drops down to no hardware and few personnel

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 25/29

LSU 01/18/2005 Project Life Cycle 25

Project Risk Management

“The essence of project management is risk management” 

• Probability of a disaster decreases during the life of a project

• Cost to recover from a problem increases during the project

Catch & correct problems early!

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 26/29

LSU 01/18/2005 Project Life Cycle 26

Project Milestones

There are three major reviews during the project• Preliminary Design Review (PDR)

 – Follows design phase

• Critical Design Review (CDR)

 – Follows development phase

• Flight Readiness Review (FRR)

 – Prior to flight

• The team must prepare written documents andoral presentations for each review

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 27/29

LSU 01/18/2005 Project Life Cycle 27

Preliminary Design Review (PDR)

The PDR should cover results from your design phaseincluding:

 – Goals & objectives

 – Preliminary System design

 – Concept hardware & software design

 – Tasks, schedule, resource needs, long-lead items

 – Preliminary risk assessment & management plan

• Should show that you have “thought the problem

through” 

• Include written document and oral presentation

 – Format of document will be discussed in Lecture 8

• A member of the LA ACES Project will attend and

participate in the PDR

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 28/29

LSU 01/18/2005 Project Life Cycle 28

Critical Design Review (CDR)

The CDR should cover results from your developmentphase including:

 – Resolving issues identified during the PDR

 – Prototyping results and “proven” designs 

 – Completed system design and defined interfaces

 – Finalize tasks, schedule, procedures and costs

 – Updated risk assessment & management plan

 – Preliminary MO & DA plan

• Determines whether you are ready to begin building your

payload• Include written report and oral presentation

• Precise date for CDR should be identified during PDR

8/2/2019 Project Mgt and Life Cycle

http://slidepdf.com/reader/full/project-mgt-and-life-cycle 29/29

LSU 01/18/2005 Project Life Cycle 29

Flight Readiness Review (FRR)

The FRR reviews all aspects of your payload – Documentation of as-built configuration

 – Is payload safe?

 – Will payload perform properly?

 – Does payload satisfy the flight constraints?

• The FRR will determine whether you are allowed to attachyour payload to the flight vehicle!

• Written FRR document sent to LA ACES Project 2 weeksbefore flight

Oral FRR presentation during the launch trip• Details about what is expected during the FRR are

provided in Ballooning Unit, Lecture 5