3. project charter, check sheet, pareto analysis & c&e diagram & matrix
Project ManagementDay 3 in the am Project Management (PM) CHECK.
-
Upload
arlene-bond -
Category
Documents
-
view
220 -
download
3
Transcript of Project ManagementDay 3 in the am Project Management (PM) CHECK.
Day 3 in the am # 5 / 24Project Management Cook
Earned Value Analysis
EVA is a performance measurement technique that integrates scope, time, and cost data
Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals
You must enter actual information periodically to use EVA
Day 3 in the am # 6 / 24Project Management Cook
EVA Terminology
Budgeted cost of work scheduled (BCWS) is the portion of the approved cost estimate planned to be spent on an activity during a given period
Actual cost of work performed (ACWP) is the total of the direct and indirect costs incurred in doing the work on an activity during a given period
Budgeted cost of work performed (BCWP), also called earned value, is the percentage of work actually completed multiplied by the cost (BCWS)
Day 3 in the am # 8 / 24Project Management Cook
Deriving EVA Metrics
Weeks Elapsed = WE = ((actual task beginning) – (report date)) / 7
Weeks Performed = WP = WE * (SD)/(ED) (note: “D” is for duration) Where: SD = ((scheduled project beginning) - (scheduled completion)) / 7 ED = ((actual project beginning) - (expected completion)) / 7
Budgeted Cost of Work Scheduled = BCWS = BCF(1) + … BCF (WE) Where: BCF = Budgeted Cash Flow and ACF = Actual Cash Flow
Budgeted Cost of Work Performed = BCWP = BCF(1) + … BCF (WP)
Schedule Variance = BCWP - BCWS (measured in $, not time)
Actual Cost of Work Performed = ACWP = ACF(1) + … ACF(WE)
Spend Comparison = BCWS – ACWP (commonly reported)
Cost Performance Index = BCWP / ACWP (>1 is good)
Budgeted Performance Index = BCWP / BCWS (>1 is good)
Day 3 in the am # 9 / 24Project Management Cook
1. Expected Completion 200__.____.____ (95% confidence)
2. Δ Actual Cost (in-house) ____ , _____ RMB (+ => expense)3. Δ Actual Cost (contracted) ____ , _____ RMB (+ => overrun)4. Δ Actual Cost (purchases) ____ , _____ RMB (- => refund)5. Δ Quality Issues? ___ (if “N”, then quality is presumed excellent)6. Δ Subcontracting Issues? ___ (if “Y”, attach explanation)7. Δ Resource Issues? (Staff, Material, Equipment) ___ , ___ , ___8. Δ Integration/Dependency Issues? ___ 9. Δ Catastrophe Possibility? ___10. Δ Other Issues? ___ (Scope, surprise, opportunity, infrastructure, …)11. Δ Notices (vacations, emergencies, changes, conntact, …): _______ _____________________________________________
Weekly Task Report (by WBS)
Day 3 in the am # 10 / 24Project Management Cook
EVA Trend Analysis
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
1 2 3 4 5 6 7 8 9 10 11 12
Month
$
BCWS or Cumulative Plan ACWP or Cumulative Actual BCWP or Cumulative EV
BCWS
ACWP
BWCP
BAC
Day 3 in the am # 11 / 24Project Management Cook
1. Expected Completion 20__.____.____ (95% confidence)
2. Δ Actual Cost (in-house) ____ , _____ RMB (+ => expense)3. Δ Actual Cost (contracted) ____ , _____ RMB (+ => acceptance)4. Δ Actual Cost (purchases) ____ , _____ RMB (- => refund)5. Δ Quality Issues? ___ (if “N”, then quality is presumed excellent)6. Δ Contracting Issues? ___ (if “Y”, attach explanation)7. Δ Resource Issues? (Staff, Material, Equipment) ___ , ___ , ___8. Δ Integration/Dependency Issues? ___ 9. Δ Catastrophe Possibility? ___10. Δ Other Issues? ___ (Scope, surprise, opportunity, infrastructure, …)11. Δ Notices (vacations, emergencies, changes, contact, …): ________ _____________________________________________
Weekly Task Report (by WBS)
Day 3 in the am # 12 / 24Project Management Cook
Weekly Project Summary<NAME>
(<Budget> : <Scheduled completion>)
In-House(<Budget> : %$)
Contracted(<Budget> : %$)
Purchases(<Budget> : %$)
Schedule: % on-time (budget wtd.)
% completed (budget weighted)
Schedule variance (budget wtd.)
Estimated completion date
Estimation trend (10 week)
Schedule Performance Index
Serious issues open (# : trend)
Cost: % within budget
Estimated completion date
Estimation trend (10 week)
Schedule Performance Index
Serious issues open (# : trend)
Spent to date ($ : <budget> %)
Situation: (need mgmt. help?)
Day 3 in the am # 14 / 24Project Management Cook
MS Reporting Capability
Reports Views and Table Views Filters Overview reports: critical
tasks and milestones Current activities reports:
unstarted tasks, tasks startingsoon, tasks in progress,completed tasks, should havestarted tasks, and slippingtasks
Assignment reports: whodoes what when
Gantt chart, PERTchart, Tracking Gantt,schedule, tracking,variance, constraintdates, and delay
All tasks,completed tasks,critical tasks,incomplete tasks,and milestonetasks
Day 3 in the am # 15 / 24Project Management Cook
Basic Financial Terms
Life cycle costing is estimating the cost of a project over its entire life
Cash flow analysis is used for determining the estimated annual costs and benefits for a project
Benefits and costs can be tangible or intangible, direct or indirect, but will have to be quantified
Sunk cost is money spent in the past and should not be a criteria in project selection
Learning curve theory – when many items are produced repetitively, unit cost decreases
Reserves – money included in cost estimate Contingency reserves – allowances for future situations
Day 3 in the am # 17 / 24Project Management Cook
Return on Investment
Return On Investment (ROI) : ROI = ((Discounted Benefits) – (Discounted Costs)) / (Discounted Costs)
Breakeven Analysis:
BE = (Time when DB-DC =0) – (Time when DC began)
Where: DB is Discounted Benefits and DC is Discounted Costs
Day 3 in the am # 21 / 24Project Management Cook
Controlling
Controlling is the process ofmeasuring progress towards project objectivesmonitoring deviation from the plan taking corrective action to match progress with the plan
Controlling cuts across all of the other phases of the project life cycle and involves seven knowledge areas
Day 3 in the am # 22 / 24Project Management Cook
Control ProcessesKnowledge Area Process Outputs
Integration Overall Change Control Project Plan Updates Corrective Actions Lessons Learned Scope Scope Change Control Scope Changes Corrective Actions Lessons Learned Time Schedule Control Schedule Updates Corrective Actions Lessons Learned Cost Cost Control Revised Cost Estimates Budget Updates Corrective Actions Estimate at Completion Lessons Learned Quality Quality Control Quality Improvement Acceptance Decisions Rework Completed Checklists Process Adjustments Communications Performance Reporting Performance Reports Change Requests Risk Risk Response Control Corrective Actions Updates to Risk Management Plan
Day 3 in the am # 23 / 24Project Management Cook
Cost Control
Project cost control includesmonitoring cost performanceensuring that only appropriate project changes
are included in a revised cost baselineinforming project stakeholders of authorized
changes to the project that will affect costs
Earned value analysis is an important tool for cost control