PROJECT MANAGEMENT USING EARNED VALUE (and the Problems & Lessons Learned from it)
description
Transcript of PROJECT MANAGEMENT USING EARNED VALUE (and the Problems & Lessons Learned from it)
1
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
PROJECT MANAGEMENT
USING EARNED VALUE
(and the Problems & Lessons Learned from it)
Jim Pennington – Business Operations Director
Dated November 2007
2
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
AGENDA
• OMB objections and requirements for EVMS• What is EVMS?• Implementing Directives• Traditional versus Earned Value Accounting• How does EV fit into the Program Management Life Cycle• Problems and Lessons Learned over the PM EVM Life Cycle• Comments
Backup Charts • Essential Elements of EVM• Tailored Earned Value Management
3
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
According to the Third Edition of Earned Value Project Management by Fleming and Koppelman, "Earned Value is a technique to better manage projects. It is not intended for use on continuing business processes, operations that have
no unique deliverables. Earned Value is for the management of one-time-only projects, and portfolios of projects within an organization".
In alignment with this statement OMB mandates the use of EVMS within OMB Circular A-11 for major development/ modernization/enhancement (DME) projects, but not all DME projects.
OMB Circular A-11 defines a major project as:– A system or project requiring special management attention because of its importance to the mission or function of the Agency, a
component of the Agency, or another organization;– Is for financial management and obligates more than $500,000 annually;– Has significant program or policy implications;– Has high executive visibility;– Has high development, operating, or maintenance costs; or– Is defined as major by the Agency’s capital planning and investment control process– In addition, OMB memorandum M-05-23 asked each agency to work with OMB to identify “high risk” projects by August 15, 2005.
Circular A-11 defines high-risk projects as those requiring special attention from oversight authorities and the highest levels of agency management.
What is Earned Value and when does OMB want it implemented
4
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
Agencies follows the requirements set forth in:• ANSI/EIA STD – 748• OMB Circular A-11, Part 7, Federal Acquisition Regulation Case 2004-019• OMB Memorandum M-04-24 (dated 8/23/04)• OMB Memorandum M-05-23 by using the NDIA EVMS Intent Guide, NDIA PMSC Surveillance Guide (dated
8-4-05)• NDIA* Program Manager’s Guide to the Integrated Baseline Review (IBR) Process, and EVM
Implementation Guide
To provide for a uniform approach to implementing EVMS and to confirm that the processes and procedures continue to satisfy the guidelines as they change
Note * = NDIA – National Defense Industry Association Program Management Systems Committee Working group
Where is the Earned Value Requirements and Standards the Process Defined
5
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
Technical
CostSchedule
EVMS
EVMS is the primary project management tool that integrates the technical, schedule and cost aspects
of the project or contract scope of work
6
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
A Program or Project’s Technical, cost and schedule performance are interrelated
Problems in one area can, and usually will, cause problems in the other areas
You can design and build the fastest, toughest and lightest widget in the world, but if it costs too much, or is late:
It may adversely affect the total funding required to complete Could impact ability to get funding for future projects or may required
greater effort to obtain enough funding for programs later in the future
Why is Earned Value Information important to the Program Manager
7
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
Earned Value (EV)
...is a predetermined amount of value that is claimed, or earned, when the corresponding work is accomplished.
# of Widgets
# of Pages
Lines of Code
# of SysReqmts
8
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
• Objective rather than subjective project status information
• Cost and Schedule impact of known problems
• Identification of problems not previously recognized
• Capability to trace the problem to the source
• Quantitative measure of schedule deviation in dollars
• Performance measured against a program oriented baseline
EARNED VALUE DOES NOT GUARANTEE SUCCESS
Earned Value Management provides
9
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
GOVERNMENT
• Mandatory procedures for major defense acquisition programs (DoDI 5000.2-R)
• Defines policies governing earned value
• Earned Value Management Information Guide (EVMIG)• Provides detailed discussions of the EV criteria• Written for the Government program offices
• OMB Directives to Agencies:• OMB Circular A-11, Part 7, Federal Acquisition Regulation Case 2004-019• OMB Memorandum M-04-24 (dated 8/23/04)• OMB Memorandum M-05-23 by using the NDIA EVMS Intent Guide, NDIA
PMSC Surveillance Guide (dated 8-4-05)
INDUSTRY
• Industry guidelines for Earned Value Management Systems (ANSI-ESI 748)
• Industry Standard for Earned Value• Incorporated in DoDI 5000.2R
Some Implementing Directives
10
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
ACWP = Actual cost of work performed (Basically costs extracted from work in process)
BCWP = Budgeted cost of work performed (Earned Value)
BCWS = Budgeted cost of work scheduled (Budget spread to time)
BAC = Budget at completion (Total budget for a given task)
CVAR = Cost variance (BCWP-ACWP)
EAC = Estimate at completion
SVAR = Schedule variance (BCWP-BCWS)
Earned Value Management Terms
11
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
0
200
400
600
800
1000
BCWS
ACWP
TimeNow
Time
All we really know is that we spent more than we planned
TRADITIONAL VS EARNED VALUE ACCOUNTING
Budget versus Actuals
12
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
0
200
400
600
800
1000
BCWS BCWP ACWP
TimeNow
Time
Earned value provides an objective measure of work accomplished. It tells you what you got for what you spent
TRADITIONAL VS EARNED VALUE
ACCOUNTING
(Using EVM approach)
13
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
PROGRAM MANAGEMENT PROCESS
Initiate
Plan
Execute
Control
Close Out
Pro
ject
Man
age
me
nt C
ycle Organize
work and teams
Develop a realistic plan of work scope,
budget, and schedule
Authorize work properly
ControlChanges
Performancereporting
Understand variances
CorrectiveActions
Forecast of final cost and
schedule
PROGRAM MANAGER NEEDS
14
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
EARNED VALUE MANAGEMENT
• Organize• Plan work scope – schedule and budget• Authorize work• Control changes• Report performance • Understand variances• Corrective actions• Forecast final cost and schedule
PROGRAM MANAGEMENT PROCESS
Initiate
Plan
Execute
Control
Close Out
Pro
ject
Man
age
me
nt C
ycle
15
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
Earned Value Problems &
Lessons Learnedover the Program Management
EVM Life Cycle
16
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical Initiate Phase of Program
Problems and Lessons Learned Problems• Baseline is not stable • EVM Staffing Resources not in place
at time of ATP• Program Management as not assigned
responsibilities to CAMs• Program Team is not experienced or
trained• IBR (Integrated Baseline Review)
Deliverables not defined• Contracting Officer or COTR wants to
deviate from SOW or Contract EVM direction w/o proper modifications
• Different set of assumptions from the proposal submittal
• Variance Thresholds are not defined • Variance Analysis Guidelines not
agreed upon prior to start
Lessons Learned• Establish early baseline basis• Have contractor or internal personnel
identified during negotiations • PMs must plan to execute program like
it was proposed (Work per SOW)• Have Program Team (PMs, CAMs,
EVM and Customer) trained together• Establish specific contract SOW app.
for EVM and for Integrated Schedule• Keep CO and COTR (& PM) diligent on
proper contracting practices• Develop clear walkdown of deltas in
Scope and assumptions (document)• Variance Thresholds by % & $ off plan• Analysis must be to a specific level of
WBS, contents identified & Corr. Action
17
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical Planning Phase of Program
Problems and Lessons Learned Problems• No set deadline to freeze plan
(Continuous Churn)• IPTs (Integrated Product Teams) are
not working to same schedule• Baseline Changes are not controlled at
the beginning (Loss of string from Prop to Baseline-Rates, Sch, Scope)
• IBR (Integrated Baseline Review) delayed due to baseline flux or continued negotiations
• No plan for Contract Changes (No CCB board and/or no COTR involved )
• Program Management Reserve and Undistributed Budget not well defined
• Current Forecasts and recovery plans do not change the baseline planning
Lessons Learned• Establish a EVM Implementation
schedule and hold everyone to it• IPTs must complete earlier for IMS
integration with other teams and tasks• Contractor should be able to walkdown
Proposal as Submittal to IBR Baseline• Push to hold IBR schedule and work
SOW, schedule or scope changes later (as formal changes / plan maintenance)
• Must have established CCB with PM, Finance, Contracts, IPTs (Govt / Contr)
• Undistributed Budget is not Reserve, if it is not needed convert to PM Reserve
• Only Customer approved changes impact the Baseline (Establish a window for change approval and freeze the plan for near term changes)
18
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical Execution Phase of Program
Problems and Lessons Learned Problems• Program seems to not meet the EVM
reporting schedule • Status or Earned Performance inputs
are not consistent with period cutoffs• No established Performance Criteria
identified for tasks and completion • Errors or Inconsistent Reporting • Inconsistent Subcontractor or
Procurement Status• No reconciliations of Ledger Actuals to
EVM (Accrued Costs)• Program Management does not use or
analyze the EVM information• PMs manage to the IMS or Schedule
and EVM data must be incorrect• Program Plan Risks are not defined or
PM Reserve is not earmarked
Lessons Learned• Establish a EVM Status and Reporting
Business Rhythm • EVM Staffing Resources not in place at
time of ATP• Must have EV method and completion
criteria defined for tasks (agreed upon)• CAM/EV data reviews prior to release• Establish a ICD approach for Vendor and
Subcontractor Accruals / Receipts• Have defined reconciliation process to
validate EVM ACWP reported & deltas• Make EV data part of monthly review
deliverables and status reviews• Report number of late IMS workpackage
starts and completions by WBS• Risks that have not been realized should
have MR allotted plus mitigation plans
19
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical Control Phase of Program
Problems and Lessons Learned Problems• Contract Changes are too frequent and
formal plan changes are not timely• Variance Analysis is too vague or is not
determined in a timely manner• IPTs do not take ownership of their
variances or mitigation plans• Program has a large cost and/or
schedule variance that plan is relevant• Program does not properly close
workpackages when replanned• Scope Creep and workscope/rate trades
from well minded PMs and CO/COTRs• Inconsistent EVM performance and
reporting over the life of the program• EVM process adherence is not
objectively evaluated or tested
Lessons Learned• CCB process should be defined and
IPT provide estimates at CCB meetings• EVM and variance root cause analysis
must be timely to be effective• IPT must be given labor reports by
name to validate charges and resp.• Program should establish a over target
or baseline replan to make plan valid• You must close incomplete tasks and
replan them as new tasks with replan• Small unapproved changes and creep
drive variances & impacts future work• Contractor should have proven and
documented process to operate consistently
• Establish a Joint Surveillance Plan
20
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical Close Out Phase of Program (or task)
Problems and Lessons Learned Problems• Last months of program, data appears to
be incorrect• Final Estimates to Complete are off by a
large amount• Costs continues to come into the
workpackage after it is completed• Indirect rate impacts hit after the
program or task is completed• Subcontract or Material Costs does not
match Ledger• Final EVM Report does not match
current Invoice Totals or Balances
Lessons Learned• Be sure contractor does not get sloppy
w/ charging practices (>95%)• Be sure final EACs include remaining
material commitments, labor suspense• Be sure all charge accounts closed,
clear suspense & transfer bad charges• Understand contractor financial
calendar and rate adjustment process• Have contractor complete a walk-down
of the EVM ACWP and the ledger $s• Contractor should create a projection
when all costs will be final and on the books of record
21
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical Closing Comments
• With the problems on the FBI Virtual Case File Program, IT programs will continue to have additional OBM scrutiny and needs for oversight
• If you are going to spend the money on EVM, use it (effectively!)
• Manage the EVM process, do not let the process manage you
• Do not just look at the big variances, drive for better analysis and corrective actions that are meaningful (remember you have a boss too!)
• One little rule: If your TCPI is 1.06 after being more than 15%,
You will not recover to the original baseline! (LMC history)
22
EVMSEVMS
ScheduleScheduleCostCost
TechnicalTechnical
Questions and Answers
Comments or Questions??