Project Management
November 22, 2013
![Page 2: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/2.jpg)
Engineering Economics
Macroeconomics
OperationsResearch
Linear programmingPERT/CPM
Queueing Theory
Accounting
![Page 3: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/3.jpg)
Project Management Tools:
Work breakdown structure: what there is to do
Gantt Chart: times to do things
Critical Path Method: dependencies; time/cost trade-offs
![Page 4: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/4.jpg)
Work breakdown structure: what there is to do
E.g., “Prepare beans on toast”
![Page 5: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/5.jpg)
Prepare Beans on Toast
Prepare Beans Prepare Toast Combine
Open Can
Place Beans in saucepan
Place Saucepan on stove
Light stove
Stir beans till warm
Slice bread
Place bread in toaster
Depress toaster button
Remove toast from toaster
Butter the toast
![Page 6: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/6.jpg)
WBS activities should be mutually exclusive andcollectively exhaustive
The WBS allows us to calculate total project costand personnel requirements
It can include time estimates for each activity, butit doesn’t, by itself, allow us to calculate projectduration.
![Page 7: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/7.jpg)
Task Start
End 9:00
9:02
9:04
9:06
9:08
9:10 9:12
1 Open can 9:00 9:01
2 Fill saucepan
9:01 9:03
3 Saucepan on stove
9:03 9:04
4 Light stove
9:04 9:05
5 Stir 9:05 9:10
6 Cut bread
9:00 9:01
7 Bread in toaster
9:01 9:06
8 Butter toast
9:06 9:07
9 Beans onto toast
9:10 9:11
A Gantt Chart for Beans on Toast
![Page 8: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/8.jpg)
Task Start
End 9:00
9:02
9:04
9:06
9:08
9:10 9:12
1 Open can 9:00 9:01
2 Fill saucepan
9:01 9:03
3 Saucepan on stove
9:03 9:04
4 Light stove
9:04 9:05
5 Stir 9:05 9:10
6 Cut bread
9:00 9:01
7 Bread in toaster
9:01 9:06
8 Butter toast
9:06 9:07
9 Beans onto toast
9:10 9:11
Dependencies shown, but not self-evident
![Page 9: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/9.jpg)
CPM: Two conventions
Start
Can Open
Bread cut
Beans on Toast Ready
Beans Ready
Toast Ready
Open Can
Slice bread
Toast Bread
Heat Beans
Beans onto toast
Dummy
AOA
AON Start
Open Can
Slice bread
Heat Beans
Toast bread
Beans onto toast
End
![Page 10: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/10.jpg)
Finding the critical path
Start
Open Can T:ES: EF:LS: LF:
Slice breadT:ES: EF:LS: LF:
Heat BeansT:ES: EF:LS: LF:
Toast breadT:ES: EF:LS: LF:
Beans onto toastT:ES: EF:LS: LF:
End
Add notation: “T” = time, “ES” = Earliest Start, “EF” = Earliest Finish“LS” = Latest Start, “LF” = Latest Finish
![Page 11: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/11.jpg)
Finding the critical path
Start
Open Can T: 1:00ES: EF:LS: LF:
Slice breadT:1:00ES: EF:LS: LF:
Heat BeansT: 5:00ES: EF:LS: LF:
Toast breadT:3:00ES: EF:LS: LF:
Beans onto toastT: 1:00ES: EF:LS: LF:
End
Fill in the times.
![Page 12: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/12.jpg)
Finding the critical path
Start
Open Can T: 1:00ES:0 EF:1LS: LF:
Slice breadT:1:00ES: 0 EF:1LS: LF:
Heat BeansT: 5:00ES: EF:LS: LF:
Toast breadT:3:00ES: EF:LS: LF:
Beans onto toastT: 1:00ES: EF:LS: LF:
End
ES for the first activity is zero, EF is ES + T
![Page 13: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/13.jpg)
Finding the critical path
Start
Open Can T: 1:00ES:0 EF:1LS: LF:
Slice breadT:1:00ES: 0 EF:1LS: LF:
Heat BeansT: 5:00ES:1 EF:6LS: LF:
Toast breadT:3:00ES:1 EF:4LS: LF:
Beans onto toastT: 1:00ES:6 EF:7LS: LF:
End
For subsequent activities, ES is max(EF of all upstream activities), EF is ES + T
![Page 14: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/14.jpg)
Finding the critical path
Start
Open Can T: 1:00ES:0 EF:1LS: LF:
Slice breadT:1:00ES: 0 EF:1LS: LF:
Heat BeansT: 5:00ES:1 EF:6LS: LF:
Toast breadT:3:00ES:1 EF:4LS: LF:
Beans onto toastT: 1:00ES:6 EF:7LS: LF:
End
For subsequent activities, ES is max(EF of all upstream activities), EF is ES + T
![Page 15: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/15.jpg)
Finding the critical path
Start
Open Can T: 1:00ES:0 EF:1LS: LF:
Slice breadT:1:00ES: 0 EF:1LS: LF:
Heat BeansT: 5:00ES:1 EF:6LS: LF:
Toast breadT:3:00ES:1 EF:4LS: LF:
Beans onto toastT: 1:00ES:6 EF:7LS: LF:7
End
The earliest finish of the final activity is also the latest acceptable finish for thefinal activity, assuming we don’t want the project completion to be delayed.
![Page 16: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/16.jpg)
Finding the critical path
Start
Open Can T: 1:00ES:0 EF:1LS:0 LF:1
Slice breadT:1:00ES: 0 EF:1LS: 2 LF: 3
Heat BeansT: 5:00ES:1 EF:6LS:1 LF:6
Toast breadT:3:00ES:1 EF:4LS:3 LF: 6
Beans onto toastT: 1:00ES:6 EF:7LS:6 LF:7
End
Then we do a second, backwards, pass through the network, where for each node,LF is min(LS of all downstream nodes) and LS is LF - T
![Page 17: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/17.jpg)
Finding the critical path
Start
Open Can T: 1:00ES:0 EF:1LS:0 LF:1
Slice breadT:1:00ES: 0 EF:1LS: 2 LF: 3
Heat BeansT: 5:00ES:1 EF:6LS:1 LF:6
Toast breadT:3:00ES:1 EF:4LS:3 LF: 6
Beans onto toastT: 1:00ES:6 EF:7LS:6 LF:7
End
The difference between EF and LF for a node is the slack for that activity
Slack = 2 Slack = 2
![Page 18: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/18.jpg)
Finding the critical path
Start
Open Can T: 1:00ES:0 EF:1LS:0 LF:1
Slice breadT:1:00ES: 0 EF:1LS: 2 LF: 3
Heat BeansT: 5:00ES:1 EF:6LS:1 LF:6
Toast breadT:3:00ES:1 EF:4LS:3 LF: 6
Beans onto toastT: 1:00ES:6 EF:7LS:6 LF:7
End
Activities with no slack are on the critical path
Slack = 2 Slack = 2
![Page 19: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/19.jpg)
Crashing a Project
Crashing an activity means spending more money in order to get it done faster
(Important note: This doesn’t always work – seeBrooks, “The Mythical Man-Month”)
It’s obviously a waste of money to crash any activity that has slack.
![Page 20: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/20.jpg)
Crashing a Project
1. Assume linearity:
Crash cost – normal cost
Crash cost/ unit time =
Normal Time –Crash Time
2. Find minimum crash cost/unit time on the critical path
3. Reduce time as much as possible
4. Repeat
![Page 21: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/21.jpg)
You own a start-up software company. You and your colleagues are planning the launch of a new computer.
“Before we can start designing the Mark II, we need to complete three steps: there’s the market research, which will take about six weeks, there’s about five weeks of technical research needed to identify the best chip set, and meanwhile we’re going to have to raise capital to pay for all of this – we should allow four weeks for that. The good news is that all those activities can go on independently. When they’re all complete, we’ve reached Milestone 1 and we can start working on the hardware and software.” “That’s a dependency – we can’t write the software till we’ve got a machine to run it on.” “There’s a way round that: we can emulate the Mark II on a Mark I machine. It won’t run as fast, but we can use it for debugging. So we can develop the pre-prototype hardware, which should take about twelve weeks, and write software on an emulated machine at the same time – we should be able to get that done in ten weeks. Once both those things are done, we’re at Milestone 2.”
“Once the pre-prototype hardware is done, we can adapt the software to run on it. That will take another twelve weeks. Meanwhile our hardware engineers can build the prototype Mark II. That’s going to be the longest step in the whole process – we’ll allow twenty-four weeks for that. And once those two steps are complete, we’re at Milestone 3.”
![Page 22: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/22.jpg)
“Once we’re past Milestone 3, there’s a lot of things we can get started on. We can start designing the production version of the Mark II, and at the same time design the production tooling. Both those steps should take about sixteen weeks. We’ll also be in a position to release guidelines to applications developers, inside and outside the company. We can expect the first applications to be ready within twenty weeks, ideally just as the Mark II is put on the market.” “Milestone 3 is also the point at which we can start adapting the software to the prototype machine. Let’s allow eighteen weeks for that. ” “So when the production tooling and the production version of the Mark II are complete, and assuming the software for the prototype machine is ready by that time, we’ve at Milestone 4. Then all we’ve got to do is design the hardware packaging – call that a six-week job – adapt the software to the production version of the machine – allow twelve weeks for that – once the software is complete, we package that too, which shouldn’t take more than four weeks – and, as long as the applications developers are on schedule, we can put the machine on the market.”
Represent the project as a Gantt chart, and calculate the earliest possible finish date.
![Page 23: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/23.jpg)
![Page 24: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/24.jpg)
2.Represent the project using both an AOA and an AON network diagram. Note that it may be useful to use `dummy arcs’ to represent the dependencies between some activities 3.Using the AON diagram developed in 2, perform a critical path analysis and complete a table showing the slack for each activity.
![Page 25: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/25.jpg)
First, the Activity-on-Arc representation. The arcs are labelled according to the table below. We use dummy arcs, indicated by grey lines, to indicate that one activity cannot begin before others are completed. The milestones correspond to the nodes labelled `M’.
![Page 26: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/26.jpg)
![Page 27: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/27.jpg)
We next construct the AON network. This time we’ll use square nodes, and provide them with labels ready for a CPM analysis.
![Page 28: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/28.jpg)
We can now begin the CPM analysis. We start going through the diagram, filling in the earliest start times. We define the earliest we can start as time 0, so this goes into the first row of boxes. Then we add the duration times to get the earliest each activity can finish. When we get to the second row of boxes, we apply the rule that the earliest an activity can start is the latest that any of the activities it depends upon can finish. All of the boxes in the second row depend on all of the boxes in the first row, so the earliest any of them can start is 6 weeks into the project.
![Page 29: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/29.jpg)
We carry on in this way till we get to the bottom of the diagram, where we find that the earliest we can finish the project is in 76 weeks, the same answer as we got from the Gantt diagram. Then we start working our way back up the diagram, this time using the rule that the latest any activity can finish is the latest that any of the activities that depend on it can start. This gives us the `LF’ entry, and the `LS’ entry is the value of the LF entry minus the activity duration. When we’re done, the diagram should look like this, where we’ve marked the critical activities in yellow and the critical path in red:
![Page 30: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/30.jpg)
![Page 31: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/31.jpg)
4.You discover that a rival company is planning to put out a product that will compete with the Mark II. Every week that you can shorten your time to market is worth $1 000 000 in increased sales. You know that each of the relevant activities can be shortened by a certain percentage, with per-week costs as follows:
What is your most profitable strategy?
![Page 32: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/32.jpg)
Production Tooling: 16 weeksES: 42 EF: 58LS: 54 LF: 70
EndEF: 76LF: 76
Package Software: 4 weeksES: 72 EF: 76LS: 72 LF: 76
Production Software: 12 weeksES:60 EF:72LS: 60 LF:72
Package Hardware: 6 weeksES: 58 EF:64LS: 70 LF: 76
Production Hardware: 16 weeksES:42 EF: 58LS: 44 LF: 60
Step 1: Crash Software Packaging 2 weeks
Prototype Software: 18 weeksES:42 EF:60LS: 42 LF: 30
Develop apps: 20 weeksES:42 EF:62LS: 56 LF: 76
![Page 33: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/33.jpg)
Production Tooling: 16 weeksES: 42 EF: 58LS: 54 LF: 70
EndEF: 74LF: 74
Package Software: 2 weeksES: 72 EF: 74LS: 72 LF: 74
Production Software: 12 weeksES:60 EF:72LS: 60 LF:72
Package Hardware: 6 weeksES: 58 EF:64LS: 68 LF: 74
Production Hardware: 16 weeksES:42 EF: 58LS: 44 LF: 60
Prototype Software: 18 weeksES:42 EF:60LS: 42 LF: 60
Develop apps: 20 weeksES:42 EF: 62LS: 54 LF: 74
Critical Path has not changed, but it’s shorter
![Page 34: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/34.jpg)
Market Research: 6 weeksES: 0 EF:6LS: 0 LF: 6
Start
Technical Research: 5 weeksES:0 EF:5LS: 1 LF: 6
Raise Capital: 4 weeksES:0 EF:4LS: 2 LF: 6
Pre-prototype Hardware: 12 weeksES:6 EF:18LS: 6 LF: 18
Software on emulated machine: 10 weeksES:6 EF:16LS: 20 LF: 30
Step 2: crash market research 1 week
![Page 35: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/35.jpg)
Market Research: 6 weeksES: 0 EF:5LS: 0 LF: 5
Start
Technical Research: 5 weeksES:0 EF:5LS: 0 LF: 5
Raise Capital: 4 weeksES:0 EF:4LS: 1 LF: 5
Pre-prototype Hardware: 12 weeksES:5 EF:17LS: 5 LF: 17
Software on emulated machine: 10 weeksES:5 EF:16LS: 19 LF: 29
Critical Path has changed
![Page 36: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting.](https://reader030.fdocuments.us/reader030/viewer/2022032517/56649cac5503460f9496dd84/html5/thumbnails/36.jpg)