Project Management Lecture 2/9/2015. Fundamental “Rules” of Project Engineering 1.While there is...
-
Upload
ashlynn-walters -
Category
Documents
-
view
215 -
download
0
Transcript of Project Management Lecture 2/9/2015. Fundamental “Rules” of Project Engineering 1.While there is...
Project Management
Lecture2/9/2015
Fundamental “Rules” of Project Engineering
1. While there is never enough time to do it right, there is always enough time to do it again.
2. No surprises.3. At some point you have to build the plant.
Chemical Engineering Design
Why Are ChE’s Paid So WellTo Work in So Many Different Industries?
• They can start from a vaguely defined problem statement such as a customer need or a set of experimental results
• From the problem statement they develop an understanding of the important underlying physical science relevant to the problem
• Using this understanding they can develop a plan of action and set of detailed specifications, which if followed will lead to a predicted financial outcome
All the other ChE classes you took
The design courseaddresses these
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
Chemical Engineering Design
The Design ProcessProblem statement
Implementation
PlanFinancialoutcome
XYZ Co.
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
Chemical Engineering Design
Design Work Process
Determine Customer Needs
Set DesignSpecifications
R&D if Needed
Evaluate Economics& Select Design
Predict FitnessFor Service
Build PerformanceModels
Generate DesignConcepts
Procurement& Construction
Begin Operation
CustomerApproval
Detailed Design &Equipment Selection
Common to all design problems in all industries© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
Chemical Engineering Design
How do companies implement this design process?
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
Chemical Engineering Design
The Design Team
ProjectSponsor
ContractorsCivil
Engineers
BusinessInput
R&DSpecialists
TechnicalSpecialists
Cost EngineerControl
EngineerConsultants
MechanicalEngineer(s)
ProcessEngineer(s)
ProjectManager
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
Chemical Engineering Design
Nowadays(For most companies, most sectors)
ProjectSponsor
ContractorsCivil
Engineers
BusinessInput
R&DSpecialists
TechnicalSpecialists
Cost EngineerControl
EngineerConsultants
MechanicalEngineer(s)
ProcessEngineer(s)
ProjectManager
E&CCompany
TechnologyVendor
OperatingCompany
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
Chemical Engineering Design
Implications
• Most major projects involve several companies working together
• “OpCo” might itself be a joint venture between several companies
• The companies might all be based in different regions of the world
• Teamwork, technology transfer and effective communications have high impact and value
• Good project management is more important than ever
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
“Stage Gated” Project Life Cycle
P1P2 P3
P4
Project Estimates, Plans, Schedules
• Each Engineering Discipline normally submits an estimate of hours needed to complete the project, along with a resource loaded schedule showing “milestone” dates for completion of deliverables, or specific % complete targets relevant to each project phase.
• These are built around the deliverables and known activities for each engineering discipline.
P1Conceptual
P2Evaluate
P3Define
P4Detailed Design
Process Capacity(s) A D D
Process Design Basis P D IFD
Block Flow Diagams (BFD's)
Process Sketches P
Process Simulation P D
Heat & Material Balance D
Process Flow Diagrams (PFD's) P IFD IFC
Material Selection Diagram (MSD's) P IFD IFC
Piping & Instrumentation Diagrams (P&ID's) P (?) IFD IFC
PSV Files P D
PHA Study A A
HAZOP Study D
LOPA Study D
Hydraulic Calculations P D
Process Equipment Data Sheets P D IFC
Sparing Philosophy A P D
LEGENDBLANK = Not Required or Applicable
A = Assumed (no engineering developed)
IFD = Issued for Design IFC = Issued for Construction
P = Preliminary (limited engineering work)
D = Definitive Based on Completed Work
Deliverables
Pro
cess
En
gin
eeri
ng
Typical Process Engineering Deliverables for Stage Gated Project
P1Conceptual
P2Evaluate
P3Define
P4Detailed Design
Project Name & Location D D D
Project Scope Description P P D
Product Description P D D
Interfaces with Existing Facilities P P D
Site Visit Results P D
Project Work Breakdown Structure P D
Engineering, Equipment & Installation Job Specifications & Standards
A D IFC
Labor Availability A P
Current Labor Market A P
Taxes/Laws Cost Impact A D
APP D D D
T/A Interdependability P P D
Project Execution Plan A P D
Contracting Strategy A P P
Purchasing Strategy P D
Approved Vendor List D
Estimate Plan D D D
Schedule P P D
Constructability Study P D
Construction Laydown Area & Crane Access P
Analyzed Final Cost Report D
Benchmarking Study & Performance Analysis P
Closeout Report D
Project Services Estimate D D D
Confidence Range -50%+100% +-30% +-15%
TIC Estimate Basis D D D
Approximate Unallocated Provision (Contingency) 25% 20% 10%
Risk (Cost) Analysis yes yes
Estimating MethodRATIO/
CAPACITY CURVE
Factored from Equipment
Equipment Quotes &
MTO's
Definitive using IFC Packages (90% Engrg)
Engineering Percent Complete <1% <5% 25-30
LEGENDBLANK = Not Required or Applicable
A = Assumed (no engineering developed)
IFD = Issued for Design IFC = Issued for Construction
Est
imat
e
P = Preliminary (limited engineering work)
D = Definitive Based on Completed Work
Deliverables
PM
AC
For Other Types of Projects – See Text Chapt. 1
• “Techno-Economic Analysis” (aka Feasibility Study) ….see Table 1.1 for Deliverables-Engineering Report Sections.
• “Technical Proposal” ….see Table 1.2 for typical parts of a proposal that must be generated.
• Note: A Basic Engineering Design Report (BEDR) – Table 1.3 puts together all the typical Stage Gated Project Deliverables…at different Phases of each Project.
Chemical Engineering Design
The Project Plan
• Is developed & implemented by the project manager
• Sets deadlines for completion of activities & intermediate deliverables
• Allows scheduling of subordinate or dependent tasks
• Allows estimation of the required manpower resources at each stage of the project
• Determines the procurement schedule & gives an estimate of when cash outlays are expected
ID Task Name
1 Project KO Meeting2 Process Commercialization
3 Verify Operating Conditions
4 Process Design - Flowsheet
5 Verify Full Design Criteria
6 Process Design/Optimization
7 Cold Flow Modeling8 Design Sparger9 Approve Sparger Design10 Construction of Wedge11 PP design/construction/shakedown12 Cold Flow Testing13 Catalyst Scale-up
14 Catalyst Scale-up
15 Demonstration Plant
16 Commercialization Team Formed
17 Demo Plant Design Basis
18 Process Engineering
19 PFD Review
20 Basic Engineering
21 P&ID review
22 Detailed Engineering
23 Layout Review
24 Procurement
25 Fabrication
26 Delivery & Installation
27 Begin Run
3/31
74 days
206 days
7/15
150 days
251 days
1/12
2/22
5/18
8/31
12/28
M-1 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
Chemical Engineering Design
Example: 11-Week Plan for a Process Design Project
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
Chemical Engineering Design
What’s In a Project Plan?
List of tasksList of tasks
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
Chemical Engineering Design
What’s In a Project Plan?
Durations, startand end dates
Durations, startand end dates
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
Chemical Engineering Design
What’s In a Project Plan?
Predecessortasks
Predecessortasks
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
Chemical Engineering Design
What’s In a Project Plan?
ResourceallocationsResource
allocations
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
Chemical Engineering Design
What’s In a Project Plan?
GanttchartGanttchart
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
Chemical Engineering Design
Tools for Project Planning
• Specialized software for larger projects– MS Project– SureTrak– Primavera Project Planner– Enterprise PM– Cobra
• Small project plans & Gantt charts can be drawn in spreadsheets or using cheap software (<$100)– AceProject (free on-line)– TurboProject– Project Vision– Quick Gantt
© 2012 G.P. Towler / UOP. For educational use in conjunction with Towler & Sinnott Chemical Engineering Design only. Do not copy
How do you develop a Project Plan?
1. Develop Project Scope, and Design Basis (Rough Draft-Outline Based on what you have been told)
2. Develop Project Man Hour Estimate3. Develop Project Schedule4. Resource Load the Schedule based on Man Hour
Estimate5. Iterate with Resource and Schedule Constraints to
meet project requirements.6. Publish Documents (Scope, Estimate, Schedule) for
Review & Approval
How do you develop a Project Plan?
• Start by “Scoping” your project:– “In Scope” means you have deliverables for your
project.– “Out of Scope” means no deliverables, or any
other considerations, calculations, etc.– Write up a Scope of Study document, listing
project intent and deliverables.– Develop and initial Design (or Study) Basis
Document, to identify your basis (and things you need to pin down in your project later as TBD).
Project Plan Development, cont.
• Next - Estimate the man-hours needed for each deliverable. Note that each deliverable may have several separate activities/tasks you need to estimate.– Add in required hours for reviews, meetings,
travel, etc.– Include your own safety/risk review.
Project Plan Development, cont.
• Develop the Schedule. Organize your separate activities/tasks in order by which you can complete them (Identify predecessors). – Start from Deadline and work backwards…or..– Start with Kick-off date and work forwards.
• Identify Milestone dates. These can include:– Completion dates (or % Complete dates).– When Deliverables are to be issued for review & comment.– Review Meetings.– Key Decision Points.
Project Plan Development, cont.
• Document resources available to accomplish required man-hours
• Iterate?• Demonstrate Plan via GANT chart, Flowchart,
etc.
Cost Estimates for “Stage Gated” Project Life Cycle
P1P2 P3
P4
PFD’s0% 100%
P&ID’s 0% 30 to 50% 100%
Project Cost Estimate Quality
P1 P2 P3 P4
Class 5 EstimateClass 4 Estimate
Text Book AACE Cost Estimate Classes:
Class 3 Estimate
Class 2 Estimate
Project Life Cycle
Inherently Safe Design (ISD)
P1P2
P3
P4
Impact of Cost & Schedule + Need for ISD
on Process Engineering
• You must PLAN your work.• You must Estimate your work.• You must Schedule your work.• You must Track your progress on
your work.• You must report your progress and
update your Estimate & Schedule as Needed.
Fundamental “Rules” of Project Engineering(For Process Engineers)
1. While there is never enough time to do it right, there is always enough time to do it again.
• You have to “Scope, Estimate, and Plan (Schedule, and Resource Load) your project”.
2. No surprises.• You need to update your Estimate & Plan
3. At some point you have to build the plant.• You need to produce your Deliverables.