Project Management Karen J Kirkby DJ 18 01 School of Electronics & Physical Sciences.

25
Project Project Management Management Karen J Kirkby DJ 18 01 School of Electronics & Physical Sciences

Transcript of Project Management Karen J Kirkby DJ 18 01 School of Electronics & Physical Sciences.

Project ManagementProject Management

Karen J Kirkby DJ 18 01

School of Electronics & Physical Sciences

ContentsContents

2 Lectures + 1 Assignment

Why Plan?

What Plan

Project Manager/ Leader

Network Analysis

Critical Path

Gantt charts

PERT

AssignmentAssignment

Week 6

Friday Lab groups

Tuesday 15:00 - 17:00

Tuesday Lab groups

Friday 15:00 - 17:00

(see timetable)

WHY PLAN?WHY PLAN?

Why do projects fail?

Failing to plan is planning to fail

ReappraiseProject

ReappraiseProject

What Plan?What Plan?

Define ProjectDefine Project

Define TasksDefine Tasks

Define PlanDefine Plan

Monitor Progress

Monitor Progress

Commence Work

Commence Work

AimsSpecFeasibility

Subprojects

DependenciesTimeResourcesFacilities

ReviewsTargetsCosts

CompleteProject

CompleteProject

RedefineProject

RedefineProject

Corrective Action

Corrective Action

The Project ManagerThe Project ManagerAbilities

* Organise & plan

* People Management

* Communication skills

* Problem solving

* Technical knowledge

* Enthusiasm & ability to motivate

* Focussed

* Ability to change

Network AnalysisNetwork Analysis

* Break project down into manageable sub-groups

* Define tasks in sub-group

* Establish linkages & dependencies between tasks

* Establish order in which tasks undertaken

* Establish sequential and parallel tasks

* Determine time & resources for each task

* Project objectives clearly defined

Network AnalysisNetwork Analysis

Activity on node diagrams

activity - rectangular box

linked by arrows - order

NETWORK ANALYSIS NETWORK ANALYSIS

1. open cereal box

1

2. put cereal in bowl

2

3. fetch milk from fridge

3 4

4. add milk to cereal EAT

Simple example - Breakfast

Network AnalysisNetwork Analysis

OK that was a simple example

Now move on to a more realistic case

Same principles

Break down problem into activities

What is the activity

What has to precede that activity

How long does the activity take

Don’t panic

Network AnalysisNetwork Analysis

ACTIVITY DURATION PRECURSORSA 4 -B 3 -C 6 A,BD 1 BE 7 DF 2 CG 5 C,EH 8 EJ 4 GK 5 F,GL 6 J,HM 3 L,K

DURATION

L6

START0

A4

C6

D1

F2

E7

B3

K5

H8

FINISH0

M3

G5

J4

NETWORK ANALYSISNETWORK ANALYSIS

Earliest Start, Earliest Finish

JSTART

0

A

4

C

6

D

1

F

2

E

7

B

3

K

5

H

8

FINISH

0

M

3

L

6

G

5 4

0 3

Earliest Finish

0

4

4 10

10 12

4 113 4

11 16

11 19

16 20

16 21

20 26 26 29 29 29

Earliest Start

0

0

NETWORK ANALYSIS NETWORK ANALYSIS

Latest Start, Latest Finish

Latest Start

Latest Finish

JSTART

0

A

4

C

6

D

1

F

2

E

7

B

3

K

5

H

8

FINISH

0

M

3

L

6

G

5 4

0 3

0

0

0

4

4 10

10 12

4 113 4

11 16

11 19

16 20

16 21

20 26 26 29 29 29

4 11

0

0

0

3

1 5 21 26

16 2011 16

3 4

19 21

5 11

29 2926 2920 2612 20

Project ManagementProject Management

Karen J Kirkby DJ 18 01

School of Electronics & Physical Sciences

ContentsContents

2 Lectures + 1 Assignment

Why Plan?

What Plan

Project Manager/ Leader

Network Analysis

Critical Path

Gantt charts

PERT

NETWORK ANALYSIS NETWORK ANALYSIS

Critical Path

Critical Path ES =LS EF=LFshown as a thick lineFLOAT = LF-duration-ES

JSTART

0

A

4

C

6

D

1

F

2

E

7

B

3

K

5

H

8

FINISH

0

M

3

L

6

G

5 4

0 3

0

0

0

4

4 10

10 12

4 113 4

11 16

11 19

16 20

16 21

20 26 26 29 29 29

4 11

0

0

0

3

1 5 21 26

16 2011 16

3 4

19 21

5 11

29 2926 2920 2612 20

If duration of activities on critical path increases then time required for project increases

NETWORK ANALYSISNETWORK ANALYSIS

Float

FLOAT = LF-duration-ES

JSTART

0

A

4

C

6

D

1

F

2

E

7

B

3

K

5

H

8

FINISH

0

M

3

L

6

G

5 4

0 3

0

0

0

4

4 10

10 12

4 113 4

11 16

11 19

16 20

16 21

20 26 26 29 29 29

4 11

0

0

0

3

1 5 21 26

16 2011 16

3 4

19 21

5 11

29 2926 2920 2612 20

ACTIVITY H 20-8-11 = 1 = FLOAT

ACTIVITYFLOAT

A

1

B

0

C

1

D

0

E

0

F

9

G

0

H

1

J

0

K

5

L

0

M

0

Critical path when float = 0

NETWORK ANALYSISNETWORK ANALYSIS

Activity on node diagrams in which finish to start (F-S) links have a duration will now be considered

Nature and duration of link shown on arrow

(F-S) Activity 2 cannot start until 1 week after completion of activity 1.

1 2F-S (1) 3F-S (2)

Activity 3 cannot start until 2 weeks after completion of activity 2

NETWORK ANALYSISNETWORK ANALYSIS

Activity Duration Precursor Link L duration

C 12 B S-S 6

F-F 3

A

A 4 -

0 4

40 4B

F-S (0)

B 24 A F-S 0

4 28

284 24

C10 31

3119 12

S-S (6)

Can start 6 weeks after the start of B 4+6 = 10

F-F (3)

Has to finish 3 weeks after the end of B 28+3 = 31

Critical Path

Gantt ChartsGantt Charts

Developed by Henry Gantt during the first world war

Activities drawn as bars across a time mapABCD

E

F

G

H

J

K

L

MCritical path Non critical activity

PERTPERT

Programme Evaluation & Review Technique

Developed by US Navy 58-60 for Polaris submarine construction programme

PERT takes into account the difficulty of estimating duration of activity

So uses:

most optimistic duration

most pessimistic duration

most likely duration

PERTPERT

6

bm4ate

6ab

s

uses a frequency distribution

calculates the expected mean duration and the standard deviation as follows:

te = expected mean duration

a = most optimistic duration b = most pessimistic duration

m = most likely duration s = standard deviation

PERTPERTACTIVITY a m b PRECURSORS

A 3 5 9 -B 4 6 8 -C 5 8 10 A,BD 3 6 9 BE 6 9 15 DF 3 4 5 CG 8 12 15 C,EH 2 6 8 EJ 4 7 9 GK 3 5 10 F,GL 7 9 11 J,HM 10 12 15 L,K

ACTIVITY te s

A 5.3 1B 6 0.67C 7.8 0.83D 6 1E 9.5 1.5F 4 0.33G 11.8 1.17H 5.7 1J 6.8 0.83K 5.5 1.17L 9 0.67M 12.2 0.83

PERTPERTThe variance for the project duration is the sum of the variances of the activities along the critical path

The standard deviation for the duration of

the project is the square root of the variance

ConclusionsConclusions

Why Plan?

What Plan

Project Manager/ Leader

Network Analysis

Critical Path

Gantt charts

PERT