Project Management Inspections and Reviews

20
Project Management Inspections and Reviews 1 February

description

Project Management Inspections and Reviews. 1 February. What you should be doing. Update web site and functional spec per meeting Write a draft contract Post on web email me when you have it done and I will give you feedback as soon as possible - PowerPoint PPT Presentation

Transcript of Project Management Inspections and Reviews

Page 1: Project Management Inspections and Reviews

Project ManagementInspections and Reviews

1 February

Page 2: Project Management Inspections and Reviews

What you should be doing Update web site and functional spec

per meeting Write a draft contract

Post on web email me when you have it done and I

will give you feedback as soon as possible

Signed contracts due next week. You do not need to schedule a special meeting with clients to sign

Page 3: Project Management Inspections and Reviews

Contract Content Key goals and requirements Deliverables

Deliverable dates (milestones) Software Testing Documentation (user, administrative, maintenance)

Client responsibilities Meetings (when and with whom)

Constraints, risks and dependencies What needs to be included Template

Page 4: Project Management Inspections and Reviews

Project Management Tools

PERT ChartsGantt Charts

Page 5: Project Management Inspections and Reviews

PERT Charts Critical path analysis or method

Program Evaluation and Review Technique Also known as activity networks

Developed by Navy in 1958 Three stages:

Planning (tasks and sequence) Scheduling (start and finish times) Analysis (float and revisions)

Two different models Activities are nodes (most common) or arcs

Page 6: Project Management Inspections and Reviews

Pert Chart Activity Box

Page 7: Project Management Inspections and Reviews

Pert Charts

Page 8: Project Management Inspections and Reviews

CPM: Critical Path Method

Alternative to PERT Dupont 1957 Graphical view of project Predicts time required to complete Shows which activities are critical

to maintaining the schedule

Page 9: Project Management Inspections and Reviews

Planning: PERT and CPM1. Identify the specific

activities and milestones. 2. Determine the proper

sequence of the activities.

3. Construct a network diagram.

4. Estimate the time required for each activity.

5. Determine the critical path.

6. Update the PERT chart as the project progresses.

1. Specify the individual activities.

2. Determine the sequence of those activities.

3. Draw a network diagram. 4. Estimate the completion

time for each activity. 5. Identify the critical path

(longest path through the network)

6. Update the CPM diagram as the project progresses.

Page 10: Project Management Inspections and Reviews

Gantt Charts

Milestone charts Invented by Harvey Gantt in 1916 Advantages

Less detailed Amenable to management overlays

Page 11: Project Management Inspections and Reviews

Gantt Chart

Page 12: Project Management Inspections and Reviews

Gantt Chart with Overlays

Page 13: Project Management Inspections and Reviews

Scheduling Steps and Tools Put together minimal solution

Primary requirements Start with external commitments

Product descriptions Milestones from contract

Introduce internal milestones Work breakdown structure Product Flow PERT Chart, Gantt chart

Focus on the risks Risks from contract

Add next level of features where possible Secondary requirements

Page 14: Project Management Inspections and Reviews

Project Plan for this project Use simple Excel spreadsheet (or equivalent)

Deliverable/Milestone Responsible Due Revision 1 Delivered

project web site Sam 20-Jan 20-Janarchitecture Jane (all) 8-Feb 15-Feb 23-Febproject plan Harry 10-Feb 15-Feb 16-Febinitial user interface Sam 13-Feb 15-Feb 18-Febcontract Jane 20-Feb 15-Feb 18-Feb

Page 15: Project Management Inspections and Reviews

What you should be able to tell from your project plan

What is Joe working on this week? Who can help me if I run into

trouble? If I have to choose an activity to be

late, which one will impact the project more?

Page 16: Project Management Inspections and Reviews

Software Sources Open source tools:

dmoz.org/Computers/Software/Project_Management/Open_Source/

Page 17: Project Management Inspections and Reviews

Reviews and Inspections

Page 18: Project Management Inspections and Reviews

Reviews and Inspections Why?

Developer can’t correct unseen errors More eyes to catch problems Earlier is cheaper

Integration fix typically 3-10 times the cost at design

Difference in terms Review implies completed work, often

reviewed by someone at a different level Inspection implies peer review of work in

progress

Page 19: Project Management Inspections and Reviews

Inspections

Introduced by Michael Fagin in 76 (IBM Systems Journal)

Formalized process Specific roles and steps Heavy preparation and follow-up

Used for documents and code

Page 20: Project Management Inspections and Reviews

Will you review or inspect?What will you review or inspect?How will you review or inspect?