Project Management for Construction_ Organization and Use of Project Information

download Project Management for Construction_ Organization and Use of Project Information

of 16

Transcript of Project Management for Construction_ Organization and Use of Project Information

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    1/16

    Go Up to Table of Contents

    Go To Chapter 13

    (Quality Control and

    Safety During

    Construction)

    Go To Chapter 14

    (Organization and

    Use of Project

    Information)

    Organization and Use of Project

    Information

    Types of Project Information

    Accuracy and Use of Information

    Computerized Organization and Use of

    Information

    Organizing Information in Databases Relational Model of Databases

    Other Conceptual Models of Databases

    Centralized Database Management

    Systems

    Databases and Applications Programs

    Information Transfer and Flow

    References

    Problems

    Footnotes

    14. Organization and Use of Project Information

    14.1 Types of Project Information

    Construction projects inevitably generate enormous and complex sets of information. Effectively managing this

    bulk of information to insure its availability and accuracy is an important managerial task. Poor or missing

    information can readily lead to project delays, uneconomical decisions, or even the complete failure of the

    desired facility. Pity the owner and project manager who suddenly discover on the expected delivery date that

    important facility components have not yet been fabricated and cannot be delivered for six months! With better

    information, the problem could have been identified earlier, so that alternative suppliers might have been located

    or schedules arranged. Both project design and control are crucially dependent upon accurate and timely

    information, as well as the ability to use this information effectively. At the same time, too much unorganized

    information presented to managers can result in confusion and paralysis of decision making.

    As a project proceeds, the types and extent of the information used by the various organizations involved will

    change. A listing of the most important information sets would include:

    cash flow and procurement accounts for each organization,

    intermediate analysis results during planning and design,

    design documents, including drawings and specifications,

    construction schedules and cost estimates,quality control and assurance records,

    chronological files of project correspondence and memorandum,

    construction field activity and inspection logs,

    legal contracts and regulatory documents.

    Some of these sets of information evolve as the project proceeds. The financial accounts of payments over the

    entire course of the project is an example of overall growth. The passage of time results in steady additions in

    these accounts, whereas the addition of a new actor such as a contractor leads to a sudden jump in the number

    of accounts. Some information sets are important at one stage of the process but may then be ignored. Common

    examples include planning or structural analysis databases which are not ordinarily used during construction or

    operation. However, it may be necessary at later stages in the project to re-do analyses to consider desired

    changes. In this case, archival information storage and retrieval become important. Even after the completion of

    construction, an historical record may be important for use during operation, to assess responsibilities in case of

    facility failures or for planning similar projects elsewhere.

    The control and flow of information is also important for collaborative work environments, where manyprofessionals are working on different aspects of a project and sharing information. Collaborative work

    environments provide facilities for sharing datafiles, tracing decisions, and communication via electronic mail or

    video conferencing. The datastores in these collaborative work environments may become very large.

    Based on several construction projects, Maged Abdelsayed of Tardif, Murray & Assoc (Quebec, Canada)

    estimated the following average figures for a typical project of US$10 million:

    Number of participants (companies): 420 (including all suppliers and sub-sub-contractors)

    Number of participants (individuals): 850

    Number of different types of documents generated: 50

    Number of pages of documents: 56,000

    Number of bankers boxes to hold project documents: 25

    Number of 4 drawers filin cabinets: 6

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 1/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    2/16

    While there may be substantial costs due to inaccurate or missing information, there are also significant costs

    associated with the generation, storage, transfer, retrieval and other manipulation of information. In addition to the

    costs of clerical work and providing aids such as computers, the organization and review of information

    command an inordinate amount of the attention of project managers, which may be the scarcest resource on any

    construction project. It is useful, therefore, to understand the scope and alternatives for organizing project

    information.

    Back to top

    14.2 Accuracy and Use of Information

    Numerous sources of error are expected for project information. While numerical values are often reported to

    the nearest cent or values of equivalent precision, it is rare that the actual values are so accurately known. Livingwith some uncertainty is an inescapable situation, and a prudent manager should have an understanding of the

    uncertainty in different types of information and the possibility of drawing misleading conclusions.

    We have already discussed the uncertainty inherent in making forecasts of project costs and durations sometime

    in the future. Forecast uncertainty also exists in the short term. For example, consider estimates of work

    completed. Every project manager is familiar with situations in which the final few bits of work for a task take an

    inordinate amount of time. Unforeseen problems, inadequate quality on already completed work, lack of

    attention, accidents, or postponing the most difficult work problems to the end can all contribute to making the

    final portion of an activity actually require far more time and effort than expected. The net result is that estimates

    of the actual proportion of work completed are often inaccurate.

    Some inaccuracy in reports and estimates can arise from conscious choices made by workers, foremen or

    managers. If the value of insuring accuracy is thought to be low or nonexistent, then a rational worker will not

    expend effort or time to gather or to report information accurately. Many project scheduling systems flounder on

    exactly this type of non-reporting or mis-reporting. The original schedule can quickly become extremely

    misleading without accurate updating! Only if all parties concerned have specific mandates or incentives to reportaccurately will the data be reliable.

    Another source of inaccuracy comes from transcription errors of various sorts. Typographical errors, incorrect

    measurements from reading equipment, or other recording and calculation errors may creep into the sets of

    information which are used in project management. Despite intensive efforts to check and eliminate such errors,

    their complete eradication is virtually impossible.

    One method of indicating the relative accuracy of numerical data is to report ranges or expected deviations of an

    estimate or measurement. For example, a measurement might be reported as 198 ft. + 2 ft. There are two

    common interpretations of these deviations. First, a range (such as + 2) might be chosen so that the actual value

    is certain to be within the indicated range. In the case above, the actual length would be somewhere between

    196 and 200 feet with this convention. Alternatively, this deviation might indicate the typicalrange of the estimate

    or measurement. In this case, the example above might imply that there is, say, a two-thirds chance that the

    actual length is between 196 and 200.

    When the absolute range of a quantity is very large or unknown, the use of a statistical standard deviation as a

    measure of uncertainty may be useful. If a quantity is measured n times resulting is a set of values x i (i = 1,2,...,n),

    then the average or mean value then the average or mean value is given by:

    (14.1)

    The standard deviation can be estimated as the square root s of the sample variance s2, i.e. , where:

    (14.2)

    The standard deviation is a direct indicator of the spread or variability in a measurement, in the same units as

    the measurement itself. Higher values of the standard deviation indicate greater and greater uncertainty about theexact value of the measurement. For the commonly encountered normal distribution of a random variable, the

    average value plus or minus one standard deviation, + , will include about two-thirds ofx the actual

    occurrences. A related measure of random variability is the coefficient of variation, defined as the ratio of the

    standard deviation to the mean:

    (14.3)

    Thus, a coefficient of variation indicates the variability as a proportion of the expected value. A coefficient of

    variation equal to one (c = 1) represents substantial uncertainty, whereas a value such as c = 0.1 or ten percent

    indicates much smaller variability.

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 2/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    3/16

    interpreting recorded information without involving any conceptual understanding of how the information is

    actually gathered, stored and recorded or how work on the project actually proceeds.

    Example 14-1: Sources of Delay and Cost Accounts

    It is common in construction activity information to make detailed records of costs incurred and

    work progress. It is less common to keep detailed records of delays and their causes, even though

    these delays may be the actual cause of increased costs and lower productivity. [1] Paying

    exclusive attention to costaccounts in such situations may be misleading. For example, suppose that

    the accounts for equipment and material inventories show cost savings relative to original estimates,

    whereas the costs associated with particular construction activities show higher than estimated

    expenditures. In this situation, it is not necessarily the case that the inventory function is performing

    well, whereas the field workers are the cause of cost overrun problems. It may be that construction

    activities are delayed by lack of equipment or materials, thus causing cost increases. Keeping alarger inventory of materials and equipment might increase the inventory account totals, but lead to

    lower overall costs on the project. Better yet, more closely matching demands and supplies might

    reduce delay costs without concurrent inventory cost increases. Thus, simply examining cost

    account information may not lead to a correct diagnosis of a problem or to the correct managerial

    responses.

    Example 14-2: Interest Charges

    Financial or interest charges are usually accumulated in a separate account for projects, while the

    accounts associated with particular activities represent actual expenditures. For example, planning

    activities might cost $10,000 for a small project during the first year of a two year project. Since

    dollar expenditures have a time value, this $10,000 cost in year 1 is notequivalent in value to a

    $10,000 cost in year 2. In particular, financing the early $10,000 involves payment of interest or,

    similarly, the loss of investment opportunities. If the borrowing rate was 10%, then financing the first

    year $10,000 expenditure would require $10,000 x 0.10 = $1,000 and the value of the expenditure

    by the end of the second year of the project would be $11,000. Thus, some portion of the overallinterest charges represents a cost associated with planning activities. Recognizing the true value of

    expenditures made at different periods of time is an important element in devising rational planning

    and management strategies.

    Back to top

    14.3 Computerized Organization and Use of Information

    Numerous formal methods and possible organizations exist for the information required for project management.

    Before discussing the details of computations and information representation, it will be useful to describe a record

    keeping implementation, including some of the practical concerns in design and implementation. In this section,

    we shall describe a computer based system to provide construction yard and warehouse management

    information from the point of view of the system users. [2] In the process, the usefulness of computerized

    databases can be illustrated.

    A yard or warehouse is used by most construction firms to store equipment and to provide an inventory of

    materials and parts needed for projects. Large firms may have several warehouses at different locations so as to

    reduce transit time between project sites and materials supplies. In addition, local "yards" or "equipment sheds"

    are commonly provided on the job site. Examples of equipment in a yard would be drills, saws, office trailers,

    graders, back hoes, concrete pumps and cranes. Material items might include nails, plywood, wire mesh, forming

    lumber, etc.

    In typical construction warehouses, written records are kept by warehouse clerks to record transfer or return of

    equipment to job sites, dispatch of material to jobs, and maintenance histories of particular pieces of equipment.

    In turn, these records are used as the basis for billing projects for the use of equipment and materials. For

    example, a daily charge would be made to a project for using a concrete pump. During the course of a month,

    the concrete pump might spend several days at different job sites, so each project would be charged for its use.

    The record keeping system is also used to monitor materials and equipment movements between sites so that

    equipment can be located.

    One common mechanism to organize record keeping is to fill out cards recording the transfer of items to or from

    a job site. Table 14-1 illustrates one possible transfer record. In this case, seven items were requested for the

    Carnegie-Mellon job site (project number 83-1557). These seven items would be loaded on a delivery truck,along with a copy of the transfer record. Shown in Table 14-1 is a code number identifying each item (0609.02,

    0609.03, etc.), the quantity of each item requested, an item description and a unit price. For equipment items, an

    equipment number identifying the individual piece of equipment used is also recorded, such as grinder No. 4517

    in Table 14-1; a unit price is not specified for equipment but a daily rental charge might be imposed.

    TABLE 14-1 Illustration of a Construction Warehouse Transfer Record

    TRANSFER SHEET NUMBER 100311

    Deliver To: Carnegie-Mellon

    Received From: Pittsburgh Warehouse

    Job. No. 83-1557

    Job No. 99-PITT

    ITEM NO. EQ. NO. QTY DESCRIPTION UNIT PRICE

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 3/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    4/16

    0996.01

    0607.03

    0172.00

    0181.53

    4517

    3

    4

    1

    1

    Paint, Spray

    Plywood, 4 x 8 x 1/4"

    Grinder

    Grinding Wheel, 6" Cup

    5.57

    11.62

    14.97

    Preparer: Vicki Date: x/xx/xx

    Transfer sheets are numbered (such as No. 100311 in Table 14-1), dated and the preparer identified to facilitate

    control of the record keeping process. During the course of a month, numerous transfer records of this type are

    accumulated. At the end of a month, each of the transfer records is examined to compile the various items or

    equipment used at a project and the appropriate charges. Constructing these bills would be a tedious manualtask. Equipment movements would have to be tracked individually, days at each site counted, and the daily

    charge accumulated for each project. For example, Table 14- 1 records the transfer of grinder No. 4517 to a job

    site. This project would be charged a daily rental rate until the grinder was returned. Hundreds or thousands of

    individual item transfers would have to be examined, and the process of preparing bills could easily require a

    week or two of effort.

    In addition to generating billing information, a variety of reports would be useful in the process of managing a

    company's equipment and individual projects. Records of the history of use of particular pieces of equipment are

    useful for planning maintenance and deciding on the sale or scrapping of equipment. Reports on the cumulative

    amount of materials and equipment delivered to a job site would be of obvious benefit to project managers.

    Composite reports on the amount, location, and use of pieces of equipment of particular types are also useful in

    making decisions about the purchase of new equipment, inventory control, or for project planning. Unfortunately,

    producing each of these reports requires manually sifting through a large number of transfer cards. Alternatively,

    record keeping for these specific projects could have to proceed by keeping multiple records of the same

    information. For example, equipment transfers might be recorded on (1) a file for a particular piece of equipment

    and (2) a file for a particular project, in addition to the basic transfer form illustrated in Table 14-1. Even withthese redundant records, producing the various desired reports would be time consuming.

    Organizing this inventory information in a computer program is a practical and desirable innovation. In addition to

    speeding up billing (and thereby reducing borrowing costs), application programs can readily provide various

    reports orviews of the basic inventory information described above. Information can be entered directly to the

    computer program as needed. For example, the transfer record shown in Table 14-1 is based upon an input

    screen to a computer program which, in turn, had been designed to duplicate the manual form used prior to

    computerization. Use of the computer also allows some interactive aids in preparing the transfer form. This type

    of aid follows a simple rule: "Don't make the user provide information that the system already knows." [3] In

    using the form shown in Table 14-1, a clerk need only enter the code and quantity for an item; the verbal

    description and unit cost of the item then appear automatically. A copy of the transfer form can be printed locally,

    while the data is stored in the computer for subsequent processing. As a result, preparing transfer forms and

    record keeping are rapidly and effectively performed.

    More dramatically, the computerized information allows warehouse personnel both to ask questions about

    equipment management and to readily generate the requisite data for answering such questions. The records of

    transfers can be readily processed by computer programs to develop bills and other reports. For example,

    proposals to purchase new pieces of equipment can be rapidly and critically reviewed after summarizing the

    actual usage of existing equipment. Ultimately, good organization of information will typically lead to the desire to

    store new types of data and to provide new views of this information as standard managerial tools.

    Of course, implementing an information system such as the warehouse inventory database requires considerable

    care to insure that the resulting program is capable of accomplishing the desired task. In the warehouse inventory

    system, a variety of details are required to make the computerized system an acceptable alternative to a long

    standing manual record keeping procedure. Coping with these details makes a big difference in the system's

    usefulness. For example, changes to the status of equipment are generally made by recording transfers as

    illustrated in Table 14-1. However, a few status changes are not accomplished by physical movement. One

    example is a charge for air conditioning in field trailers: even though the air conditioners may be left in the field,

    the construction project should not be charged for the air conditioner after it has been turned off during the cold

    weather months. A special status change report may be required for such details. Other details of record keeping

    require similar special controls.

    Even with a capable program, simplicity of design for users is a critical factor affecting the successfulimplementation of a system. In the warehouse inventory system described above, input forms and initial reports

    were designed to duplicate the existing manual, paper-based records. As a result, warehouse clerks could readily

    understand what information was required and its ultimate use. A good rule to follow is the Principle of Least

    Astonishment: make communications with users as consistent and predictable as possible in designing programs.

    Finally, flexibility of systems for changes is an important design and implementation concern. New reports or

    views of the data is a common requirement as the system is used. For example, the introduction of a new

    accounting system would require changes in the communications procedure from the warehouse inventory system

    to record changes and other cost items.

    In sum, computerizing the warehouse inventory system could save considerable labor, speed up billing, and

    facilitate better management control. Against these advantages must be placed the cost of introducing computer

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 4/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    5/16

    14.4 Organizing Information in Databases

    Given the bulk of information associated with construction projects, formal organization of the information is

    essential so as to avoid chaos. Virtually all major firms in the arena of project management have computer based

    organization of cost accounts and other data. With the advent of micro-computer database managers, it is

    possible to develop formal, computerized databases for even small organizations and projects. In this section, we

    will discuss the characteristics of such formal databases. Equivalent organization of information for manual

    manipulation is possible but tedious. Computer based information systems also have the significant advantage of

    rapid retrieval for immediate use and, in most instances, lower overall costs. For example, computerized

    specifications writing systems have resulted in well documented savings. These systems have records of common

    specification phrases or paragraphs which can be tailored to specific project applications. [4]

    Formally, a database is a collection of stored operational information used by the management and application

    systems of some particular enterprise. [5] This stored information has explicit associations or relationships

    depending upon the content and definition of the stored data, and these associations may themselves be

    considered to be part of the database. Figure 14-1 illustrates some of the typical elements of a database. The

    internal modelis the actual location and representation of the stored data. At some level of detail, it consists of

    the strings of "bits" which are stored in a computer's memory, on the tracks of a recording disk, on a tape, or on

    some other storage device.

    Figure 14-1 Illustration of a Database Management System Architecture

    A manager need not be concerned with the details of data storage since this internal representation and

    manipulation is regulated by theDatabase Manager Program (DBM). The DBM is the software program that

    directs the storage, maintenance, manipulation and retrieval of data. Users retrieve or store data by issuing

    specific requests to the DBM. The objective of introducing a DBM is to free the user from the detail of exactly

    how data are stored and manipulated. At the same time, many different users with a wide variety of needs can

    use the same database by calling on the DBM. Usually the DBM will be available to a user by means of a special

    query language. For example, a manager might ask a DBM to report on all project tasks which are scheduled tobe underway on a particular date. The desirable properties of a DBM include the ability to provide the user with

    ready access to the stored data and to maintain the integrity and security of the data. Numerous commercial

    DBM exist which provide these capabilities and can be readily adopted to project management applications.

    While the actual storage of the information in a database will depend upon the particular machine and storage

    media employed, a Conceptual Data Modelexists which provides the user with an idea or abstract

    representation of the data organization. (More formally, the overall configuration of the information in the

    database is called the conceptual schema.) For example, a piece of data might be viewed as a particular value

    within a recordof a datafile. In this conceptual model, a datafile for an application system consists of a series of

    records with pre-defined variables within each record. A record is simply a sequence of variable values, which

    may be text characters or numerals. This datafile model is one of the earliest and most important data

    organization structures. But other views of data organization exist and can be exceedingly useful. The next section

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 5/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    6/16

    database. In some systems, data dictionaries are limited to descriptions of the items in the database. More

    general systems employ the data dictionary as the information source for anything dealing with the database

    systems. It documents the design of the database: what data are stored, how the data is related, what are the

    allowable values for data items, etc. The data dictionary may also contain user authorizations specifying who may

    have access to particular pieces of information. Another important element of the data dictionary is a specification

    of allowable ranges for pieces of data; by prohibiting the input of erroneous data, the accuracy of the database

    improves.

    External models are the means by which the users view the database. Of all the information in the database, one

    particular user's view may be just a subset of the total. A particular view may also require specific translation or

    manipulation of the information in the database. For example, the external modelfor a paycheck writing

    program might consist solely of a list of employee names and salary totals, even if the underlying database would

    include employee hours and hourly pay rates. As far as that program is concerned, no other data exists in the

    database. The DBM provides a means of translating particular external models or views into the overall datamodel. Different users can view the data in quite distinct fashions, yet the data itself can be centrally stored and

    need not be copied separately for each user. External models provide the format by which any specific

    information needed is retrieved. Database "users" can be human operators or other application programs such as

    the paycheck writing program mentioned above.

    Finally, theDatabase Administratoris an individual or group charged with the maintenance and design of the

    database, including approving access to the stored information. The assignment of the database administrator

    should not be taken lightly. Especially in large organizations with many users, the database administrator is vital to

    the success of the database system. For small projects, the database administrator might be an assistant project

    manager or even the project manager.

    Back to top

    14.5 Relational Model of Databases

    As an example of how data can be organized conceptually, we shall describe the relational data model. In thisconceptual model, the data in the database is viewed as being organized into a series ofrelations or tables of

    data which are associated in ways defined in the data dictionary. A relation consists of rows of data with columns

    containing particular attributes. The term "relational" derives from the mathematical theory of relations which

    provides a theoretical framework for this type of data model. Here, the terms "relation" and data "table" will be

    used interchangeably. Table 14-2 defines one possible relation to record unit cost data associated with particular

    activities. Included in the database would be one row (or tuple) for each of the various items involved in

    construction or other project activities. The unit cost information associated with each item is then stored in the

    form of the relation defined in Table 14-2.

    TABLE 14-2 Illustration of a Relation Description: Unit Price Information Attributes

    Attribute Name Attribute Description Attribute Type Key

    ITEM_CODE

    DESCRIPTION

    WORK_UNIT

    CREW_CODE

    OUTPUT

    TIME_UNIT

    MATL_UNIT_COST

    DATEMCOS

    INSTCOST

    DATEICOS

    Item Code Number

    Item Description

    Standard Unit of

    Work for the Item

    Standard Crew Code for Activity

    Average Productivity of Crew

    Standard Unit of OUTPUT

    Material Unit Cost

    Date of MATL_UNIT_COST

    Installation Unit Cost

    Date of INSTCOST

    Pre-defined Code

    Text

    Text

    (restricted to allowable units)

    Pre-defined Code

    Numerical

    Text

    Numerical

    Date Text

    Numerical

    Date Text

    Yes

    No

    No

    No

    No

    No

    No

    No

    No

    No

    Using Table 14-2, a typical unit cost entry for an activity in construction might be:

    ITEM_CODE: 04.2-66-025

    DESCRIPTION: common brick masonry, 12" thick wall, 19.0 bricks per S.F.

    WORK_UNIT: 1000 bricks

    CREW_CODE: 04.2-3

    OUTPUT: 1.9

    TIME_UNIT: Shift

    MATL_UNIT_COST: 124

    DATEMCOS: June-09-79

    INSTCOST: 257

    DATEICOS: August-23-79

    This entry summarizes the unit costs associated with construction of 12" thick brick masonry walls, as indicated

    by the item DESCRIPTION. The ITEM_CODE is a numerical code identifying a particular activity. This code

    might identify general categories as well; in this case, 04.2 refers to general masonry work. ITEM_CODE might

    be based on the MASTERFORMAT or other coding scheme. The CREW_CODE entry identifies the standard

    crew which would be involved in the activity. The actual composition of the standard crew would be found in a

    CREW RELATION under the entry 04.2-3, which is the third standard crew involved in masonry work (04.2).

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 6/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    7/16

    WORK_UNIT, OUTPUT and TIME_UNIT summarize the expected output for this task with a standard crew

    and define the standard unit of measurement for the item. In this case, costs are given per thousand bricks per

    shift. Finally, material (MATL_UNIT_COST) and installation (INSTCOSTS) costs are recorded along with the

    date (DATEMCOS and DATEICOS) at which the prices were available and entered in the database. The date

    of entry is useful to insure that any inflation in costs can be considered during use of the data.

    The data recorded in each row could be obtained by survey during bid preparations, from past project

    experience or from commercial services. For example, the data recorded in the Table 14-2 relation could be

    obtained as nationwide averages from commercial sources.

    An advantage of the relational database model is that the number of attributes and rows in each relation can be

    expanded as desired. For example, a manager might wish to divide material costs (MATL_UNIT_COST) into

    attributes for specific materials such as cement, aggregate and other ingredients of concrete in the unit costrelation defined in Table 14-2. As additional items are defined or needed, their associated data can be entered in

    the database as another row (or tuple) in the unit cost relation. Also, new relations can be defined as the need

    arises. Hence, the relational model of database organization can be quite flexible in application. In practice, this is

    a crucial advantage. Application systems can be expected to change radically over time, and a flexible system is

    highly desirable.

    With a relational database, it is straightforward to issue queries for particular data items or to combine data from

    different relations. For example, a manager might wish to produce a report of the crew composition needed on a

    site to accomplish a given list of tasks. Assembling this report would require accessing the unit price information

    to find the standard crew and then combining information about the construction activity or item (eg. quantity

    desired) with crew information. However, to effectively accomplish this type of manipulation requires the

    definition of a "key" in each relation.

    In Table 14-2, the ITEMCODE provides a unique identifier orkey for each row. No other row should have the

    same ITEMCODE in any one relation. Having a unique key reduces the redundancy of data, since only one row

    is included in the database for each activity. It also avoids error. For example, suppose one queried the database

    to find the material cost entered on a particular date. This response might be misleading since more than onematerial cost could have been entered on the same date. Similarly, if there are multiple rows with the same

    ITEMCODE value, then a query might give erroneous responses if one of the rows was out of date. Finally, each

    row has only a single entry for each attribute. [6]

    The ability to combine or separate relations into new arrangements permits the definition of alternative views or

    external models of the information. Since there are usually a number of different users of databases, this can be

    very useful. For example, the payroll division of an organization would normally desire a quite different

    organization of information about employees than would a project manager. By explicitly defining the type and

    organization of information a particular user group or application requires, a specific view or subset of the entire

    database can be constructed. This organization is illustrated in Fig. 14-1 with the DATA DICTIONARY serving

    as a translator between the external data models and the database management system.

    Behind the operations associated with querying and manipulating relations is an explicit algebraic theory. This

    algebra defines the various operations that can be performed on relations, such as union (consisting of all rows

    belonging to one or the other of two relations), intersection (consisting of all rows belonging to both of two

    relations), minus (consisting of all rows belonging to one relation and not another), or projection (consisting of asubset of the attributes from a relation). The algebraic underpinnings of relational databases permits rigorous

    definitions and confidence that operations will be accomplished in the desired fashion. [7]

    Example 14-3: A Subcontractor Relation

    As an illustration of the preceding discussion, consider the problem of developing a database of

    possible subcontractors for construction projects. This database might be desired by the cost

    estimation department of a general contractor to identify subcontractors to ask to bid on parts of a

    project. Appropriate subcontractors appearing in the database could be contacted to prepare bids

    for specific projects. Table 14-3 lists the various attributes which might be required for such a list

    and an example entry, including the subcontractor's name, contact person, address, size (large,

    medium or small), and capabilities.

    TABLE 14-3 Subcontractor Relation Example

    Attribute Example

    NAMECONTACT

    PHONE

    STREET

    CITY

    STATE

    ZIPCODE

    SIZE

    CONCRETE

    ELECTRICAL

    MASONRY

    etc.

    XYZ Electrical Co.Betty XYZ

    (412) xxx-xxxx

    xxx Mulberry St.

    Pittsburgh

    PA

    152xx

    large

    no

    yes

    no

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 7/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    8/16

    To use this relation, a cost estimator might be interested in identifying large, electrical subcontractors

    in the database. A query typed into the DBM such as:

    SELECT from SUBCONTRACTORS

    where SIZE = Large and ELECTRICAL = Yes

    would result in the selection of all large subcontractors performing electrical work in the

    subcontractor's relation. More specifically, the estimator might want to find subcontractors in a

    particular state:

    SELECT from SUBCONTRACTORS

    where SIZE = Large and ELECTRICAL = Yes and STATE = VI.

    In addition to providing a list of the desired subcontractors' names and addresses, a utilityapplication program could also be written which would print mailing labels for the selected firms.

    Other portions of the general contracting firm might also wish to use this list. For example, the

    accounting department might use this relation to record the addresses of subcontractors for

    payment of invoices, thereby avoiding the necessity to maintain duplicate files. In this case, the

    accounting code number associated with each subcontractor might be entered as an additional

    attribute in the relation, and the accounting department could find addresses directly.

    Example 14-4: Historical Bridge Work Relation

    As another simple example of a data table, consider the relation shown in Table 14-0 which might

    record historical experience with different types of bridges accumulated by a particular agency. The

    actual instances or rows of data in Table 14-4 are hypothetical. The attributes of this relation are:

    PROJECT NUMBER - a 6-digit code identifying the particular project.

    TYPE OF BRIDGE - a text field describing the bridge type. (For retrieval purposes, a

    numerical code might also be used to describe bridge type to avoid any differences interminology to describe similar bridges).

    LOCATION - The location of the project.

    CROSSING - What the bridge crosses over, eg. a river.

    SITE CONDITIONS - A brief description of the site peculiarities.

    ERECTION TIME - Time required to erect a bridge, in months.

    SPAN - Span of the bridge in feet.

    DATE - Year of bridge completion.

    ACTUAL-ESTIMATED COSTS - Difference of actual from estimated costs.

    These attributes could be used to answer a variety of questions concerning construction experience

    useful during preliminary planning.

    TABLE 14-4 Example of Bridge Work Relation

    Project

    Number

    Type of

    Bridge Location Crossing Site Conditions

    Erection

    Time

    (Months)

    Span

    (ft.)

    Estimated less

    Actual Cost

    169137

    170145

    197108

    Steel Plate

    Girder

    Concrete

    Arch

    Steel Truss

    Altoona

    Pittsburgh

    Allentown

    Railroad

    River

    Highway

    200' Valley

    Limestone

    250' High

    Sandy Loam

    135' Deep Pile

    Foundation

    5

    7

    8

    240

    278

    256

    -$50,000

    -27,500

    35,000

    As an example, suppose that a bridge is to be built with a span of 250 feet, located in Pittsburgh

    PA, and crossing a river with limestone sub-strata. In initial or preliminary planning, a designer might

    query the database four separate times as follows:

    SELECT from BRIDGEWORK where SPAN > 200 and SPAN < 300 and where

    CROSSING = "river"

    SELECT from BRIDGEWORK where SPAN > 200 and SPAN < 300 and where SITECONDITIONS = "Limestone"

    SELECT from BRIDGEWORK where TYPE OF BRIDGE = "Steel Plate Girder" and

    LOCATION = "PA"

    SELECT from BRIDGEWORK where SPAN < 300 and SPAN > 200 and ESTIMATED

    LESS ACTUAL COST < 100,000.

    Each SELECT operation would yield the bridge examples in the database which corresponds to the

    desired selection criteria. In practice, an input/output interpreter program should be available to

    translate these inquiries to and from the DBM and an appropriate problem oriented language.

    The four queries may represent subsequent thoughts of a designer faced with these problem

    conditions. He or she may first ask, "What experience have we had with bridges of this span over

    " "

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 8/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    9/16

    Back to top

    14.6 Other Conceptual Models of Databases

    While the relational model offers a considerable amount of flexibility and preserves considerable efficiency, there

    are several alternative models for organizing databases, including network and hierarchical models. The

    hierarchical model is a tree structure in which information is organized as branches and nodes from a particular

    base. [8] As an example, Figure 14-2 illustrates a hierarchical structure for rented equipment costs. In this case,

    each piece of equipment belongs to a particular supplier and has a cost which might vary by the duration of use.

    To find the cost of a particular piece of equipment from a particular supplier, a query would first find the supplier,

    then the piece of equipment and then the relevant price.

    The hierarchical model has the characteristic that each item has a single predecessor and a variable number of

    subordinate data items. This structure is natural for many applications, such as the equipment cost information

    described above. However, it might be necessary to construct similar hierarchies for each project to record the

    equipment used or for each piece of equipment to record possible suppliers. Otherwise, generating these lists of

    assignments from the database illustrated in Figure 14-2 would be difficult. For example, finding the least

    expensive supplier of a crane might involve searching every supplier and every equipment node in the database to

    find all crane prices.

    Figure 14-2 Hierarchical Data Organization

    The network model or database organization retains the organization of information on branches and nodes, but

    does not require a tree of structure such as the one in Figure 14-2. [9] This gives greater flexibility but does not

    necessarily provide ease of access to all data items. For example, Figure 14-3 shows a portion of a network

    model database for a building. The structural member shown in the figure is related to four adjoining members,

    data on the joints designed for each end, an assembly related to a room, and an aggregation for similar members

    to record member specifications.

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 9/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    10/16

    Figure 14-3 Example of a Network Data Model

    While the early, large databases were based on the hierarchical or network organizations, the relational model is

    now preferred in many applications due to its flexibility and conceptual simplicity. Relational databases form the

    kernel for large systems such as ORACLE or SAP. However, databases distributed among numerous servers

    may have a network structure (as in Figure 14-3), with full relational databases contained at one or more nodes.

    Similarly, "data warehouse" organizations may contain several different types of databases and information files.

    For these data warehouses, more complicated search approaches are essential, such as automatic indexing of

    multi-media files such as photographs.

    More recently, some new forms of organized databases have appeared, spurred in part by work in artificial

    intelligence. For example, Figure 14-4 illustrates a frame data structure used to represent a building design

    element. This frame describes the location, type, cost, material, scheduled work time, etc. for a particular

    concrete footing. A frame is a general purpose data representation scheme in which information is arranged inslots within a named frame. Slots may contain lists, values, text, procedural statements (such as calculation rules),

    pointers or other entities. Frames can be inter-connected so that information may be inheritedbetween slots.

    Figure 14-5 illustrates a set of inter-connected frames used to describe a building design and construction plan.

    [10]Object orienteddata representation is similar in that very flexible local arrangements of data are permitted.

    While these types of data storage organizations are active areas of research, commercial database systems based

    on these organizations are not yet available.

    Figure 14-4 Illustration of Data Stored in a Frame

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 10/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    11/16

    Figure 14-5 Illustration of a Frame Based Data Storage Hierarchy

    Back to top

    14.7 Centralized Database Management Systems

    Whichever conceptual model or database management system is adopted, the use of a central database

    management system has a number of advantages and some costs compared to the commonly employed special

    purpose datafiles. A datafile consists of a set of records arranged and defined for a single application system.

    Relational information between items in a record or between records is not explicitly described or available to

    other application systems. For example, a file of project activity durations and scheduled times might be

    assembled and manipulated by a project scheduling system. This datafile would not necessarily be available to

    the accounting system or to corporate planners.

    A centralized DBM has several advantages over such stand-alone systems: [11]

    Reduced redundancy good planning can allow duplicate or similar data stored in different files for

    different applications to be combined and stored only once.

    Improved availability information may be made available to any application program through the use of

    the DBM

    Reduced inconsistency if the same data is stored in more than one place, then updating in one place and

    not everywhere can lead to inconsistencies in the database.

    Enforced data security authorization to use information can be centralized.

    For the purpose of project management, the issue of improved availability is particularly important. Most

    application programs create and own particular datafiles in the sense that information is difficult to obtain directly

    for other applications. Common problems in attempting to transfer data between such special purpose files are

    missing data items, unusable formats, and unknown formats.

    As an example, suppose that the Purchasing Department keeps records of equipment rental costs on each

    project underway. This data is arranged so that payment of invoices can be handled expeditiously and project

    accounts are properly debited. The records are arranged by individual suppliers for this purpose. These records

    might not be particularly useful for the purpose of preparing cost estimates since:

    Some suppliers might not exist in the historical record.

    Finding the lowest cost supplier for particular pieces of equipment would be exceedingly tedious since

    every record would have to be read to find the desired piece of equipment and the cost.

    No direct way of abstracting the equipment codes and prices might exist.

    An alternative arrangement might be to separately record equipment rental costs in (1) the Purchasing

    Department Records, (2) the Cost Estimating Division, and (3) the Company warehouse. While these multiple

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 11/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    12/16

    A manager need not conclude from this discussion that initiating a formal database will be a panacea. Life is

    never so simple. Installing and maintaining databases is a costly and time consuming endeavor. A single database

    is particularly vulnerable to equipment failure. Moreover, a central database system may be so expensive and

    cumbersome that it becomes ineffective; we will discuss some possibilities for transferring information between

    databases in a later section. But lack of good information and manual information management can also be

    expensive.

    One might also contrast the operation of a formal, computerized database with that of a manual filing system. For

    the equipment supplier example cited above, an experienced purchasing clerk might be able to immediately find

    the lowest cost supplier of a particular piece of equipment. Making this identification might well occur in spite of

    the formal organization of the records by supplier organization. The experienced clerk will have his (or her) own

    subjective, conceptual model of the available information. This subjective model can be remarkably powerful.

    Unfortunately, the mass of information required, the continuing introduction of new employees, and the need for

    consistency on large projects make such manual systems less effective and reliable.

    Back to top

    14.8 Databases and Applications Programs

    The usefulness of a database organization is particularly evident in integrated design or management

    environments. In these systems, numerous applications programs share a common store of information. Data is

    drawn from the central database as needed by individual programs. Information requests are typically performed

    by including pre-defined function calls to the database management system within an application program. Results

    from one program are stored in the database and can be used by subsequent programs without specialized

    translation routines. Additionally, a user interface usually exists by which a project manager can directly make

    queries to the database. Figure 14-6 illustrates the role of an integrated database in this regard as the central data

    store.

    Figure 14-6 Illustration of an Integrated Applications System

    An architectural system for design can provide an example of an integrated system. [12] First, a database can

    serve the role of storing a library of information on standard architectural features and component properties.

    These standard components can be called from the database library and introduced into a new design. The

    database can also store the description of a new design, such as the number, type and location of individual

    building components. The design itself can be composed using an interactive graphics program. This program

    would have the capability to store a new or modified design in the database. A graphics program typically has the

    capability to compose numerous, two or three dimensional views of a design, to introduce shading (to represent

    shadows and provide greater realism to a perspective), and to allow editing (including moving, replicating, or

    sizing individual components). Once a design is completed and its description stored in a database, numerous

    analysis programs can be applied, such as:

    structural analysis,

    daylight contour programs to produce plots of available daylight in each room,

    a heat loss computation program

    area, volume and materials quantities calculations.

    Production information can also be obtained from the integrated system, such as:

    dimensioned plans, sections and elevations,

    component specifications,

    construction detail specifications,

    electrical layout,

    system isometric drawings,

    bills of quantities and materials.

    The advantage of an integrated system of this sort is that each program need only be designed to communicate

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 12/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    13/16

    program for joint design might be included in the design system described above. Similarly, a construction

    planning and cost estimating system might also be added.

    The use of integrated systems with open access to a database is not common for construction activities at the

    current time. Typically, commercial systems have a closed architecture with simple datafiles or a "captive,"

    inaccessible database management system. However, the benefits of an open architecture with an accessible

    database are considerable as new programs and requirements become available over time.

    Example 14-5: An Integrated System Design

    As an example, Figure 14-7 illustrates the computer aided engineering (CAE) system envisioned for

    the knowledge and information-intensive construction industry of the future. [13] In this system,

    comprehensive engineering and "business" databases support different functions throughout the life

    time of a project. The construction phase itself includes overlapping design and constructionfunctions. During this construction phase, computer aided design (CAD) and computer aided

    manufacturing (CAM) aids are available to the project manager. Databases recording the "as-built"

    geometry and specifications of a facility as well as the subsequent history can be particularly useful

    during the use and maintenance life cycle phase of the facility. As changes or repairs are needed,

    plans for the facility can be accessed from the database.

    Figure 14-7 Computer Aided Engineering in the Construction Industry

    (Reprinted with permission from from Y. Ohaski and M. Mukimo, "Computer-Aided Engineering

    in the Construction Industry,"Engineering with Computers, Vol. 1, no. 2, 1985.

    Back to top

    14.9 Information Transfer and Flow

    The previous sections outlined the characteristics of a computerized database. In an overabundance of optimism

    or enthusiasm, it might be tempting to conclude that all information pertaining to a project might be stored in a

    single database. This has never been achieved and is both unlikely to occur and undesirable in itself. Among the

    difficulties of such excessive centralization are:

    Existence of multiple firms or agencies involved in any project. Each organization must retain its

    own records of activities, whether or not other information is centralized. Geographic dispersion of work

    even within the same firm can also be advantageous. With design offices around the globe, fast track

    projects can have work underway by different offices 24 hours a day.

    Advantages of distributed processing. Current computer technology suggests that using a number of

    computers at the various points that work is performed is more cost effective than using a single,

    centralized mainframe computer. Personal computers not only have cost and access advantages, they also

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 13/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    14/16

    Database diseconomies of scale. As any database gets larger, it becomes less and less efficient to find

    desired information.

    Incompatible user perspectives. Defining a single data organization involves trade-offs between

    different groups of users and application systems. A good organization for one group may be poor for

    another.

    In addition to these problems, there will always be a set of untidy information which cannot be easily defined or

    formalized to the extent necessary for storage in a database.

    While a single database may be undesirable, it is also apparent that it is desirable to structure independent

    application systems or databases so that measurement information need only be manually recorded once and

    communication between the database might exist. Consider the following examples illustrating the desirability of

    communication between independent application systems or databases. While some progress has occurred, the

    level of integration and existing mechanisms for information flow in project management is fairly primitive. By andlarge, information flow relies primarily on talking, written texts of reports and specifications and drawings.

    Example 14-6: Time Cards

    Time card information of labor is used to determine the amount which employees are to be paid and

    to provide records of work performed by activity. In many firms, the system of payroll accounts

    and the database of project management accounts (i.e., expenditure by activity) are maintained

    independently. As a result, the information available from time cards is often recorded twice in

    mutually incompatible formats. This repetition increases costs and the possibility of transcription

    errors. The use of a preprocessor system to check for errors and inconsistencies and to format the

    information from each card for the various systems involved is likely to be a significant improvement

    (Figure 14-8). Alternatively, a communications facility between two databases of payroll and

    project management accounts might be developed.

    Figure 14-8 Application of an Input Pre-processor

    Example 14-7: Final Cos t Estimation, Scheduling and Monitoring

    Many firms maintain essentially independent systems for final cost estimation and project activity

    scheduling and monitoring. As a result, the detailed breakdown of the project into specific job

    related activities must be completely re-done for scheduling and monitoring. By providing a means

    ofrolling-overor transferring the final cost estimate, some of this expensive and time-consuming

    planning effort could be avoided.

    Example 14-8: Design Representation

    In many areas of engineering design, the use of computer analysis tools applied to facility modelshas become prevalent and remarkably effective. However, these computer-based facility models

    are often separately developed or encoded by each firm involved in the design process. Thus, the

    architect, structural engineer, mechanical engineer, steel fabricator, construction manager and others

    might all have separate computer-based representations of a facility. Communication by means of

    reproduced facility plans and prose specifications is traditional among these groups. While transfer

    of this information in a form suitable for direct computer processing is difficult, it offers obvious

    advantages in avoiding repetition of work, delays and transcription errors. A de facto standard for

    transfer of geometric information emerged with the dominance of the AUTOCAD design system in

    the A/E/C industry. Information transfer was accomplished by copying AUTOCAD files from user

    to user, including uses on construction sites to visualize the design. More flexible and extensive

    standards for design information transfer also exist, such as the Industry Foundation Classes (IFC)

    standard developed by the International Alliance for Interoperability (See http://www.iai-

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 14/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    15/16

    Back to top

    14.10 References

    1. Au, T., C. Hendrickson and A. Pasquale, "Introduction of a Relational Database Within a Cost Estimating

    System," Transportation Research Record1050, pp. 57-62, 1986.

    2. Bosserman, B.E. and M.E. Ford, "Development of Computerized Specifications,"ASCE Journal of

    Construction Engineering and Management, Vol. 110, No. CO3, 1984, pp. 375-384.

    3. Date, C.J.,An Introduction to Database Systems, 3rd Ed., Addison-Wesley, 1981.

    4. Kim, W., "Relational Database Systems,"ACM Computing Surveys, Vol. 11, No. 3, 1979, pp. 185-

    211.

    5. Mitchell, William J., Computer Aided Architectural Design, Van Nostrand Reinhold Co., New York,

    1977.6. Vieceli, A.M., "Communication and Coding of Computerized Construction Project Information,"

    Unpublished MS Thesis, Department of Civil Engineering, Carnegie Mellon University, Pittsburgh, PA,

    1984.

    7. Wilkinson, R.W., "Computerized Specifications on a Small Project,"ASCE Journal of Construction

    Engineering and Management, Vol. 110, No. CO3, 1984, PP. 337-345.

    8. Latimer, Dewitt and Chris Hendrickson, Digital Archival of Construction Project Information,

    Proceedings of the International Symposium on Automation and Robotics for Construction, 2002."

    Back to top

    14.11 Problems

    1. Suppose we wish to develop a database consisting of contractor names, addresses and particular

    specialties as in Table 14-3.

    Suggest two hierarchicalorganizations of this data.

    Suggest an alternative relationalorganization for this data.Which organization would you recommend for implementation of a database?

    2. Suggest four reports which could be obtained from the warehouse inventory system described in Section

    14.3 and describe what each report might be used for and by whom.

    3. Suppose that a general contractor wished to keep a historical database of the results of bid competitions.

    Suggest (a) the information that might be stored, and (b) a possible organization of this information.

    4. For your suggested database from Problem 3, implement a prototype system on a spreadsheet software

    program.

    5. Describe a relational database that would be useful in storing the beginning, ending and all intermediate

    stages for blockworld robot movements as described in Problem 6 in Chapter 9.

    6. Describe a relational database that would be appropriate for maintaining activity scheduling information

    during project monitoring. Be explicit about what relations would be defined, the attributes in each relation,

    and allowable ranges of values.

    Back to top

    14.12 Footnotes1. See D.F. Rogge, "Delay Reporting Within Cost Accounting System,"ASCE Journal of Construction

    Engineering and Management, Vol. 110, No. 2, 1984, pp. 289-292. Back

    2. The system is based loosely upon a successful construction yard management system originally for Mellon-

    Stuart Company, Pittsburgh, PA. in 1983. The authors are indebted to A. Pasquale for providing the information

    and operating experience of the system. Back

    3. Attributed to R. Lemons in J. Bentley "Programming Pearls," Communications of the ACM, Vol. 28, No. 9,

    1985, pp. 896-899. Back

    4. See Wilkinson, R.W. "Computerized Specifications on a Small Project,"ASCE Journal of Construction

    Engineering and Management, Vol. 110, No. CO3, 1984, pp. 337-345. Back

    5. See C.J. Date,An Introduction to Database Systems, 3rd ed., Addison-Wesley Publishing Company,

    Reading, MA, 1981. Back

    6. This is one example of a normalization in relational databases. For more formal discussions of the

    normalizations of relational databases and the explicit algebra which can be used on such relations, see Date op

    cit. Back

    7. For a discussion of relational algebra, see E.F. Codd, "Relational Completeness of Data Base Sublanguages,"

    Courant Computer Science Symposia Series, Vol. 6, Prentice-Hall, l972. Back

    8. See D.C. Trichritzis and F.H. Lochovsky, "Hierarchical Data-Base Management,"ACM Computing Surveys

    Vol. 8, No. 1, 1976, pp. 105-123. Back

    9. For a more extensive comparison, see A.S. Michaels, B. Mittman, and C.R. Carlson, "A Comparison of

    Relational and CODASYL Approaches to Data-Base Management,"ACM Computing Surveys, Vol. 8, No.

    1 1976 . 125-157. Back

    12/11/2010 Project Management for Construction:

    cmu.edu/14_Organization_and_Use_ 15/

  • 8/3/2019 Project Management for Construction_ Organization and Use of Project Information

    16/16

    Design and Construction,"Proc. of the Fifth ASCE Conference on Computing in Civil Engineering, 1987

    Back

    11. For a discussion, see D.R. Rehak and L.A. Lopez, Computer Aided Engineering Problems and

    Prospects, Civil Engr. Systems Lab., Univ. of Illinois, Urbana, IL, 1981. Back

    12. See W.J. Mitchell, Computer-Aided Architectural Design, Van Nostrand Reinhold Co., New York,

    1977. Back

    13. This figure was adapted from Y. Ohsaki and M. Mikumo, "Computer-aided Engineering in the Construction

    Industry,"Engineering with Computers, vol. 1, no. 2, 1985, pp. 87-102. Back

    Previous Chapter| Table of Contents

    12/11/2010 Project Management for Construction: