1 Resource Allocation and Negotiation Problems. 2 Resource allocation models.
Project Management Chapter 6 Resource Allocation
description
Transcript of Project Management Chapter 6 Resource Allocation
Project Management
Chapter 6
Resource Allocation
6-2
Resource Allocation
Activities compete with one another and Projects compete with one another for resources
Allocate scarce recourses to competing activities in an efficient way. Material Human Resources Capital Resources- i.e. equipment
Resource allocation requires trade-offs time constraint resource constraint Performance constraint
04/20/23 Ardavan Asef-Vaziri 6-2
Resource Loading
1. For each resource
2. For each time period: Determine the total resource time required by all activities
3. If total Time Required < Capacity Go to 2
4. Re-schedule some activities to eliminate resource overloading in that time period
5. Delay activities that have slack time first; No impact on CP
6. If that doesn’t work, then delay one or more critical activity
7. Go to 1
6-4
Resource Loading/Leveling and Uncertainty
28,282 Hours Needed during the next 34 weeks
Group Capacity21 (people) 40 (hours/week) 34 weeks = 28,560 labor hours
Correction for Holidays21 (people) 3 (days) 8 (hours) = 504 labor hours
Vacations11 (people) 2 (weeks) 40 (hours) = 880 labor hours
Hours Available28,560 - 504 - 880 = 27,176
about 1100 less than needed
28,282/27176 = 1.04, or 104% of capacity
04/20/23 Ardavan Asef-Vaziri 4
6-5
Resource Loading/Leveling and Uncertainty
04/20/23 Ardavan Asef-Vaziri 5
6-6
Allocation Priority Rules
As soon as possible: Standard rule in scheduling. Activities are scheduled to start on their ESTs
As late as possible: Activities start on their LSTs whenever possible without increasing the project’s duration
Shortest task duration first: Consistent with technological precedence's,
Minimum slack first: Tasks are supplied with resources in inverse order of their slacks
Most critical followers: Activities with a higher number of critical successors take precedence
Most successors: Same as previous rule except all successors are counted
Most resources first: The greater the use of a specific resource on a task, the higher the task’s priority for the resource
04/20/23 Ardavan Asef-Vaziri 6
6-7
Standards to Measure Schedule Effectiveness
Schedule Slippage The difference between actual completion date and the planned date Slippage may cause penalties Expediting one project can cause others to slip Taking on a new project can cause existing projects to slip
Resource Utilization The percentage of a resource actually used We prefer balanced utilization among most of the resource types
In-Process Inventory The volume of work waiting to be processed because there is a
shortage of some resource Similar to WIP in manufacturing The cost here is holding cost of the resources waiting
04/20/23 Ardavan Asef-Vaziri 7
04/20/23 3-8
Assignments
Review Questions: 1,3,4,5,8
Discussion Questions: 12,13,14,18
Problems: 23
Cases: 1 St. Dismas -4
04/20/23 Ardavan Asef-Vaziri 1-8