Project Management

38
Project Management Lecture Developing the Project Plan

description

Project Management. Lecture Developing the Project Plan. Introduction Project planning Gantt chart and WBS. Project planning Resource analysis Risk management Quality Budgets and cost control Project teams. Plan. Introduction Project planning Gantt chart and WBS Project planning - PowerPoint PPT Presentation

Transcript of Project Management

Page 1: Project Management

Project Management

LectureDeveloping the Project Plan

Page 2: Project Management

• Introduction• Project planning

– Gantt chart and WBS• Project planning

– Network analysis I• Project planning

– Network analysis II

• Introduction• Project planning

– Gantt chart and WBS

Plan

• Project planning– Resource analysis

• Risk management• Quality• Budgets and cost

control• Project teams

Page 3: Project Management

Project Planning

• “The larger, more complex or uncertain an endeavour is, the more important planning becomes”

Lockyer & Gordon

• What measures would you use to determine the complexity of a project?

Page 4: Project Management

Measures of Project Complexity

Page 5: Project Management

Why Plan?

• IS development is complex and time consuming

• There are usually a number of people involved with a project

• Communication– Informs Project Manager/Team of the state of the

project– Customer confidence

Page 6: Project Management

Why Plan?

• Projects are unique and therefore there will always be uncertainties– Need to plan for these (Plan B)

• So…– For anything more than the smallest project,

planning must be a formal process

Page 7: Project Management

Project Planning for IS

• Requires knowledge drawn from:– Development techniques– Application domain– Project planning techniques– Skills abilities and motivation of developers– Business and organisational environment

Page 8: Project Management

Project Proposals

• Project planning starts with the project proposal - Result of Conception Phase

• Maybe a response to a project brief– prepared by an external or internal customer

Page 9: Project Management

Project Initiation

• Project initiation document– Internal or external

• Project manager needs a good appreciation of requirements– This may require extra work

• Customer needs report on unknowns– protects both the project team and the customer

Page 10: Project Management

The Project Plan – Simple Form

• The project plan is an attempt to timetable all the activities that make up a project– How will the project be divided– Who does what– When are tasks carried out

Page 11: Project Management

The Project Plan

• More detail can be added to the plan to indicate:– Level of performance and quality– Costs

• Further detail indicates:– availability of the resources required to carry out

each task

Page 12: Project Management

The Project Plan• Summary plan

– Shows key tasks, events and milestones in the systems project

– Primarily used for reporting progress• Detailed plan

– Task plan– Time control plans– Resource plan– Cost plans– Primarily used as a working tool

Page 13: Project Management

Monitor & Review

Planning and Control Cycle

Plan

Page 14: Project Management

Iterative Process

• The plan will evolve as the project evolves• The plan is reviewed and updated as more

information becomes available and uncertainties become less uncertain

Monitor & Review

Plan

Monitor & Review

Plan

Monitor & Review

Plan

Page 15: Project Management

The Project Plan – Simple Form

• How will the project be divided?– Work breakdown structure– Product breakdown structure

• When will the work be carried out?– Gantt Chart

• Who does what?

Page 16: Project Management

Work Breakdown Structure

• Work broken down in a hierarchical manner until:– Each task is “atomic” – Duration can be estimated with reasonable accuracy– Can be carried out by one person

• Each task :– Has a well defined beginning and end– Will consume resources– May be dependant on other tasks

Page 17: Project Management

WBS Example

Project

Conduct Investigation

Produce Report

Investigate Other Systems

Analyse Requirements

Investigate Packages

Investigate Hardware

Conduct Interviews

Finance Director

Stores Manager

Sales Manager Etc. Managing Director

Write Notes Review Notes Create DFD’s Review DFD’s Conduct Interview

Page 18: Project Management

Product breakdown structure

• Concentrates on what is to be done, rather than how it is to be done

• More difficult to forget a product/element• Easier to assign quality measures/procedures• Process is more likely to fit if developed after

productexample

Page 19: Project Management

PBS Example

Project

Design Deliverables

Database Deliverables

GUI Deliverables

Functional Deliverables

Project Management Deliverables

Page 20: Project Management

PBS Example

Project

Design Deliverables

Database Deliverables

GUI Deliverables

Functional Deliverables

Project Management Deliverables

Produce Class Diagrams

Produce Use Cases

Produce Activity Diagrams

Page 21: Project Management

The Project Plan – Simple Form

• How will the project be divided?– Work breakdown structure

• When will the work be carried out?– Gantt Chart

• Who does what?

• How will the project be divided?– Work breakdown structure

• When will the work be carried out?– Gantt Chart

• Who does what?

Page 22: Project Management

Example Gantt chart

Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14ABCDEFG

Week Number

Page 23: Project Management

Example Gantt chart

Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14ABCDEFG

Week Number

Page 24: Project Management

Gantt chart components

An Activity/Task is represented as follows:

The length of the bar is proportional to the duration time of the activity

Start

Finish

Page 25: Project Management

Gantt chart components

Progress on an Activity/Task can be shown as follows:

The length of the bar is proportional to the amount of work completed. This example is approx 50% complete

Start

Finish

Page 26: Project Management

Example Gantt chart

Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14ABCDEFG

Week Number

Page 27: Project Management

Example Gantt chart

Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14ABCDEFG

Week Number

Page 28: Project Management

Exercise

Activity Start (Week No) Duration (Weeks) % CompleteA 1 5 100B 2 3 100C 1 8 75D 3 4 100E 5 5 60F 2 4 25G 10 6 0H 6 6 100I 7 2 50J 8 6 50

Page 29: Project Management

Exercise

Activity Start (Week No) Duration (Weeks) % CompleteA 1 5 100B 2 3 100C 1 8 75D 3 4 100E 5 5 60F 2 4 25G 10 6 0H 6 6 100I 7 2 50J 8 6 50

Page 30: Project Management

Gantt chart advantages

• It is good at showing timing• It shows project progress clearly• It is therefore an ideal tool for the summary

plan

Page 31: Project Management

Gantt chart disadvantages

• Not ideal for showing inter-relationships– MS Project does do this

• Locating an activity requires three simultaneous decisions:– Method– Time– Resources

Page 32: Project Management

• How will the project be divided?– Work breakdown structure

• When will the work be carried out?– Gantt Chart

• Who does what?

The Project Plan – Simple Form

• How will the project be divided?– Work breakdown structure

• When will the work be carried out?– Gantt Chart

• Who does what?

Page 33: Project Management

The Cost of Planning

• Labour and associated expenses• Planner's tools• Cost of preparing the written plan• Opportunity costs - what could those involved

be doing if they weren't planning?

Page 34: Project Management

Benefits of Planning

• Avoids the cost of the chaos that would ensue if the project was unplanned

• Filters out projects that would provide a negative return

• Being able to resolve problems in advance• Being able to allocate resources in advance

Page 35: Project Management

Two Views to a Plan

• The Plan is a straight-jacket– Very Precise– Focus on data

• The Plan is a working tool– Very Accurate– Focus on information

Page 36: Project Management

Who Does Planning

• Developing the project plan is an iterative process that involves:– Project manager– Project team– Project sponsor – Customer– Other stakeholders

Page 37: Project Management

Iterative Process

• The plan will evolve as the project evolves• The plan is reviewed and updated as more

information becomes available and uncertainties become less uncertain

Monitor & Review

Plan

Monitor & Review

Plan

Monitor & Review

Plan

Page 38: Project Management

• Introduction• Project planning

– Gantt chart and WBS• Project planning

– Network analysis I• Project planning

– Network analysis II

• Introduction• Project planning

– Gantt chart and WBS

Plan

• Project planning– Resource analysis

• Risk management• Quality• Budgets and cost

control• Project teams