Aspen Square
Remodeling project list
Reynoldsburg, Ohio, 2 years$ 1,196,000 260 unitsNew drywall as need, new trim work, baseboard, door casing as needed, two tone paint,New counter tops, cabinet refacing, new plumbing as needed, new electrical lighting outlets switches, New interior doors, new vinyl flooring, new carpet, new windows as needed
Office clubhouse and fitness center business center remodel $ 140,000Gutted walls to studs, added new electrical, new walls, new insulation, new drywall, new trim workNew paint job, new tile work, new carpeting, cat 5 and low voltage wiring
San Antonio TX. 2 years$ 1,400,000 280 units$ 120,000 Office, clubhouse, fitness center, business center, remodel Remodeling same as Reynoldsburg Ohio
Irmo South Carolina 1.5 years$ 1,548,000 180 units$ 125,000 Office, clubhouse, fitness center, business center, remodelRemodeling same as Reynoldsburg and San Antonio
Daryl A. Barnett101 Meadowbrook Dr. Unicoi TN. 37692
(979)-219-3978 (H/C)
Project List.
Ground-up projects
Emerald estates (single family housing)
Vero beach, Florida
1200 to 3600 sq. ft., cinder block construction metal and wood stud framing
69 homes 1.5 years to complete, 12 million dollar project
Tamarind Lakes (Townhomes)
Vero beach, Florida
1300 to 1800 sq. ft. cinder block construction metal and wood stud framing
32 homes less than one year 5.2 million dollars
Citrus Springs community (single family housing)
Vero beach, Florida
1600 to 2300 sq. ft. Cinder block construction metal and stud framing
45 homes 2 years 11.6 million dollars