Project Initiation Document This document defines what is to be produced and/or done within the scope of this project and when. Activity and resources trackers are used to plan the work and record progress (this document should be updated with actual data on a regular basis). Upload to MicroP2 and ensure that team members have been added to the project. 1. Project reference no.:
038
2. Project title:
Nimbus – Desktop Infrastructure Replacement
3. Version control
Version No Date revised Summary of changes
0.1 17/02/2012 Initial draft
1.0 20/02/2012 Submitted to SDB
1.1 09/03/2012 Updated to remove / amend timescales in preparation for submission to SMB
2.0 12/03/2012 Submitted to SMB
2.1 10/04/2012 Updated to incorporate comments from SMB before submission to EFA Policy & Strategy Committee
3.0 10/04/2012 Submitted to Call Over for EFA Policy & Strategy Committee
3.1 25/04/2012 Updated to incorporate comments from Call Over before final submission to EFA Policy & Strategy Committee
4.0 26/04/2012 Submitted to EFA Policy & Strategy Committee
4. Author
Name Paul Gardiner
Role ICT Project Manager
5. Who has this document been distributed to?
Jan Swanwick, SDB, SMB, EFA Policy & Strategy Committee
Executive Summary The desktop infrastructure replacement programme has authority to proceed from the Fire Authority. This is a wide ranging programme which comprises of many projects that are expected to run over the next two years.
The most significant project is to replace the desktop environment and devices used throughout the Service.
The strategic objectives of the project are to design, build and deliver a fully operational desktop environment built on industrial strength infrastructure and software. This new model will satisfy the business requirements, provide a future-proofed design and be immediately capable of rapidly scaling and deployment across the estate by the purchase and installation of additional hardware and software licences as required. The new environment will provide: -
Sound technology basis for cost effective and rapid delivery of follow-on projects from ITTP
Cost effective, modern desktop (featuring Windows 7 appearance and Office 2010) Positively transformed and standardised end user experience regardless of location,
role or working pattern Improved security, reliability and availability Improved end user satisfaction with Desktop IT services Reduced annual revenue and capital expenditure Reduced IT maintenance and support effort requirement to maintain a new higher
standard of service Improved ability to quickly accommodate new business requirements and
organisational changes
To focus on the desired business outcome and minimise the risk at each stage, the project is utilising a delivery-horizon approach where we will move, with suitable approval, from one clearly understood and defined outcome to the next. This approach currently calls for four phases to the overall delivery: - 1. Phase 1: Technical Proof Of Concept (Completed)
a. A technology proof-of-concept
2. Phase 2: Analysis, Design and Build of a fully working model (Proceeding to Pilot) a. A fully working model that satisfies the ITTP objectives as described in Section 8 of
the Gateway 1 document. b. Integration testing of existing ECFRS business applications. c. Definition and build of service support model for new desktop. d. Delivery of latest Windows 7 / MS Office 2010 products for phased deployment.
3. Phase 3: Full scale deployment a. Deployment of licensing and hardware infrastructure providing enterprise scalability
and DR (Industrialisation). b. Deployment of new desktop devices and services within ECFRS. c. Deployment of service support model for new desktop. d. Deployment of current version of business software. e. Deployment of latest versions of Windows 7 and Microsoft Office 2010 products. f. Deployment of individual email accounts.
Phase 3 will be split into the following four Stages, in order to provide immediate operational benefits in line with current priorities: -
1) One-for-one replacement of current Neoware devices with new Wyse thin client devices in all Stations.
2) Installation of additional network points and new Wyse thin client devices in all Stations, to support additional ICT business requirements for all Service Delivery personnel.
2
3) Replacement of current PC’s in all Area Commands, Service Delivery Points, Training Centres, Workshops and Emergency Planning.
4) Replacement of current PC’s in Service Headquarters (Kelvedon Park and remaining personnel in Hutton, including Control).
4. Phase 4: Business Application Upgrades a. Delivery of operational SharePoint installation for use across the Service.
Phase 2 is currently proceeding to Pilot, initially at Harlow Command and Station and then subsequently at Burnham-on-Crouch station, in order that the impact, capability and capacity at Retained stations can also be assessed prior to full scale deployment. A fully working model has been built and tested in collaboration with Esteem Group (our chosen professional services provider), utilising the latest Citrix VDI-In-a-Box technology. This creates and runs a virtual Windows 7 / MS Office 2010 desktop for each user on central servers, with the latest Wyse thin client devices deployed to end users.
Wyse were selected to supply the thin client devices following a full evaluation of the market place. A shortlist of three vendors was drawn up, including the two market leaders – HP and Wyse – and a relatively new vendor to the UK, 10ZiG. Each vendor was invited on-site for a day to demonstrate their products, in order that ECFRS could evaluate them against the following predetermined requirements and criteria: -
Functionality, including graphical capability and ability to support Flash Performance, including seamless and rapid start-up for the end user and network usage Size and mounting options Heat generation and dissipation Power consumption Currency and life cycle of products Management of the thin clients, including capabilities and ease of use of the
management interface and maintenance / deployment of images Vendor engagement and support Costs, including initial purchase price, warranty and on-going Support & Maintenance
HP was discounted at an early stage, as the quality of their vendor engagement and support was poor, and their products didn’t meet our functional requirements.
Wyse and 10ZiG engagement and support was good from both vendors, and both met our functional requirements. However, Wyse was selected on the basis of their superior video capability, most current and longer life cycle for their product, and only a small price differential between them and 10ZiG.
The intention was that the Pilot would have been completed prior to submission of Gateway 3 documents, but this hasn’t been possible due to protracted resolution of issues with Citrix during ICT System Testing. Therefore, due to the urgency of the project and financial considerations, this paper seeks approval to deliver Phase 3, Full Scale Deployment of the proposed architecture, on the basis that we have now completed the analysis and design to provide enterprise scalability and deployment, even though we haven’t yet been able to complete the Pilot rollout.
3
The overall revised costs and effort for the project are summarised below: -
Project Totals
Original Estimate
Actual Effort / Costs
Original Estimate
Actual Effort / Costs
Stage 1 Stage 2 Stage 3 Stage 4 Current Estimate
Project Management / BA Effort (days) 96 50 66 124 74 0 33 33 313
Project Management / BA Costs £51,000 £26,500 £35,000 £59,740 £29,400 £0 £13,000 £13,000 £141,640
ICT Technical Support (days) 0 0 0 100 188 34 63 65 450
Vendor Professional Services £5,000 £8,500 £54,345 £46,970 £28,400 £0 £0 £0 £83,870
IT - Hardware £10,000 £0 £23,460 £54,992 £370,438 £10,425 £0 £0 £435,855
IT - Software Licensing £0 £0 £8,732 £4,483 £28,291 £0 £0 £0 £32,774
Training £0 £0 £0 £8,250 £49,875 £4,125 £7,500 £8,250 £78,000
Total Effort 96 50 66 224 261 34 96 98 763
Total Costs £66,000 £35,000 £121,537 £174,435 £506,403 £14,550 £20,500 £21,250 £772,138
Phase 3 - Full Scale Deployment
Nimbus - Summary of Costs / Effort and Variations for Project Initiation DocumentBusiness Case
Nimbus Costs Phase 2 - Fully Working Model
The following points should be noted regarding the costs: - The costs for Phase 2 - Fully Working Model are higher than the original estimate due to
protracted issues during the procurement process with a previous supplier. It was consequently decided that they were unable to meet our requirements; hence we have now engaged Esteem Group to provide us with a more suitable and appropriate solution.
The costs for Phase 3 / Stage 1 are significantly higher than the other Stages because all Hardware and Software Licensing will be purchased up front, in order to obtain best prices for volume purchases. Delivery of hardware will then be phased in line with requirements for each Stage.
No allowance has currently been made for potential Property Services costs to provide new desks and chairs to support the additional terminals in stations, if required. These will be subject to individual site surveys at each station, but would typically cost around £300 per workstation, although this may be less per unit depending on volumes. If we assumed an average of one additional desk per station, this would be a total additional cost of around £15,000.
Please see Appendix A for a full breakdown of costs for each Phase / Stage.
Contributions to Carbon Management Plan
Based on current and predicted usage, reduced power consumption will result in an energy saving of approximately 1,500kwh per annum for each desktop PC replaced by the selected Wyse thin terminal, and approximately 1,300kwh per annum for each Neoware terminal replaced.
At current energy prices, the Wyse terminals will provide a return on investment in 2-3 years.
Recommendations
The EFA Policy & Strategy Committee is asked to approve the delivery of Phase 3: Full Scale Deployment of the new Nimbus desktop infrastructure, based on the approach and rationale as defined in this Project Initiation Document.
4
Project Controls Throughout the project, the following controls will be used by the Project Manager.
Event Response
An exception occurs (any deviation from the tolerances agreed in this document).
Present an Exception Report to the project board and agree a course of action.
A change is requested to a product or acceptance criteria.
Record in the Issues and Changes Log and, if the change is accepted, consider revisions to the Business Case and PID/stage plans.
A new project risk emerges. Update the Risk Register and implement control measures.
Moving from one project stage to the next.
Present an End Stage Report to the Project Board and ensure next Stage Plan is prepared.
Any other issue arises. Record in the Issues and Changes Log and take any necessary action.
Project is completed. Present a Project Closure Report to the Strategic Delivery Board (SDB) or SITOG and upload to MicroP2. Change MicroP2 project status to “Completed”.
6. How many stages will the project be organised into? The Full Scale Deployment of the project will be split into four Stages, in order to provide immediate operational benefits in line with current priorities. High level summary of Project Gateways, Stages and Timescales is as follows: -
Number Description Start Date End Date
1 Gateway 1 - Project Brief 25/10/2010 25/01/2011
2 Gateway 2 - Business Case 31/01/2011 24/02/2011
3 Phase 2 – Fully Working Model and Pilot 03/01/2012 18/05/2012
4 Gateway 3 - Project Initiation Document 13/02/2012 08/05/2012
Specific timescales have not yet been defined for Phases 3 and 4, only high level durations. These will be defined once final project approval is received and the project can be prioritised, scheduled and specific resources allocated.
Number Description Start Date End Date
5 Phase 3 – Full Scale Deployment Month 1 Month 7
5.1 Stage 1 – Replace current Neoware terminals Month 1 Month 4
5.2 Stage 2 – Additional terminals in Stations Month 2 Month 4
5.3 Stage 3 – Replace PC’s in all other sites Month 3 Month 5
5.4 Stage 4 – Replace PC’s in SHQ Month 4 Month 7
6 Phase 4 – Delivery of SharePoint TBD TBD
1
7. Project tolerances. These are the predicted outcomes for the project. Deviation outside these tolerances will be brought to the attention of the Project Executive in an Exception Report.
A tolerance of 10% has been set for Costs and Effort, and a tolerance of three weeks has been set for Time.
Planned Minimum Maximum
Costs £772,138 £695,000 £850,000
Time 30 weeks 27 weeks 33 weeks
Effort 763 days 685 days 840 days
8. How frequently will the Project Manager produce Highlight Reports for the Board?
Monthly
Project Team 9. The project team is agreed as follows:
Project Executive Jan Swanwick
Project Manager Paul Gardiner
Senior Users Mark Wilson / Julian Ashley
Senior Supplier Esteem Group
Team Members
Name/role Contact Details
Matt Hughes, DO Support Service, East Division Area Command
[email protected] Tel: 07768 910256
Ray Skinner, DO Support Service, West Area Command
[email protected] Tel: 07979 748691
John White, ICT Technical Team Leader [email protected] Ext. 6404
Jim Culling, ICT Technical Expert - Systems [email protected] Ext. 6405
Gary Seddon, ICT Senior Technical Officer [email protected] Ext. 6408
Stuart Wash, ICT Technical Officer, Security [email protected] Ext. 6417
Richard Duke, ICT Applications Lead [email protected] Ext. 6416
Philip Butt, ICT Applications Lead [email protected] Ext. 6418
Nikki Keary, ICT Service Desk Manager [email protected] Ext 6499
Gavin Lowrie, ICT Installations Technician [email protected] Ext. 6499
Chris Eldridge, ICT Service Desk Analyst [email protected] Ext. 6499
2
Team Members
Name/role Contact Details
Spencer Connelly, ICT Business Analyst [email protected] Ext. 6429
Will Brooks, Sales Manager, Esteem [email protected] Tel: 07717 760362
Paul Mission, Project Manager, Esteem [email protected] Tel: 07736 895221
Terry Hooper, Citrix Practice Lead, Esteem [email protected] Tel: 07920 135781
Paul Grant, Solution Architect, Esteem [email protected] Tel: 07920 496941
Stephen Cooke, Regional Sales Manager, Wyse
[email protected] Tel: 07798 933196
Ben Cross, UK Sales, Wyse [email protected] Tel: 07799 352169
Chris Reeves, Systems Engineer, Wyse [email protected] Tel: 07775 915063
Paula Wheeler, IT Training Essex [email protected] Tel: 07941 059473
Nora Ridley, IT Training Essex [email protected] Tel: 07557 192434
10. Training
Have all the project team members received project management/ MicroP2 training? List any that have not.
Those for whom it’s required have received training.
Windows 7 / MS Office 2010 training will be delivered by IT Training Essex for the Harlow and Burnham-on-Crouch Pilots, using a two tiered approach, depending on users’ needs an experience. Training approach and costs for full scale deployment have been based on this approach, but may be subject to change following completion and evaluation of the Harlow Pilot.
Communication Plan 11. Plot the current position of the key stakeholders and groups involved with this project.
High
Service Delivery Management
Service Support Management
Project Executive
SDB
SMB
SITOG
ICT
Med
Agreement with the project
Low
Low Medium High
Power and Influence
3
12. Service department(s) affected:
All Service departments will be affected. Stages 1 and 2 will affect all Stations and staff. Stage 3 will affect the following departments and staff: -
Area Commands Service Delivery Points All Training Centres Workshops Emergency Planning
Stage 4 will affect Service Headquarters and all departments and staff still based at Hutton, including Control.
13. External parties involved:
The Citrix VDI-In-a-Box system will be supplied, installed and supported by Esteem Group: -
Esteem Group Rofta House Rudgate Thorp Arch Wetherby LS23 7QA
Esteem Group were selected following an evaluation of their services and solutions, including a number of technical workshops with ECFRS. They are the only Citrix Platinum Solution Partner in the UK. The end-user thin client devices will be provided and supported by Wyse: -
Wyse Technology (UK) Ltd. 1 The Pavilions Ruscombe Park Twyford, Berks RG10 9NN United Kingdom Windows 7 / Microsoft Office 2010 training for the Harlow Pilot will be delivered by IT Training Essex, who were selected following an evaluation of responses received from a number of training providers against predetermined ECFRS requirements and criteria. We will use them to test and validate the training approach at Harlow, before deciding on the best approach and training provider to rollout training across the whole Service.
4
14. Consider stakeholders’ needs and set out your project communication plan:
Stakeholder/
group Information required
Information provider
Communication method / format
Frequency
All Headline progress and RAG status
Paul Gardiner ICT Team Information report published on the Intranet
Weekly
Senior Users RAG status, progress against Plan, Risks, Issues and Costs
Paul Gardiner Progress meetings Monthly
Project Executive SITOG SDB SMB
RAG status, detailed progress against Plan, Risks, Issues and Costs
Paul Gardiner Highlight Reports Monthly
Service Delivery / Service Support
Training and Deployment approach, plans and progress
Paul Gardiner Operational bulletins, Intranet, Parade News
Regular project updates, commencing at least 4 weeks before deployment for affected areas
Service Delivery / Service Support
Training media Paul Gardiner
Windows 7 / MS Office 2010 Tier 1 / 2 familiarisation sessions and Quick Reference Guides
Training to be delivered in parallel with deployment for each Stage
15. Equality Impact Assessment (EIA)
Consider the project’s objectives, outcomes and stakeholders. If the project might have a differential impact on the following groups, note any evidence (presumed or otherwise) and refer to the EIA guidance available at http://servicenet/1791.htm.
Group Could the project have a differential impact? (Yes/No)
If ‘Yes’, please add comments
Race No
Gender No
Disability Yes The move to widespread use of ICT within the Service may have an impact on those with visual / reading impairments e.g. dyslexia. To mitigate any difficulties, the new system will have all Microsoft Accessibility Options installed and will have Dragon Voice Recognition software available for those who need it.
Religion or belief No
Sexuality No
Age No
5
Stakeholder Engagement 16. The following stakeholders have been consulted about the content of this PID:
Stakeholder/ group
Jan Swanwick, Head of ICT SDB SMB
External Dependencies 17. The other projects with a direct interface to this project are:
There are two key External Dependencies for this project: - Individual User Accounts project, to ensure that access controls are in place to enable
all users have a secure, individual sign-on and e-mail account to support functional requirements of Nimbus.
Improved Paper Handling and Printing Efficiency, to ensure that new printers are delivered in a timely manner to support Nimbus requirements.
Additionally, the following projects are dependent on Nimbus to deliver the new desktop infrastructure as soon as possible to support additional ICT requirements and usage for all Service Delivery staff: -
SAP ESS / MSS / TEM Electronic Rota Book TASK Self Service
Planning Assumptions 18. In estimating and planning the following assumptions have been made:
That no significant issues or changes will result from the Harlow and Burnham-on-Crouch Pilots
That all hardware can be ordered and delivered in a timely manner That Wide Area Network capacity will support business requirements in all locations That all ICT Technical resource requirements can be sourced internally within current
team and there is no requirement to employ external contract staff That external electrical contractor can carry out additional cabling / installations in a
timely manner, with no significant variations in cost estimates That external Training provider can provide sufficient trainers in a timely manner to
support the training programme, with particular consideration to operational Watch rotas
That currently proposed Windows 7 / MS Office 2010 Tier 1/2 familiarisation sessions will meet the vast majority of training requirements. Tier 3 training can be provided for expert users on an ad hoc basis, but hasn’t been included in current estimates
That Individual User Accounts project will deliver to meet deadlines for deployment of Nimbus
That Improved Paper Handling and Printing Efficiency project will deliver to meet deadlines for deployment of Nimbus
6
Risks 19. Highlight the key risks from the Risk Register:
Risk no. Risk and description/explanation Residual
risk rating
RS0001 Harlow and Burnham-on-Crouch Pilots may give rise to significant Issues or Changes, resulting in additional hardware or application requirements that have not been planned for. Full station requirements analysis has been carried out and signed off by West Area Command and Harlow Station, so risk should be low.
Low
RS0002 New servers / infrastructure may not be delivered in time to commence the Full Scale Deployment. Server specifications finalised as part of initial build and performance testing carried out by ICT. ‘Smart Quote’ already initiated through Esteem Group in order to expedite the process and obtain best price.
Medium
RS0003 Wyse may not be able to deliver sufficient thin client devices in a timely manner to support the rollout plan. Wyse already engaged and aware of our requirements and timescales, paperwork for order will be completed in advance of Gateway 3 approval, Wyse will adopt a phased delivery approach to ensure our requirements can be accommodated.
High
RS0004 Virtual desktop solution may not support additional application requirements for all sites. Full application requirements analysis will be completed for all sites in advance of Stages 3 and 4 of the rollout to ensure that all requirements are captured, incorporated in final image and tested before deployment.
Medium
RS0005 Wide Area Network capacity / performance may not support business requirements in all locations. Network Quality of Service installed at Harlow prior to Pilot, initial testing proved successful, but additional testing and monitoring to be carried out as part of the Pilot. If performance not acceptable, consideration to be given to installing Citrix Branch Repeaters, but this would incur additional costs.
Medium
RS0006 Individual User Accounts / Sign-on will not be delivered to meet deadlines for deployment of Nimbus. All users across the service have now been setup in Active Directory, but will need to be setup in new Group Policies as part of the rollout process, which will be proven as part of Harlow Pilot.
Medium
RS0007 Improved Paper Handling and Printing Efficiency project will not be delivered to meet deadlines for deployment of Nimbus. Nimbus deadlines will be incorporated in Improved Paper Handling and Printing Efficiency plans as external deliverables.
Medium
7
8
Risk no. Risk and description/explanation Residual
risk rating
RS0008 ICT Technical Officers and Service Desk staff may not be available to support the project due to conflicting Support and other Project commitments. Resource requirements will be planned out in full with Service Delivery Manager and if necessary, will look to backfill staff with external contract staff, although this will incur additional costs.
High
RS0009 External electrical contractor can’t carry out additional cabling / installations in a timely manner and / or within budget. All estimates based on work already carried out for Harlow Pilot. External contractor will be engaged as soon as PID approved by SMB, in order to plan and cost full programme of work to support Stage 2, to run in parallel with Stage 1.
Medium
RS0010 Training approach not yet proven due to delay in Harlow Pilot. This may give rise to significant Issues or Changes in Training requirements / timescales that have not been planned for and which selected Training provider can’t accommodate. Training programme has been planned in detail with Training vendor, both for Harlow Pilot and full scale deployment. Approach, timings and costs will be proven during the Pilot and adjusted as required, although this may mean that we have to select another Training provider with greater capacity to deliver the programme, which may incur additional costs.
Medium
RS0011 In-house ICT Training courses / manuals / user guides may become out-of-date. PM to liaise with IT Training Dept to determine what training material will need updating prior to full rollout.
Low
RS0012 Nimbus Full Scale Deployment will conflict with Olympics Change Freeze from 1st July to 10th September. Agreed that if the back-end infrastructure is in place and tested in advance of the Change Freeze, we will continue with the deployment into Stations, as no new systems will be introduced. However, it may still be prudent to avoid migrating key operational locations during the Change Freeze.
Low
20. Products Define all deliverables for the project, with input from the end users. External products (marked as such) should be included if the project depends on their completion. These products should be divided between the Stage Plans if you are using them. All dates are provisional, subject to final project approval, prioritisation, scheduling and resource allocation.
Product What will the product consist of? Why is this product necessary? What criteria / quality
standards must be met? Who is
responsible?
Which products need to be completed before this
one (if any)? Deadline
Status Not started In progress Complete
SDB Documents Project Initiation Document, revised Business Case and Covering Paper, seeking approval to proceed with project to deploy Nimbus across the Service.
Governance documents Initial review, approval and submission by Project Executive
Paul Gardiner Jan Swanwick
17/02/2012 Complete
SDB Approval Initial approval by members of SDB SDB approval required before submission to SMB
Approval recommended by SDB
SDB SDB Documents 28/02/2012 Complete
SMB Documents Project Initiation Document, revised Business Case and Covering Paper updated in line with any changes required by SDB.
Governance documents Review, approval and submission by Deputy Chief Fire Officer, Service Support
Paul Gardiner Jan Swanwick Adam Eckley
SDB Approval 09/03/2012 Complete
SMB Approval Approval by members of SMB SMB approval required before submission to Policy & Strategy
Approved by SMB SMB SMB Documents 20/03/2012 Complete
Policy & Strategy Committee Approval
Approval by Policy & Strategy Committee Cannot proceed without it Approved by Policy & Strategy Committee
Policy & Strategy SMB Approval 08/05/2012 Not started
Esteem Group Professional Services Contract
Contractual agreement on recommended solution, scope of engagement, objectives and timeline
To ensure that both parties are clear on requirements, terms of engagement and costs to build environment to support Full Scale Deployment
Esteem Group can commit to meet ECFRS requirements for the project
Paul Gardiner Esteem Group
Policy & Strategy Committee Approval
11/05/2012 Not started
Purchase Order for Esteem Group
Purchase Order To provide commercial basis for engagement
Purchase Order approved by Head of ICT
Paul Gardiner Jan Swanwick
Esteem Group Professional Services Contract
11/05/2012 Not started
Citrix Licences Purchase Order for 350 x Citrix VDI-In-a-Box concurrent user licences and 1 year software maintenance
To ensure that Citrix licensing requirements are met for Full Scale Deployment
Purchase Order approved by Head of ICT
Paul Gardiner Jan Swanwick
Technical Workshop 11/05/2012 Not started
Server Quotes Three competitive quotes from: - - Esteem Group - HP - Silicon Alley
To ensure that we obtain best price for hardware
Quotes within budgetary expectations and servers can be delivered by 13/04
John White Procurement
Policy & Strategy Approval 11/05/2012 In progress
Purchase Order for Servers Purchase Order for chosen supplier Order required servers Purchase Order approved by Head of ICT
John White Jan Swanwick
Server Quotes 11/05/2012 Not started
9
Status Which products need to What criteria / quality Who is Not started Product What will the product consist of? Why is this product necessary?
standards must be met? responsible? be completed before this Deadline
In progress one (if any)? Complete
Purchase Order for Client Devices
Purchase Order for Wyse thin client devices
Order required Client Devices Purchase Order approved by Head of ICT
Paul Gardiner Jan Swanwick
Policy & Strategy Approval 11/05/2012 Not started
Purchase Order for screens, keyboards and mice
Purchase Order for various suppliers - screens will be Dell P2312H, keyboards / mice will be Dell / Microsoft, depending on feedback from Pilot.
Order additional end-user equipment Purchase Order approved by Head of ICT
Paul Gardiner Jan Swanwick
Policy & Strategy Approval 11/05/2012 Not started
Purchase Order for Encrypted USB Drives
Purchase Order for required number of Integral Courier 4GB 256 Bit Encrypted USB's
Order additional end-user equipment Purchase Order approved by ICT Governance Manager
Paul Gardiner Chris Maas
Policy & Strategy Approval 11/05/2012 Not started
Training Vendor Engagement E-mail to all potential Vendors asking them to outline what their approach would be based on feedback from training for the Pilot in terms of: - - Delivery method – classroom / CBT / eLearning etc. - Location(s) – on / off-site - Documentation – training / reference manuals supplied - How you would address varying skill levels - Your capacity to deliver to that number of delegates within those timescales – how quickly could you deliver training to potential maximum of 1,700 users? - Indicative costs
To identify shortlist of potential vendors that can meet our requirements in line with overall build and deployment plans
Vendors can provide considered and detailed proposals as to how they will address our needs
Paul Gardiner Policy & Strategy Approval 11/05/2012 Not started
Purchase Order for Printers (Stage 1)
Purchase Order for required Printer(s) in line with overall Printing Strategy
Order required Printer(s) Purchase Order approved by Head of ICT
Jeff Stembridge Jan Swanwick
Policy & Strategy Approval 11/05/2012 Not started
Delivered Servers Servers delivered to ECFRS as specified To provide backend infrastructure to host Citrix VDI-in-a-box
Servers supplied as per specifications by 13/04
John White Purchase Order for Servers 25/05/2012 Not started
Briefing Presentations To provide Senior Officers with an overview / demonstration of the new environment, results of Pilot and communication, training and deployment strategies, to get their feedback on what needs to be included for full scale deployment.
Required to ensure that the business community are aware of the project, its aims and its progress
Positive feedback from attendees
Jan Swanwick Paul Gardiner
Policy & Strategy Approval 25/05/2012 Not started
10
Status Which products need to What criteria / quality Who is Not started Product What will the product consist of? Why is this product necessary?
standards must be met? responsible? be completed before this Deadline
In progress one (if any)? Complete
Training Vendor Selected Further detailed discussions / proposals from shortlisted Vendors in terms of: - - Delivery method – classroom / CBT / eLearning etc. - Location(s) – on / off-site - Documentation – training / reference manuals supplied - How you would address varying skill levels - Your capacity to deliver to that number of delegates within those timescales – how quickly could you deliver training to potential maximum of 1,700 users? - Definitive costs
To identify and select training vendor that can meet our requirements in line with overall build and deployment plans
Suitable Training Vendor selected
Paul Gardiner Training Vendor Engagement
25/05/2012 Not started
Installed Servers Servers installed and cabled to ECFRS standards
To provide backend infrastructure to host Citrix VDI-in-a-box
Servers installed, cabled and tested to ECFRS standards by 30/12
John White Delivered Servers 01/06/2012 Not started
Quotes for LAN Upgrades Competitive quotes from three suppliers for LAN upgrades required to support Stage 2
To ensure that we obtain best price for LAN upgrades
Quotes within budgetary expectations and upgrades can be accommodated in line with rollout plan
Paul Gardiner Policy & Strategy Approval 01/06/2012 Not started
Purchase Order for Training Vendor
Purchase Order for selected Training Vendor
Book and schedule required Training Purchase Order approved by Head of ICT
Paul Gardiner Jan Swanwick
Training Vendor Selected 01/06/2012 Not started
Citrix VDI-In-a-Box Environment
Servers built and configured as per High Level Design: - - Microsoft Windows 2008 R2 - Server Virtualisation using Hyper-V - Citrix VDI-In-a-Box - Microsoft Windows 7 template
Provide back-end infrastructure to support Citrix VDI-In-a-Box
Signed-off by Esteem / ECFRS Terry Hooper Installed Servers 08/06/2012 Not started
Purchase Order for LAN Upgrades
Purchase Order for all Station LAN Upgrades required to support Stage 2
To engage vendor and schedule work Purchase Order approved by Head of ICT
Paul Gardiner Jan Swanwick
Quotes for LAN Upgrades 08/06/2012 Not started
Disaster Recovery Environment
Original Pilot servers moved to Hutton to provide Disaster Recovery capabiliy
Provide DR infrastructure to support Citrix VDI-In-a-Box
Signed-off by Esteem / ECFRS Terry Hooper Citrix VDI-In-a-Box Environment
08/06/2012 Not started
System Tested Environment Full System / Integration Testing of new servers once environment fully built and everything installed and baselined
To ensure that all components function as intended before signing-off VDI-In-a-Box environment
All High priority issues resolved, any outstanding Medium or Low priority issues documented and accepted by PM / Head of ICT before releasing for UAT.
Paul Gardiner Thin client Image Unit Tested Environment Anti-virus Software Tested AD / GP changes Upgraded VDI Servers
15/06/2012 Not started
11
Status Which products need to What criteria / quality Who is Not started Product What will the product consist of? Why is this product necessary?
standards must be met? responsible? be completed before this Deadline
In progress one (if any)? Complete
Network Quality of Service Network configuration changes at all Stations to optimise network performance
To ensure that Wide Area Network link to all stations is optimised prior to Full Scale Deployment
Station WAN links successfully load / performance tested
John White Policy & Strategy Approval 15/06/2012 Not started
Stage 1 - Replace Current Neoware Boxes
Transition Plan (Stage 1)
Transition Plan / Go-Live Playbook identifying all Implementation tasks for rollout of Stage 1 of Full Scale Deployment, including all installations, Training Plan, Communication Plan, Checklist for each user (including securing data from C: drives and old USB's) and Backout Plan for each component.
To ensure that all aspects of Transition are documented, approved and managed through to completion.
Sign-off by Head of ICT and Area Commanders
Paul Gardiner System Tested Environment
18/06/2012 Not started
Delivered Client Devices (Stage 1)
Wyse Client Devices imaged and delivered to ECFRS
To provide End-user infrastructure to support Citrix VDI-in-a-box configured to ECFRS requirements
Client Devices supplied as per specifications prior to commencement of Stage 1 deployment
Wyse (Getech) Purchase Order for Client Devices
18/06/2012 Not started
Delivered screens, keyboards and mice (Stage 1)
Screens, keyboards and mice delivered to ECFRS as specified
To provide End-user infrastructure to support Citrix VDI-in-a-box
Screens, keyboards and mice supplied as per specifications prior to commencement of Stage 1 deployment
Paul Gardiner Purchase Order for screens, keyboards and mice
18/06/2012 Not started
Delivered Printer(s) (Stage 1) Printer(s) delivered to ECFRS as specified To provide End-user printing requirements for Full Scale Deployment
Printer(s) supplied as per specifications by prior to commencement of Stage 1 deployment
Jeff Stembridge Purchase Order for Printer(s)
18/06/2012 Not started
Individual User Accounts (Stage 1)
Individual User Accounts for all Station personnel setup in Active Directory and all application groups as required
To ensure that all Station personnel have correct access to applications and network drives etc. according to their roles and responsibilities
All users added and checked prior to commencement of Stage 1 deployment
ICT Service Desk 18/06/2012 Not started
MS Exchange 2010 Migration (Stage 1)
All Station personnel migrated to / setup in (for new users) MS Exchange 2010 as prerequisite for using MS Outlook 2010
To ensure that all Station personnel have correct access to MS Outlook
All users migrated prior to commencement of Stage 1 deployment
John White 18/06/2012 Not started
Full Scale Deployment (Stage 1)
Installation and configuration of Client Devices, screens, keyboards and mice at all Stations
To deploy Nimbus hardware to all Stations
All hardware installed and functional
Paul Gardiner John White Gavin Lowrie
Transition Plan Delivered Client Devices (Stage 1) Delivered Screens, Keyboards and Mice (Stage 1)
07/09/2012 Not started
12
Status Which products need to What criteria / quality Who is Not started Product What will the product consist of? Why is this product necessary?
standards must be met? responsible? be completed before this Deadline
In progress one (if any)? Complete
User Account Migrations (Stage 1)
Individual User Accounts for all Station personnel migrated to new Group Policy Objects, profiles and network drives as required
To ensure that all Station personnel have correct access to applications and network drives etc. according to their roles and responsibilities
All users able to access and carry out normal business functions
ICT Service Desk Individual User Accounts (Stage 1)
07/09/2012 Not started
Trained Users (Stage 1)
Training delivered to all Station staff as required
To ensure that all staff involved in Stage 1 of the Full Scale Deployment are trained to the appropriate level in parallel with deployment
90% attendance of all staff, positive feedback, mop-up sessions to be setup as required
Training Vendor Purchase Order for Training Vendor
07/09/2012 Not started
Installed Printers (Stage 1) Installation and configuration of Printers at all Stations and add to new Print server
To enable all Stations to have printing capability for the Nimbus Full Scale Deployment
Printer(s) installed, all users able to access and carry out printing functions
Jeff Stembridge John White Gavin Lowrie
Delivered Printers (Stage 1) 07/09/2012 Not started
Updated Asset Register (Stage 1)
All new hardware to be input into new Cherwell service management system
Ensure that all assets are recorded in order to support ITIL Service Support / Service Delivery processes going forward
All hardware recorded correctly, signed off by Service Delivery Manager
John White Delivered Client Devices (Stage 1) Delivered Printers (Stage 1)
07/09/2012 Not started
Hardware Disposal (Stage 1) All old hardware to be disposed off through ICE
Disposed off through ICE in order that it can be retained for one month in case anything still required or we need to backout Full Scale Deployment
All hardware disposed of appropriately
Paul Gardiner Full Scale Deployment (Stage 1)
12/10/2012 Not started
Stage 2 – Install Additional Wyse Terminals in all Stations
Transition Plan (Stage 2)
Transition Plan / Go-Live Playbook identifying all Implementation tasks for rollout of Stage 2 of Full Scale Deployment, including all installations, Communication Plan, Checklist for each device and Backout Plan for each component.
To ensure that all aspects of Transition are documented, approved and managed through to completion.
Sign-off by Head of ICT and Area Commanders
Paul Gardiner System Tested Environment
16/07/2012 Not started
Delivered Client Devices (Stage 2)
Wyse Client Devices imaged and delivered to ECFRS
To provide End-user infrastructure to support Citrix VDI-in-a-box configured to ECFRS requirements
Client Devices supplied as per specifications prior to commencement of Stage 2 deployment
Wyse (Getech) Purchase Order for Client Devices
16/07/2012 Not started
Delivered screens, keyboards and mice (Stage 2)
Screens, keyboards and mice delivered to ECFRS as specified
To provide End-user infrastructure to support Citrix VDI-in-a-box
Screens, keyboards and mice supplied as per specifications prior to commencement of Stage 2 deployment
Paul Gardiner Purchase Order for screens, keyboards and mice
16/07/2012 Not started
Delivered Printer(s) (Stage 2) Printer(s) delivered to ECFRS as specified To provide End-user printing requirements for Full Scale Deployment
Printer(s) supplied as per specifications by prior to commencement of Stage 2 deployment
Jeff Stembridge Purchase Order for Printer(s)
16/07/2012 Not started
13
Status Which products need to What criteria / quality Who is Not started Product What will the product consist of? Why is this product necessary?
standards must be met? responsible? be completed before this Deadline
In progress one (if any)? Complete
Upgraded Local Area Networks (Stage 2)
Harlow Command and Station LAN's upgraded with additional cabling / ports / power
To meet End-user network requirements for Full Scale Deployment
LAN's upgraded as per specifications by 10/02
Property Services / Facilities
Purchase Order for LAN Upgrade
07/09/2012 Not started
Full Scale Deployment (Stage 2)
Installation and configuration of additional Client Devices, screens, keyboards and mice at all Stations
To deploy additional Nimbus hardware to all Stations
All additional hardware installed and functional
Paul Gardiner John White Gavin Lowrie
Transition Plan (Stage 2) Delivered Client Devices (Stage 2) Delivered Screens, Keyboards and Mice (Stage 2)
07/09/2012 Not started
Installed Printers (Stage 2) Installation and configuration of additional Printers at all Stations and add to new Print server
To enable all Stations to have additional printing capability for the Nimbus Full Scale Deployment
Additional Printer(s) installed, all users able to access and carry out printing functions
Jeff Stembridge John White Gavin Lowrie
Delivered Printers (Stage 2) 07/09/2012 Not started
Updated Asset Register (Stage 2)
All new hardware to be input into new Cherwell service management system
Ensure that all assets are recorded in order to support ITIL Service Support / Service Delivery processes going forward
All hardware recorded correctly, signed off by Service Delivery Manager
John White Delivered Client Devices (Stage 2) Delivered Printers (Stage 2)
07/09/2012 Not started
Hardware Disposal (Stage 2) All old hardware to be disposed off through ICE
Disposed off through ICE in order that it can be retained for one month in case anything still required or we need to backout Full Scale Deployment
All hardware disposed of appropriately
Paul Gardiner Full Scale Deployment (Stage 2)
12/10/2012 Not started
Stage 3 – Replacement of current PC’s in all Area Commands, Service Delivery Points, Training Centres, Workshops and Emergency Planning
Application Requirements Analysis (Stage 3)
User / Application matrix, defining who uses which applications for users at all other remote sites
To ensure that new Citrix VDI environment incorporates all application requirements for Full Scale Deployment
Signed-off by SDO's / DO's, as appropriate
Spencer Connelly 30/07/2012 Not started
End-user Device Requirements (Stage 3)
Definition of all End-user Device usage and requirements for all locations
To ensure that new Citrix VDI environment supports all end-user device requirements and all necessary software installed for rollout to all sites in Stage 3
Signed-off by SDO's / DO's, as appropriate
Spencer Connelly 30/07/2012 Not started
Printer Requirements (Stage 3)
Updated Building Plans / Network Diagrams for all locations, identifying all current and additional Printer(s) required
To ensure that all current and additional printer requirements are captured to support 'end-state' user requirements for rollout to all other sites
Signed-off by SDO's / DO's, as appropriate
Spencer Connelly 30/07/2012 Not started
Desktop Image (Stage 3)
Base ECFRS image with any additional applications installed
Provide virtual desktop for all remote users, incorporating additional applications as required
All additional applications / tools successfully installed, configured and verified
Jim Culling Gary Seddon
Application Requirements Analysis (Stage 3)
13/08/2012 Not started
14
Status Which products need to What criteria / quality Who is Not started Product What will the product consist of? Why is this product necessary?
standards must be met? responsible? be completed before this Deadline
In progress one (if any)? Complete
System Tested Environment (Stage 3)
Full System Testing of all additional applications once environment fully built and everything installed and baselined, including AD / GP changes.
To ensure that all additional components function as intended before signing-off VDI-In-a-Box environment
All High priority issues resolved, any outstanding Medium or Low priority issues documented and accepted by PM / Head of ICT before releasing for UAT.
Paul Gardiner Desktop Image (Stage 3)
27/08/2012 Not started
User Acceptance Tested Environment (Stage 3)
User Acceptance Testing of all additional applications
To ensure that all components function as intended before progressing with Stage 3
All High priority issues resolved, any outstanding Medium or Low priority issues documented and accepted by SDO's / DO's before releasing for UAT.
Spencer Connelly System Tested Environment (Stage 3)
10/09/2012 Not started
Transition Plan (Stage 3)
Transition Plan / Go-Live Playbook identifying all Implementation tasks for rollout of Stage 3 of Full Scale Deployment, including all installations, Training Plan, Communication Plan, Checklist for each user (including securing data from C: drives and old USB's) and Backout Plan for each component.
To ensure that all aspects of Transition are documented, approved and managed through to completion.
Sign-off by SDO's / DO's, as appropriate
Paul Gardiner User Acceptance Tested Environment (Stage 3)
10/09/2012 Not started
Delivered Client Devices (Stage 3)
Wyse Client Devices imaged and delivered to ECFRS
To provide End-user infrastructure to support Citrix VDI-in-a-box configured to ECFRS requirements
Client Devices supplied as per specifications prior to commencement of Stage 3 deployment
Wyse (Getech) Purchase Order for Client Devices
10/09/2012 Not started
Delivered screens, keyboards and mice (Stage 3)
Screens, keyboards and mice delivered to ECFRS as specified
To provide End-user infrastructure to support Citrix VDI-in-a-box
Screens, keyboards and mice supplied as per specifications prior to commencement of Stage 3 deployment
Paul Gardiner Purchase Order for screens, keyboards and mice
10/09/2012 Not started
Delivered Printer(s) (Stage 3) Printer(s) delivered to ECFRS as specified To provide End-user printing requirements for Full Scale Deployment
Printer(s) supplied as per specifications by prior to commencement of Stage 3 deployment
Jeff Stembridge Purchase Order for Printer(s)
10/09/2012 Not started
Individual User Accounts (Stage 3)
Individual User Accounts for all personnel setup in Active Directory and all application groups as required
To ensure that all personnel have correct access to applications and network drives etc. according to their roles and responsibilities
All users added and checked prior to commencement of Stage 3 deployment
ICT Service Desk 10/09/2012 Not started
MS Exchange 2010 Migration (Stage 3)
All personnel migrated to / setup in (for new users) MS Exchange 2010 as prerequisite for using MS Outlook 2010
To ensure that all personnel have correct access to MS Outlook
All users migrated prior to commencement of Stage 3 deployment
John White 10/09/2012 Not started
15
Status Which products need to What criteria / quality Who is Not started Product What will the product consist of? Why is this product necessary?
standards must be met? responsible? be completed before this Deadline
In progress one (if any)? Complete
File Servers (Stage 3) Move all remote File Servers to Kelvedon Park
To ensure that all local user drives on file server are moved / copied and re-mapped to VDI environment
Server / data moved / copied and re-mapped to VDI environment with no loss of data, minimum loss of availability and acceptable backout / recovery plan
John White File Server Strategy 05/10/2012 Not started
Full Scale Deployment (Stage 3)
Installation and configuration of Client Devices, screens, keyboards and mice at all locations
To deploy Nimbus hardware to all locations
All hardware installed and functional
Paul Gardiner John White Gavin Lowrie
Transition Plan Delivered Client Devices (Stage 3) Delivered Screens, Keyboards and Mice (Stage 3)
12/10/2012 Not started
User Account Migrations (Stage 3)
Individual User Accounts for all personnel migrated to new Group Policy Objects, profiles and network drives as required
To ensure that all personnel have correct access to applications and network drives etc. according to their roles and responsibilities
All users able to access and carry out normal business functions
ICT Service Desk Individual User Accounts (Stage 3)
12/10/2012 Not started
Trained Users (Stage 3)
Training delivered to all staff as required To ensure that all staff involved in Stage 3 of the Full Scale Deployment are trained to the appropriate level in parallel with deployment
90% attendance of all staff, positive feedback, mop-up sessions to be setup as required
Training Vendor Purchase Order for Training Vendor
12/10/2012 Not started
Installed Printers (Stage 3) Installation and configuration of Printers at all locations and add to new Print server
To enable all locations to have printing capability for the Nimbus Full Scale Deployment
Printer(s) installed, all users able to access and carry out printing functions
Jeff Stembridge John White Gavin Lowrie
Delivered Printers (Stage 3) 12/10/2012 Not started
Updated Asset Register (Stage 3)
All new hardware to be input into new Cherwell service management system
Ensure that all assets are recorded in order to support ITIL Service Support / Service Delivery processes going forward
All hardware recorded correctly, signed off by Service Delivery Manager
John White Delivered Client Devices (Stage 3) Delivered Printers (Stage 3)
12/10/2012 Not started
Hardware Disposal (Stage 3) All old hardware to be disposed off through ICE
Disposed off through ICE in order that it can be retained for one month in case anything still required or we need to backout Full Scale Deployment
All hardware disposed of appropriately
Paul Gardiner Full Scale Deployment (Stage 3)
09/11/2012 Not started
Stage 4 – Replacement of current PC’s in SHQ - Kelvedon Park and remaining personnel in Hutton, including Control
Application Requirements Analysis (Stage 4)
User / Application matrix, defining who uses which applications for all users at SHQ
To ensure that new Citrix VDI environment incorporates all application requirements for Full Scale Deployment
Signed-off by SDO's / DO's, as appropriate
Spencer Connelly 27/08/2012 Not started
16
Status Which products need to What criteria / quality Who is Not started Product What will the product consist of? Why is this product necessary?
standards must be met? responsible? be completed before this Deadline
In progress one (if any)? Complete
End-user Device Requirements (Stage 4)
Definition of all End-user Device usage and requirements for SHQ
To ensure that new Citrix VDI environment supports all end-user device requirements and all necessary software installed for rollout to all sites in Stage 4
Signed-off by SDO's / DO's, as appropriate
Spencer Connelly 27/08/2012 Not started
Printer Requirements (Stage 4)
Identify all current and additional Printer(s) required
To ensure that all current and additional printer requirements are captured to support 'end-state' user requirements for rollout to SHQ
Signed-off by SDO's / DO's, as appropriate
Spencer Connelly 27/08/2012 Not started
Desktop Image (Stage 4)
Base ECFRS image with any additional applications installed
Provide virtual desktop for all SHQ users, incorporating additional applications as required
All additional applications / tools successfully installed, configured and verified
Jim Culling Gary Seddon
Application Requirements Analysis (Stage 4)
17/09/2012 Not started
System Tested Environment (Stage 4)
Full System Testing of all additional applications once environment fully built and everything installed and baselined, including AD / GP changes.
To ensure that all additional components function as intended before signing-off VDI-In-a-Box environment
All High priority issues resolved, any outstanding Medium or Low priority issues documented and accepted by PM / Head of ICT before releasing for UAT.
Paul Gardiner Desktop Image (Stage 4)
01/10/2012 Not started
User Acceptance Tested Environment (Stage 4)
User Acceptance Testing of all additional applications
To ensure that all components function as intended before progressing with Stage 4
All High priority issues resolved, any outstanding Medium or Low priority issues documented and accepted by SDO's / DO's before releasing for UAT.
Spencer Connelly System Tested Environment (Stage 4)
15/10/2012 Not started
Transition Plan (Stage 4)
Transition Plan / Go-Live Playbook identifying all Implementation tasks for rollout of Stage 4 of Full Scale Deployment, including all installations, Training Plan, Communication Plan, Checklist for each user (including securing data from C: drives and old USB's) and Backout Plan for each component.
To ensure that all aspects of Transition are documented, approved and managed through to completion.
Sign-off by SDO's / DO's, as appropriate
Paul Gardiner User Acceptance Tested Environment (Stage 4)
15/10/2012 Not started
Delivered Client Devices (Stage 4)
Wyse Client Devices imaged and delivered to ECFRS
To provide End-user infrastructure to support Citrix VDI-in-a-box configured to ECFRS requirements
Client Devices supplied as per specifications prior to commencement of Stage 4 deployment
Wyse (Getech) Purchase Order for Client Devices
15/10/2012 Not started
Delivered screens, keyboards and mice (Stage 4)
Screens, keyboards and mice delivered to ECFRS as specified
To provide End-user infrastructure to support Citrix VDI-in-a-box
Screens, keyboards and mice supplied as per specifications prior to commencement of Stage 4 deployment
Paul Gardiner Purchase Order for screens, keyboards and mice
15/10/2012 Not started
17
Status Which products need to What criteria / quality Who is Not started Product What will the product consist of? Why is this product necessary?
standards must be met? responsible? be completed before this Deadline
In progress one (if any)? Complete
Delivered Printer(s) (Stage 4) Printer(s) delivered to ECFRS as specified To provide End-user printing requirements for Full Scale Deployment
Printer(s) supplied as per specifications by prior to commencement of Stage 4 deployment
Jeff Stembridge Purchase Order for Printer(s)
15/10/2012 Not started
Individual User Accounts (Stage 4)
Individual User Accounts for all SHQ personnel setup in Active Directory and all application groups as required
To ensure that all SHQ personnel have correct access to applications and network drives etc. according to their roles and responsibilities
All users added and checked prior to commencement of Stage 4 deployment
ICT Service Desk 15/10/2012 Not started
MS Exchange 2010 Migration (Stage 4)
All SHQ personnel migrated to / setup in (for new users) MS Exchange 2010 as prerequisite for using MS Outlook 2010
To ensure that all SHQ personnel have correct access to MS Outlook
All users migrated prior to commencement of Stage 4 deployment
John White 15/10/2012 Not started
Full Scale Deployment (Stage 4)
Installation and configuration of Client Devices, screens, keyboards and mice at all SHQs
To deploy Nimbus hardware to all SHQs
All hardware installed and functional
Paul Gardiner John White Gavin Lowrie
Transition Plan Delivered Client Devices (Stage 4) Delivered Screens, Keyboards and Mice (Stage 4)
16/11/2012 Not started
User Account Migrations (Stage 4)
Individual User Accounts for all SHQ personnel migrated to new Group Policy Objects, profiles and network drives as required
To ensure that all SHQ personnel have correct access to applications and network drives etc. according to their roles and responsibilities
All users able to access and carry out normal business functions
ICT Service Desk Individual User Accounts (Stage 4)
16/11/2012 Not started
Trained Users (Stage 4)
Training delivered to all SHQ staff as required
To ensure that all staff involved in Stage 4 of the Full Scale Deployment are trained to the appropriate level in parallel with deployment
90% attendance of all staff, positive feedback, mop-up sessions to be setup as required
Training Vendor Purchase Order for Training Vendor
16/11/2012 Not started
Installed Printers (Stage 4) Installation and configuration of Printers at all SHQs and add to new Print server
To enable all SHQs to have printing capability for the Nimbus Full Scale Deployment
Printer(s) installed, all users able to access and carry out printing functions
Jeff Stembridge John White Gavin Lowrie
Delivered Printers (Stage 4) 16/11/2012 Not started
Updated Asset Register (Stage 4)
All new hardware to be input into new Cherwell service management system
Ensure that all assets are recorded in order to support ITIL Service Support / Service Delivery processes going forward
All hardware recorded correctly, signed off by Service Delivery Manager
John White Delivered Client Devices (Stage 4) Delivered Printers (Stage 4)
16/11/2012 Not started
Hardware Disposal (Stage 4) All old hardware to be disposed off through ICE
Disposed off through ICE in order that it can be retained for one month in case anything still required or we need to backout Full Scale Deployment
All hardware disposed of appropriately
Paul Gardiner Full Scale Deployment (Stage 4)
07/12/2012 Not started
18
19
21. Project Schedule All dates are provisional, subject to final project approval, prioritisation, scheduling and resource allocation.
22. Resources
Internal Resources The following table denotes the number of days’ effort for each internal team member during the course of the project.
Name/role Number of Days Effort
Jim Culling, ICT Technical Expert - Systems 75
Gary Seddon, ICT Senior Technical Officer 75
Stuart Wash, ICT Technical Officer, Security 75
Richard Duke, ICT Applications Lead 20
Philip Butt, ICT Applications Lead 20
Gavin Lowrie, ICT Installations Technician 82
Chris Eldridge, ICT Service Desk Analyst 103
Total Days Internal Effort 450
External Resources The following table denotes the number of days’ effort for each external team member during the course of the project.
Name/role Number of Days Effort
Henry Dennis, ICT Project Manager 128
Paul Gardiner, ICT Project Manager 155
ICT Business Analyst 30
Total Days External Effort 313
Overall Total Effort (internal and external) for project is 763 days.
1
23. Quality Plan All Product documents will be reviewed and approved by Project Executive, Project Manager or Senior User, as defined by each Product’s criteria / quality standards. Acceptance Criteria / quality standards and Tolerances for Nimbus transition into Production will be defined in the Transition Plans for each Stage.
24. Approval
Each new version of the PID must be approved by the Strategic Delivery Board or the Senior IT Owners Group. Confirm approval below.
Version no. Gateway approval given by… (Group) Date approved
1.0 SDB 28/02/2012
2.0 SMB 20/03/2012
3.0 Call Over for EFA Policy & Strategy Committee 16/04/2012
4.0 EFA Policy & Strategy Committee
Following approval, the Project Manager should upload the PID to MicroP2. Contact Business Planning Section or IT Training if you are not sure how to do this.
2
Appendix A
Full Breakdown of Costs
3
Phase 2 - Citrix VDI-In-a-Box Fully Working Model The following is a full breakdown of costs for the procurement process with Esteem Group, build and testing of the fully working model and the Pilot for Harlow Command / Station and Burnham-on-Crouch station.
DescriptionDaily Rate / Unit Cost
No. of Days / Units
Cost
Project Management
Contract Project Manager (assume 3.5 days per week to end of February) £400 46 £18,400
£18,400
ICT Technical Support
ICT Senior Technical Officers £0 60 £0ICT Technical Officers £0 40 £0
£0
Vendor Professional ServicesEsteem £800 40 £32,000RKeyTec £880 9 £7,920Clarity £650 3 £1,950
£41,870
IT - HardwareHarlow LAN Upgrade – funded by Property Services £0 0 £0
Printer(s) – TBD, we can use 2 x HP’s already in stock, but may need additional b/w printer for station annex £0 0 £0Wyse Thin Client Devices £317 50 £15,833Citrix servers £8,274 2 £16,548
Citrix server upgrades (additional SSD’s and memory) £17,991
Screens (35 x Dell P2312H @ £111) £111 35 £3,885Keyboards (10 x Wyse UK PS2 keyboards @ £5.56) £6 10 £56Keyboards (15 x Dell standard USB keyboards @ £11) £11 15 £165
Keyboards (10 x Microsoft standard USB keyboards @ £13) £13 10 £130
Mice (35 x Dell / Microsoft USB mouse @ £11) £11 35 £385
Encrypted USB drives (32 x Integral Courier 4GB @ £14) - treat as ICT consumables, zero cost to project £0 32 £0£54,992
IT - Software Licensing
Citrix VDI-In-a-Box concurrent licenses (x50) £408 11 £4,483Microsoft VDA licenses (x50) – retail is $100 per year per device, but confirmed that we don’t need them £0 0 £0
£4,483
Training (as per IT-Training-Essex proposal)Training (as per IT-Training-Essex proposal) £375 22 £8,250
£8,250VDIB Pilot Total Costs £127,995
Procurement Process (Esteem) and Harlow Pilot
4
Phase 3 / Stage 1 - Replace Current Neoware Devices in all Stations
The following is a full breakdown of costs for Stage 1 of the Full Scale Deployment.
DescriptionDaily Rate / Unit Cost
No. of Days / Units
Cost
Project Management / Business Analysis
Contract Project Manager (assume 3.5 days per week from beginning March to end of July) £400 74 £29,400
£29,400
ICT Technical Support
ICT Senior Technical Officers (30 days to complete environment build, 2 days per week support for rollout) £0 60 £0
ICT Technical Officer (15 days to complete environment build, 1 day per week support for rollout) £0 30 £0
ICT Installations Technician (1 hour to install / setup each device and screen) £0 18 £0
Service Desk Analyst (0.5 hours to setup / migrate each of 1200 users) £0 80 £0
£0
Vendor Professional Services
Esteem £800 30 £24,000RKeyTec £880 5 £4,400
£28,400
IT - HardwareLAN Upgrades – excluded from Stage 1 £0 0 £0Printer(s) – costs will be picked up by Improved Paper handling & Printing Efficiency project £0 0 £0Wyse Thin Client Devices - all devices will be purchased up front for all Stages £317 629 £199,173Citrix servers £17,270 5 £86,350Screens (Dell P2312H) £111 629 £69,819Keyboards (Dell / Microsoft standard USB keyboards) £13 629 £8,177Mice (Dell / Microsoft USB mouse) £11 629 £6,919
Encrypted USB Drives (Integral Courier 4GB @ £14) - treat as ICT consumables, zero cost to project £0 334 £0
£370,438
IT - Software LicensingCitrix VDI-In-a-Box concurrent licenses (for all concurrent users) £62 350 £21,630Citrix VDI-In-a-Box 1st Year Software Maintenance (for all concurrent users) £19 350 £6,661
£28,291
Training (as per IT-Training-Essex proposal)Training (Whole-time - 4 Watches) - 8 days per Station (4 days Tier 1 and 4 days Tier 2) for 12 Stations - this could be halved if no follow-up support after familairisation sessions £375 96 £36,000Training (Day Crew - 2 Watches) - 4 days per Station (2 days Tier 1 and 2 days Tier 2) for 5 Stations (including USAR) - this could be halved if no follow-up support after familairisation sessions £375 20 £7,500Training (Retained) - 0.5 days per Station (1.5 hours Tier 1 and 2.5 hours Tier 2 evening sessions) for 34 Stations - no follow-up support after familairisation sessions due to time constraints £375 17 £6,375
£49,875
Stage 1 Total Costs £506,403
Replace Current Neoware Boxes
5
Phase 3 / Stage 2 - Install Additional Wyse terminals in all Stations
The following is a full breakdown of costs for Stage 2 of the Full Scale Deployment.
DescriptionDaily Rate / Unit Cost
No. of Days / Units
Cost
Project Management / Business Analysis
Contract Project Manager (assume 3.5 days per week during July, no cost as overlaps with Stage 1) £400 0 £0
£0
ICT Technical Support
ICT Senior Technical Officers (2 days per week support for rollout) £0 10 £0
ICT Technical Officer (1 day per week support for rollout) £0 5 £0
ICT Installations Technician (1 hour to install / setup each device and screen) £0 19 £0
Service Desk Analyst (not required, all Station users setup / migrated in Stage 1) £0 0 £0
£0
Vendor Professional Services
Esteem £800 0 £0RKeyTec £880 0 £0
£0
IT - HardwareLAN Upgrades – assumed cost of £75 per additional network port, based on work done at Harlow £75 139 £10,425Printer(s) – costs will be picked up by Improved Paper handling & Printing Efficiency project £0 0 £0Wyse Thin Client Devices - all purchased within Stage 1 £317 0 £0Citrix servers - all included in Stage 1 £17,270 0 £0Screens (Dell P2312H) - all purchased within Stage 1 £111 0 £0Keyboards (Dell / Microsoft standard USB keyboards) - all purchased within Stage 1 £13 0 £0Mice (Dell / Microsoft USB mouse) - all purchased within Stage 1 £11 0 £0
Encrypted USB Drives (Integral Courier 4GB @ £14) - all purchased within Stage 1 £14 0 £0
£10,425
IT - Software LicensingCitrix VDI-In-a-Box concurrent licenses - all included in Stage 1 £62 0 £0Citrix VDI-In-a-Box 1st Year Software Maintenance - all included in stage 1 £19 0 £0
£0
Training (as per IT-Training-Essex proposal)Training (Whole-time - 4 Watches) - all included in Stage 1, but included 4 days mop-up £375 4 £1,500Training (Day Crew - 2 Watches) - all included in Stage 1, but included 2 days mop-up £375 2 £750Training (Retained) - all included in Stage 1, but included 5 days mop-up £375 5 £1,875
£4,125
Stage 2 Total Costs £14,550
Install Additional Wyse terminals in all Stations
6
Phase 3 / Stage 3 – Replacement of all PC’s in all other remote sites
The following is a full breakdown of costs for Stage 3 of the Full Scale Deployment.
DescriptionDaily Rate / Unit Cost
No. of Days / Units
Cost
Project Management / Business Analysis
Contract Project Manager (assume 3.5 days per week for 5 weeks during August / September) £400 18 £7,000
Contract Business Analyst (assume 10 days to carry out analysis and test any additional application requirements) £400 15 £6,000
£13,000
ICT Technical Support
ICT Senior Technical Officers (2 days per week support for rollout) £0 10 £0
ICT Technical Officer (1 day per week support for rollout) £0 5 £0
ICT Technical Officer (install and test any additional application requirements) £0 15 £0
ICT Installations Technician (1 hour to install / setup each device and screen) £0 22 £0
Service Desk Analyst (0.5 hours to setup / migrate each of 167 users) £0 11 £0
£0
Vendor Professional Services
Esteem £800 0 £0RKeyTec £880 0 £0
£0
IT - HardwareLAN Upgrades – assumed no additional LAN requirements £75 0 £0Printer(s) – costs will be picked up by Improved Paper handling & Printing Efficiency project £0 0 £0Wyse Thin Client Devices - all purchased within Stage 1 £317 0 £0Citrix servers - all included in Stage 1 £17,270 0 £0Screens (Dell P2312H) - all purchased within Stage 1 £111 0 £0Keyboards (Dell / Microsoft standard USB keyboards) - all purchased within Stage 1 £13 0 £0Mice (Dell / Microsoft USB mouse) - all purchased within Stage 1 £11 0 £0
Encrypted USB Drives (Integral Courier 4GB @ £14) - treat as ICT consumables, zero cost to project £0 89 £0
£0
IT - Software LicensingCitrix VDI-In-a-Box concurrent licenses - all included in Stage 1 £62 0 £0Citrix VDI-In-a-Box 1st Year Software Maintenance - all included in stage 1 £19 0 £0
£0
Training (as per IT-Training-Essex proposal)Training (Day Users) - 17 days @ 10 users per day, plus 3 days mop-up £375 20 £7,500
£7,500
Stage 3 Total Costs £20,500
Replacement of current PC’s in all Area Commands, Service Delivery Points, Training Centres, Workshops and Emergency Planning (167 terminals / users)
7
Phase 3 / Stage 4 – Replacement of all PC’s in SHQ The following is a full breakdown of costs for Stage 4 of the Full Scale Deployment.
DescriptionDaily Rate / Unit Cost
No. of Days / Units
Cost
Project Management / Business Analysis
Contract Project Manager (assume 3.5 days per week for 5 weeks during September / October) £400 18 £7,000
Contract Business Analyst (assume 20 days to carry out analysis and test any additional application requirements) £400 15 £6,000
£13,000
ICT Technical Support
ICT Senior Technical Officers (2 days per week support for rollout) £0 10 £0
ICT Technical Officer (1 day per week support for rollout) £0 5 £0
ICT Technical Officer (install and test any additional application requirements) £0 15 £0
ICT Installations Technician (1 hour to install / setup each device and screen) £0 23 £0
Service Desk Analyst (0.5 hours to setup / migrate each of 175 users) £0 12 £0
£0
Vendor Professional Services
Esteem £800 0 £0
RKeyTec £880 0 £0
£0
IT - Hardware
LAN Upgrades – assumed no additional LAN requirements £75 0 £0
Printer(s) – costs will be picked up by Improved Paper handling & Printing Efficiency project £0 0 £0
Wyse Thin Client Devices - all purchased within Stage 1 £317 0 £0
Citrix servers - all included in Stage 1 £17,270 0 £0
Screens (Dell P2312H) - all purchased within Stage 1 £111 0 £0
Keyboards (Dell / Microsoft standard USB keyboards) - all purchased within Stage 1 £13 0 £0
Mice (Dell / Microsoft USB mouse) - all purchased within Stage 1 £11 0 £0
Encrypted USB Drives (Integral Courier 4GB @ £14) - treat as ICT consumables, zero cost to project £0 20 £0
£0
IT - Software LicensingCitrix VDI-In-a-Box concurrent licenses - all included in Stage 1 £62 0 £0Citrix VDI-In-a-Box 1st Year Software Maintenance - all included in Stage 1 £19 0 £0
£0
Training (as per IT-Training-Essex proposal)Training (Day Users) - 18 days @ 10 users per day, plus 4 days mop-up £375 22 £8,250
£8,250
Stage 4 Total Costs £21,250
Replacement of current PC’s in SHQ - Kelvedon Park and remaining personnel in Hutton, including Control(175 terminals / users)
8