Project Information Meeting Route 28 Corridor Improvement Program
As of August 05, 2016
Route 28 Phase 3 Length =1.4 miles
Vint Hill Extended Length =0.75 miles
Route 28 Phase 2 Length = 1.7 miles
Project Information Meeting Route 28 Corridor Improvement Program
Agenda
Project Leadership
Project Location
Project Overview
Request for Qualifications Summary
Contents of Statement of Qualifications
Major Work Elements
Questions\Answers
Project Information Meeting Route 28 Corridor Improvement Program
Project Leadership
Mr. Rick Canizales, Director, PWC Dept. of Transportation Mr. Laurence Farrell, P.E., PMP., PWC Capital Projects Division Chief _________________________________________________________ Mr. Mohammad Ayyoubi, PWC Capital Projects Division Construction Manager Mr. Sherif Bialy, CCM, PWC Capital Project Construction Manager Quinn Consulting Services Inc., Office Engineers, Consultants, and Inspectors _________________________________________________________ Ms. Shana Terry, VCCO, VCO, PWC Senior Contract Specialist Mr. Mark Gunn, P.E. DBIA , Rinker Design Associates, P.C
Project Information Meeting Route 28 Corridor Improvement Program
Project Location
Route 28 Phase 3 Length=1.4 miles
Vint Hill Extended Length=0.75 miles
Route 28 Phase 2 Length=1.7 miles
Project Information Meeting Route 28 Corridor Improvement Project
Umbrella Contract Timeline: Advertise RFQ - Summer 2016 Advertise RFP - Fall 2016 Award Design/Build Contract - Late Fall 2016 Projected Completion Dates: Route 28 Phase II: Summer 2019 (Milestone) Vint Hill Road Extended: Summer 2019 (Milestone) Route 28 Phase III: Summer 2020 Benefits: Estimated significant savings vice bidding these as
separate projects. Internal staff efficiencies and time savings. The total project duration can be reduced. Reduced citizen frustration by having a centralized
point of contact for responding to their concerns as well as by having coordinated work zones that will allow better traffic flow.
Project Overview (pg. 2 of 2)
Vint Hill Ext.
Route 28 Phase 2
Route 28 Phase 3
Prince William County Route 28 Corridor Improvement Program (Design/Build Contract)
Route 28 PH II Fitzwater Dr. to Aden Rd.
1.7 Miles •100% sealed plans. •ROW and dry utility relocation
requirements not included in contract.
•Dry utility relocations ongoing.
•Bids to include QA/QC. •Payment by schedule of
values. •Federal Design
Vint Hill Rd Ext. Schaffer Ln. to Sudley Manor Dr. (0.75 Miles)
•30% plans. (PFI Plans LD-436) •Bids to include QA/QC, all
ROW and all utility relocation expenses.
• (5) Fuel line crossings. •Est. Design Completion: Fall
2017 (TBD by Contractor). •Payment by schedule of
values. •Non Federal Design •Waterline Betterment Plans.
Route 28 PH III Vint Hill Rd. to Penn. Ave.
1.4 Miles •Scoping documents to include
borings, corings, traffic counts, pavement design, and suggested lane configuration. (PM-100)
•Bids to include QA/QC, all ROW and all utility relocation expenses.
•Est. Design Completion: May 2018. (TBD by Contractor)
•Construction completion: summer 2020.
•Payment by schedule of values.
•Federal Design Construction Completion: Summer 2019
• Non-Federal construction except “Buy American”; Uniform Act applies to all three (3) projects. • Award to be made to the lowest price proposal. • Dates assume fall 2016 award; day to day slippage on NTP. • Traditional design-build contract following 2012 VDOT Minimum Requirements for Quality Assurance.
Traditional Design Build
Project Information Meeting Route 28 Corridor Improvement Program
RFQ Summary (pg. 1 of 6)
PWC POC: Shana Terry, VCCO, VCO Prince William County Purchasing Division Email: [email protected] PWC Capital Projects Division Chief : Laurence Farrell, P.E., P.M.P Prince William County Department of Transportation Email: [email protected] Designer of Record and Bridging Documents: Mark Gunn, P.E. Rinker Design Associates, P.C. Email: [email protected] All questions relating to this RFQ shall be submitted in writing via email to the PWC POC with a copy to the Capital Projects Division Chief and
Designer of Record no later than 3:00 PM on Aug 15, 2016.
Project Information Meeting Route 28 Corridor Improvement Program
RFQ Summary (pg. 2 of 6)
Award to be made to the lowest, responsive, responsible bidder. The County’s evaluation team will rate and score the Offeror’s SOQs based on
the below evaluation criteria. County intends to short-list the three (3) highest ranking Offerors. Only short-listed Offerors will receive the RFP. RFQ Information Package can be ordered using Attachment 2.8.
Project Information Meeting Route 28 Corridor Improvement Program
RFQ Summary (pg. 3 of 6)
RFQ Information Package can be ordered using Attachment 2.8. Project Documentation can be down loaded:
• Using Windows Explorer (Not internet explorer) copy and paste link to address bar via the link below:
ftp://PWCdotDBUmbrella16:[email protected]
• Or you can also connect to the FTP server using any standard FTP Client such as FTPVoyager, WSFTP, or CuteFTP. To connect using your FTP Client use the settings below.
FTP Host: files155.cyberlynk.net Username: PWCdotDBUmbrella16 Password: 16$dbPWCDoT
• If you do not have an FTP client you can purchase or download a FREE trial copy via the link http://www.ftpclientlisting.com or you can also use the Web Based JAVA FTP Client from any Windows computer:
Project Information Meeting Route 28 Corridor Improvement Program
RFQ Documents and any Addenda will be posted on the PWC eProcurement website at: http://www2.pwcgov.org/e-proc/
RFQ Summary (pg. 4 of 6)
Project Information Meeting Route 28 Corridor Improvement Program
Attachment 2.10 will be included with any Addenda. Applicants need to include a signed and dated copy of it with their SOQ submission.
RFQ Summary (pg. 5 of 6)
Project Information Meeting Route 28 Corridor Improvement Program
RFQ Summary (pg. 6 of 6)
Tentative Project Schedule:
Jul 29, 2016: Advertise RFQ Aug 05, 2016: Project Information Meeting Aug 15, 2016: Deadline to Submit Questions Sept 02, 2016: SOQ Submission Date Sept 16, 2016: Evaluation and Recommendations Complete Sept 23, 2016: Notification to Applicants of Short-list Sept 26, 2016: Anticipate RFP Release Oct 03, 2016: RFP Meeting Oct 10, 2016: Proprietary Meetings Nov 07, 2016: Letters of Submittals are due Nov 09, 2016: Price Proposals are due Nov 10, 2016: Open Price Proposals Dec 01, 2016: Anticipate Award Date Dec 15, 2016: Anticipate NTP Summer 2020: Estimated Project Completion Date
Project Information Meeting Route 28 Corridor Improvement Program
Statement of Qualifications (SOQ) (pg. 1 of 5)
Offeror’s Team Structure:
Design-Build Project Manager (DBPM) • Responsible for the overall project construction • Authority to bind Contractor • Coordinate any public outreach and public meetings • Attend weekly project meeting on a bi-weekly basis and all monthly senior
leader meetings
Quality Assurance Manager (QAM) • Responsible for the quality assurance (QA) inspection • Professional engineer (PE) • Attend all weekly construction meetings, Preparatory Inspection meetings,
and any recurring meeting related to the quality of the construction. • Responsible for designating a primary point of contact for notification for
inspection at Hold Points and Witness Points.
Project Information Meeting Route 28 Corridor Improvement Program
Statement of Qualifications (SOQ) (pg. 2 of 5)
Offeror’s Team Structure: Design Manager
• Responsible for the coordinating the design efforts. • Professional engineer (PE)
Lead Utility Coordination Manager
• Responsible for the coordination of all utility relocations.
Construction Manager (Must be on-site at all times) • Responsible for managing the construction process including QC • One for entire Program
Right of Way Manager
• Responsible for managing the process to acquire all of right-of-way and easements.
Project Information Meeting Route 28 Corridor Improvement Program
Key Personnel Resume Form (Attachment 3.3.1):
Include experience and
qualifications of the Key Personnel using the forms provided in the solicitation.
Provide DPOR license detail
for each Key Personnel. The proposed team shall
remain intact throughout the duration of the of the contract.
Statement of Qualifications (SOQ) (pg. 3 of 5)
Project Information Meeting Route 28 Corridor Improvement Program
Statement of Qualifications (SOQ) (pg. 4 of 5)
Experience:
Lead Contractor - (3) Projects • Completed within the last four (4) years • (1) with construction value greater than $35M • (2) with construction value greater than $20M • Include Project Experience Information on Attachment 3.4.1
Lead Designer - (3) Projects
• No minimum design amount. • No sunset window on experience. • Include Project Experience Information on Attachment 3.4.1(b)
Project Information Meeting Route 28 Corridor Improvement Program
Statement of Qualifications (SOQ) (pg. 5 of 5)
Identify 3 Critical Project Risks:
Why is the risk critical? What is the potential impact? Mitigation strategies? PWC’s role?
Representative Schedule and Narrative:
Outline the intended flow of work. Schedule should not exceed 400 activities. Work Breakdown Structure is solely up to the Offeror's discretion.
Project Information Meeting Route 28 Corridor Improvement Program
Route 28 Phase II - Major Work Elements (pg. 1 of 3)
• Project Design • 100% Complete Approved for
Construction Plans
• Environmental • Environmental Documentation
Complete • Environmental Permit Obtained &
Mitigation Credits Purchased • Permit Requirements – Kettle Run
• Mussell survey and relocation required
• TOYR Restriction on In-Stream Work (4/15-6/15 & 8/15-9/30)
• Right of Way
• Acquisition Completed by PWC
• Utilities • Utility relocation to be completed by PWC -
October 2016
• Construction & QA/QC • Roadway Improvements • Bridge over Kettle Run • Traffic Signal @ Fitzwater Drive • Major Culvert Crossings • SWM Facilities • Maintenance of Traffic
Project Information Meeting Route 28 Corridor Improvement Program
Vint Hill Extension - Major Work Elements (pg. 2 of 3)
• Project Design • RFP Plans – Approx. 50% Complete • Traffic Analysis – Complete • Geotechnical Data Report (GDR) & Minimum
Pavement Section - Complete • City of Manassas Water Improvements –
100% Complete (36” - Extends to Route 28) • Environmental
• Preliminary Environmental Inventory Complete
• Jurisdictional Determination Complete • Additional Agency Coordination & Permitting
by Design-Builder • Right of Way
• Acquisition by Design-Builder
• Utilities • Petroleum Lines
• Design by Williams/Transco & Colonial Pipeline Ongoing
• City of Manassas Water & PWCSA Facilities
• Utility Relocation Coordination by Design-Builder
• Construction & QA/QC • Roadway Improvements • Traffic Signals – Kettle Run Road &
Sudley Manor Drive • Water & Sewer Construction • SWM Facilities • Maintenance of Traffic
Project Information Meeting Route 28 Corridor Improvement Program
Route 28 Phase III - Major Work Elements (pg. 3 of 3)
• Project Design • RFP Plans – Schematic Plans Only • Traffic Data Collection – Complete
(Supplemented as necessary by Design-Builder)
• Geotechnical – Geotechnical Data Report (GDR) & Minimum Pavement Section to be Completed by PWC
• Environmental • NEPA – EA Re-Evaluation of 2003
Route 28 EA to be completed by Design-Builder
• All Environmental Coordination, Documentation, and Permitting by Design-Builder
• Right of Way • Acquisition by Design-Builder
• Utilities • Utility Relocation Coordination by
Design-Builder • Additional 24” City of Manassas
Water Line
• Construction & QA/QC • Roadway Improvements • Traffic Signals • Water Line • SWM Facilities • Maintenance of Traffic
• Bridge • Bridge over Broad Run already accommodates 6 lanes. No major structural work anticipated
Project Information Meeting Route 28 Corridor Improvement Program
Questions/Answers:
Blasting and hoe ramming as part of the Route 28 Phase I project