PROJECT IMPLEMENTATION APPROACH (PLANNING, … Health Facility/6.Project... · scope of work of...
Transcript of PROJECT IMPLEMENTATION APPROACH (PLANNING, … Health Facility/6.Project... · scope of work of...
Presented By:
Dr. Hasli IbrahimCawangan Kerja Kesihatan,Ibu Pejabat JKR Malaysia.
11 Oktober 2016
PROJECT IMPLEMENTATION APPROACH(PLANNING, DESIGN & PROCUREMENT PHASE)
1. Overview
2. Project Life Cycle
3. Project Implementation Approach:
a) Planning
b) Procurement
c) Design
4. Summary
5. Q & A
1. Overview
2. Project Life Cycle
3. Project Implementation Approach:
a) Planning
b) Procurement
c) Design
4. Summary
5. Q & A
CONTENT
a. Project Implementation:
Process whereby “project inputs are converted to project
outputs”.
Looked at as:
Putting in action the activities of the project,
Putting into practice what was proposed in the project brief into
the actual project, and
Management of the project or executing the project intentions
(time, cost and quality).
“Doing Right Project Rightly”
1.0 OVERVIEW
2.0 Project Life Cycle”Competing Demands
Cost to
Planning
- Initial
Design
- Develop
Procurement
- Execute
Construction
- Finish
Planning Execution
Total Project Life Cycle
Decre
asin
g O
pp
ort
un
ity
Incre
asin
g C
ost
Time
Constructive
Opportunity
Destructive
Intervention
Handing Over /
DLP
HODT
Lead HODT (Coordination)
PROJECT FROM INCEPTION TO HANDING OVER BY JKRPROJECT FROM INCEPTION TO HANDING OVER BY JKR
PLANNING
HODT’S
DESIGN PROCUREMENT
LA CPC
KKM
CONSTRUCTION /
H/OVER / DLP
Issue Related With Design
Lead HODT Vs. HOPT:
Design Review / Verification – Lead HODT
Design Acceptance / Validation - HOPT
CKK Ar Str Civ Elek Mek
Ar
HODT / S.O.S.O.
QS
MONITORING
PPPK (B) / Negeri / JD
PASUKAN PROJEK
ROLE & RESPONSIBILITY CKK, JKR AS “PROGRAM MANAGER”
PMO / HOPT
PMO / HOPT
HODT + SO
HOPT / SO /HODT
HOPT
PRE CONTRACT POST CONTRACT
QS KKMCKK
KKM
TASK DAN TANGGUNGJAWAB
Task
Tanggungjawab
KKM JKR
1. SkopMedical Brief
(MBOR)Teknikal Brif
2. Tapak Cadangan / LokasiPandangan /
Ulasan Teknikal
3. Peruntukan Siling Projek PDA / ATDA
4. Pengurusan Nilai VM / VA VE / VR
5. RekabentukPersetujuan
secara Dasar
Penyediaan /
Kelulusan
• BPPP (Borang Permulaan Pelaksanaan Projek)
i. Project Brief Medical BriefMedical Equipment RequirementEngineering Brief Needs Statement
ii. Ceiling Cost
iii. Location Plan
• Project Register in SKALA JKR Achieved Category 3 (Land, Brief & Ceiling - ok)
Siling / Kos
Nota:Ketepatan untuk “Translate Medical Brief” kepada‘Projek Brief” & “Kos Projek” sangat penting – bagimengelakkan perbezaan jurang ketara Brif Projekberbanding Kos Projek yang diperuntukkan.
• Appointment of Head of Project Team (HOPT) by Program Manager
• Appointment of Head of Design Team (HODT) by Program Manager
i. HODT Architect
ii. HODT Mechanical
iii. HODT Electrical + ICT
iv. HODT Civil
v. HODT Structure
vi. HODT QS
• BPPP + Brief to HODTs + Meeting
(B) Design and Build– Tender
• Pre-Q (open tender)(by JKR) – No Letter of Intent to Contractors.
• Selective Tender (Name of Contractors by Treasury) -Issue letter of invitation to contractors.
(B) Design and Build– Tender
• Pre-Q (open tender)(by JKR) – No Letter of Intent to Contractors.
• Selective Tender (Name of Contractors by Treasury) -Issue letter of invitation to contractors.
(A) Design & Build- Direct Negotiation
• Issue Letter of Intent to contractor (Appointed by Treasury) for direct negotiation project.
Note: Contractor to submit name of consultants for JKR approval.
(A) Design & Build- Direct Negotiation
• Issue Letter of Intent to contractor (Appointed by Treasury) for direct negotiation project.
Note: Contractor to submit name of consultants for JKR approval.
HOPT All HODTsMOH
• HODTs to prepare queries to MOH for clarification /discrepancies of Medical Brief.
• Clarification of scope of works (e.g. ICT, HICT, THISrequirement, medical equipment, loose medicalequipment, furniture and space requirements)
• MOH to issue addendum if any / MOH to reply in writingon any changes of requirement. If major, revise theMedical Brief.
• Finalise Medical Brief
• Preparation of Technical Need Statements of Architecture,Civil and Structure, Mechanical, Electrical and ICT based onfinalised Medical Brief (2 – 3 weeks).
• Discuss Implementation Schedule - JKR to prepare Q-Planand D-Plan.
• Inform of Site Visit date.
• Prepare SPB Form Borang JKR.PK(O).01-2 – Borang VerifikasiHarta Pelanggan.
• Prepare SPB Form Borang JKR.PK(O).01-3 – Senarai SemakanLawatan Tapak. Enclose with HODTs comments on sitecondition.
• HODTs to study site condition. Site requirement / informationto be included in the Technical Need Statements forcontractor to comply.
(e.g. Demolishing works, utility requirement, water supply,sewerage, telephone and TNB requirements etc.)
Comprises of :
Technical Need Statements
Financial Need Statements
Volume 1 – Contractual and General Requirements
Volume 2 – Architectural Requirements
– Medical Brief (MBOR)
Volume 3 – Civil Requirements
Volume 4 – Structural Requirements
Volume 5 – Mechanical Requirements
Volume 6 – Electrical Requirements
Volume 7 – ICT Requirements
Volume 8 – Environmental and Energy Efficiency
Volume 9 – Medical, Non-Medical Equipment, Furniture and Vehicles.
* VA must complete & PDA must be approved before issuing Pre-Bid
• After issue Pre-Bid, No discussion with individual tenderer.
• Contractual and General Requirements under instructionto tenderer. After 1 week of issuing Pre-Bid, tenderers cansend queries to Project Director for clarification.
• Project Director may issue further instructions /information / addendum to Pre-Bid.
• Briefings may be given to all tenderers.
• HOPT held meeting with all HODTs an KKM to agree onevaluation format - weightage and percentage of eachscope of work of respective disciplines.
• HOPT develop overall weightage format agreed by allHODTs & KKM.
• HODTs to evaluate all contractors technical proposal usingformat of compliance / non compliance consisting ofscoring system / rating system and prepare NCR report.
• HODT CKUB evaluate financial proposal.
• MOH to evaluate on medical planning requirement andequipment requirement and prepare NCR report.
• Medical Equipment Mechanical and Electrical related.Specification as in Pre-Bid document. Proposed bycontractor to be evaluated by MOH and JKR.
• Loose Medical Equipment (Not specified in NeedStatement evaluate by MOH)
Four different groups of Medical Equipment / furniture :-
Group I:
Supplied and installed by contractor. Major items includeMechanical and Electrical related (sterilizer equipment,autoclaves, surgical lights, imaging equipment includingbuilt-in furniture.)
Group II:
Supplied by client and installed by contractor.Equipments with Mechanical and Electrical requirement(e.g. salvageable from existing hospital)
Group III:
Supplied and installed by client. (Plug and playequipment requirement, electrical outlets/water sources,loose furniture and portable medical equipment – occupyspace).
Group IV:
Other items with storage implication (e.g. linen andconsumable.)
• Tender Evaluation Report (Technical + Financial) andrecommendation to Tender Board.
< RM 100 million approval by JKR
> RM 100 million approval by Treasury
• SPP Bil 5 Tahun 2007 / Garis Panduan Penilaian Tender(SAP 21 Mac 2008)
• Issue Letter of Intent to the successful tenderer with all theNCR report.
• Finalise zoning and layout floor plan. Minor changes to suitfunction with NO CHANGES ON THE BUILDING FOOTPRINT.
• Room Data Interaction:
No additional items added unless to comply to function andneed statement of pre-bid document.
• Preparation of Architectural drawings, loaded drawings /preliminary / concept drawings for mechanical and electricalrequirement.
• Contractor to prepare coordinated drawings. (Architecture,M&E and Structure).
• Finalizing and confirmation of finishes and materialoffered by successful tenderer.
• Confirm systems offered.
• Confirm brands; medical and non medical equipment.
• All NCR to be closed.
• Issue Letter of Acceptance (LA).
“No Additional Cost Should Be Allowed In Closing The NCR
i.e. Finalizing The Materials, Finishes, Equipment Layout
Floor Plans, Room Data Interactions Must Be Within The
Tendered Cost”
(a) Architecture
• Working drawing • Landscaping
• Sanitary fittings • Kitchen layout
• Ironmongery • Colour scheme
• Signages • ID works
• Built in furniture and loose furniture
• Miscellaneous details (e.g. Hatches, grills etc)
• Room Data Documentation should be bound between 6 months
– 1 year after LA (about 20% work progress on site)
• Finalised coordinated drawings 6 – 12 months after Letter of
Acceptance.
(b) Medical Equipment
• Schedule of Technical Specification Adherence (TSA)submission agreed by JKR and MOH
• TSA documentation concurred by JKR and MOH (in stages)
(c) Electrical Scope of Works
• Detail Design and all scopes of electrical works
• E.g. Standard size of circuit, DB etc, Location of electrical rooms
• Coordination of electrical security system and architectural security requirement
• Detail drawings of inter electrical services • TSA – Technical Specification Adherence
• Detail coordinated drawings of Mechanical & Electrical services, Architecture and Structural drawings
• E.g. Location of light fittings, PA system, CCTV, MATV etc.
• Coordination drawings of ceiling pattern, air condition ducting and grills
• Contract Documentation (4 months after LA)
• Shop drawings related to design
(d) Mechanical Scope of Works
• Detail Design and all scopes of mechanical works E.g. Chiller size, AHU, Medical Gas, Plant Room Size
• Detail of final selected systems E.g. AHU/FCU manifold system / plant system
• Shop drawings related to design.(Working drawings / construction drawings based on shop drawings approved by consultants)
• Detail coordinated drawings of Mechanical & Electrical services
• TSA – Technical Specification Adherence
• Final calculation endorsed by consultants • Contract Documentation
PELAKSANAAN PROJEK HOSPITAL SEMASA
1. Tempoh Perancangan SEBENAR Projek Hospital:
Kategori Projek Tempoh
a) Rekabentuk Piawai 9 Bulan
b) Rekabentuk One-off (Normal) 15-18 Bulan
c) Rekabentuk One-Off (Major) 20-24 Bulan
d) Rekabentuk D&B 15-18 Bulan
Continued..
2. Ringkasan
Program Kerja:Pelaksanaan Projek Secara D&B
Total = 278 Hari Bekerja
≈ 12.6 Bulan
PELAKSANAAN PROJEK HOSPITAL SEMASA (Samb..)
2. Tempoh Pembinaan (Kontrak) Projek Hospital:
3. Pelaksanaan projek-projek Fasiliti Kesihatan sangat memerlukankerjasama erat di antara Pelanggan dan Agensi Pelaksanadisebabkan kompleksiti dan keunikan tersendiri projek tersebutberbanding fasiliti-fasiliti awam yang lain.
Kategori Projek Tempoh
a) Naik Taraf Hospital / Fasiliti Kesihatan 30-36 Bulan
b) Hospital Baru 40-48 Bulan