7
Project first prototype Group NJT2C
Transcript of Project first prototype NJT2C 1
Manufacturing Process
Many Parts1.injection molding 2.joining 3.assembly
4.decoration
For this model1.cutting 2.pushing 3.joining 4.assembly
5.decoration
Problems and Solutions
1. P: That it does not fit the part. It was designed not to look at the materials available in the market.
S: we modified the CAD.2. P: The materials in the markets is not available for assembly. s: we modified them.3. P:The operation is complicated and complex. Because the parts is high resolution due to smaller parts. S:We use precise machine.
Process Duration
Injection molding Ca. 10-15 s
Assembly ca. 1 hr