Project Finance Ava

download Project Finance Ava

of 54

Transcript of Project Finance Ava

  • 8/22/2019 Project Finance Ava

    1/54

    PROJECT FINANCE

    AROLKAR ABHAY VASANTPartner,

    M/s A.V.Arolkar & Co., Chartered Accountants

    MUMBAI

    April 28, 2012 1A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    2/54

    INTRODUCTION

    With a view to harnessing advancements in

    economic development, GoI laid emphasis on

    industrialisation through successive Five Year

    Plans.

    Rapid industrial development needed massive

    investment.

    Prior to independence, there were no

    institutional arrangements for term finance.

    April 28, 2012 2A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    3/54

    INTRODUCTION

    GoI, therefore, established the following

    financial institutions:

    Indl. Finance Corporation of India (1948) Indl. Credit & Inv. Corpn. of India (1955)

    Indl. Development Bank of India (1964) &

    Indl. Reconstruction Bank of India (1971)

    Similarly, State Governments also established

    SFCs in their respective states.April 28, 2012 3A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    4/54

    INTRODUCTION

    For long, commercial banks confined their

    lendings to meet WC requirements only and

    they did not play any active role in extending

    term finance.

    However, with increasing proportion of Term

    Deposits in their deposit portfolio and the

    paucity of resources in the country, it was felt

    that banks could enter the field of term

    finance, in a role complementary to that of

    Term Lending Institutions.April 28, 2012 4A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    5/54

    PROJECT BACKGROUND

    The purpose of term assistance is to meet a

    part of the capital expenditure of a project.

    A project can be defined as A scheme ofthings to be done during a specified period in

    future for deriving expected benefits under

    certain assumed conditions.

    A project may be in the nature of setting up a

    new industrial unit, modernisation, expansion,

    diversification and promotion of R&D.April 28, 2012 5A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    6/54

    PROJECT BACKGROUND

    To set up a project, certain capitalexpenditure needs to be incurred in acquiringassets such as L&B, P&M and otherinfrastructural facilities like roads, watersupply, railway sidings, etc., in addition to thePreliminary / Pre-Operative Expenses andmargin on WC Limits.

    Where promoters of a project are unable tomeet the entire capital expenditure out oftheir own resources, Term Loans are

    sanctioned to supplement the promoterscontribution.April 28, 2012 6A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    7/54

    PROJECT BACKGROUND

    Promoters of an industrial project can

    constitute themselves into any of the

    following forms of business organisations to

    implement the project : Sole Proprietorship,JHF, Partnership, Co-operative Society & Joint

    Stock Company.

    Our discussion of the subject would revolve

    around Joint Stock Company as promoter.

    April 28, 2012 7A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    8/54

    PROJECT BACKGROUND

    The Promotion Stage is a crucial stage in the

    entire life cycle of a project. Promotion in

    relation to a project will comprise broadly the

    following functions:

    I] Identification of a project

    II] Feasibility investigation

    III] Assembling the proposition

    IV] Financing the propositionApril 28, 2012 8A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    9/54

    I] Identification of a Project

    The first step in the project promotion is the

    identification of a project. An industrial

    project originates as an idea in a promoter

    when he observes the existence of a potentialmarket for a certain product.

    The promoter, on the basis of his experience,

    background and ability, then considers the

    feasibility of manufacturing and marketing the

    product at a remunerative price.

    April 28, 2012 9A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    10/54

    II] Feasibility Investigation

    A detailed feasibility study is a costly exercise.It is, therefore, desirable that, before it is

    undertaken, marketability of the product to

    be manufactured is firmly established.

    There are agencies, specialising in market

    research, which conduct such market studies.

    Promoters may take advantage of theirservices.

    A market study aims at assessing the

    aggregate demand for a product.April 28, 2012 10A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    11/54

    II] Feasibility Investigation

    The promoter will now undertake the detailed

    feasibility investigation proper, comprising

    two feasibility studies:

    i) The Technical Feasibility Study

    ii) The Economic Feasibility Study

    April 28, 2012 11A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    12/54

    II] Feasibility Investigation

    - Technical Feasibility

    Technical Feasibility Study covers thefollowing aspects:

    Location of the project

    Lay-out of the PlantSize of the Plant

    Factory construction

    Manufacturing process / TechnologyProcess Design

    Product Design

    Scale of Operation

    Infrastructural facilitiesApril 28, 2012 12A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    13/54

    II] Feasibility Investigation

    - Economic Feasibility

    The prime objective of setting up a project is

    to derive a fair return on the investment.

    Economic Feasibility Study, therefore,concerns itself with matching of economic

    resources with the physical requirements of a

    project and determining the viability of

    investment therein.

    April 28, 2012 13A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    14/54

    III] Assembling the Proposition

    - CoP & MoF

    When a promoter is satisfied about thetechnical feasibility and economic viability ofa project, the next task is to work out the

    Cost of the Project and the Means of financingit.

    The Cost of the Project would broadly include:

    (a) L&B (b) P&M (c) Misc. Fixed Assets (d)Technical Know-how, Engg. & Consultancyfees (e) Preliminary and Pre-operativeexpenses (f) Provision for contingencies (g)

    Margin on WC LimitsApril 28, 2012 14A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    15/54

    IV] Financing the Proposition

    Setting up of a project involves acquisition ofFixed Assets which facilitate the process ofproduction. Fixed Assets have a relatively

    longer life and are generally not meant forresale. They are required to be retained overa period of time to exploit their productivepotential.

    C/A go through the operating cycle of RM, WIPand FG, which when sold bring in cash. Thiscycle is generally completed in a short period

    of less than one year.April 28, 2012 15A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    16/54

    IV] Financing the Proposition

    Thus, investment in C/A is realised over a

    short term, while investment in Fixed Assets is

    long term in nature.

    It is realised through surplus generated in the

    form of Net Profits, Depreciation and other

    non-cash write-offs.

    As it takes a long time for the Fixed Assets to

    pay for themselves, the promoter should raise

    suitable long term funds to finance a project.April 28, 2012 16A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    17/54

    IV] Financing the Proposition

    Keeping the foregoing in view, the promoter

    will explore the financial feasibility of the

    project by examining

    a) The possible long term sources of finance

    b) The feasible financial leverage

    c) The expected return on the investment

    April 28, 2012 17A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    18/54

    IV] Financing the Proposition

    Equity Preference

    Share Capital Retained Earnings

    OWNED CAPITAL

    Debentures Term Loans, DPGs Public Deposits

    BORROWED CAPITAL

    LONG TERM SOURCES

    April 28, 2012 18A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    19/54

    IV] Financing the Proposition

    - Long Term Sources

    The aggregate amount of finance raised for

    financing a project is referred to as Capital,

    comprising two components (a) Owned

    Capital and (b) Borrowed Capital.

    The other sources of long term funds are:

    (a) Capital Subsidy applicable to projects

    coming up in certain notified backward areas,

    and (b) Interest free sales tax loans offered by

    State Governments.

    April 28, 2012 19A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    20/54

    IV] Financing the Proposition

    - Financial Leverage

    After considering availability of long terms

    sources of finance, the promoter will decide

    about a suitable financial structure for the

    Company.

    It will depend upon the financial leverage

    envisaged in the combination of sources of

    finance under the two categories, viz., Owned

    Capital and Borrowed Capital.

    Few projects can be financed entirely byApril 28, 2012 20A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    21/54

    IV] Financing the Proposition

    - Financial Leverage

    The divergent interests of debt and equity are

    brought into alignment by the concept of Debt

    / Equity gearing which determines the level of

    debt that can be supported by a givenquantum of equity.

    For this purpose, Debt means Funded Debt

    including all term liabilities and equity will

    include Share Capital and retained earnings, if

    available.

    April 28, 2012 21A. V. Arolkar & Co., Chartered Accountants

    IV] Financing the Proposition

  • 8/22/2019 Project Finance Ava

    22/54

    IV] Financing the Proposition- Return on Investment

    The amount invested in a project can be

    recouped through annual cash flows, over a

    period of time.

    In arriving at a financial plan for the project, a

    promoter will examine the attractiveness of

    the project, vis--vis alternative sources ofinvestment.

    The process which assists the management in

    such a task is collectively known as CapitalApril 28, 2012 22A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    23/54

    IV] Financing the Proposition

    - Return on Investment

    The most important and widely used Capital

    Investment Evaluation techniques are:

    Pay-back MethodNet Terminal Surplus Method

    Excess Present Value Method

    Internal Rate of Return Method

    April 28, 2012 23A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    24/54

    IV] Financing the Proposition

    - Return on Investment

    The object of Pay-back Method is to find out

    the period of time required for recovering the

    entire amount of investment made in a

    project.

    The cash flows (Net Profit + Depreciation +

    Other non-cash write-offs) are compared with

    the outlay on the project to determine the

    pay-back period. Years to pay back would be:

    Total InvestmentApril 28, 2012 24A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    25/54

    IV] Financing the Proposition

    - Return on Investment

    Net Terminal Surplus Method employs the

    concept of compounding which involves

    re-investing the simple interest earned each

    year along with the principal so that theprincipal grows each year by the amount of

    interest earned during the previous year and

    interest being calculated on the increasedprincipal also grows.

    Future Value = Principal x (1+i)

    April 28, 2012 25A. V. Arolkar & Co., Chartered Accountants

    ] h

  • 8/22/2019 Project Finance Ava

    26/54

    IV] Financing the Proposition

    - Return on Investment

    Excess Present Value Method is based on thediscounted cash flow technique and uses the conceptof discounting which is just the opposite ofcompounding.

    In discounting, we arrive at the Present value of afuture sum to which the original amount (which wewant to find out), invested at a particular compound

    rate of interest has grown.PV = Future sum

    (1+i)

    April 28, 2012 26A. V. Arolkar & Co., Chartered Accountants

    IV] Fi i h P i i

  • 8/22/2019 Project Finance Ava

    27/54

    IV] Financing the Proposition

    - Return on Investment

    Internal Rate of Return Method It is that rate at

    which the sum of the discounted cash flows is equal

    to the investment outlay. In other words, IRR is the

    rate which makes the Present Value (PV) of benefitsequal to the Present Value of costs or reduces the

    Net Present Value (NPV) to zero. The object of this

    method is to find the rate of return which a project

    is likely to earn over its useful life.

    IRR =Lower Discount Rate + Diff. Between the two discount rates x NPV at lower discount rateAbs. diff. between the two NPVs.

    April 28, 2012 27A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    28/54

    Types of Term Assistance

    The types of term assistance extended by the

    Bank can be broadly classified into:

    I] Term Loans (Incl. Forex Loans)

    II] Deferred Payment Guarantees

    III] Bill Discounting Facilities

    IV] Underwriting of Shares / Debentures

    April 28, 2012 28A. V. Arolkar & Co., Chartered Accountants

    T f T A i

  • 8/22/2019 Project Finance Ava

    29/54

    Types of Term Assistance

    -Term Loan

    A Term Loan is a loan granted for a fixed term

    of not less than one year, intended normally

    for financing fixed assets acquired / to be

    acquired, carrying interest at a specified rate,and scheduled for repayment in instalments.

    Depending on the term for which the said

    terms loans are granted, they could be

    classified into (a) Short Term Loans (b)

    Medium Term Loans and (c) Long Term Loans.

    April 28, 2012 29A. V. Arolkar & Co., Chartered Accountants

    T f T A i t

  • 8/22/2019 Project Finance Ava

    30/54

    Types of Term Assistance

    -DPG

    Deferred Payment Guarantee (DPG) is a contract topay to the supplier the price of machinery, suppliedby him on deferred terms, in agreed instalments withstipulated interest on the respective due dates in

    case of default in payment thereof by the buyer.

    A DPG is, in many respects, a substitute for a TermLoan and, as far as the buyer of P&M is concerned, it

    serves the same purposes as a Term Loan. Standards of appraisal are the same as TL.

    April 28, 2012 30A. V. Arolkar & Co., Chartered Accountants

    T f T A i t

  • 8/22/2019 Project Finance Ava

    31/54

    Types of Term Assistance

    - Bills Discounting

    Under a contract for sale of machinery on

    deferred payment basis, the balance

    remaining to be paid after the initial down

    payment represents the deferred receivablesof the seller.

    Thus, the funds of the seller get blocked for

    unduly long periods and the seller requires

    finance against such deferred receivables to

    replenish his Working Capital.

    April 28, 2012 31A. V. Arolkar & Co., Chartered Accountants

    T f T A i t

  • 8/22/2019 Project Finance Ava

    32/54

    Types of Term Assistance

    - Bills Discounting

    To facilitate availment of finance against the

    deferred receivables, the seller usually draws

    a series of usance bills with graded maturities

    to coincide with the due dates of payment ofthe relative instalments (including applicable

    interest).

    The usance bills drawn by the seller will be

    accepted by the buyer before they are

    discounted by the sellers banker.

    April 28, 2012 32A. V. Arolkar & Co., Chartered Accountants

    T f T A i t

  • 8/22/2019 Project Finance Ava

    33/54

    Types of Term Assistance

    - Underwriting of Shares

    The necessity for underwriting arrangementarises only in the case of a Public LimitedCompany resorting to raise through the capital

    issue market, a part of the Share Capital forpart-financing a project.

    Underwriting is a contract whereby a person

    agrees, in consideration, to take up aspecified number of shares or debentures oramount of debenture stock to be offered tothe public, in the event of the public not

    subscribing for them.April 28, 2012 33A. V. Arolkar & Co., Chartered Accountants

    T f T A i t

  • 8/22/2019 Project Finance Ava

    34/54

    Types of Term Assistance

    - Underwriting of Shares

    Underwriting as a business will come under the scope of

    Investment Banking as distinct from Commercial

    Banking.

    In view of this, therefore, a high degree of selectivityshould continue to be exercised in undertaking

    underwriting business.

    However, the business stemmed not so much from the

    point of view of earnings on the investment as from the

    consideration that no viable project enjoying national

    priority should suffer for want of underwriting support.

    April 28, 2012 34A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    35/54

    Project Appraisal

    The purpose of Project Appraisal is to ascertainwhether the project will be sound technically,economically, financially and managerially andultimately viable as a commercial proposition.

    The appraisal of a project will involve theexamination of:

    a) Technical Feasibility : To determine the suitability

    of the technology selected and the adequacy of thetechnical investigation, and design.

    April 28, 2012 35A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    36/54

    Project Appraisal

    b) Economic Feasibility : To determine theconduciveness of economic parameters to setting upthe project and their impact on the scale ofoperations.

    c) Financial Feasibility : To determine the accuracyof cost estimates, suitability of the envisaged patternof financing and general soundness of the capital

    structure. d) Commercial Viability : To ascertain the extent of

    profitability of the project and its sufficiency inrelation to the repayment obligations pertaining to

    term finance.April 28, 2012 36A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    37/54

    Project Appraisal

    e) Managerial Competency : To ascertain thatcompetent men are behind the project toensure its successful implementation and

    efficient management after commencement ofcommercial production.

    A project should also be examined, wherever

    appropriate, from the point of view of itsvalue to the national economy in terms ofsocio-economic benefits like generation ofemployment opportunities, forex earnings, the

    quantum of import substitution, etc.April 28, 2012 37A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    38/54

    Project Appraisal

    The first step in Project Appraisal is to find out

    whether the project is prima facie acceptable byexamining salient features such as:

    The background and experience of the applicants,particularly in the proposed line of activity

    The potential demand for the product

    The availability of the required inputs, utilities andother infrastructural facilities

    Whether the project is in keeping with the priorities,

    if any, laid down by the Government.April 28, 2012 38A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    39/54

    Project Appraisal

    The original application may not contain all the basicdata / information. In such cases, it may benecessary to provide all the necessary data /information with a view to give an overall idea aboutthe general feasibility of the project at the time ofinterview by the bankers.

    After satisfying itself about the prima facie

    acceptability of the project, the Bankers will call foran prescribed Application, containing the followingessential data / information, such as:

    April 28, 2012 39A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    40/54

    Project Appraisal

    a) Particulars of the project along with a copy

    of the Project Report furnishing details of the

    technology, manufacturing process,

    availability of construction / productionfacilities, etc.

    b) Estimates of cost of the project detailing

    the itemised assets acquired / to be acquired,

    inclusive of Preliminary / Pre-operative

    Expenses and WC margin requirements.April 28, 2012 40A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    41/54

    Project Appraisal

    c) Details of the proposed means of financingindicating the extent ofpromoters contribution, thequantum of Share Capital to be raised by publicissue, the composition of the borrowed capitalportion with particulars of Term Loans, DPGs, ForeignCurrency Loans, etc.

    d) WC requirements at the peak level (i.e., when the

    level of Gross Current Assets is at the peak) duringthe first year of operations after the commencementof commercial production and the bankingarrangements to be made for financing the WC

    requirements.April 28, 2012 41A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    42/54

    Project Appraisal

    e) Project Implementation Schedule.

    f) Organisational set up along with a list ofBoard of Directors and indicating thequalifications, experience and competence of(i) The key personnel to be in charge ofimplementation of the project during the

    construction period and (ii) The executives tobe in charge of the functional areas ofpurchase, production, marketing and financeafter commencement of commercial

    production.April 28, 2012 42A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    43/54

    Project Appraisal

    g) Demand projection based on the overall

    market prospects together with a copy of the

    market survey report.

    h) Estimates of sales, CoP and profitability.

    i) Projected P&L Account and B/S for the

    operating years during the currency of theBanks term assistance.

    j) Proposed amortisation schedule, i.e.,

    repayment programme.April 28, 2012 43A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    44/54

    Project Appraisal

    k) Projected Funds Flow Statement covering

    both the construction period and the

    subsequent operating years during the

    currency of the Term Loan.

    l) Details of the nature and value of the

    securities offered.

    m) Consents from the Government / other

    authorities and any other relevant

    information.April 28, 2012 44A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    45/54

    Project Appraisal

    In respect of existing concerns, in addition to

    this information, particulars regarding the

    history of the concern, its past performance,

    present financial position, etc., should also becalled for.

    The Application completed in all respects

    and duly signed by the authorised signatories

    of the Company will form the basis for the

    detailed appraisal of the project.April 28, 2012 45A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    46/54

    Project Appraisal

    An inspection of the project site (or factory in thecase of existing units) will be done by the bankers.

    Each project has to be examined in proper

    perspective having due regard to its nature, size andscope.

    Although the basic techniques employed forappraising the viability of various projects are moreor less the same, there could be no standard oruniform approach for appraising all projects.

    April 28, 2012 46A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    47/54

    Project Appraisal

    The ultimate objective of the appraisal

    exercise is to ascertain the viability of a

    project with a view to ensuring the repayment

    of the borrowers obligations under the Banksterm assistance.

    Therefore, it is not so much the quantum of

    the proposed term assistance as the prospects

    of its repayment that weighs with the bankers

    while appraising a project.April 28, 2012 47A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    48/54

    Project Appraisal

    In project appraisal, nothing is assumed or taken for

    granted, so be truthful and give facts

    All the data / information would be checked and,

    wherever possible, counter-checked through inter-

    firm and inter-industry comparisons.

    It should be borne in mind that bankers believe

    Healthy scepticism is a cardinal virtue in projectappraisal.

    April 28, 2012 48A. V. Arolkar & Co., Chartered Accountants

  • 8/22/2019 Project Finance Ava

    49/54

    Project Appraisal Memorandum

    1. PROPOSAL

    Nature of proposal;

    Purpose : New project, expansion, modernisation, diversification or for any other approved purpose

    2. BRIEF HISTORY

    Brief account of corporate history; MA & AA; Regd. address; Present organisational set up with BoD; Qualifications, experience and background;

    Line of activities, Financial position, etc., of Associate Concerns; Overall structure of inter-corporate investments

    3. PAST PERFORMANCESummary of Company's past performance in terms of licensed / installed / operating capacities, sales, operating profit and Net Profit for

    the past 3 years; Capacity utilisation; Sales & profitability; Dividend policy; Capital expenditure programmes implemented by the Company

    during the past 3 years and how they were financed; Company's management-labour relations

    4. PRESENT FINANCIAL POSITION

    Company's audited Balance Sheets & P/L Accounts for the past 3 years with analysis; Company's Capital structure; Summarise conclusions

    of financial analysis; Method of depreciation; Revaluation of F/A; Record of major defaults; Position of Company's tax assessment; ContingentLiabilities; Pending suits; Qualifications / Adverse remarks by auditors

    PROJECT APPRAISAL MEMORANDUM

    49

  • 8/22/2019 Project Finance Ava

    50/54

    Project Appraisal Memorandum

    5. PROJECT

    (a) Description of the project (Modernisation, expansion, diversification or a new venture) ; Standing, experience and reliability of

    outside agency who prepared the Project Report; (b) Collaboration Arrangement (Technical or Financial); (c) Technical Feasibility covering

    suitability of technology, size & location of plant, technical arrangements & mfg. process (d) Financial Feasibility covering Cost of Project & Means of Finance

    6. PROJECT IMPLEMENTATION SCHEDULE

    With reference to Bar Chart or PERT / CPM Chart and in the light of actual implementation; Main stages in the project implementation and whether the time

    schedule for construction, erection / installation of P&M, start-up / trial run, commencement of commercial production is reasonable & acceptable

    7. PRODUCTION FACTORS

    (a) Mfg. Process - Basis of selection & justification; (b) Raw Materials - Imported / Indigenous, Names of main suppliers, Pattern of unit prices & fluctuation;

    (c) Utilities & Essential Services - Requirements of power, fuel, water, transport, railway siding with comments on adequacy of arrangements, treatment

    and disposal of effluents; (d) Operating Organisation - Experience and expertise of Managerial / Technical personnel, other staff required

    8. WORKING CAPITAL REQUIREMENTS

    Assessment of total WC requirements at the peak level (GCA) during the first year of operations after commencement of commercial production;

    sharing of business among member banks; financing of additional WC requirments in case of existing companies

    PROJECT APPRAISAL MEMORANDUM

    50

  • 8/22/2019 Project Finance Ava

    51/54

    Project Appraisal Memorandum

    9. MARKETING

    (a) Sales prospects and underlying assumptions, demand projections on the basis of past consumption, total supply position, general condition of industry

    (b) Selling Price - Trend to see whether stable, Govt. price controls, quota systems, etc.; (c) Propsects for exports - Export obligations;

    (d) Marketing Organisation - Adequacy, Distributors / Selling Agents, Terms of arrangement, remuneration, competence, Asso. Concerns - Siphoning of profits

    10. COMMERCIAL VIABILITY - CoP & PROFITABILITY

    (A) Sales Volume / Value - (a) Volume; (b) No. of working days; (c) Capacity utilisation; (d) Value (B) CoP - (a) Matls. consumed; (b) Utilities (PW&F); (c) Wages & Salaries

    (d) Factory Overheads; (e) Depreciation - SLM / WDV- Consistency; (f) Selling Exp.; (g) Financial Exp.; (h) Admn. Exp.; (i) Royalty & Know-how; (j) Preliminary / Pre-operative

    Exp.; (k) Taxation (C) Profitability (CMA Data and ratios) (D) Inter-firm comparison

    11. COMMERCIAL VIABILITY - DSCR & REPAYMENT PROGRAMME(a) DSCR (Gross) and (Net) ['Core Test' Ratio], Margin of safety and extent of risk coverage; (b) Break-Even Analysis - For first full year of production and

    the year of maximum capacity utilisation; (c) Cost-Volume-Price (CVP) or Senstivity Analysis - For the year with operating profit nearest to the average operating profit to

    determine 'Span of Resiliency' of the project; (d) Repayment Programme based on the above factors and initial moratorium (start-up) period

    12. FUNDS FLOW ANALYSIS

    Funds Flows to be divided into Long Term Funds Flows and Short Term Funds Flows - Dif. would indicate Long Term Surplus or Deficit / Movements in C/A & OCL leading to

    increase or decrease in WCG; Essential expenditure on F/A, repayment obligations, taxes and dividends are fully provided for; Cash generation would be adequate to meet

    all commitments during the entire repayment period.

    PROJECT APPRAISAL MEMORANDUM

    51

  • 8/22/2019 Project Finance Ava

    52/54

    Project Appraisal Memorandum

    13. PROJECTED BALANCE SHEETS

    (a) Projected B/S covering the entire period of repayment to be scrutinised; (b) CoP, MoF, Profitability estimates, Funds Flow projections and projected B/S are all inter-related

    (c) Projected B/S to be scrutinised analytically with reference to all other related essential data to ensure that all the projections, made realistically and accurately,

    have been woven into well co-ordinated financial statements.

    14. SECURITY & MARGIN AND RATE OF INTEREST

    (a) Complete details of security to be offered for the Term Loan; (b) Detailed Opinion Report on guarantors; (c) Security Margin Coverage Ratio; (d) Whether security offered

    and the margin available are adequate and satisfactory (e) Credit Rating to be done and interest rate (Pricing) to be in line with this rating, unless market forces demand

    otherwise

    15. SPECIAL TERMS & CONDITIONS(a) Right of examination of borrower's books; (b) Restriction with regard to change in Capital Structure; (c) Restriction with regard to (i) Repayment of deposits from F&R

    without the permission of the Bank (ii) Rate of interest payable on such deposits to be lower than the rate of interest charged by the Bank; (d) Restriction with regard to

    transfer of controlling interest in the Co. or drastic change in the Company's management set-up without Bank's prior permission; (e) Other standard T&C.

    16. ECONOMICS OF UNDERWRITING

    In case of composite proposal, (a) Underwriting tie-up; (b) Capital Market trends; (c) Market response to the proposed public issue; (d) Lock-up of funds;

    (e) Comparative Earnings Analysis - Underwriting Commission, Dividends, Capital Gains after Tax; (f) Comparison of total earnings thus arrived at with total earnings thatwould accrue to the Bank if the amount (Value of shares devolving) is lent by way of Term Loans for the same period

    PROJECT APPRAISAL MEMORANDUM

    52

  • 8/22/2019 Project Finance Ava

    53/54

    Project Appraisal Memorandum

    17. CONSENTS FROM GOVERNMENT AND OTHERS

    These will relate, inter alia, to (a) Industrial Licence; (b) Approval for collaboration agreement and technical know-how arrangement; (c) Clearance for import of P&M;

    (d) Approval for making payments for imported P&M on deferred terms and specific clearance for tax exemption on interest; (e) Consent from Controller of Capital Issues

    (f) Various approvals / No Objection Certificates from CG / SG / Local Authorities, etc. (g) Present position

    18. GROUP COMPANIES

    (a) Brief resume of Group Companies indicating the extent to which they are dependent on the parent company / other companies in the Group; (b) Company's liability in

    respect of partly paid shares in subsidiary companies

    19. MANAGERIAL COMPETENCY

    (a) Company's management set-up; (b) Composition of the BoD; (c) CEO in charge of day-to-day affairs of the Company; (d) Quality of the Company's management

    and the level of managerial expertise built-up within the Group; (e) Whether all departments are well served by professionals

    20. OTHERS AND RECOMMENDATIONS

    (a) Verify RBI's List of Defaulters / Wilful Defaulters / Suit Filed Accounts; (b) Verify ECGC's Specific Approval List; (c) Indicate the IRR for the project and comments on

    comparison with the IRRs for similar projects in the same industry; (d) Indicate the importance of the project in terms of national priority and impact thereon; (e) Detail the

    value of the Company / Group's connections to the Bank; (f) Whether, all considered, the proposal is a fair banking risk; (g) Recommendations for sanction of Term Loan.

    PROJECT APPRAISAL MEMORANDUM

  • 8/22/2019 Project Finance Ava

    54/54

    THANK YOU