Project Finance Ava
Transcript of Project Finance Ava
-
8/22/2019 Project Finance Ava
1/54
PROJECT FINANCE
AROLKAR ABHAY VASANTPartner,
M/s A.V.Arolkar & Co., Chartered Accountants
MUMBAI
April 28, 2012 1A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
2/54
INTRODUCTION
With a view to harnessing advancements in
economic development, GoI laid emphasis on
industrialisation through successive Five Year
Plans.
Rapid industrial development needed massive
investment.
Prior to independence, there were no
institutional arrangements for term finance.
April 28, 2012 2A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
3/54
INTRODUCTION
GoI, therefore, established the following
financial institutions:
Indl. Finance Corporation of India (1948) Indl. Credit & Inv. Corpn. of India (1955)
Indl. Development Bank of India (1964) &
Indl. Reconstruction Bank of India (1971)
Similarly, State Governments also established
SFCs in their respective states.April 28, 2012 3A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
4/54
INTRODUCTION
For long, commercial banks confined their
lendings to meet WC requirements only and
they did not play any active role in extending
term finance.
However, with increasing proportion of Term
Deposits in their deposit portfolio and the
paucity of resources in the country, it was felt
that banks could enter the field of term
finance, in a role complementary to that of
Term Lending Institutions.April 28, 2012 4A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
5/54
PROJECT BACKGROUND
The purpose of term assistance is to meet a
part of the capital expenditure of a project.
A project can be defined as A scheme ofthings to be done during a specified period in
future for deriving expected benefits under
certain assumed conditions.
A project may be in the nature of setting up a
new industrial unit, modernisation, expansion,
diversification and promotion of R&D.April 28, 2012 5A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
6/54
PROJECT BACKGROUND
To set up a project, certain capitalexpenditure needs to be incurred in acquiringassets such as L&B, P&M and otherinfrastructural facilities like roads, watersupply, railway sidings, etc., in addition to thePreliminary / Pre-Operative Expenses andmargin on WC Limits.
Where promoters of a project are unable tomeet the entire capital expenditure out oftheir own resources, Term Loans are
sanctioned to supplement the promoterscontribution.April 28, 2012 6A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
7/54
PROJECT BACKGROUND
Promoters of an industrial project can
constitute themselves into any of the
following forms of business organisations to
implement the project : Sole Proprietorship,JHF, Partnership, Co-operative Society & Joint
Stock Company.
Our discussion of the subject would revolve
around Joint Stock Company as promoter.
April 28, 2012 7A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
8/54
PROJECT BACKGROUND
The Promotion Stage is a crucial stage in the
entire life cycle of a project. Promotion in
relation to a project will comprise broadly the
following functions:
I] Identification of a project
II] Feasibility investigation
III] Assembling the proposition
IV] Financing the propositionApril 28, 2012 8A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
9/54
I] Identification of a Project
The first step in the project promotion is the
identification of a project. An industrial
project originates as an idea in a promoter
when he observes the existence of a potentialmarket for a certain product.
The promoter, on the basis of his experience,
background and ability, then considers the
feasibility of manufacturing and marketing the
product at a remunerative price.
April 28, 2012 9A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
10/54
II] Feasibility Investigation
A detailed feasibility study is a costly exercise.It is, therefore, desirable that, before it is
undertaken, marketability of the product to
be manufactured is firmly established.
There are agencies, specialising in market
research, which conduct such market studies.
Promoters may take advantage of theirservices.
A market study aims at assessing the
aggregate demand for a product.April 28, 2012 10A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
11/54
II] Feasibility Investigation
The promoter will now undertake the detailed
feasibility investigation proper, comprising
two feasibility studies:
i) The Technical Feasibility Study
ii) The Economic Feasibility Study
April 28, 2012 11A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
12/54
II] Feasibility Investigation
- Technical Feasibility
Technical Feasibility Study covers thefollowing aspects:
Location of the project
Lay-out of the PlantSize of the Plant
Factory construction
Manufacturing process / TechnologyProcess Design
Product Design
Scale of Operation
Infrastructural facilitiesApril 28, 2012 12A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
13/54
II] Feasibility Investigation
- Economic Feasibility
The prime objective of setting up a project is
to derive a fair return on the investment.
Economic Feasibility Study, therefore,concerns itself with matching of economic
resources with the physical requirements of a
project and determining the viability of
investment therein.
April 28, 2012 13A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
14/54
III] Assembling the Proposition
- CoP & MoF
When a promoter is satisfied about thetechnical feasibility and economic viability ofa project, the next task is to work out the
Cost of the Project and the Means of financingit.
The Cost of the Project would broadly include:
(a) L&B (b) P&M (c) Misc. Fixed Assets (d)Technical Know-how, Engg. & Consultancyfees (e) Preliminary and Pre-operativeexpenses (f) Provision for contingencies (g)
Margin on WC LimitsApril 28, 2012 14A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
15/54
IV] Financing the Proposition
Setting up of a project involves acquisition ofFixed Assets which facilitate the process ofproduction. Fixed Assets have a relatively
longer life and are generally not meant forresale. They are required to be retained overa period of time to exploit their productivepotential.
C/A go through the operating cycle of RM, WIPand FG, which when sold bring in cash. Thiscycle is generally completed in a short period
of less than one year.April 28, 2012 15A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
16/54
IV] Financing the Proposition
Thus, investment in C/A is realised over a
short term, while investment in Fixed Assets is
long term in nature.
It is realised through surplus generated in the
form of Net Profits, Depreciation and other
non-cash write-offs.
As it takes a long time for the Fixed Assets to
pay for themselves, the promoter should raise
suitable long term funds to finance a project.April 28, 2012 16A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
17/54
IV] Financing the Proposition
Keeping the foregoing in view, the promoter
will explore the financial feasibility of the
project by examining
a) The possible long term sources of finance
b) The feasible financial leverage
c) The expected return on the investment
April 28, 2012 17A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
18/54
IV] Financing the Proposition
Equity Preference
Share Capital Retained Earnings
OWNED CAPITAL
Debentures Term Loans, DPGs Public Deposits
BORROWED CAPITAL
LONG TERM SOURCES
April 28, 2012 18A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
19/54
IV] Financing the Proposition
- Long Term Sources
The aggregate amount of finance raised for
financing a project is referred to as Capital,
comprising two components (a) Owned
Capital and (b) Borrowed Capital.
The other sources of long term funds are:
(a) Capital Subsidy applicable to projects
coming up in certain notified backward areas,
and (b) Interest free sales tax loans offered by
State Governments.
April 28, 2012 19A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
20/54
IV] Financing the Proposition
- Financial Leverage
After considering availability of long terms
sources of finance, the promoter will decide
about a suitable financial structure for the
Company.
It will depend upon the financial leverage
envisaged in the combination of sources of
finance under the two categories, viz., Owned
Capital and Borrowed Capital.
Few projects can be financed entirely byApril 28, 2012 20A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
21/54
IV] Financing the Proposition
- Financial Leverage
The divergent interests of debt and equity are
brought into alignment by the concept of Debt
/ Equity gearing which determines the level of
debt that can be supported by a givenquantum of equity.
For this purpose, Debt means Funded Debt
including all term liabilities and equity will
include Share Capital and retained earnings, if
available.
April 28, 2012 21A. V. Arolkar & Co., Chartered Accountants
IV] Financing the Proposition
-
8/22/2019 Project Finance Ava
22/54
IV] Financing the Proposition- Return on Investment
The amount invested in a project can be
recouped through annual cash flows, over a
period of time.
In arriving at a financial plan for the project, a
promoter will examine the attractiveness of
the project, vis--vis alternative sources ofinvestment.
The process which assists the management in
such a task is collectively known as CapitalApril 28, 2012 22A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
23/54
IV] Financing the Proposition
- Return on Investment
The most important and widely used Capital
Investment Evaluation techniques are:
Pay-back MethodNet Terminal Surplus Method
Excess Present Value Method
Internal Rate of Return Method
April 28, 2012 23A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
24/54
IV] Financing the Proposition
- Return on Investment
The object of Pay-back Method is to find out
the period of time required for recovering the
entire amount of investment made in a
project.
The cash flows (Net Profit + Depreciation +
Other non-cash write-offs) are compared with
the outlay on the project to determine the
pay-back period. Years to pay back would be:
Total InvestmentApril 28, 2012 24A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
25/54
IV] Financing the Proposition
- Return on Investment
Net Terminal Surplus Method employs the
concept of compounding which involves
re-investing the simple interest earned each
year along with the principal so that theprincipal grows each year by the amount of
interest earned during the previous year and
interest being calculated on the increasedprincipal also grows.
Future Value = Principal x (1+i)
April 28, 2012 25A. V. Arolkar & Co., Chartered Accountants
] h
-
8/22/2019 Project Finance Ava
26/54
IV] Financing the Proposition
- Return on Investment
Excess Present Value Method is based on thediscounted cash flow technique and uses the conceptof discounting which is just the opposite ofcompounding.
In discounting, we arrive at the Present value of afuture sum to which the original amount (which wewant to find out), invested at a particular compound
rate of interest has grown.PV = Future sum
(1+i)
April 28, 2012 26A. V. Arolkar & Co., Chartered Accountants
IV] Fi i h P i i
-
8/22/2019 Project Finance Ava
27/54
IV] Financing the Proposition
- Return on Investment
Internal Rate of Return Method It is that rate at
which the sum of the discounted cash flows is equal
to the investment outlay. In other words, IRR is the
rate which makes the Present Value (PV) of benefitsequal to the Present Value of costs or reduces the
Net Present Value (NPV) to zero. The object of this
method is to find the rate of return which a project
is likely to earn over its useful life.
IRR =Lower Discount Rate + Diff. Between the two discount rates x NPV at lower discount rateAbs. diff. between the two NPVs.
April 28, 2012 27A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
28/54
Types of Term Assistance
The types of term assistance extended by the
Bank can be broadly classified into:
I] Term Loans (Incl. Forex Loans)
II] Deferred Payment Guarantees
III] Bill Discounting Facilities
IV] Underwriting of Shares / Debentures
April 28, 2012 28A. V. Arolkar & Co., Chartered Accountants
T f T A i
-
8/22/2019 Project Finance Ava
29/54
Types of Term Assistance
-Term Loan
A Term Loan is a loan granted for a fixed term
of not less than one year, intended normally
for financing fixed assets acquired / to be
acquired, carrying interest at a specified rate,and scheduled for repayment in instalments.
Depending on the term for which the said
terms loans are granted, they could be
classified into (a) Short Term Loans (b)
Medium Term Loans and (c) Long Term Loans.
April 28, 2012 29A. V. Arolkar & Co., Chartered Accountants
T f T A i t
-
8/22/2019 Project Finance Ava
30/54
Types of Term Assistance
-DPG
Deferred Payment Guarantee (DPG) is a contract topay to the supplier the price of machinery, suppliedby him on deferred terms, in agreed instalments withstipulated interest on the respective due dates in
case of default in payment thereof by the buyer.
A DPG is, in many respects, a substitute for a TermLoan and, as far as the buyer of P&M is concerned, it
serves the same purposes as a Term Loan. Standards of appraisal are the same as TL.
April 28, 2012 30A. V. Arolkar & Co., Chartered Accountants
T f T A i t
-
8/22/2019 Project Finance Ava
31/54
Types of Term Assistance
- Bills Discounting
Under a contract for sale of machinery on
deferred payment basis, the balance
remaining to be paid after the initial down
payment represents the deferred receivablesof the seller.
Thus, the funds of the seller get blocked for
unduly long periods and the seller requires
finance against such deferred receivables to
replenish his Working Capital.
April 28, 2012 31A. V. Arolkar & Co., Chartered Accountants
T f T A i t
-
8/22/2019 Project Finance Ava
32/54
Types of Term Assistance
- Bills Discounting
To facilitate availment of finance against the
deferred receivables, the seller usually draws
a series of usance bills with graded maturities
to coincide with the due dates of payment ofthe relative instalments (including applicable
interest).
The usance bills drawn by the seller will be
accepted by the buyer before they are
discounted by the sellers banker.
April 28, 2012 32A. V. Arolkar & Co., Chartered Accountants
T f T A i t
-
8/22/2019 Project Finance Ava
33/54
Types of Term Assistance
- Underwriting of Shares
The necessity for underwriting arrangementarises only in the case of a Public LimitedCompany resorting to raise through the capital
issue market, a part of the Share Capital forpart-financing a project.
Underwriting is a contract whereby a person
agrees, in consideration, to take up aspecified number of shares or debentures oramount of debenture stock to be offered tothe public, in the event of the public not
subscribing for them.April 28, 2012 33A. V. Arolkar & Co., Chartered Accountants
T f T A i t
-
8/22/2019 Project Finance Ava
34/54
Types of Term Assistance
- Underwriting of Shares
Underwriting as a business will come under the scope of
Investment Banking as distinct from Commercial
Banking.
In view of this, therefore, a high degree of selectivityshould continue to be exercised in undertaking
underwriting business.
However, the business stemmed not so much from the
point of view of earnings on the investment as from the
consideration that no viable project enjoying national
priority should suffer for want of underwriting support.
April 28, 2012 34A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
35/54
Project Appraisal
The purpose of Project Appraisal is to ascertainwhether the project will be sound technically,economically, financially and managerially andultimately viable as a commercial proposition.
The appraisal of a project will involve theexamination of:
a) Technical Feasibility : To determine the suitability
of the technology selected and the adequacy of thetechnical investigation, and design.
April 28, 2012 35A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
36/54
Project Appraisal
b) Economic Feasibility : To determine theconduciveness of economic parameters to setting upthe project and their impact on the scale ofoperations.
c) Financial Feasibility : To determine the accuracyof cost estimates, suitability of the envisaged patternof financing and general soundness of the capital
structure. d) Commercial Viability : To ascertain the extent of
profitability of the project and its sufficiency inrelation to the repayment obligations pertaining to
term finance.April 28, 2012 36A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
37/54
Project Appraisal
e) Managerial Competency : To ascertain thatcompetent men are behind the project toensure its successful implementation and
efficient management after commencement ofcommercial production.
A project should also be examined, wherever
appropriate, from the point of view of itsvalue to the national economy in terms ofsocio-economic benefits like generation ofemployment opportunities, forex earnings, the
quantum of import substitution, etc.April 28, 2012 37A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
38/54
Project Appraisal
The first step in Project Appraisal is to find out
whether the project is prima facie acceptable byexamining salient features such as:
The background and experience of the applicants,particularly in the proposed line of activity
The potential demand for the product
The availability of the required inputs, utilities andother infrastructural facilities
Whether the project is in keeping with the priorities,
if any, laid down by the Government.April 28, 2012 38A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
39/54
Project Appraisal
The original application may not contain all the basicdata / information. In such cases, it may benecessary to provide all the necessary data /information with a view to give an overall idea aboutthe general feasibility of the project at the time ofinterview by the bankers.
After satisfying itself about the prima facie
acceptability of the project, the Bankers will call foran prescribed Application, containing the followingessential data / information, such as:
April 28, 2012 39A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
40/54
Project Appraisal
a) Particulars of the project along with a copy
of the Project Report furnishing details of the
technology, manufacturing process,
availability of construction / productionfacilities, etc.
b) Estimates of cost of the project detailing
the itemised assets acquired / to be acquired,
inclusive of Preliminary / Pre-operative
Expenses and WC margin requirements.April 28, 2012 40A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
41/54
Project Appraisal
c) Details of the proposed means of financingindicating the extent ofpromoters contribution, thequantum of Share Capital to be raised by publicissue, the composition of the borrowed capitalportion with particulars of Term Loans, DPGs, ForeignCurrency Loans, etc.
d) WC requirements at the peak level (i.e., when the
level of Gross Current Assets is at the peak) duringthe first year of operations after the commencementof commercial production and the bankingarrangements to be made for financing the WC
requirements.April 28, 2012 41A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
42/54
Project Appraisal
e) Project Implementation Schedule.
f) Organisational set up along with a list ofBoard of Directors and indicating thequalifications, experience and competence of(i) The key personnel to be in charge ofimplementation of the project during the
construction period and (ii) The executives tobe in charge of the functional areas ofpurchase, production, marketing and financeafter commencement of commercial
production.April 28, 2012 42A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
43/54
Project Appraisal
g) Demand projection based on the overall
market prospects together with a copy of the
market survey report.
h) Estimates of sales, CoP and profitability.
i) Projected P&L Account and B/S for the
operating years during the currency of theBanks term assistance.
j) Proposed amortisation schedule, i.e.,
repayment programme.April 28, 2012 43A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
44/54
Project Appraisal
k) Projected Funds Flow Statement covering
both the construction period and the
subsequent operating years during the
currency of the Term Loan.
l) Details of the nature and value of the
securities offered.
m) Consents from the Government / other
authorities and any other relevant
information.April 28, 2012 44A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
45/54
Project Appraisal
In respect of existing concerns, in addition to
this information, particulars regarding the
history of the concern, its past performance,
present financial position, etc., should also becalled for.
The Application completed in all respects
and duly signed by the authorised signatories
of the Company will form the basis for the
detailed appraisal of the project.April 28, 2012 45A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
46/54
Project Appraisal
An inspection of the project site (or factory in thecase of existing units) will be done by the bankers.
Each project has to be examined in proper
perspective having due regard to its nature, size andscope.
Although the basic techniques employed forappraising the viability of various projects are moreor less the same, there could be no standard oruniform approach for appraising all projects.
April 28, 2012 46A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
47/54
Project Appraisal
The ultimate objective of the appraisal
exercise is to ascertain the viability of a
project with a view to ensuring the repayment
of the borrowers obligations under the Banksterm assistance.
Therefore, it is not so much the quantum of
the proposed term assistance as the prospects
of its repayment that weighs with the bankers
while appraising a project.April 28, 2012 47A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
48/54
Project Appraisal
In project appraisal, nothing is assumed or taken for
granted, so be truthful and give facts
All the data / information would be checked and,
wherever possible, counter-checked through inter-
firm and inter-industry comparisons.
It should be borne in mind that bankers believe
Healthy scepticism is a cardinal virtue in projectappraisal.
April 28, 2012 48A. V. Arolkar & Co., Chartered Accountants
-
8/22/2019 Project Finance Ava
49/54
Project Appraisal Memorandum
1. PROPOSAL
Nature of proposal;
Purpose : New project, expansion, modernisation, diversification or for any other approved purpose
2. BRIEF HISTORY
Brief account of corporate history; MA & AA; Regd. address; Present organisational set up with BoD; Qualifications, experience and background;
Line of activities, Financial position, etc., of Associate Concerns; Overall structure of inter-corporate investments
3. PAST PERFORMANCESummary of Company's past performance in terms of licensed / installed / operating capacities, sales, operating profit and Net Profit for
the past 3 years; Capacity utilisation; Sales & profitability; Dividend policy; Capital expenditure programmes implemented by the Company
during the past 3 years and how they were financed; Company's management-labour relations
4. PRESENT FINANCIAL POSITION
Company's audited Balance Sheets & P/L Accounts for the past 3 years with analysis; Company's Capital structure; Summarise conclusions
of financial analysis; Method of depreciation; Revaluation of F/A; Record of major defaults; Position of Company's tax assessment; ContingentLiabilities; Pending suits; Qualifications / Adverse remarks by auditors
PROJECT APPRAISAL MEMORANDUM
49
-
8/22/2019 Project Finance Ava
50/54
Project Appraisal Memorandum
5. PROJECT
(a) Description of the project (Modernisation, expansion, diversification or a new venture) ; Standing, experience and reliability of
outside agency who prepared the Project Report; (b) Collaboration Arrangement (Technical or Financial); (c) Technical Feasibility covering
suitability of technology, size & location of plant, technical arrangements & mfg. process (d) Financial Feasibility covering Cost of Project & Means of Finance
6. PROJECT IMPLEMENTATION SCHEDULE
With reference to Bar Chart or PERT / CPM Chart and in the light of actual implementation; Main stages in the project implementation and whether the time
schedule for construction, erection / installation of P&M, start-up / trial run, commencement of commercial production is reasonable & acceptable
7. PRODUCTION FACTORS
(a) Mfg. Process - Basis of selection & justification; (b) Raw Materials - Imported / Indigenous, Names of main suppliers, Pattern of unit prices & fluctuation;
(c) Utilities & Essential Services - Requirements of power, fuel, water, transport, railway siding with comments on adequacy of arrangements, treatment
and disposal of effluents; (d) Operating Organisation - Experience and expertise of Managerial / Technical personnel, other staff required
8. WORKING CAPITAL REQUIREMENTS
Assessment of total WC requirements at the peak level (GCA) during the first year of operations after commencement of commercial production;
sharing of business among member banks; financing of additional WC requirments in case of existing companies
PROJECT APPRAISAL MEMORANDUM
50
-
8/22/2019 Project Finance Ava
51/54
Project Appraisal Memorandum
9. MARKETING
(a) Sales prospects and underlying assumptions, demand projections on the basis of past consumption, total supply position, general condition of industry
(b) Selling Price - Trend to see whether stable, Govt. price controls, quota systems, etc.; (c) Propsects for exports - Export obligations;
(d) Marketing Organisation - Adequacy, Distributors / Selling Agents, Terms of arrangement, remuneration, competence, Asso. Concerns - Siphoning of profits
10. COMMERCIAL VIABILITY - CoP & PROFITABILITY
(A) Sales Volume / Value - (a) Volume; (b) No. of working days; (c) Capacity utilisation; (d) Value (B) CoP - (a) Matls. consumed; (b) Utilities (PW&F); (c) Wages & Salaries
(d) Factory Overheads; (e) Depreciation - SLM / WDV- Consistency; (f) Selling Exp.; (g) Financial Exp.; (h) Admn. Exp.; (i) Royalty & Know-how; (j) Preliminary / Pre-operative
Exp.; (k) Taxation (C) Profitability (CMA Data and ratios) (D) Inter-firm comparison
11. COMMERCIAL VIABILITY - DSCR & REPAYMENT PROGRAMME(a) DSCR (Gross) and (Net) ['Core Test' Ratio], Margin of safety and extent of risk coverage; (b) Break-Even Analysis - For first full year of production and
the year of maximum capacity utilisation; (c) Cost-Volume-Price (CVP) or Senstivity Analysis - For the year with operating profit nearest to the average operating profit to
determine 'Span of Resiliency' of the project; (d) Repayment Programme based on the above factors and initial moratorium (start-up) period
12. FUNDS FLOW ANALYSIS
Funds Flows to be divided into Long Term Funds Flows and Short Term Funds Flows - Dif. would indicate Long Term Surplus or Deficit / Movements in C/A & OCL leading to
increase or decrease in WCG; Essential expenditure on F/A, repayment obligations, taxes and dividends are fully provided for; Cash generation would be adequate to meet
all commitments during the entire repayment period.
PROJECT APPRAISAL MEMORANDUM
51
-
8/22/2019 Project Finance Ava
52/54
Project Appraisal Memorandum
13. PROJECTED BALANCE SHEETS
(a) Projected B/S covering the entire period of repayment to be scrutinised; (b) CoP, MoF, Profitability estimates, Funds Flow projections and projected B/S are all inter-related
(c) Projected B/S to be scrutinised analytically with reference to all other related essential data to ensure that all the projections, made realistically and accurately,
have been woven into well co-ordinated financial statements.
14. SECURITY & MARGIN AND RATE OF INTEREST
(a) Complete details of security to be offered for the Term Loan; (b) Detailed Opinion Report on guarantors; (c) Security Margin Coverage Ratio; (d) Whether security offered
and the margin available are adequate and satisfactory (e) Credit Rating to be done and interest rate (Pricing) to be in line with this rating, unless market forces demand
otherwise
15. SPECIAL TERMS & CONDITIONS(a) Right of examination of borrower's books; (b) Restriction with regard to change in Capital Structure; (c) Restriction with regard to (i) Repayment of deposits from F&R
without the permission of the Bank (ii) Rate of interest payable on such deposits to be lower than the rate of interest charged by the Bank; (d) Restriction with regard to
transfer of controlling interest in the Co. or drastic change in the Company's management set-up without Bank's prior permission; (e) Other standard T&C.
16. ECONOMICS OF UNDERWRITING
In case of composite proposal, (a) Underwriting tie-up; (b) Capital Market trends; (c) Market response to the proposed public issue; (d) Lock-up of funds;
(e) Comparative Earnings Analysis - Underwriting Commission, Dividends, Capital Gains after Tax; (f) Comparison of total earnings thus arrived at with total earnings thatwould accrue to the Bank if the amount (Value of shares devolving) is lent by way of Term Loans for the same period
PROJECT APPRAISAL MEMORANDUM
52
-
8/22/2019 Project Finance Ava
53/54
Project Appraisal Memorandum
17. CONSENTS FROM GOVERNMENT AND OTHERS
These will relate, inter alia, to (a) Industrial Licence; (b) Approval for collaboration agreement and technical know-how arrangement; (c) Clearance for import of P&M;
(d) Approval for making payments for imported P&M on deferred terms and specific clearance for tax exemption on interest; (e) Consent from Controller of Capital Issues
(f) Various approvals / No Objection Certificates from CG / SG / Local Authorities, etc. (g) Present position
18. GROUP COMPANIES
(a) Brief resume of Group Companies indicating the extent to which they are dependent on the parent company / other companies in the Group; (b) Company's liability in
respect of partly paid shares in subsidiary companies
19. MANAGERIAL COMPETENCY
(a) Company's management set-up; (b) Composition of the BoD; (c) CEO in charge of day-to-day affairs of the Company; (d) Quality of the Company's management
and the level of managerial expertise built-up within the Group; (e) Whether all departments are well served by professionals
20. OTHERS AND RECOMMENDATIONS
(a) Verify RBI's List of Defaulters / Wilful Defaulters / Suit Filed Accounts; (b) Verify ECGC's Specific Approval List; (c) Indicate the IRR for the project and comments on
comparison with the IRRs for similar projects in the same industry; (d) Indicate the importance of the project in terms of national priority and impact thereon; (e) Detail the
value of the Company / Group's connections to the Bank; (f) Whether, all considered, the proposal is a fair banking risk; (g) Recommendations for sanction of Term Loan.
PROJECT APPRAISAL MEMORANDUM
-
8/22/2019 Project Finance Ava
54/54
THANK YOU