Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

16
Project Execution Plan By UJAAS ENERGY LIMITED, Indore. 50 MW Solar Project Three Spring

Transcript of Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Page 1: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Project Execution Plan

By

UJAAS ENERGY LIMITED, Indore.

50 MW Solar Project

Three Spring

Page 2: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Stages- PV Plant Development(India)

Page 3: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Execution Plan

50 MW, Solar Plant

Page 4: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Initial Steps......

• Signing of Term Sheet

• Preparation of Contract documents

• Verification of Contract documents by both

• Signing of Contract

Expected time line for above .............

Page 5: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Financial Closure......

• Opening of LC

• Organizing fund by Ujaas within 6 / 8 weeks from

receipt of LC

• Fund disbursement by "Institution"

• Any disbursement to subcontractor will be after

disbursement by institution.

Expected date of opening LC: ........

Page 6: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Project Execution....

Nominate Project Manager

Page 7: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Project Manager' job

• Co-ordinate for WORK PERMIT

• Preparation of Manuals as per Laws for – Work procedure

– Health and Safety

– Environment

– Any other as needed

• Getting Manuals approved by Authorities

cont'd.......

Page 8: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Project Manager' job

• Kick start of project

• System Audit

• Co-ordination with all, time to time

• Weekly / monthly progress meetings

• Handing over on commissioning

• Post commissioning O&M for 3 months.

Page 9: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Project Execution....

• Nominate Project Manager

• Formation of dedicated team

Page 10: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Jobs for dedicated team - HQ

• Sub-group for Technical

– Contract Administration

– Detailed Engineering

– Documentations

– Co-ordination for client's engineers

– Assistance in Commissioning

Cont'd.......

Page 11: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Jobs for dedicated team - HQ

• Sub - group for Commercials

– Contract Administration

– Procurements

– Logistics

– Documentations

– Support to site group

Page 12: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Project Execution....

• Nominate Project Manager

• Formation of dedicated team in

HQ

• Formation of team at SITE

Page 13: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

• Civil group

• Mechanical group

• Electrical & Electronic group

• Quality Control group

• HR & Safety group

• General Administration group

Team at SITE

Page 14: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Project Executions....

• Nominate Project Manager

• Formation of dedicated team in

HQ

• Formation of team at SITE

• Operation & Maintenance

Page 15: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.

Operation & Maintenance

• Module Cleaning

• DC & AC Maintenance

• Monthly, Quarterly, Half yearly & Yearly checks

• Preventive, Corrective & Condition Based

Maintenance

Page 16: Project Execution Plan By UJAAS ENERGY LIMITED, Indore.