Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was...

98
Project Earned Value Analysis

Transcript of Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was...

Page 1: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Project Earned Value Analysis

Page 2: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000.

He created Transport for London to oversee the city’s road and transport services that were previously managed separately. Mission: to upgrade London’s transportation infrastructure with a toll system project

Traffic congestion is a major problem for central London. Transport for London developed a plan to install a system that would identify and charge car owners that enter defined congestion zones

Technological risks were identified, and the project was divided into 5 smaller components (to be managed separately, as opposed to purchasing one large system)

Project team worked together in one location on the five components to the system

The project was successfully implemented by February 2003. Transport for London reports that traffic in the congestion zone has decreased by 20%, with a 5% increase during travel times

Page 3: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Project Monitoring Defined Collecting, recording, and

reporting information concerning any and all aspects of project performance that the project manager or others wish to know

Page 4: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Monitoring Has Several Uses Project Monitoring has secondary uses

Project auditing “Lessons learned” Reporting to client and senior management

But the primary use is project control Ensuring that decision-makers have timely

information enabling effective control over the project

Page 5: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

The Planning-Monitoring-Controlling Cycle Effective monitoring and control begins

with good project planning What are the critical areas? How and when can progress be measured? Who gathers and reports info, to whom?

The plan-monitor-control cycle continues through the entire project

Page 6: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Project Monitoring System for

Control Information System Structure

What data are collected? Current status of project (schedule and cost)

Remaining cost to compete project

Date that project will be complete

Potential problems to be addressed now

Out-of-control activities requiring intervention

Cost and/or schedule overruns and the reasons for them

Forecast of overruns at time of project completion

Page 7: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Project Monitoring System… (cont’d)

Information System Structure (cont’d) Collecting data and analysis

Who will collect project data? How will data be collected? When will the data be collected? Who will compile and analyze the data?

Reports and reporting Who will receive the reports? How will the reports be transmitted? When will the reports be distributed?

Page 8: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Project Progress Report Format Progress since last report Current status of project

Schedule Cost Scope

Cumulative trends Problems and issues since last report

Actions and resolution of earlier problems New variances and problems identified

Corrective actions planned

Page 9: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Figure: Project Control Information Flow

Page 10: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

The Project Control ProcessControl

The process of comparing actual performance against plan to identify deviations, evaluate courses of action, and take appropriate corrective action.

Project Control Steps1. Setting a baseline plan.2. Measuring progress and performance.3. Comparing plan against actual.4. Taking actions

Page 11: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Monitoring Time Performance Tools used to catch negative

variances from plan and communicate project schedule status: Tracking and baseline Gantt charts

Show expected, actual, and trend data for event duration performance.

Control charts Plot the difference in scheduled time on the

critical path with the actual point on the critical path.

Page 12: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Baseline and Tracking Gantt Charts

Page 13: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Designing the Monitoring System 1. Start with the key factors to be

controlled Pareto analysis: a relatively few

activities determine most of the project’s success

Use the project plan to identify items to be monitored

Although other areas might be added also

Page 14: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Designing the Monitoring System (cont’d) 2. Develop measurement systems

Measure results, not activity; outputs, rather than inputs

Extract performance, time and cost goals from project plans

Avoid tendency to focus on that which is easily measurable

Page 15: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Designing the Monitoring System (cont’d) 3. Collecting Data: Most data falls into

one of five categories, as follows (with examples) Frequency counts: tally of occurrences . . . Raw numbers: dates, dollars, percents,

specs . . . Subjective ratings: numerical ranking, red-

yellow-green assessments . . . Indicators: surrogate measures of merit . . . Verbal measurement: oral or written

characterizations . . .

Page 16: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Designing the Monitoring System (cont’d) 4. Reporting on Data Collected: To turn

data into information, it must be contextualized: Reporting must be timely Data must be analyzed

Trends: Getting better or worse? Comparables: Performance compared to specs,

past performance, standard hours, etc. Statistical analysis Causation and correction

Page 17: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Some Behavioral Aspects of Monitoring Systems Effective monitoring reduces

surprises, and this can increase trust, morale

Some reporting bias is inevitable, but dishonesty is unacceptable

“Shooting the messenger” today just creates concealment tomorrow

Page 18: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Earned Value Analysis (EVA) Needed: An objective way to

measure overall project performance

The problem comparing actual expenditures to baseline plan is that it ignores the amount of work actually completed

Thus, Earned Value Analysis A sort of cost accounting for projects

Page 19: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EARNED VALUE MANAGEMENT

Let us take the great pyramid of Gizeh. Here is a sketch from theProject manager’s site log

Final Shape As on date

Stones in Place

Still to Finish

The Plan calls for 1,000,000 stones blocks in allCurrent Status as shown in sketch: 900,000 stone blocks in placeCan the Project Manager report the status as 90% complete?Penalty of wrong reporting: His ‘head’ (neatly chopped off)

Page 20: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EARNED VALUE MANAGEMENT

Another way to determine status: Since we have spent 35% of our budget, we have completed 35%. Advantages and Disadvantages of this method?

Still another way Project Manager feels it is ’40% complete’, guesstimate

Overall, these methods leave much to be desired

Page 21: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EARNED VALUE MANAGEMENT

Concept of US Department of Defense

Value is earned as project activities get completedTherefore, Earned value is a measure of progress

Advantages

Uniform unit of measure (Rs and Labor are not so) Consistent analysis method Basis for judging Cost performance

Page 22: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

WHY EARNED VALUE MANAGEMENT?

Page 23: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

WHY EARNED VALUE MANAGEMENT?

Looks Fine, but is Progress OKAY ?

Page 24: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

PROJECT BUDGET

Cost Accounts are created where WBS and OBS meet

Page 25: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

PROJECT BUDGET

Page 26: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Integration of WBS and OBS

FIGURE 4.5

Page 27: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Disparity Among Monitoring Systems Time-Phase Baseline Plan

Corrects the failure of most monitoring systems to connect a project’s actual performance to its schedule and forecast budget.

Systems that measure only cost variances do not identify resource and project cost problems associated with falling behind or progressing ahead of schedule.

Earned Value Cost/Schedule System An integrated project management system

based on the earned value concept that uses a time-phased budget baseline to compare actual and planned schedule and costs.

Page 28: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Glossary of Terms EV

The percent complete times its original budget. The percent of the original budget that has been earned by actual work completed. The older acronym for this value was BCWP—budgeted cost of the work performed.

PV (Planned Value) The time-phased baseline of the value of the work

scheduled. An approved cost estimate of the resources scheduled in a time-phased cumulative baseline (BCWS—budgeted cost of the work scheduled).

AC The actual cost of the work completed. The sum of the

costs incurred in accomplishing work. (ACWP—actual cost of the work performed).

Page 29: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Glossary of Terms CV

Cost variance is the difference between the earned value and the actual costs for the work completed to date where CV=EV-AC.

SV Schedule variance (SV) is the difference between the earned value and the baseline to date where SV=EV-PV.

BAC Budgeted cost at completion. The total budgeted cost of the baseline or project cost accounts.

EAC Estimated costs at completion. Includes costs to-date plus revised estimated costs for the work remaining.

Page 30: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Glossary of Terms ETC

Estimate cost to complete. VAC

Cost variance at completion (BAC-EACe), where EACe is derived by estimators in the field.

Or, alternatively, cost variance at completion (BAC-EACf), where EACf is derived from a formula using actual and earned value costs.

VAC indicates expected actual over-or underrun cost at completion.

Page 31: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Developing an Integrated Cost/Schedule System1. Define the work using a WBS.

a. Scopeb. Work packagesc. Deliverablesd. Organization unitse. Resourcesf. Budgets

2. Develop work and resource schedules.a. Schedule resource to activitiesb. Time-phase work packages into a network

3. Develop a time-phased budget using work packages included in an activity.

Page 32: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Developing an Integrated Cost/Schedule System1. Define the work using

a WBS.a. Scope

b. Work packages

c. Deliverables

d. Organization units

e. Resources

f. Budgets

2. Develop work and resource schedules.

a. Schedule resources to activities

b. Time-phase work packages into a network

3. Develop a time-phased budget using work packages included in an activity. Accumulate budgets (PV).

4. At the work package level, collect the actual costs for the work performed (AC).

5. Multiply percent complete times original budget (EV).`

6. Compute the schedule variance (EV-PV) and the cost variance (EV-AC).

Page 33: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Project Management System Overview

Page 34: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Development of Project Baselines Purposes of a Baseline (PV)

An anchor point for measuring performance A planned cost and expected schedule against

which actual cost and schedule are measured. A basis for cash flows and awarding progress

payments. A summation of time-phased budgets (cost

accounts as summed work packages) along a project timeline.

What Costs Are Included in Baselines? Labour Equipment Materials Project direct overhead costs (DOC)

Page 35: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Baseline Data Relationships

Page 36: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Development of Project Baselines (cont’d) Rules for Placing Costs in Baselines

Costs are placed exactly as they are expected to be “earned” in order to track them to their point of origin.

Per Cent Complete Rule Costs are periodically assigned to a

baseline as units of work are completed over the duration of a work package.

Page 37: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Additional Earned Value Rules Rules applied to short-duration

activities and/or small-cost activities Percentage complete rule

0/100 percent rule Assumes 100 % of budget credit is earned at once

and only when the work is completed – useful for very small duration work packages or for vendor deliveries.

50/50 rule Allows for 50% of the value of the work package

budget to be earned when it is started and 50% to be earned when the package is completed.

Page 38: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Methods of Variance Analysis Comparing Earned Value

With the expected schedule value. With the actual costs.

Assessing Status of a Project Required data elements

Data Budgeted cost of the work scheduled (PV) Budgeted cost of the work completed (EV) Actual cost of the work completed (AC)

Calculate schedule and cost variances A positive variance indicates a desirable

condition, while a negative variance suggests problems or changes that have taken place.

Page 39: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Methods of Variance Analysis

Cost Variance (CV) Indicates if the work accomplished

using labour and materials costs more or less than what was planned at any point of time in the project.

Schedule Variance (SV) Presents an overall assessment in

dollar terms of the progress of all work packages in the project scheduled to date.

Page 40: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Cost/Schedule Graph

Page 41: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Earned Value Review Exercise

Page 42: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

FIGURE: Network Diagram for the Packaging Machine Project

Page 43: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

FIGURE: Work Breakdown Structure for the Packaging Machine Project

Page 44: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

FIGURE: Budgeted Cost by Period for the Packaging Machine Project

Page 45: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

FIGURE: Cumulative Budgeted Cost Curve for the Packaging Machine Project

Page 46: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

FIGURE: Actual Cost by Period for the Packaging Machine Project

Page 47: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

FIGURE: Cumulative Budgeted and Actual Cost for the Packaging Machine Project

Page 48: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

FIGURE: Cumulative Percent Complete by Period for the Packaging Machine Project

Page 49: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

FIGURE: Cumulative Earned Value by Period for the Packaging Machine Project

Page 50: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

FIGURE: Cumulative Budgeted, Actual, and Earned Value for the Packaging Machine Project

Page 51: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

FIGURE: Packaging Machine Project Status as of Week 8

Page 52: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Developing A Status Report:Another Hypothetical Example

Assumptions Each cost account has only one work

package, and each cost account will be represented as an activity on the network.

The project network early start times will serve as the basis for assigning the baseline values.

Baseline value will be assigned linearly, unless stated differently.

From the moment work on an activity begins, some actual costs will be incurred each period until the activity is completed.

Page 53: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Work Breakdown Structure and Cost Accounts

Page 54: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Digital Camera Prototype Project Baseline Gantt Chart

Page 55: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Digital Camera Prototype Project Baseline

Page 56: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Digital Camera Prototype Status Reports: Periods 1–3

Page 57: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Digital Camera Prototype Status Reports: Periods 4–6

Page 58: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Digital Camera Prototype Status Reports: Period 7

Page 59: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Digital Camera Prototype Summary Graph (000)

Page 60: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Digital Camera Project Tracking Gantt Chart

Showing Status—Through Period 7

Page 61: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Digital Camera Project Rollup at End Period 7 (000)

Page 62: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Indexes to Monitor Progress Performance Indexes

Cost Performance Index (CPI) Measures the cost efficiency of work

accomplished to date. CPI = EV/AC

Scheduling Performance Index (SPI) Measures scheduling efficiency SPI = EV/PV

Percent Complete Indexes Indicates how much of the work accomplished

represents of the total budgeted (BAC) and actual (AC) dollars to date.

PCIB = EV/BAC PCIC = AC/EAC

Page 63: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Interpretation of Indexes

Page 64: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Indexes Periods 1–7

Page 65: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Forecasting Final Project Cost Methods used to revise estimates of

future project costs: EACe

Allows experts in the field to change original baseline durations and costs because new information tells them the original estimates are not accurate.

EACf Uses actual costs-to-date plus an efficiency

index to project final costs in large projects where the original budget is unreliable.

Page 66: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Forecasting Model: EACf

The equation for this forecasting model:

Page 67: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Example Assume a work package expected to be

finished today, at cost of $1500. But you’re only 2/3 complete, and you’ve spent $1350.

CPI = EV/AC = $1000/$1350 = .74

SPI = EV/PV = $1000/$1500 = .67

CSI = CPI*SPI = .74 X .67 = .49

Page 68: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Example (cont’d) Then you can calculate the estimated

cost to complete the project (ETC) and the estimated cost at completion (EAC)

ETC = (BAC – EV)/((EV/AC) = CPI)

= $(1500 – 1000)/.74

= $676

EAC = AC + ETC

= $1350 + $676

= $2026

Page 69: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Project Control

Page 70: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Project Control Defined CONTROL: The act of reducing the

difference between plan and reality The last element in the plan-

implement-monitor-control cycle Uses the information from the

monitoring process to get and keep a project on track

Page 71: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Control Can Be Complicated Performance, cost, and schedule

issues all have a human element Symptoms are obvious, but root

causes never are “Messes” vs. “problems”

Hard to separate random events from systemic difficulties

Page 72: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Two Fundamental Purposes of Project Control

Regulate project results through alteration of activities

Efficiently use and protect organizational assets

Page 73: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Purpose of Control To make the actual meet the plan

The Process 1. Identify key performance areas 2. Set standards 3. Measure performance 4. Compare 5. Take corrective action

Page 74: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Project Schedule Control Chart

Page 75: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Indices Help Visualize Performance Projects on cost, on schedule will have

indices = 1.0 Indices below 1.0 are unfavorable

Cost Performance Index (CPI) Schedule Performance Index (SPI) Cost-Schedule Index (CSI), also simply called

the Critical Ratio (basically equal to (actual progress/scheduled progress) x (budgeted cost/actual cost)) = CPI X SPI

CSI is plotted as a control variable as in a quality control chart, PM will ignore this ratio in some ranges, typically 0.9-1.1

Page 76: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Critical Ratio Control Limits

Page 77: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Effective Control Systems Must be Balanced Balance means

Measuring both tangibles and intangibles

Looking at both long-term and short Keeping flexibility in the system Addressing human factors Focusing on correction, not punishment Optimizing control, not maximizing it

Page 78: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

A Question of Balance Too little control? Too much control?

$

Amount of Control

CControl

CMistakes

Page 79: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Controlling Changes and Scope Creep Changes can drive higher costs

and stretched out schedules So controlling them is an essential

project management task A formal change system is a must for

project control

Page 80: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

Five Principles of a Formal Change Program All contracts specify formal change

process All changes require formal change

order All change orders approved in writing

by client and project organization Project manager is always consulted The approved change order becomes

part of the master plan

Page 81: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EARNED VALUE MANAGEMENT EXERCISE 2

A company has a fixed cost contract for the supply, installationTesting and commissioning of 200 computers at a cost of 600 Lakhs. Company estimates it can put up 10 computers per day.

A Review on Day 16 reveals that 380 Lakhs have been spent And 120 computers installed

Page 82: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EARNED VALUE MANAGEMENT EXERCISE 2

ANSWERS

Cost per computer = 600/200 = 3LPV= 16 days * 10 * (600/200) = 480 LEV= 120 * 3 ` = 360 LAC = 380 LCV= EV – AC = 360-380 = -20LCPI 360/380 = 0.947SV EV – PV = 360 – 480 = -120LSPI 360/480 = 0.75

EAC AC + (BAC-EV) / CPI380 + (600-360)/0.947 = 633L

TAC 20/0.75 = 26.67 d

Page 83: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EVA Game

Bathroom (5 hours) (1.2 liters)

Bedroom 1

(10 hours)

(1.8 liters)

Bedroom 2

(10 hours)

(1.8 liters)

Kitchen

(10 hours) (1.6 liters)

Living-room

(15 hours)

(3.6 liters)

The sequence isBedroom1, Bathroom, Living, Kitchen and Bedroom 2.

Page 84: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EVA Game

Bathroom (5 hours) (1.2 liters)

Bedroom 1

(10 hours)

(1.8 liters)

Bedroom 2

(10 hours)

(1.8 liters)

Kitchen

(10 hours) (1.6 liters)

Living-room

(15 hours)

(3.6 liters)

The sequence isBedroom1, Bathroom, Living, Kitchen and Bedroom 2.

You have to paint a house in 5 days of 10 hours each with 10l of paint

Page 85: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EVA Game

DAY – 1For people born in the first six months of the year, the day started badly. You relative’s dog overturned the paint while you were preparing your materials. Luckily, you were able to tighten the tin before too much had been spilt. However, you spent half an hour cleaning up the mess.For people born in the second six months of the year, painting the ceiling proved much more difficult than anticipated. You had to use more paint than you had planned.

AC = 2.0 litres (dog victims)AC = 2.2 litres (ceiling difficulties)

Project progress = + 15 percent

Page 86: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

DAY 1 PROJECTIONS

DAY – 1

EV = 1.5LPV = 1.8L

AC = 2.0 litres (dog victims)AC = 2.2 litres (ceiling difficulties)

CPI= EV/AC = 1.5/2.0 = 0.75 (Dog Case)SPI=EV/PV = 1.5/1.8 = 0.83

Project progress = + 15 percent

Page 87: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

DAY 1 PROJECTIONS: COSTDAY – 1

Cost Projections (Optimistic)

EV = 1.5L (Project progress = + 15 percent)PV = 1.8LAC = 2.0 litres (dog victims)AC = 2.2 litres (ceiling difficulties)BAC = Budget at Completion = 10 L

Actual Cost +

(BAC- EV)

2 (dog case) +

(10 – 1.5) = 10.5 Liters

Page 88: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

DAY 1 PROJECTIONS: COSTDAY – 1

Cost Projections (Likely)

EV = 1.5L (Project progress = + 15 percent)PV = 1.8LAC = 2.0 litres (dog victims)AC = 2.2 litres (ceiling difficulties)BAC = Budget at Completion = 10 LCPI = 0.75

Actual Cost +

(BAC –EV) / CPI

2 (dog case) +

(10 – 1.5)/0.75

= 13.3 Liters

Page 89: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

DAY 1 PROJECTIONS: COST

DAY – 1

Cost Projections (Pessimist)

EV = 1.5L (Project progress = + 15 percent)PV = 1.8LAC = 2.0 litres (dog victims)AC = 2.2 litres (ceiling difficulties)BAC = Budget at Completion = 10 LCPI = 0.75

AC + BAC –EV (CPI * SPI )

Assumes Time and Cost relationship

Page 90: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

DAY 1 PROJECTIONS: TIME

DAY – 1

Time Projections (Optimistic)

EV = 1.5L (Project progress = + 15 percent)PV = 1.8LAC = 2.0 litres (dog victims)AC = 2.2 litres (ceiling difficulties)BAC = Budget at Completion = 10 LCPI = 0.75 SPI = 1.5/1.8

(Elapsed Time / SPI + Time Remaining as per schedule)

10/(1.5/1.8) + 40 = 10*1.8 /1.5 +40 = 12 +40 = 52 hrs

Page 91: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

DAY 1 PROJECTIONS: TIME

DAY – 1

Time Projections (Likely)

EV = 1.5L (Project progress = + 15 percent)PV = 1.8LAC = 2.0 litres (dog victims)AC = 2.2 litres (ceiling difficulties)BAC = Budget at Completion = 10 LCPI = 0.75 SPI = 1.5/1.8

Total Scheduled Time / SPI

= 50/ (1.5/1.8) = (50 *1.8)/1.5 = 60 hrs

Page 92: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

DAY 1 PROJECTIONS: TIME

DAY – 1

Time Projections (Pessimist)

EV = 1.5L (Project progress = + 15 percent)PV = 1.8LAC = 2.0 litres (dog victims)AC = 2.2 litres (ceiling difficulties)BAC = Budget at Completion = 10 LCPI = 0.75 SPI = 1.5/1.8

Actual Time spent + (Time Remaining as per schedule / CR)

= 10+(40 / (SPI*CPI))

Page 93: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EVA Game

DAY – 2You finished the first bedroom during the day (20 percent completion) and started the bathroom. People whose first name begins A to J made a mess of the mirror and wasted time cleaning off the paint. People whose first name begins K to Z took an hour’s break for a shower and a cup of coffee. You finished the bathroom (10 per cent) and started the lounge / living-room. AC = + 1.4 litres Project progress = + 17 percent (names A to J)

+ 19 percent (names K to Z)

Page 94: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EVA Game

DAY – 2You finished the first bedroom during the day (20 percent completion) and started the bathroom. People whose first name begins A to J made a mess of the mirror and wasted time cleaning off the paint. People whose first name begins K to Z took an hour’s break for a shower and a cup of coffee. You finished the bathroom (10 per cent) and started the lounge / living-room. AC = + 1.4 litres Project progress = + 17 percent (names A to J)

+ 19 percent (names K to Z)

PV = 4.2

Page 95: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EVA GameDAY – 3You had a full day painting your way around the living-room. People with brown eyes were inspired by the music on the radio and worked much more quickly and efficiently than on the previous two days. People with eyes other than brown were joined by a friend for the day. Although the work was done more quickly, the friend needed a lot of guidance and used far more paint than was necessary. At the end of the day the living room was nearly finished.

AC = + 3.2 liters (brown eyes) AC = + 3.6 liters (not brown eyes)

Project Progress = + 25 percent (brown eyes)+ 30 percent (not brown eyes))

Page 96: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EVA GameDAY – 3You had a full day painting your way around the living-room. People with brown eyes were inspired by the music on the radio and worked much more quickly and efficiently than on the previous two days. People with eyes other than brown were joined by a friend for the day. Although the work was done more quickly, the friend needed a lot of guidance and used far more paint than was necessary. At the end of the day the living room was nearly finished.

AC = + 3.2 liters (brown eyes) AC = + 3.6 liters (not brown eyes)

Project Progress = + 25 percent (brown eyes)+ 30 percent (not brown eyes))

PV = 6.6

Page 97: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EVA Game

DAY – 4You finished the living-room (30 per cent) in the morning and started the kitchen. Males had trouble accessing some of the tight spots between the wall unit and the roof, between the shelves, and between the oven and the wall. As a consequence they used up more paint than was necessary. Females had trouble painting behind the refrigerator, and had to return to this at the end of the day. AC = + 1.6 litres (males)

+ 1.3 litres (females) Project progress = + 18 per cent (males)

+ 16 per cent (females)

Page 98: Project Earned Value Analysis. Real World Example Vignette: London Traffic Ken Livingstone was London’s first directly elected mayor in 2000. He created.

EVA GameDAY – 5You finished off the kitchen (20 per cent) and worked more or less continuously to try to finish the second bedroom. People wearing glasses found their painting experience really starting to pay off and worked faster than on the previous days. People not wearing glasses found their brushstrokes becoming more effective and economical than on previous days. If you reached 100 per cent or more of physical progress then the work was finished within the 50 hours. If not, then you had to return on the sixth day in order to round things off and to tidy up your materials. AC = + 1.7 litres (wearing glasses)

+ 1.4 litres (not wearing glasses) Project progress = + 24 per cent (wearing glasses)

+ 21 per cent (not wearing glasses)

PV = 10.0