Project Complexity (Case study)
-
Upload
sunny-mahajan -
Category
Engineering
-
view
76 -
download
3
Transcript of Project Complexity (Case study)
“Big Dig” ProjectTHE CENTRAL ARTERY/TUNNEL PROJECT (CA/T)
A CASE STUDY ON PROJECT COMPLEXITY.
Project Description
Located in Boston, MA, on the northeast coast of the United States.
Includes tunnels, highway interchange connections, bridges and pedestrian facilities
Project Map
Project Description
Rerouted the Central Artery (Interstate 93), into a 3.5-mile (5.6-km) tunnel.
Construction of the Ted Williams Tunnel.
Construction of the Leonard P. Zakim Bunker Hill Memorial Bridge over the Charles River.
Construction of the Rose Kennedy Greenway in the space vacated by the previous I-93 elevated roadway.
Project Description Planning Phase started in 1982 Construction work – 1991-2006 Estimated Completion - 1998 Actual Completion – Dec 31, 2007Estimated Cost - $2.8 billionFinal Cost - $14.6 billionCost over run – 190%
Official project owner - Massachusetts Turnpike Authority Joint venture of Bechtel and Parson Brinkerhoff
Source: http://www.roadtraffic-technology.com
Why Boston Needed the Big Dig?
Traffic improvements and substantial reductions in congestion Improving mobility in downtown Boston Reconnect neighborhoods severed by the old elevated highway
Source: http://www.massdot.state.ma.us
Central Artery: Before and After
Source:http://www.bigdig.com
Problems faced
Escalating costsScheduling overrunsDesign flawsCharges of poor execution and use of substandard materialsFatal Ceiling CollapseCriminal arrests and one death
Source: http://www.roadtraffic-technology.com
Complexity Factors - Cost Contingency Usage
◦ Construction Contracts◦ Management Contingency◦ Massachusetts Turnpike Authority CEO Contingency
Risk Analysis◦ Location◦ Utilities
Estimate Formation◦ Ted Williams Tunnel◦ Zakim Bunker Hill Bridge◦ Center Artery (I-93)
Complexity Factors - Cost
Figure. Big Dig Project Cost Growth (National Research Council 2003)
55%
15%
8%
7%
5%
3%
2%5%
Chart Title
Inflation
Environmental/Mitigation
Scope Growth
Accounting Changes
Traffic
Schedule Maintenance
Contingency for Unknowns
Other
Complexity Factors - Schedule Timeline Requirements
◦ Community Conflicts
Milestones
Schedule Control◦ Software Programs
Complexity Factors - Technical Scope of Project
Owner’s Internal Structure
Design Method
Complexity Factors - Context Public
◦ Economic Value of Boston
Utility Coordination◦ 29 Miles of Underground Utility Relocation and Updating
Land Use Impact◦ 300 acres of Green Space
Complexity Factors - Financing Federal Funding
State Funding
Borrowing Against Future Funding
Project Dimension Complexity Ranking
DIMENSION RANK
Context 5
Cost 4
Technical 3
Financing 2
Schedule 1
Project Dimension Complexity Rating
DIMENSIONS SCALE (0 – 100)
Cost DimensionComplexity
99
Schedule DimensionComplexity
90
Technical Dimension Complexity 95
ContextDimension Complexity
100
Financing Dimension Complexity 92
Complexity MapThe Big Dig Project
Technical
Cost
FinancingContext
Schedule
0102030405060708090100
Critical Planning and Analysis Methods
Method 1: Define Critical Success Factors◦ Community Needs◦ Political Restrictions◦ Federal and State Funding◦ Major Project Components
◦ Center Artery (I-93)◦ Ted Williams Tunnel◦ Zakim Bunker Hill Bridge
Method 2: Assemble Project Team Communication Collaboration
◦ Example◦ Ted Williams Tunnel Ceiling Panel Collapse
Method 3: Project Arrangements Design-Bid-Build
Value Engineering
Dispute Resolution
Dispute Resolution Board
Method 4: Early Cost Model and Finance Plan
Incorrect Initial Cost Model and Finance Plan
The cost model would have included ◦ Inflation◦ Project Risk- Account for Cost Overruns◦ More detail over Design Costs
Method 5: Develop Project Action Plans
Major Obstacles◦ Restrictive Legislation◦ Acquisition of ROW◦ Cooperation of Utilities◦ Community Support
Tools for Managing Complex Projects The following tools were used in the Big Dig Project:
•Public involvement plan
•Critical permit issues
•Offsite fabrication
•Co-locate team
•Dispute resolution plan
Public Involvement Plan◦ Project planners worked with community groups, government & business leaders to
create a consensus of how the project would be built
◦ Mitigation: The process of keeping the city open and making certain all affected groups would be treated fairly
◦ Informed, organized interest groups press for their demands
◦ Public involvement plan produces early project wins of consensus but at the expense of late project soaring project costs
Critical Permit Issues◦ Bechtel/Parsons Brinkerhoff (B/PB):
◦ Engineering authority that approved, permitted, and released designs for construction◦ Construction managers in charge of contractors & sub-contractors
◦ B/PB operated the project with the philosophy of getting this done, ask questions later
◦ Many plans that were permitted and released for construction were incomplete, contained numerous errors, and lacked proper subsurface exploration
◦ The lax oversight produced an estimated $750 million in construction over-runs
Offsite Fabrication◦ Utilized successfully on the CA/T project
◦ Several examples are:◦ Immersed steel tubes for the Ted Williams Tunnel◦ Steel box girder sections for the Bunker Hill Bridge
◦ Utilized successfully on the CA/T project
◦ Offsite fabrication of box girders and steel tubes produced accurate sections per specification that could be test connected at the factory to insure smooth and timely installation
◦ Quicker assembly time at the job site with smaller construction crews as compared to onsite fabrication
◦ Exposure of construction workers to difficult job environments was reduced as compared to onsite fabrication
Co-Locate Team◦ Co-Locate elements of the project team to produce a cohesive team effort to complete a
project
◦ Perhaps the most controversial tool
◦ In 1998, State of Massachusetts combined B/PB with state workers into one integrated project organization
◦ Massachusetts Turnpike Authority was at the top of the organization chart
◦ State of Massachusetts designated B/PB as “owner’s representative” in several instances
◦ Who is in charge?
Dispute Resolution Plan◦ Two noteworthy dispute resolution plan techniques were utilized on the CA/T project:
◦ Partnering◦ Mediation
◦ Partnering was practiced on the CA/T project for construction projects with a duration of least one year and a value of $1 million or more
◦ Mediation was utilized to resolve the dispute of responsibility for leaks at the Fort Point Channel tunnel area
References◦ Bartlett School of Planning (UCL). (2011). “The Central Artery/Third Harbor Tunnel Project (‘The Big Dig’), Omega Centre.” Bloomsbury,
London. ◦ Gelinas, N. (2007). “Lessons of Boston’s Big Dig.” City Journal Autumn. New York, New York. ◦ Greirman, V. (2010). “The Big Dig: Learning from a Mega Project.” NASA, <
http://appel.nasa.gov/2010/07/15/the-big-dig-learning-from-a-mega-project/> (November 13, 2013).◦ Hsu, J. Mckay, S., McKnight, M. (2003). “Cost-Benefit Analysis of Boston’s Central Artery/Tunnel Project” Carnegie Mello University.
Pittsburgh, PA.◦ Lewis, R. and Murphy, S. (2003). “Artery Errors Cost More Than $1b.” The Boston Globe, <
http://www.boston.com/globe/metro/packages/bechtel/> (November 13, 2013). ◦ Massachusetts Department of Transportation (MassDOT). (2013). “The Central Artery/Tunnel Project-The Big Dig.” MassDOT Highway
Division. <http://www.massdot.state.ma.us/highway/TheBigDig.aspx> (October 5, 2013).◦ National Research Council. “Completing the "Big Dig": Managing the Final Stages of Boston's Central Artery/Tunnel Project. Washington, DC:
The National Academies Press, 2003.◦ Poole, R.W., Samuel, P. (2011). “Transportation Mega-Projects and Risk.” Reason Foundation Policy Brief 97. Los Angeles, CA. ◦ Saltzman, J. (2009). “Big Dig Contractor Modern Continental Pleads Guilty.” Boston Globe. <
http://www.boston.com/news/local/breaking_news/2009/05/modern_continen_2.html> (October 5, 2013).◦ Salvucci, F. P. (2008). “Unearthing the Big Dig.” Massachusetts Institute of Technology. Cambridge, MA.◦ Wood, D. (2001). “Learning From the Big Dig.” Federal Highway Administration: Public Roads, <
http://www.fhwa.dot.gov/publications/publicroads/01julaug/bigdig.cfm> (November 13, 2013).