Project Completion Tiverton to Wolverton Road Upgrade
![Page 2: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/2.jpg)
2
![Page 3: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/3.jpg)
3
• Location & Details
• Project achievements
• Customers and Stakeholders
• Project Performance
• Next steps
Project Completion Report
![Page 4: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/4.jpg)
4
Location
• The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The route extends from Wolverton Street along Tiverton Road and New Windsor Road to the intersection with Maioro Street.
• The project involved upgrading the capacity and infrastructure of the route, by expanding the two-lane sections to four-lane capacity.
![Page 5: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/5.jpg)
5
• Division: Capital Development Division - Roading Central
• Designer: Beca
• Contractor: Downer
• Cost: $42.2M
• Programme: 10 years (historic ACC project), construction 2yrs
• Key activities:
Project Summary
• 2.2 km of new road pavement • 350 power/light poles removed • 5 new signalised intersections • 5.6 km of new water main • 4 new pedestrian crossing points • 21.0 km new utility ducts • 10 new bus shelters • 3,100 m2 of new footpath • 143 new street lights • Significant retaining walls • 8.6 km of new underground power • 2 new stormwater filter structures
![Page 6: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/6.jpg)
6
Project Achievements
• Signalised intersections and CCTV upgrades: Improved flow and incident management
![Page 7: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/7.jpg)
7
Project Achievements
• New footpath: Improved walking access and pedestrian experience
![Page 8: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/8.jpg)
8
Project Achievements
• Upgrade of utilities: Improvement to visual amenity and future proofing of route
![Page 9: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/9.jpg)
9
Project Achievements
• New pedestrian crossing and refuges: improved pedestrian safety and access
![Page 10: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/10.jpg)
10
Project Achievements
• Lighting upgrade: Improved the visibility of route for pedestrians, drivers and residents
![Page 11: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/11.jpg)
11
Project Achievements
• Four lane the route: Improvements in travel time and reliability, reduction in fuel consumption and CO2
![Page 12: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/12.jpg)
12
• Early communication
• Resourced team during construction
• Clear communication of programme
Customers and Stakeholders
![Page 13: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/13.jpg)
13
Project Performance • Benefit
• Cost
• Risk
• Zero Harm
• Property & Planning
• Lessons Learnt
![Page 14: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/14.jpg)
14
Project Performance – Schedule
Actual Plan
AUC
KLAN
D C
ITY
CO
UN
CIL
AUC
KLAN
D T
RAN
SPO
RT
SCHEME ASSESMENT
CONSTRUCTION
FEASIBILITY
SCHEME ASSESMENT
DESIGN
CONSTRUCTION
2012 2013 2014 2015 2016
FEASIBILITY
2006 2007 2008 2009 2010 20112003 2004 2005
DESIGN
![Page 15: Project Completion - Auckland Transport€¦ · • The Tiverton to Wolverton project relates to improvements to a key arterial route linking New Lynn to NZTA’s SH20 corridor. The](https://reader036.fdocuments.us/reader036/viewer/2022071100/5fd9669202064d70c3378746/html5/thumbnails/15.jpg)
15
• Lessons learnt review (design and construction)
• Benefit realisation plan (set activities and deliverable details)
• Complete 1yr, 5yr and 10yr benefit realisation planning
• Post implementation traffic model review (due late 2014)
Next Steps