Project Change Management - Project Life Cycle
-
Upload
ismail-aji-cordiatno -
Category
Documents
-
view
451 -
download
11
Transcript of Project Change Management - Project Life Cycle
Project Change ManagementBasic Approach in Project Life Cycle Overviews, Risk and Change Management
Dr. Iwan Ratman MSc PEVice President Project Management BPMIGAS
Jakarta, 20 December 2010
2010 © BPMIGAS – All rights reserved
Agenda
• Project Life Cycle Overview– Initiating, Planning, Execution and Closing– Project Stage Gate Process
• Project Risk Management– Project Risk Management– Cost Estimating, Planning & Scheduling– Uncertainty & Contingency Planning
• Project Change Management – Project Change Management– Type of Changes– Change Management Elements
• Conclusion
Project Life Cycle Overview
2010 © BPMIGAS – All rights reserved
Definition
A project is a finite endeavor - having specific start and completion dates - undertaken to meet particular goals and objectives, usually to brings about beneficial change or added value.
2010 © BPMIGAS – All rights reserved
Project Life Cycle Overview
Time Distribution of Project Effort
Feasibility Study Conceptual Study
Design Engineering
Construction/EPCI Operation
2010 © BPMIGAS – All rights reserved
Project Stages
Appraise Select Define Execute Operate
Execute OperateFEL-0 Identify
FEL-1 Appraise
FEL-1Select
FEL-2 Optimize
FEL-3 Define
Phase-1Identify & Assess Opportunity
Phase-2Generate & Select Alternative(s)
Phase-3Develop Preferred Alternative
Phase-4Execute
Phase-5Operate & Evaluate
Appraisal Design Pre-Project Basic Engineering EPSC Comm & StartUp
Operations
FEED Construction OperationPre-POD
2010 © BPMIGAS – All rights reserved
Key Criteria for Distinctive Investment Performance
Operational Excellence
APPRAISE SELECT DEFINE EXECUTE OPERATE
Choose the Right Project Develop the Project Right Deliver the Project Right
Risked PortfolioManagement
Excellence in Project Management
FEED Construction OperationConceptual
2010 © BPMIGAS – All rights reserved
BPMIGAS Business Process
Pengajuan usulan kegiatanPre-POD
Evaluasi dan Persetujuan POD
Pengajuan usulan AFE FEED
Evaluasi Teknis & Biaya
Pelaksanaan FEEDSpesifikasi TeknisGambar Teknis
Estimasi Biaya KonstruksiContracting Strategy
Pengajuan usulan AFE Konstruksi
Evaluasi Teknis & Biaya
KonstruksiPelaksanaan Detailed Eng, Fab’n, Instal’n,
Sertifikasi, Konsultasi PLK
AFE Close Out
Placed Into Service
AFE Close Out(AFE) Close Out
EKS/EPT/PPA MP PBOJIAN/PPA
PenanggungJawab:
Setuju?Tidak
Ya
Sub-Surface, Pemboran, Skenario Fas Prod, Off Taker,
Hukum, Keekonomian
Pelaksanaan Pre-POD
Setuju?Tidak Ya
Evaluasi Teknis & Biaya
Setuju? Tidak
Ya
Sesuai dengan POD?
Tidak Ya
Deviasi bisa
diterima?
Tidak
Ya
Setuju?Tidak
Ya
Pengadaan FEED
PMA
PengadaanKontrak Konstruksi
PersetujuanPLK
Start-Up andCommissioning
2010 © BPMIGAS – All rights reserved
Business Process - Pre POD
KKKS BPMIGASJIAN
Awal Kegiatan Kick Off Meeting
Akhir Kegiatan Sasaran Tercapai?
EKS/PPA PMA SDM
Usulan POD
EPT EKS PMA
MP OL
PPA PMG HSPFIn Progress
Identifikasi danSeleksi Konsep
PBO PMAEKS
SDM PMG
PO
PPA
2010 © BPMIGAS – All rights reserved
Business Process - FEED
KKKS BPMIGASMPM
Awal KegiatanSesuai denganpersetujuan?
In Progress
Tech Tepat Guna?Surplus Material?
Produk Lokal?Optimum Design?
StrategiPengadaan
Lingkup KerjaTender
Akhir Kegiatan
Lingkup proyektelah terdefinisi
dengan baik?Sesuai POD?
EPT/PPA PMA SDM
OL PO PMG
JIAN PBO PMA
OL PO PMG
Usulan AFE EPCI
EPT/PPA SDM HSPF
EPT/PPA PMA JIAN
2010 © BPMIGAS – All rights reserved
Business Process - EPCI
KKKS BPMIGASMPM
Awal KegiatanSesuai denganpersetujuan?
In Progress
Biaya, Mutu & Waktu?
Perijinan?Sertifikasi?
Akhir Kegiatan
EPT/PPA PMA SDM
OL PO PMG
JIAN PBO PMA
OL PO PMGSasaranTercapai?
Persetujuan PIS
Operations
EPT/PPA SDM HSPF
EPT/PPA PMA PBO
SDM JIANHSPF
Project Risk Management
2010 © BPMIGAS – All rights reserved
What is a Risk?
• A Risk is anything that could happen that would significantly affect the achievement of the Project Objectives. (Cost, Schedule, Construction, Staffing, Operability, etc.)
• Each Risk has a Likelihood of Occurrence and a consequence or Impact to the Project if it does.
• A Risk can have a Positive (Opportunity) or Negative (Threat) Impact on the Project
• When a Risk occurs, it becomes an Issue that must be resolved so that the Project Objectives can be met
2010 © BPMIGAS – All rights reserved
Flow Diagrams
Project Risk Management Flow Diagrams
IdentifyRisk / Changes
Analyse Probability and
Impact
ApplyAvoidance or
Reduction
DefineContingency
Plans
Monitor &Manage
2010 © BPMIGAS – All rights reserved
Cost Estimation
AACE Cost Estimate Classification
2010 © BPMIGAS – All rights reserved
Accuracy and Contingency Ranges
Phase FEL-0 FEL-1(AFF-GATE)
FEL-2(AFD-GATE)
FEL-3(AFE-GATE)
AACEI Classification
Class 5 Class 4 Class 3 Class 2
Accuracy -20% to +50% -20% to +40% -15% to +25% -10% to +15%
% Engineering Complete
0% to 2% 1% to 5% 2% to 10% 15% to 30%
Contingency 20% to 40% 20% to 30% 15% to 30% 15% to 25%
Basis Very Broad At least 1 Viable Concept
Optimized Concept Complete FEL
2010 © BPMIGAS – All rights reserved
Level Probability vs Cost Estimate
Cost & Schedule Probability Curve (S-curve)
A D B CE
P90
P70
P50
P35
P10
A : Value P10B : Value P50C : Value P90D : Deterministic EstimateE : Deterministic By PM
DeterministicEstimate
(IncludingAllowance)
ContingencyP50 – Determin. Estimate
COST
P
Sample
2010 © BPMIGAS – All rights reserved
Uncertainty & Contingency
100
90
50
10
ACCURACY LEVEL
CONTINGENCY
P10 BASE
COST
P50 P90
COST
-30% +100%
EXPECTED
Uncertainty results from variations in the scope of a project.Contingency is allowance to cover unforseen costs or time within a defined scope.
2010 © BPMIGAS – All rights reserved
Contingency Plan
CONTINGENCY PLAN
Project Change Management
2010 © BPMIGAS – All rights reserved
Change Management
2010 © BPMIGAS – All rights reserved
Project Change Management
Must be evaluated within the context of the original plan or activity.
– During the detailed design stage – the Basis of Design is the reference point for scope change.
– Once procurement orders are placed and Authorized for Construction Drawings are issued – the procurement orders, awarded contracts, and AFC documents are the reference points for scope change.
– The Project Manager may also impose a “design freeze” which defines the reference point for scope change.
2010 © BPMIGAS – All rights reserved
Project Changes Management
Manage Project Changes with Risk Management.
Possible outcomes for each risk (Changes):• Take action to avoid the risk, reduce its likelihood, or reduce
its impact, • Make contingency plans and deal with the impact and
mitigate the risk should it occur, • Agree that it is an acceptable business risk to take no action
and hope that the risk does not occur.
Do not wait for situations to come up before you address them
2010 © BPMIGAS – All rights reserved
Scope Changes
SCOPE CHANGES
Is it unsafe? Will it not work? Is it illegal?
Mandatory Discretionary
All other changes to project premise or scope of work
Scope Changes can be mandatory or discretionary
2010 © BPMIGAS – All rights reserved
Project Changes
• Scope Change is a deviation that results in noncompliance with the project premises or is any change to the project scope, execution methodology or schedule. Project scope is normally defined at the time of AFE approval. This is not intended to include cost changes due to Cost Trends. It is a change that modifies the project scope of work or premise, requiring proper authorization to provide additional funding to the project.
• Cost and Schedule Trend is a deviation in the project plan or design that does not result in noncompliance with the project premises.
2010 © BPMIGAS – All rights reserved
Trends
Trends are changes that do not alter the project premiseExamples:• Market escalation – material or contract pricing, including
foreign exchange rates• Productivity – field labor productivity, engineering
productivity, construction errors and rework• Estimate variations – quantity and wage rate variations,
installation rate (not productivity) variations• Design growth – omissions to drawings, design interferences,
additional design development in accordance with the BOD• Back charges and / or rework• Other – claims, legal, insurance, vendor errors, changes to the
project execution plan
Conclusion
2010 © BPMIGAS – All rights reserved
Project Management Areas
Onshore Offshore
Integration Scope Risk
Time
Cost
Quality Procurement
Communication
HR
Project Objectives
Flawless Startup
Achieved Production
BPMIGAS Supervision,
Monitoring and Approval
External Party Audit
PSCs PROJECTS
Banyu UripMasela
IDD
2010 © BPMIGAS – All rights reserved
Achieving Business Objectives
1) Develop a disciplined approach to project management with emphasis on:
– Capital Efficiency– Efficient Cycle Times
2) Appropriate application of the process would improve credibility through:
– Predictable Outcomes– Improved Operability
THANK YOUMerci Beaucoup
Terima Kasih