PROJECT 2
GROUP 9
TOPICAL LECTURES
GROUP 9 (NIKHEF) PROJECT 2 25/03/2015 1 / 5
Setup
Distance67 cm between scintillators45 degree orientation.Opening angle ≈ 24 deg.
GROUP 9 (NIKHEF) PROJECT 2 25/03/2015 2 / 5
Calibration
CalibrationTuned threshold : to haveapprox. equal count rate.Count rate checked foreach individual scintillatorand in coincidence.
GROUP 9 (NIKHEF) PROJECT 2 25/03/2015 3 / 5
Measurements
Two configurations : W→E and E→W
CountsN1 N2 Counts/min
East 736 807 4.6879 ± 0.16904West 657 759 4.2932 ± 0.16170
Time(min) 152 178
GROUP 9 (NIKHEF) PROJECT 2 25/03/2015 4 / 5
Results and Conclusions
Statistical uncertaintiesA = f W −f E
f W +f E
σ2A = A2
[σ2
(f W −f E )2 + σ2
(f W +f E )2
]σ2 = σ2
f W + σ2f E
Final resultsA = -0.0439 ± 0.0260P(A<0) ≈ 0.95
ConclusionsExcess from the East (or lack of experimental capabilities)
GROUP 9 (NIKHEF) PROJECT 2 25/03/2015 5 / 5