Progress Review On
Ongoing Construction Projectsaimed at
Budget - 2016
Professor Ranjith Premalal De Silva
Vice ChancellorUva Wellassa University, Sri
LankaDr. Gamani Chandrasena
Vice ChancellorUva Wellassa University, Sri Lanka
Construction (Capital) Projects of Uva Wellassa 1. Phase I
2. Phase IIPhase I
i. Administration Building Block ii. Lecture Hall + Lab (Block A)iii. Lecture Hall + Lab (Block B)iv. Lecture Hall + Lab (Block C)
Total Cost Estimated (Amended TCE) => Rs. 350 MillionActual Expenditure incurred to 30.06.2015 => Rs. 348 MillionFuture Commitment (Final Bill to be Settled) => Rs 10 MillionPhysical Process : 100% Financial Progress : 99%
Administration Building Block
• Awarding On : 03rd Aug 2005
• Completed On : 16th Oct 2006
25 August 2015
Lecture Hall + Lab (Block B)
• Awarding On : 03rd Aug 2005
• Completed On : 11th Oct 2006
Lecture Hall + Lab (Block C)
• Awarding On : 03rd Aug 2005
• Completed On : 11th Oct 2006
Lecture Hall + Lab (Block A)
• Awarding On : 03rd Aug 2005
• Completed On : 01st Nov 2006
25 August 2015
Hostel Block No. 2•Awarding On : 01st Sep 2006•Completed On : 26 Jun 2008•Physical Progress : 100%•Financial Progress : 87%
Hostel Block No. 3•Awarding On : 01st Aug 2006•Completed On : 04th Dec 2008•Physical Progress : 100%•Financial Progress : 87%
Hostel Block No. 1•Awarding On : 01st Jul 2006•Completed On : 30th Jul 2007•Physical Progress : 100%•Financial Progress : 87%
25 August 2015
Phase II
Dinning & Study Hall Kitchen for Dinning & Study Hall
•Awarding On : 15th May 2006•Completed On : 30th Jun 2006•Physical Progress : 100%•Financial Progress : 87%
Water Sump & Pump House
•Awarding On : 01st Sep 2006
•Completed On : 16 Jun 2008
•Physical Progress : 100%
•Financial Progress : 73%
Hostel Block No. 4• Awarding On : 01st Nov 2006• Completed On : 25th Jul 2008• Physical Progress : 100%• Financial Progress : 87%
25 August 2015
TCE: 457 Million
Name Board and Developments at entrance
•Awarding On : 01st Jul 2007•Completed On : 19th Jan 2008•Physical Progress : 100%•Financial Progress : 35%
Temporary Sports Court•Awarding On : 15th Jan 2007
•Completed On : 27th Feb 2006
•Physical Progress : 100%
•Financial Progress : 70%
Landscaping - Phase - 1 Area•Awarding On : 01st Jan 2007•Completed On : 19th Jan 2008•Physical Progress : 100%•Financial Progress : 70%
25 August 2015
25 August 2015
Fiber Network (IT back-born at Phase 1 buildings)
•Awarding On : 01st Dec 2007•Completed On : 31st Dec 2008•Physical Progress : 100%•Financial Progress : 97%
Vice Chancellor's Bungalow•Awarding On : 08th Sep 2008•Completed On : 09th Mar 2010•Physical Progress : 100%•Financial Progress : 98%
Play Ground (For 200m track)
•Awarding On : 01st Apr 2007
•Completed On : 13th Sep 2009
•Physical Progress : 100%
•Financial Progress: 63%
25 August 2015
Internal Road Network (A,B & D)•Awarding On : 01st Mar 2007•Completed On : 30th Mar 2009 •Physical Progress : 100%•Financial Progress: 66%
Lecture Hall + Lab (Block E)
• Awarding On : 05th Sep 2008
• Completed On : 15th Mar 2011
• Physical Progress : 100%
• Financial Progress : 65%
Lecture Hall + Lab (Block F - I)
• Awarding On : 01st Jan 2009
• Completed On : 08th Mar 2010
• Physical Progress : 100%
• Financial Progress: 65%
25 August 2015
Lecture Hall + Lab (Block F - II)• Awarding On : 27th Apr 2010• Completed On : 26 Jul 2011• Physical Progress: 100%• Financial Progress: 65%
Lecture Hall + Lab (Block D)• Awarding On : 27th Apr 2010• Completed On : 26th Aug 2011• Physical Progress: 100%• Financial Progress:65%
Storm Water Drainage System
•Awarding On : 30th Dec 2009
•Physical Progress: 65%
•Financial Progress: 17% Ongoing
25 August 2015
Quarters for Deans/ Registrar/ Bursar & Course Directors
•Awarding On : 01st Dec 2011
•Completed On : 15th Feb 2013•Physical Progress : 100%
•Financial Progress : 77%
Staff Quarters (Studio Apartments)
•Awarding On : 25th Nov 2012
•Completed On : 05th Mar 2013
•Physical Progress : 100%
•Financial Progress : 50%
Roads and Landscaping at Phase II Area
•Awarding On :17th Dec 2009
•Physical Progress : 50%
•Financial Progress : 41%
•
Ongoing
25 August 2015
Sports Center & Gymnasium
• Awarding On : 30th Dec 2014
• Physical Progress : 25%
• Financial Progress : 25%
Pavilion
•Awarding On :06th Aug 2015
•Physical Progress : 5%
•Financial Progress : 5%
(Mobilization Advance)
Ongoing
Ongoing
Cafeteria and Toilets
•Awarding On : 27th Aug 2012
•Completed On : 26th Aug 2013
•Physical Progress : 100%
•Financial Progress: 100%
25 August 2015
Maintenance section
• Awarding On : 08th Jan 2014
• Completed On : 08th Oct 2014
• Physical Progress : 100%
• Financial Progress: 66%
Senate Building
• Awarding On : 20th Mar 2013
• Physical Progress : 95%
• Financial Progress: 85% Ongoing
Balance work Roads & Landscaping
•Awarding On : 22nd Mar 2014
•Physical Progress: 65%
•Financial Progress: 44% Ongoing
Waste water drainage & treatment works (Job 01 & Job 02)
•Awarding On :14th Oct 2010 / 17th May 2013
•Physical Progress : 85%
•Financial Progress: 36%
University Guest House
•Awarding On: 05th Nov 2012
•Completed On: 17th Aug 2013
•Physical Progress: 100%
•Financial Progress: 96%
25 August 2015
Ongoing
University Guest House
•Awarding On: 05th Sep 2011
•Completed On: 20th Oct 2012
•Physical Progress: 100%
•Financial Progress: 64%