BOCOG

• IOC Coordination Commission• 2 Plenary Sessions & Work Group Meetings

in Beijing annually since 2005 • Teleconference every 2 weeks

Relations with the IOC

• A smooth and efficient communication with IWF

• The exchange of information at a regular basis has been set

• Communications with IWF to promote understanding

Relations with IWF

Sports Department

BOCOG VP & Sport DirectorBOCOG VP & Sport Director

Director of Sport DepartmentDirector of Sport Department

Deputy DirectorDeputy Director Deputy DirectorDeputy Director Deputy DirectorDeputy Director

BOCOG Deputy Secretary-General BOCOG Deputy Secretary-General

General AffairsGeneral Affairs

Planning & OperationsPlanning & Operations

PublicationsPublications

IFs RelationsIFs Relations

SEQSEQ

Sport TechnologySport Technology

CompetitionCompetition

NFs RelationsNFs Relations

Venue & EquipmentVenue & Equipment

ParalympicsParalympics

IFs & TOs ServicesIFs & TOs Services

Competition ScheduleCompetition Schedule

Test EventTest Event

Venue & EquipmentVenue & Equipment

SCCSCC

ConsultantConsultantWorking PanelsWorking Panels

FEFESHSHARARCYCYMPMPTRTREQEQ

BDBDWLWLWRWRJUJUBOBOTKTKTTTT

HOHOHBHBBBBBSOSOBKBKTETEVBVB

• 11 Divisions, 55 full-time staffs

• Mr. Yannis Sgourous and Mr. Sam Coffa

appointed by IWF as the Technical Delegates

Technical Delegates

IFsTDs

BOCOGCMs

• Ms. Wang Yan be appointed as Weightlifting Competition Manager for Beijing Olympic Games

Competition Manager

• Weightlifting competitions will be held from day 1 to day 11

• 10 Competition days (with one day rest)

Competition Schedule

• Deadline for sport entries is July 23rd, 2008

Sports Entry and Qualification System (SEQ)

Competition Venue

Beihang Gymnasium

Olympic Village

Tiananmen Square

Distance from Olympic Village to Competition Venue——3km

Competition Venue

Competition Venue

Competition Venue

Training Venues

• To meet the requirements of IWF.

• 50 Training platforms

• Training of competition management staffs

Training of Competition Staffs

NTOs Training

• NTO Training Plans for 28 sports and 38 disciplines formulated

• The 1st NTOs training course for Weightlifting will be held in Oct. 2006

• Test Event: China Open• Date: Jan. 20 – Jan. 24, 2008

Test Events

BOCOG’s Proposal

IWF’s

Confirmation

IOC

Approval

Test Events

Elements to be tested

• Operation of competition venue

• Sport and technical equipments

• Competition management

• International and National technical officials

• Competition procedures

Sports Equipment

• To follow IOC guidelines • To respect IWF rights

Sport Publications

Include:

• Pre-Games Training Guide• Explanatory Book• Guide for Technical Officials• Team Leaders’ Guides• SEQ Manual• Competition Forms• Entry Forms

Sport Presentation

• The FA of Culture & Ceremony is in charge of the overall planning of sport presentation

Olympic Results and Information Services (ORIS)

• The first and second round of the ORIS meetings for 12 disciplines has been concluded

• The ORIS meeting for weightlifting will be held in October 2006

OVR&TSOVR&TS IDS ManagerIDS Manager

CoordinatorCoordinator

ManagerManagerOMEGA ATOS ORIGIN

IDS, CRS, CIS, RDF, IDF

BOCOG

ATOS/GALANIS

TOCSCC

Duty Manager RESULTS &

INFO

Duty Manager RESULTS &

INFOIDS DMIDS DMSWATCH DMSWATCH DM

(Volunteer) (Volunteer) BOCOG

Inte

rnat

iona

l Fed

erat

ion

Inte

rnat

iona

l Fed

erat

ion

TD

Accommodation

• The Beijing Hotel and the Grand Hotel Beijing will be the IOC hotels, where IF Presidents and Secretaries General will be accommodated

Accommodation for the IF Presidents and Secretaries General

IWF officials and Technical Officials:

• Beihang Weishi Tower• Accommodation survey circulated to IWF

Accommodation

• Transportation strategic plan completed• To build up Olympic transport models

Transport

•Preliminary Strategic Plan for Olympic Security

•Working Plan for Risk Assessment of Beijing 2008 Olympic Games

Security

Medical Services

• 20 designated hospitals contracted

Doping Control

•Anti-doping Operational Plan submitted to the IOC