Progress Report of GJTI - Up to 31 st December 2015 Activities done: 1. Training Programmes; Planned as well as demanded, by different wings of GJTI 2. Testing of Water Quality; At Gandhinagar as well as in state, Water Quality Monitoring Survey 3. IEC and HRD activities; Training Material development & dissemination and Awareness / Orientation / Sensitisation programmes. Achievement: Overall Achievement as per SMART Goals Area Goals Achievement during this month Previous Achievement Total Achievement till date % of Goal Achievement Number of Trainees 3115 633 1669 2302 (Total Number of Training 50) 73.90% Water Quality Testing of Samples 198000 (Rural) 25647 193441 219088 113.98% (Urban) 743 5864 6607 Total 26390 199305 225695 Details of Achievements 1. Capacity utilisation in Training Programme 253.20% Altogether 10 training programmes were conducted through which 633 participants were trained. Wing Trainings Participants Civil 5 (426) Geological 1 (022) Mechanical 4 (185) TOTAL: 10 (633) [On an average, at least 10 training programme in each month, to cater 25 participants. Thus 10X25=250 is the total capacity. However, because of insufficient nomination, some courses were cancelled or postponed] 2. Testing of Water Quality; at Gandhinagar as well as in state. Types of samples Numbers Chemical Testing (65 labs) 17236 Bacteriological Testing (65 labs) 09154 Total samples tested 26390 3. Water Quality Monitoring Survey Surveys (by 65 laboratories) 12813

Transcript of Progress Report of GJTI - Up to 31st December 2015Progress Report of GJTI - Up to 31st December 2015...

Page 1: Progress Report of GJTI - Up to 31st December 2015Progress Report of GJTI - Up to 31st December 2015 Activities done: 1. Training Programmes; Planned as well as demanded, by different

Progress Report of GJTI - Up to 31st December 2015 Activities done: 1. Training Programmes;

Planned as well as demanded, by different wings of GJTI 2. Testing of Water Quality;

At Gandhinagar as well as in state, Water Quality Monitoring Survey

3. IEC and HRD activities; Training Material development & dissemination and Awareness / Orientation / Sensitisation programmes.

Achievement: Overall Achievement as per SMART Goals

Area Goals Achievement

during this month

Previous Achievement

Total Achievement

till date

% of Goal Achievement

Number of Trainees

3115 633 1669 2302 (Total Number of Training – 50)

73.90%

Water Quality Testing of Samples

198000

(Rural) 25647 193441 219088

113.98% (Urban) 743 5864 6607

Total 26390 199305 225695

Details of Achievements

1. Capacity utilisation in Training Programme – 253.20%

Altogether 10 training programmes were conducted through which 633 participants were trained.

Wing Trainings Participants Civil 5 (426) Geological 1 (022) Mechanical 4 (185)

TOTAL: 10 (633) [On an average, at least 10 training programme in each month, to cater 25 participants. Thus 10X25=250 is the total capacity. However, because of insufficient nomination, some courses were cancelled or postponed]

2. Testing of Water Quality; at Gandhinagar as well as in state.

Types of samples Numbers Chemical Testing (65 labs) 17236 Bacteriological Testing (65 labs) 09154

Total samples tested 26390

3. Water Quality Monitoring Survey

Surveys (by 65 laboratories) 12813

Page 2: Progress Report of GJTI - Up to 31st December 2015Progress Report of GJTI - Up to 31st December 2015 Activities done: 1. Training Programmes; Planned as well as demanded, by different

Training Details

Target Total

Achievement till date

% of Target Achievement

Total Expenditure

Training for Engineers

700 565 80.71% 232082.00

Training for Grass route Workers

500 370 74.00% 80210.00

Training for Class-I & II Officer

200 101 50.50% 69554.00

Training for Technical Staff

1000 910 91.00% 166633.00

Training for Admin. Staff

600 255 42.50% 68974.00

KRC Training 90 101 112.22% 405954.00

CPHEEO Training 25 - - -

TOTAL (Total number of

trainings – 50) 3115 2302 73.90% 1023407.00

Page 3: Progress Report of GJTI - Up to 31st December 2015Progress Report of GJTI - Up to 31st December 2015 Activities done: 1. Training Programmes; Planned as well as demanded, by different

Detailed Progress Report of GJTI for the Month of December 2015

Wing Title of the

course Dates Place

Planned or Demanded

No. of participants

Civil

KRC-Water Safety Plan and O&M of Rural Water Supply

Schemes

3-4 Infocity Club

& Resort, Gandhinagar

Planned 32

Performance Improvement of

Water Treatment Plant

18 Jal Bhawan,

Himmatnagar Planned 89

Performance Improvement of

Water Treatment Plant

22 Jal Bhawan,

Mehsana Planned 104

Performance Improvement of

Water Treatment Plant

21

seminar hall, Anand Krushi Engineering &

Technology College, Godhara

Planned 101

Performance Improvement of

Water Treatment Plant

8

Swaminarayan Mandir,

Vadhavadi Road,

Bhavnagar

Planned 100

Geological

GIS Applications in Water Resource

Management

29-30 Staff Training

college, Gandhinagar

Planned 22

Mechanical

R&D on Advance Technology & Engineering

Services

8

Meeting Room, 3rd Floor, H.O.,

Gandhinagar

Unplanned 17

Energy Audit / Energy Savings

10 Board Room,

H.O., Gandhinagar

Unplanned 51

O&M of Hand Pumps

11 Ambaji Planned 60

Energy Audit / Energy Savings

29 Staff Training

College, Gandhinagar

Planned 57

Total 10 Programmes 633

Page 4: Progress Report of GJTI - Up to 31st December 2015Progress Report of GJTI - Up to 31st December 2015 Activities done: 1. Training Programmes; Planned as well as demanded, by different

Following Faculties of GJTI gave input during various training programmes.

Wing Name of faculty

1 Civil 1. Mr. D G Ramchandani, Joint Director, GJTI, Gandhinagar

2 Geological 1. Mr. D N Rao, Geophysicist, GJTI, Gandhinagar

3 Mechanical 1. Mr. C M Thakkar, EE(Mechanical), GJTI, Gandhinagar

Following Faculties invited during various special training programmes.

Wing Name of faculty / Speakers

1 Civil

1. Mr. Vijay Anadkat, Fellow, Embarq India, New Delhi 2. Ms. Bhavnaben M Trivedi, CSO, PHE Lab., Vadodara 3. Mr. P H Shah, SE, Himmatnagar 4. Mr. D M Dalwadi, Unit Manager, WASMO 5. Mr. Bhavik Rathod, EE, GWSSB 6. Mr. Ketan V Lakhtariya, Professor, Gujarat Power Engineering &

Research Institute 7. Mr. Manoj Raje, Site Engineer, TATA Consultancy 8. Mr. Sunil Parikh, Site Engineer, TATA Consultancy 9. Mr. Himanshu Nirmal, Rachna Filter Plant 10. Mr. M K Soni, EE, PHW Sub Div.1, Bhavnagar 11. Mr. D R Hingaliya, DEE, PHS Sub Div.1, Ahwa-Dang 12. Mr. Arifbhai Rathod, Hydrologist, Mech. Div, Bhavnagar 13. Mr. Gautam V Dihora, Asst. Professor, Shantilal Shah Engg. Colg,

Bhavnagar

2 Geological

1. Mr. Ajay Patel, Project Manager, BISAG, Gandhinagar 2. Mr. jaydeepsinh kathota, Scientist, BISAG, Gandhinagar 3. Mr. M H Kaluburme, Project Director, BISAG, Gandhinagar 4. Mr. Vijay Singh, Diorector, BISAG, Gandhinagar

3 Mechanical

1. Mr. Prakash Vakani, Director, GSH Energy 2. Mr. H P Karandikar, H P Karandikar, GETRI, Vadodara 3. Mr. Ravi Solanki, CGM, GWIL, Gandhinagar 4. Mr. Dhimant Vyas, SE, H.O. GWSSB, Gandhinagar 5. Mr. V M Limbachiya, DEE, GWSSB, Palanpur 6. Mr. J S Malvi, AAE, GWSSB, Palanpur 7. Sh. B D Vaghela, Consultant, Gandhinagar 8. Sh. Jaivik Patel, Envirocare Engineering 9. Sh. Hardik Patel, Envirocare Engineering

Page 5: Progress Report of GJTI - Up to 31st December 2015Progress Report of GJTI - Up to 31st December 2015 Activities done: 1. Training Programmes; Planned as well as demanded, by different

Following photographs show some of the training activities.

1. Mr. Vijay Anadkat, Fellow, Embarq India, New Delhi is addressing the trainees

during KRC training on “Water Safety Plan and O&M of Rural Water Supply Schemes” from 3-4 December 2015 at Infocity Club & Resort, Gandhinagar.

2. Group photograph of trainees during KRC trainees during training on “Water

Safety Plan and O&M of Rural Water Supply Schemes” from 3-4 December 2015 at Infocity Club & Resort, Gandhinagar.

Page 6: Progress Report of GJTI - Up to 31st December 2015Progress Report of GJTI - Up to 31st December 2015 Activities done: 1. Training Programmes; Planned as well as demanded, by different

3. Mr. D M Dalwadi, Unit Manager, WASMO is addressing the trainees during

the Training Programme of “Performance Improvement of Water Treatment Plant” on 18 December 2015 at Jal Bhawan, Himmatnagar.

4. Trainees during the Training Programme of “Performance Improvement of

Water Treatment Plant” on 18 December 2015 at Jal Bhawan, Himmatnagar.

Page 7: Progress Report of GJTI - Up to 31st December 2015Progress Report of GJTI - Up to 31st December 2015 Activities done: 1. Training Programmes; Planned as well as demanded, by different

5. Trainees during the Training Programme of “Performance Improvement of Water Treatment Plant” on 22 December 2015 at Jal Bhawan, Mehsana.

6. Trainees during the Training Programme of “Performance Improvement of Water Treatment Plant” on 8 December 2015 at Swaminarayan Mandir, Vadhavadi Road, Bhavnagar.

Page 8: Progress Report of GJTI - Up to 31st December 2015Progress Report of GJTI - Up to 31st December 2015 Activities done: 1. Training Programmes; Planned as well as demanded, by different

7. Dignitaries during the Training Programme of “Performance Improvement of Water Treatment Plant” on 21 December 2015 at seminar hall, Anand Krushi Engineering & Technology College, Godhara.

8. Dignitaries during the Training Programme of “Energy Audit / Energy Savings”

on 29 December 2015 at Staff Training College, Gandhinagar.