Progress Recording & Cost Optimisation

download Progress Recording & Cost Optimisation

of 28

Transcript of Progress Recording & Cost Optimisation

  • 7/27/2019 Progress Recording & Cost Optimisation

    1/28

    Progress Recording,

    Cost Optimisation &Acceleration

    PRODUCTION ORGANISATION & HUMAN RESOURCE MANAGEMENT

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    11th August 2010

  • 7/27/2019 Progress Recording & Cost Optimisation

    2/28

    Project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Project Stages

    Appraisal Proposals DesignProductionInformation

    ConstructionPhases

    PostConstruction

    Pre-tender

    Pre-contract

    Contract

  • 7/27/2019 Progress Recording & Cost Optimisation

    3/28

    Project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Planning tools

  • 7/27/2019 Progress Recording & Cost Optimisation

    4/28

    Project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Planning tools

  • 7/27/2019 Progress Recording & Cost Optimisation

    5/28

    Project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Planning tools

  • 7/27/2019 Progress Recording & Cost Optimisation

    6/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Why do you need to plan?

    Time

    Quality

    Cost

  • 7/27/2019 Progress Recording & Cost Optimisation

    7/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Monitoring & Controlling Progress

    PrepareMaster

    Programme

    MeasurePerformance

    Assess

    Deviation

    DetermineAction

    Compare

    actual withplanned

    Ahead/Behind

    Replan and

    implement

    Denyer, 1972

  • 7/27/2019 Progress Recording & Cost Optimisation

    8/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Control of Progress

    Control is comparing, at regular intervals, the actual workachieved with that planned

    Necessary corrective action can be taken to bring workback on schedule

    Use of monthly and weekly meetings are invaluable in

    helping control progress work not proceeding as planned can be considered in

    detail explanations can be assessed best solutions can be discussed and implemented

    Communications on progress can be made with otherparts of the organisation

  • 7/27/2019 Progress Recording & Cost Optimisation

    9/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

  • 7/27/2019 Progress Recording & Cost Optimisation

    10/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Progressing work and

    updating information directlyon a network

    Progressing activities on a

    precedence diagram

  • 7/27/2019 Progress Recording & Cost Optimisation

    11/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Assigning

    target

    dates to

    activities

  • 7/27/2019 Progress Recording & Cost Optimisation

    12/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Updating

    activities in-

    line with

    actual

    progress

  • 7/27/2019 Progress Recording & Cost Optimisation

    13/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Network

    showing

    completed,

    started and

    remaining

    activities

  • 7/27/2019 Progress Recording & Cost Optimisation

    14/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Controlling Costs

    Cost control should enable the cost of each stage, activity or unit to bedetermined and compared with target costs to ascertain any deviations

    The timing of cost information is all important and ideally should be done as

    work is being carried out

    Problems can be identified early and remedial action taken as appropriate

    Most project management systems provide for this and enable resources and

    resources representing sections of work to be assessed in terms of cost and

    income

    The collection of cost information may be carried out via time sheets, weekly

    summary sheets and the measurement of work completed

    Cost control information is also be useful for the estimation of costs on future

    projects

  • 7/27/2019 Progress Recording & Cost Optimisation

    15/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Time/Cost optimisation

    A technique used to find the most economical way ofcarrying out a project in terms of time and cost

    The cost of a project can be considered a combination of

    direct and indirect costs

    The variation in duration of critical activities will affect

    these cost and the total cost of the project

    To accelerate activities is more expensive in terms of

    direct costs

    As a project duration increases so will the indirect costs

    Time/Cost optimisation is concerned with establishingproject duration at minimum cost

  • 7/27/2019 Progress Recording & Cost Optimisation

    16/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Time/Cost optimisation

    The reduction in duration of an activity can be achieved

    through increased resources, working overtime or

    additional shifts

    The reduction in time is termed crashing for which there

    will be an associated crash cost

    Cost slope for activities can be determined by as follows cost slope = (crash cost - normal cost) / (normal duration -

    crash duration)

    Critical activities can be accelerated in the order of least

    cost slope Direct and indirect costs can be calculated for each project

    duration to obtain the optimum cost

  • 7/27/2019 Progress Recording & Cost Optimisation

    17/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Linear relationship

    between time and cost for

    an activity

    Multi-linear relationship between time

    and cost for an activity

  • 7/27/2019 Progress Recording & Cost Optimisation

    18/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Discrete timeand cost

    relationship for

    an activity

    Non-linear

    relationship betweentime and cost for an

    activity

  • 7/27/2019 Progress Recording & Cost Optimisation

    19/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Cost curves to establish the least cost for optimum

    project duration

  • 7/27/2019 Progress Recording & Cost Optimisation

    20/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

  • 7/27/2019 Progress Recording & Cost Optimisation

    21/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Activity Duration

    (days)

    Maximum

    Compression

    (days)

    Normal

    Cost

    ()

    Cost

    Slope

    )

    A 20 5 4,700 20

    B 54 - 5,485 -

    C 11 4 6,536 First 3 days

    35 per day

    85 per day

    thereafter

    D 15 5 3,400 First 2 days

    40 per day

    95 per day

    thereafter

    E 26 10 3,950 55F Method (1) 20

    Method (2) 13

    10

    3

    1,100

    1,400

    90

    150

  • 7/27/2019 Progress Recording & Cost Optimisation

    22/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Activity Duration

    (days)

    Maximum

    Compression

    (days)

    Normal

    Cost

    ()

    Cost

    Slope

    )

    A 20 5 4,700 20

    First Compression

    Compress activity A by 5 days = 5 x 20 = 100

  • 7/27/2019 Progress Recording & Cost Optimisation

    23/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Activity Duration

    (days)

    Maximum

    Compression

    (days)

    Normal

    Cost

    ()

    Cost

    Slope

    )

    C 11 4 6,536 First 3 days

    35 per day

    85 per day

    thereafter

    E 26 10 3,950 55

    Second Compression

    Compress activity C by 3 days = 3 x 35 = 105

    Compress activity E by 3 days =3 x 55 = 165

    Total 270

  • 7/27/2019 Progress Recording & Cost Optimisation

    24/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Third Compression

    Compress activity D by 2 days2 x 40 = 80

    Compress activity E by 2 days

    2 x 55 = 110

    Total 190

    Fourth Compression

    Compress activity E by 1 day1 x 55 = 55

    Compress activity C by 1 day

    1 x 85 = 85

    Total 140

    Fifth Compression

    Compress activity E by 3 days3 x 55 = 165

    Compress activity D by 3 days

    3 x 95 = 285

    Total 450

    Sixth Compression

    Method (2) selectedCompress activity F by 3 days

    3 x 150 = 450

  • 7/27/2019 Progress Recording & Cost Optimisation

    25/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Compression Compression

    cost ()

    Normal

    Cost ()

    Direct

    Cost ()

    Indirect

    Cost ()

    Total

    Cost ()

    Duration

    (Days)

    Normal None 25,471 25,471 7,080 32,551 59

    First

    compression

    100 25,571 6,480 32,051 54

    Second

    Compression

    270 25,841 6,120 31,961 51

    ThirdCompression

    190 26,031 5,880 31,911 49

    Fourth

    Compression

    140 26,171 5,760 31,931 48

    Fifth

    Compression

    450 26,621 5,400 32,021 45

    Sixth

    Compression

    450 27,071 5,040 32,111 42

    In-direct cost are 120 per day. The optimum cost is 31,911 with a duration of 49 days

  • 7/27/2019 Progress Recording & Cost Optimisation

    26/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Summary

    Progress recording is an essential part ofcontrolling work in order to identify problems

    and initiate remedial action

    Recording progress can be carried out in

    connection with bar charts and networks

    Cost optimisation is a technique used to find

    the most economic way of carrying out a

    project in terms of time and cost

  • 7/27/2019 Progress Recording & Cost Optimisation

    27/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Activity

    The construction of part of a commercial development isrepresented by the activities shown in Table 1.

    Activity

    Reference Duration

    (weeks)

    Crash

    Duration

    (weeks)

    Cost

    ()

    Crash

    Cost

    ()

    A - B *

    A - CA - D

    B - C *

    B - F

    C - E *

    D - H

    E - H *F - G

    G - H

    14

    625

    17

    12

    14

    8

    811

    13

    11

    617

    15

    11

    12

    7

    710

    10

    7300

    910015100

    9100

    4100

    5600

    11100

    20007600

    2300

    7600

    910019100

    11100

    4600

    6300

    12100

    23008300

    2300

    * critical activities

  • 7/27/2019 Progress Recording & Cost Optimisation

    28/28

    project | control | progress recording | cost | acceleration | summary

    BSc (Hons)

    BUILDING CONSTRUCTION MANAGEMENT

    Activity

    The indirect costs associated with the development are 1700 perweek.

    1. Using cost optimisation techniques, determine the optimum

    duration and cost for the work.

    2. Describe three situations where cost optimisation techniques

    may be used in practice.