Progress Power Station Community Update 30 October 2017

Transcript of Progress Power Station - Drax

Page 1: Progress Power Station - Drax

Progress Power StationCommunity Update30 October 2017

Page 2: Progress Power Station - Drax

Agenda

Round of introductions / team updates

Quick overview – the project

Progress Power update July – October 2017

1. Drax update

1.1. Works and DCO requirements

1.2. Town & Country Planning Act application re. hedgerows

2. National Grid update

Progress Power key dates

Next steps

2

Page 3: Progress Power Station - Drax

Progress Power - work packages

(main plant, HV cable and gas pipeline)

3

Gas AGI

Main Plant

Gas pipeline corridor

Elec cable corridor

Temp new junction

Page 4: Progress Power Station - Drax

Progress Power - work packages cont’d

(Substation and access road)

4

GIS substation

Cable sealing end compound

Connection cabling

Page 5: Progress Power Station - Drax

DCO requirements & conditions

• DCO stipulates 23 requirements; they are effectively planning conditions

• Some of these must be met prior to commencement of work on site

• Drax is in process of discharging DCO requirements by submitting

documentation, plans and schemes to local authorities for approval

To name a few of these requirements:

• Landscaping and fencing plans – although final designs will be project -

specific

• Highways Access

• Surface water drainage – construction and operation

• Contaminated Land and Groundwater and Ecological Management Plan

• Archaeology

• Construction Environment Management Plan (CEMP) and Construction Traffic

Management Plan (CTMP)

5

Page 6: Progress Power Station - Drax

Current works on site – archaeology and

metal anomalies investigations

6

Page 7: Progress Power Station - Drax

Design changes to the main plant

(previous image)

7

Page 8: Progress Power Station - Drax

TCPA application – hedgerow removal

8

Page 9: Progress Power Station - Drax

National Grid update – substation timelines

Project Activities Date

Tender preparation Winter 2017

Tender Spring 2018

Contract Award June 2018

Commence Construction Spring 2019

Construction Period 18 months

Completion Summer 2020

9

Page 10: Progress Power Station - Drax

Substation DCO-approved Current design

layout

10

Page 11: Progress Power Station - Drax

MAP/ VIEW from South West

11

Page 12: Progress Power Station - Drax

NW

SW

12

Page 13: Progress Power Station - Drax

Substation and CSE profile and elevations

view from South West

13

Page 14: Progress Power Station - Drax

14

Substation profile and elevations - cont

Page 15: Progress Power Station - Drax

Profile and elevations contd. (CSEC)

15

Page 16: Progress Power Station - Drax

MAP/ VIEW from North West

16

Page 17: Progress Power Station - Drax

Substation profile and elevations

view from North West

17

Page 18: Progress Power Station - Drax

Substation indicative layout

18

Page 19: Progress Power Station - Drax

Example of similar existing GIS substation in

the UK

19

Page 20: Progress Power Station - Drax

Gas Connection layout

20

Page 21: Progress Power Station - Drax

PPL outline timetable & key decision dates

Progress Power Ltd Key Milestones When

Enter T-4 Capacity Auction 6 February 2018

Appoint contractors for all work packages End March 2018

Complete substation access road and grant NGET access to site 1 December 2018

Break ground / commence works on main site (Eye airfield) 1 December 2018

Complete hot commissioning and start commercial operation 1 October 2020

Note: Timeline subject to final contractor selection; only fixed date is Back feed Date which is set by NGC

21

Page 22: Progress Power Station - Drax

Progress Power next steps

Meeting SCC / MSDC on 31 October 2017

Metal anomalies and archaeology investigation November-December 2017

Discharging DCO requirements

Meet other requirements

• S106 obligations re. Education & Unemployment Scheme

• S106 obligations re. Local Services Scheme

• Community Benefit Fund agreement

Design Workshop January 2018

Capacity Market Auction February 2018

22

Page 23: Progress Power Station - Drax

Progress Power community benefit fund

Subject to CM award

Details on horizon and level of fund payments

Voting process

Selection of projects

Custodianship of funds

Administration

23