(Progress Invoice III)28 MAR

download (Progress Invoice III)28 MAR

of 28

Transcript of (Progress Invoice III)28 MAR

  • 8/12/2019 (Progress Invoice III)28 MAR

    1/28

    NCE

    Date :7 APR -08 wrt Weekly Report No.13

    Al NABA HADEED

    WEEKLY PROGRESS REPORT NO.13

    For

    Project : HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    Client : FLOUR

  • 8/12/2019 (Progress Invoice III)28 MAR

    2/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    A ENGINEERING & IFC

    Package 3

    E3 E3NL01 DDS of R F 2 - 10T GC, Wall Barrier & Conc.Pit 623 0.06% 3.06% 623.00 100.00% 623.00 100.00% 0.00 0.00

    E3 E3NL02 Rev & Appr R (A100 Gantrex) F,W B & CP 623 0.06% 3.06% 623.00 100.00% 623.00 100.00% 0.00 0.00

    E3 E3NL03 DDS of Asphalt Road 20 Ton Al 623 0.06% 3.06% 623.00 100.00% 623.00 100.00% 0.00 0.00

    E3 E3NL04 Rev & App of A R 20 Ton AL 623 0.06% 3.06% 623.00 100.00% 623.00 100.00% 0.00 0.00

    E3 E3XE05 DDS of Footing, GB & Pedestals of Steel Col. 624 0.06% 3.06% 624.00 100.00% 624.00 100.00% 0.00 0.00

    E3 E3XE06 Rev & Appr of Footing, GB&Pedestals of Steel Col 624 0.06% 3.06% 624.00 100.00% 624.00 100.00% 89.14 0.00

    E3 E3XE07 DDS of Steel Structure, Roof & Wall Sheetings 624 0.06% 3.06% 624.00 100.00% 624.00 100.00% 267.43 0.00E3 E3XE08 Rev & Appr of Steel Structure, Roof & Wall Sheet 624 0.06% 3.06% 530.40 85.00% 592.80 95.00% 445.71 62.40

    E3 E3XE09 DDS of Inter. Conc. Roads 40 T/sqm 624 0.06% 3.06% 530.40 85.00% 592.80 95.00% 624.00 62.40

    E3 E3XE10 Rev & Appr of Internal Conc. Roads 40T/sqm 624 0.06% 3.06% 468.00 75.00% 468.00 75.00% 624.00 0.00

    TOTAL OF ENGINEERING & IFC Package 3 6,236 0.62% 30.61% 5,893 28.93% 6,018 29.54% 2,050 124.80

    Package 1

    E1 E1BW01 DDS of Substructure 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 0.00 0.00

    E1 E1BW02 Rev & Appr of Substructure 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 0.00 0.00

    E1 E1BW03 DDS of Supper Structure 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 0.00 0.00

    E1 E1BW04 Rev & App of Supper Structure 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 0.00 0.00E1 E1BW05 DDS of Arch 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 0.00 0.00

    E1 E1BW06 Rev & Appr of Arch 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 13.86 0.00

    E1 E1BW07 DDS of Plumbing & Sanitary 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 55.43 0.00

    E1 E1BW08 Rev & Appr of Plumbing & Sanitary 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 194.00 0.00

    E1 E1BW09 DDS of Electrical(W/Panel Board Design) 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 235.57 0.00

    E1 E1BW10 Rev & Appr of Electrical (W/Panel Board Design) 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 374.14 0.00

    E1 E1BW11 DDS of HVAC( w/ Load Analysis & Design) 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 415.71 0.00

    E1 E1BW12 Rev & Appr of HVAC(w/ Load Analysis & D) 485 0.05% 2.38% 388.00 80.00% 485.00 100.00% 485.00 97.00

    E1 E1BW13 DDS of Fire Fighting & Detection System (cp) 485 0.05% 2.38% 0.00 0.00% 48.50 10.00% 485.00 48.50

    E1 E1BW14 Rev & Appr of Fire Fighting & Detection System 485 0.05% 2.38% 0.00 0.00% 0.00 0.00% 485.00 0.00

    E1 E1BW15 DDS of Tele Comm & Data System (Panel Board) 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 457.29 0.00

    E1 E1BW16 Rev & Appr of Tele Comm & Data System 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 318.71 0.00

    E1 E1SR17 DDS of Siren Room 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 277.14 0.00

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly Prog

    Evaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

  • 8/12/2019 (Progress Invoice III)28 MAR

    3/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly P

    Evaluat

    Actual % Progress Against Item

    Cummulative this monthCummulative last month

    wrt Weekly Re

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    E1 E1SR18 Rev & Appr of Siren Room 485 0.05% 2.38% 485.00 100.00% 485.00 100.00% 180.14 0.00E1 E1SR19 DDS of Siren System 485 0.05% 2.38% 412.25000 85.00% 485.00 100.00% 138.57 72.7500

    E1 E1SR20 Rev & Appr of Siren System 485 0.05% 2.38% 0.00 0.00% 0.00 0.00% 27.71 0.00

    TOTAL OF ENGINEERING & IFC Package 1 9,700 0.97% 47.62% 8,075 39.64% 8,293.5 40.71% 4,143 218.25

    Package 2

    E2 E2IR01 DDS of ALL Asphalt Conc. Roads w/ 20 ton AL 554 0.06% 2.72% 554.00 100.00% 554.00 100.00% 0.00 0.00

    E2 E2IR02 Rev & Appr of All Asphalt Conc. Roads w/ 20ton AL 554 0.06% 2.72% 498.60 90.00% 498.60 90.00% 0.00 0.00

    E2 E2IR03 DDS of H1&2 Asphalt Conc. Roads w/ 50 ton AL 554 0.06% 2.72% 554.00 100.00% 554.00 100.00% 0.00 0.00

    E2 E2IR04 Rev & Appr of H12Asphalt Conc. Roads w/ 50ton AL 554 0.06% 2.72% 554.00 100.00% 554.00 100.00% 79.14 0.00

    E2 E2IR05 Sub. of Traffic Signal System ( Cat. & Sample) 554 0.06% 2.72% 554.00 100.00% 554.00 100.00%

    237.43 0.00

    E2 E2IR06 Rev & App of Traffic Signal System(Cat & Sample) 554 0.06% 2.72% 470.90 85.00% 554.00 100.00% 395.71 83.10

    E2 E2IR07 Sub.of Street & High Mast Lighting(Cat.& Sample) 555 0.06% 2.72% 555.00 100.00% 555.00 100.00% 555.00 0.00

    E2 E2IR08 Rev & Appr Street & High Mast Lighting 555 0.06% 2.72% 555.00 100.00% 555.00 100.00% 555.00 0.00

    TOTAL OF ENGINEERING & IFC Package 2 4,434 0.44% 21.77% 4,296 21.09% 4,379 21.50% 1,822 83.10

    20,370 2.04% 100.00% 18263.55 89.66% 18689.70 91.75% 8015.83 426.15TOTAL OF ENGINEERING & IFC

  • 8/12/2019 (Progress Invoice III)28 MAR

    4/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProgrEvaluation

    Actual % Progress Against Item

    ReCummulative this monthCummulative last month

    wrt Weekly Report

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    BMobilization

    MO MO20 Processing of ID's & Permits 2,079 0.21% 0.84% 1975.05 95.00% 2079.00 100.00% 693.00 103.95

    MO MO30 Site Development 2,079 0.21% 0.84% 2079.00 100.00% 2079.00 100.00% 0.00 0.00

    MO MO40 Site Office 2,079 0.21% 0.84% 2079.00 100.00% 2079.00 100.00% 0.00 0.00

    MO MO50 Warehouse 2,079 0.21% 0.84% 2079.00 100.00% 2079.00 100.00% 0.00 0.00

    MO MO60 Fabrication Shop 1,731 0.17% 0.70% 1731.00 100.00% 1731.00 100.00% 86.55 0.00

    MO MO70 Fence & Gate 2,079 0.21% 0.84% 2079.00 100.00% 2079.00 100.00% 831.60 0.00

    MO MO80 Water Tank, Electrical & Plumbing net work 1,600 0.16% 0.65% 1600.00 100.00% 1600.00 100.00% 1200.00 0.00

    TOTAL OF Mobilization 13,726 1.37% 5.56% 13,622.05 5.52% 13,726.00 5.56% 2,811.15 103.95

    Procurment Package 3

    P3 P3NL01 Steel Rail A 100 GANTREX (Lead after PO) 693 0.07% 0.28% 693.00 100.00% 693.00 100.00% 247.50 0.00

    P3 P3NL02 Delivery of Rail A 100 GANTREX 6,929 0.69% 2.81% 1385.80 20.00% 6236.10 90.00% 6929.00 4850.30

    P3 P3NL03 Steel CP S and Perf Cab T (Lead after PO) 139 0.01% 0.06% 69.50 50.00% 111.20 80.00% 105.64 41.70

    P3 P3NL04 Delivery of cp s and Perforated Cable Tray 1,386 0.14% 0.56% 0.00 0.00% 0.00 0.00% 0.00 0.00

    P3 P3NL05 Steel Structure Roof & Wall Sheeting ( LPO) 9,560 0.96% 3.87% 8126.00 85.00% 9560.00 100.00% 4693.09 1434.00

    P3 P3NL06 Delivery of Steel Structure , Roof & Wall Sheet 83,142 8.31% 33.68% 0.00 0.00% 0.00 0.00% 0.00 0.00

    P3 P3NL07 Over Head Traveling Crane Rail (Lead after PO) 4,157 0.42% 1.68% 3117.75 75.00% 4157.00 100.00% 1870.65 1039.25

    P3 P3NL08 Delivery of Over Head Traveling Crane Rail 24,943 2.49% 10.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TOTAL OF Procurment Package 3 130,949 13.09% 53.04% 13,392.05 5.42% 20,757.30 8.41% 13,845.88 7,365.25Procurment Package 1

    P1 P1BW01 Doors & Win(Alum.), 90mfr & Wd Lead after PO) 139 0.01% 0.06% 83.40 60.00% 104.25 75.00% 61.16 20.85

    P1 P1BW02 Delivery of Doors & Windows 1,386 0.14% 0.56% 0.00 0.00% 0.00 0.00% 0.00 0.00

    P1 P1BW03 Building Internal & External Paint Lead after PO 139 0.01% 0.06% 41.70 30.00% 104.25 75.00% 54.21 62.55

    P1 P1BW04 Delivery of Internal and External Paint 1,386 0.14% 0.56% 0.00 0.00% 0.00 0.00% 0.00 0.00

    P1 P1BW05 Plumbing Fixers and Accessories Lead after PO) 139 0.01% 0.06% 41.70 30.00% 104.25 75.00% 47.26 62.55

    P1 P1BW06 Delivery of Plumbing Fixtures and Accessories 2,079 0.21% 0.84% 0.00 0.00% 0.00 0.00% 100.19 0.00

    P1 P1BW07 Electrical Material Panel Board & Breakers) 139 0.01% 0.06% 104.25 75.00% 125.10 90.00% 47.26 20.85

    P1 P1BW08 Delivery of Electrical Material Panel Board 13,857 1.39% 5.61% 0.00 0.00% 6928.50 50.00% 615.87 6928.50

    P1 P1BW09 Fire & Gas Detection and Supprs( Lead after PO) 277 0.03% 0.11% 0.00 0.00% 138.50 50.00% 80.33 138.50

    P1 P1BW10 Delivery of fire system 11,086 1.11% 4.49% 0.00 0.00% 0.00 0.00% 0.00 0.00

    P1 P1BW11 Telecommunication System (Lead after PO ) 139 0.01% 0.06% 48.65 35.00% 104.25 75.00% 33.36 55.60

    P1 P1BW12 Delivery of Telecommunication System 11,086 1.11% 4.49% 0.00 0.00% 0.00 0.00% 0.00 0.00

    MOBILIZATION / PROCURMENT / DEMOBILIZATION

  • 8/12/2019 (Progress Invoice III)28 MAR

    5/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProEvaluatio

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repo

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    P1 P1BW13 HVAC ( Lead after PO) 249 0.02% 0.10% 149.40 60.00% 211.65 85.00% 56.03 62.25P1 P1BW14 Delivery of HVAC units to site 15,240 1.52% 6.17% 0.00 0.00% 0.00 0.00% 0.00 0.00

    P1 P1BW15 Floor & Wall Tiles 346 0.03% 0.14% 86.50 25.00% 259.50 75.00% 100.34 173.00

    P1 P1BW16 Delivery of Floor & Wall Tiles 3,464 0.35% 1.40% 0.00 0.00% 0.00 0.00% 0.00 0.00

    P1 P1BW17 Counter Tops 139 0.01% 0.06% 0.00 0.00% 0.00 0.00% 33.36 0.00

    P1 P1BW18 Delivery of Counter Tops 1,386 0.14% 0.56% 0.00 0.00% 0.00 0.00% 0.00 0.00

    P1 P1BW19 Access Stairs & Monkey Cage Ladder 28 0.00% 0.01% 12.60 45.00% 21.00 75.00% 5.32 8.40

    P1 P1BW20 Delivery of Access stairs and Monkey Cage Ladder 346 0.03% 0.14% 0.00 0.00% 0.00 0.00% 0.00 0.00

    P1 P1BW21 Office & Pantry room Cabinets 139 0.01% 0.06% 0.00 0.00% 0.00 0.00% 19.46 0.00

    P1 P1BW22 Delivery of Office & Pantry Room Cabinets 1,386 0.14% 0.56% 0.00 0.00% 0.00 0.00% 0.00 0.00

    P1 P1BW23 Siren System (Lead after PO #) 277 0.03% 0.11% 249.30 90.00% 277.00 100.00% 24.93 27.70

    P1 P1BW24 Delivery of Siren System 2,771 0.28% 1.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    P1 P1BW25 Roof Membrane System & Concrete Pavers Lead after 693 0.07% 0.28% 277.20 40.00% 519.75 75.00% 92.40 242.55

    P1 P1BW26 Delivery of Roof Member system 6,929 0.69% 2.81% 0.00 0.00% 0.00 0.00% 0.00 0.00

    P1 P1BW27 Acoustic Mineral Fiber/Water Resistant F.Ceiling 277 0.03% 0.11% 96.95 35.00% 207.75 75.00% 0.00 110.80

    P1 P1BW28 Delivery of Acoustic Mineral 2,077 0.21% 0.84% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TOTAL OF Procurment Package 1 77,599 7.76% 31.43% 1,191.65 0.48% 9,105.75 3.69% 1,371.48 7,914.10

    Procurment Package 2

    P2 P2IR01 Traffic Signal System ( Lead after PO) 208 0.02% 0.08% 104.00 50.00% 208.00 100.00% 0.00 104.00

    P2 P2IR02 Delivery of Traffic Signal System 2,217 0.22% 0.90% 0.00 0.00% 0.00 0.00% 0.00 0.00P2 P2IR03 Street &High Mast Lighting (Lead after PO) 1,386 0.14% 0.56% 693.00 50.00% 1247.40 90.00% 0.00 554.40

    P2 P2IR04 Delivery of Street & High Mast Lighting 13,857 1.39% 5.61% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TOTAL OF Procurment Package 3 17,668 1.77% 7.16% 797.00 0.32% 1,455.40 0.59% 0.00 658.40

    TOTAL OF Procurment 226,216 22.62% 91.63% 15,380.70 6.23% 31,318.45 12.69% 15,217.36 15,937.75

    DM DM00 Demobilization 6,928 0.69% 2.81% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TOTAL OF MOB,PRO & DEMOB 246,870 24.69% 100.00% 29,002.75 11.75% 45,044.45 18.25% 18,028.51 16,041.70

  • 8/12/2019 (Progress Invoice III)28 MAR

    6/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProgEvaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C C 3 Storages

    C 3N New & Rod Coil Storage

    C3N C3N01 Preliminary Site Clearing and Leveling 277 0.03% 0.08% 277.00 100.00% 277.00 100.00% 0.00 0.00

    C3N C3N02 Soil Investigation & Submittal of Reports 693 0.07% 0.20% 693.00 100.00% 693.00 100.00% 0.00 0.00

    C3N C3N03 Survey & Layout Marking 693 0.07% 0.20% 693.00 100.00% 693.00 100.00% 0.00 0.00

    C3N C3N04 Excavation for footing( Conc. Pit, R F & Wall B) 693 0.07% 0.20% 0.00 0.00% 623.70 90.00% 110.88 623.70

    C3N C3N05 Compaction and FDT for Footing 693 0.07% 0.20% 0.00 0.00% 346.50 50.00% 249.48 346.50

    C3N C3N06 Form & Pouring of Lean concrete for Footing 970 0.10% 0.28% 0.00 0.00% 485.00 50.00% 543.20 485.00

    C3N C3N07 Form, Rebars & Pouring of Footing up to 0.0 EL 4,850 0.49% 1.39% 0.00 0.00% 970.00 20.00% 4018.57 970.00

    C3N C3N08 Form,Rebar& Pouring of RF & W B above 0.0 EL 4,850 0.49% 1.39% 0.00 0.00% 0.00 0.00% 4850.00 0.00

    C3N C3N09 Water Proofing of Foundation 1,386 0.14% 0.40% 0.00 0.00% 0.00 0.00% 1386.00 0.00

    C3N C3N10 Installation of A 100 GANTREX Rail 14,132 1.41% 4.06% 0.00 0.00% 0.00 0.00% 10498.06 0.00

    C3N C3N11 Laying of Marl Base , Comp & FDTs for Asphalt R 1,386 0.14% 0.40% 0.00 0.00% 0.00 0.00% 727.65 0.00

    C3N C3N12 Laying and compaction of Asphalt Concrete 20 T AL 4,850 0.49% 1.39% 0.00 0.00% 0.00 0.00% 1552.00 0.00

    C3N C3N13 Laying of Marl Base , Comp & FDTs for Storage A 1,386 0.14% 0.40% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3N C3N14 Steel Cover Plate& Perforated Cable Tray along F 1,386 0.14% 0.40% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3N C3N15 Electrical U/G conduting cable pulling 970 0.10% 0.28% 0.00 0.00% 0.00 0.00% 970.00 0.00

    C3N C3N16 Panel Board Installation & Termination 970 0.10% 0.28% 0.00 0.00% 0.00 0.00% 970.00 0.00

    TOTAL OF New & Rod Coil Storage 40,185 4.02% 11.55% 1,663.00 0.48% 4,088.20 1.18% 25,875.84 2,425.20C 3L LPF New Coil Storage

    C3L C3L01 Preliminary Site Clearing and Leveling 277 0.03% 0.08% 277.00 100.00% 277.00 100.00% 0.00 0.00

    C3L C3L02 Soil Investigation & Submittal of Reports 970 0.10% 0.28% 970.00 100.00% 970.00 100.00% 0.00 0.00

    C3L C3L03 Survey & Layout Marking 970 0.10% 0.28% 970.00 100.00% 970.00 100.00% 0.00 0.00

    C3L C3L04 Excavation for footing( Conc. Pit, R F & Wall B) 970 0.10% 0.28% 679.00 70.00% 679.00 70.00% 970.00 0.00

    C3L C3L05 Compaction and FDT for Footing 1,386 0.14% 0.40% 1316.70 95.00% 1316.70 95.00% 1386.00 0.00

    C3L C3L06 Form & Pouring of Lean concrete for Footing 1,386 0.14% 0.40% 1178.10 85.00% 1178.10 85.00% 1386.00 0.00

    C3L C3L07 Form, Rebars & Pouring of Footing up to 0.0 EL 5,125 0.51% 1.47% 4356.25 85.00% 4612.50 90.00% 4392.86 256.25

    C3L C3L08 Form,Rebar& Pouring of RF & W B above 0.0 EL 5,542 0.55% 1.59% 2771.00 50.00% 3602.30 65.00% 2519.09 831.30

    C3L C3L09 Water Proofing of Foundation 1,386 0.14% 0.40% 0.00 0.00% 693.00 50.00% 308.00 693.00

    C3L C3L10 Installation of A 100 GANTREX Rail 20,786 2.08% 5.98% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3L C3L11 Exca, Comp & Install of Curb Stone for C.Aisle 6,929 0.69% 1.99% 0.00 0.00% 0.00 0.00% 0.00 0.00

    CONSTRUCTION

  • 8/12/2019 (Progress Invoice III)28 MAR

    7/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProgEvaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C3L C3L12 Const. of Pedestal for Street Lights in C.Aisle 6,929 0.69% 1.99% 0.00 0.00% 0.00 0.00% 0.00 0.00C3L C3L13 Laying of Marl Base , Comp & FDTs for Asphalt R 6,929 0.69% 1.99% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3L C3L14 Laying and compaction of Asphalt Concrete 20T AL 13,855 1.39% 3.98% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3L C3L15 Laying of Marl Base , Comp & FDTs for Storage A 6,929 0.69% 1.99% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3L C3L16 Steel Cover Plate& Perforated Cable Tray along F 6,929 0.69% 1.99% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3L C3L17 Filling of Central Aisle with Marl base 6,929 0.69% 1.99% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3L C3L18 Electrical U/G conduting cable pulling 1,386 0.14% 0.40% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3L C3L19 Panel Board Installation & Termination 1,386 0.14% 0.40% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TOTAL OF LPF New Coil Storage 96,999 9.70% 27.89% 12,518.05 3.60% 14,298.60 4.11% 10,961.95 1,780.55

    C 3E Extention of Existing storage Steel Building

    C3E C3E01 Preliminary Site Clearing and Leveling 692 0.07% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E02 Soil Investigation & Submittal of Reports 693 0.07% 0.20% 693.00 100.00% 693.00 100.00% 0.00 0.00

    C3E C3E03 Survey & Layout Marking 693 0.07% 0.20% 0.00 0.00% 693.00 100.00% 0.00 693.00

    C3E C3E04 Excavation for footing(of the Steel Columns) 693 0.07% 0.20% 0.00 0.00% 0.00 0.00% 381.15 0.00

    C3E C3E05 Compaction and FDT for Footing 693 0.07% 0.20% 0.00 0.00% 0.00 0.00% 567.00 0.00

    C3E C3E06 Demolition of Steel Frame & Cladding 2,770 0.28% 0.80% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E07 Form & Pouring of Lean concrete for Footing 693 0.07% 0.20% 0.00 0.00% 0.00 0.00% 693.00 0.00

    C3E C3E08 Form, Rebars & Pouring of Footing below GB 693 0.07% 0.20% 0.00 0.00% 0.00 0.00% 498.96 0.00

    C3E C3E09 Water proofing of F & Backfilling comp for GB 693 0.07% 0.20% 0.00 0.00% 0.00 0.00% 363.83 0.00

    C3E C3E10 Form & Pouring Lean conc. of GB 693 0.07% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00C3E C3E11 Form, Rebars & Pouring of GB & Footing 6,929 0.69% 1.99% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E12 Form, Rebars & Pouring of Pedestals W/ GIB for C 6,929 0.69% 1.99% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E13 Water Proofing of GB & F 693 0.07% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E14 Laying of Marl Base , Comp & FDTs for Intr Roads 1,386 0.14% 0.40% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E15 Form, Rebar & Con Pour of Internal Roads 40T/sqm 6,929 0.69% 1.99% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E16 Erection of Steel Columns 69,285 6.93% 19.92% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E17 Installation of Rafter , Purling & Tie Rods 69,285 6.93% 19.92% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E18 Extension of Over Head Traveling Crane Rails 1,386 0.14% 0.40% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E19 Construction of CMU in Building Perimeter 2,770 0.28% 0.80% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E20 Plastering & Painting of CMU 1,386 0.14% 0.40% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E21 Installation of Roof Sheet w/p for Ventilation 13,857 1.39% 3.98% 0.00 0.00% 0.00 0.00% 0.00 0.00

  • 8/12/2019 (Progress Invoice III)28 MAR

    8/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthl

    Eva

    Actual % Progress Against Item

    Cummulative this monthCummulative last month

    wrt Weekly

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C3E C3E22 Installation of Wall Cladding 13,857 1.39% 3.98% 0.00 0.00% 0.00 0.00% 0.00 0.00C3E C3E23 Laying of Marl Base , Comp & FDTs for Storage A 1,386 0.14% 0.40% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E24 Extension of Steel Stock Fence 1,386 0.14% 0.40% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E25 Construction of Access roads 2,770 0.28% 0.80% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E26 Electrical conduting,Wire pulling & switches 693 0.07% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C3E C3E27 Panel Board Installation & Termination 693 0.07% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TOTAL OF Extention of Existing storage Steel Building 210,626 21.06% 60.56% 693.00 0.20% 1,386.00 0.40% 2,503.94 693.00

    TOTAL OF ALL STORAGES 347,810 34.78% 100.00% 14,874.05 4.28% 19,772.80 5.68% 39,341.73 4,898.75

    47.47% 2.03% 2.70%

  • 8/12/2019 (Progress Invoice III)28 MAR

    9/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProgEvaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C 1 Buildings & WorkshopsC 1B Building G+2, Workshop & External work

    Building G+2

    C1B C1BC01 Site Preparation Survey and Marking 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 0.00 0.00

    C1B C1BC02 Relocation of (T, F & other Utilities) 485 0.05% 0.29% 485.00 100.00% 485.00 100.00% 0.00 0.00

    C1B C1BC03 Excavation 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 0.00 0.00

    C1B C1BC04 Compaction and FDT 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 55.20 0.00

    C1B C1BC05 Survey and marking 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 69.00 0.00

    C1B C1BC06 Form & Pour Lean Concrete for footing 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 69.00 0.00

    C1B C1BC07 Re-Bars,Form & Pour Concrete for the Footing 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 69.00 0.00

    C1B C1BC08 Form & Pour Concrete of the Col below Grade Beam 206 0.02% 0.12% 206.00 100.00% 206.00 100.00% 206.00 0.00

    C1B C1BC09 Waterproofing & Backfilling below Grade Beam 69 0.01% 0.04% 55.20 80.00% 69.00 100.00% 69.00 13.80

    C1B C1BC10 Form & Pour Lean conc for GB 139 0.01% 0.08% 0.00 0.00% 139.00 100.00% 139.00 139.00

    C1B C1BC11 Re-Bars,Form &pour Conc for GB 166 0.02% 0.10% 0.00 0.00% 166.00 100.00% 166.00 166.00

    C1B C1BC12 Waterproofing & Backfilling below Grade slab 69 0.01% 0.04% 0.00 0.00% 41.40 60.00% 69.00 41.40

    C1B C1BC13 ReBar &Pour of Grade Slab 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 208.00 0.00

    C1B C1BC14 Ground Floor Columns 208 0.02% 0.12% 0.00 0.00% 62.40 30.00% 29.71 62.40

    C1B C1BC15 First Floor Slab with Sleeves of Sant,Plub&Elec 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BC16 First Floor Columns 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00C1B C1BC17 Second Floor Slab with Sleeves of Sant,Plub&Elec 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BC18 Second Floor columns 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BC21 Roof Slab 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Civil Wok 3,556 0.36% 2.10% 1,160.20 0.69% 1,582.80 0.94% 1,148.91 422.60

    C1B C1BA01 Reinforced External CMU w/Parapet wall & coping 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA02 Reinforce internal CMU 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA03 Internal Plastering 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA04 Gypsum Board Partition Dry Wall 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA05 Internal painting 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA06 Install ext Aluminum D & W 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA07 Install of int Wooden doors 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA08 Install 90m fr sp doors for Em & Ut 21 0.00% 0.01% 0.00 0.00% 0.00 0.00% 0.00 0.00

  • 8/12/2019 (Progress Invoice III)28 MAR

    10/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProgEvaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C1B C1BA09 Install Ceiling Grid & False Ceiling 277 0.03% 0.16% 0.00 0.00% 0.00 0.00%

    0.00 0.00

    C1B C1BA10 Unglazed floor tiles for offices, aisles & toilet 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA11 Glazed wall tiles for Toilet Walls 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA12 Epoxy Paint of HVAC 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA13 External plastering 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA14 External Painting 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA15 Roof Water Proofing 485 0.05% 0.29% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA16 Arch Cab & Hardware for Offices & Pantry 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BA17 Installation of Synthetic Gr Mar Counter Tops 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Arch Work 3,818 0.38% 2.26% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BP01 Installation of Potable water line 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BP02 Installation of Sanitary pipe line 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BP03 Installation of Sanitary fittings 159 0.02% 0.09% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Plumbing Work for G2 & Work Shop 437 0.04% 0.26% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BL01 Installation of Conduits 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BL02 Wire and Cable Pulling (Elec,Fire,HVAC& cat 6 ) 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BL03 Installation of Switches and Sockets 69 0.01% 0.04% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BL04 Installation of Lighting Fixtures 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BL05 Installation of Panel Boards 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Electrical Work for G2 & Work Shop 832 0.08% 0.49% 0.00 0.00% 0.00 0.00% 0.00 0.00C1B C1BH01 HVAC ducting 13,857 1.39% 8.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BH02 Insulation of Ducts 6,929 0.69% 4.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BH03 Installation HVAC units 27,714 2.77% 16.39% 0.00 0.00% 0.00 0.00% 0.00 0.00

    HVAC Work for G2 & Work Shop 48,500 4.85% 28.69% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BF01 Installation of Detectors 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BF02 Installation of Fire Alarm System 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BF03 Installation of Fighting System fire wl f H c) 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BF04 Installation of Fire Alarm Control Panels 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Fire Fighting & Detection System for G2 & Work Shop 1,803 0.18% 1.07% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BT01 Installation of Telecom & Data Panels 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Telecom & Data System for G2 & Work Shop 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BO01 Electrical System 416 0.04% 0.25% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BO11 HVAC System 416 0.04% 0.25% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BO21 Fire Fighting & Alarm System 416 0.04% 0.25% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BO31 Telecom & Data System 416 0.04% 0.25% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Testing & Commissioning 1,664 0.17% 0.98% 0.00 0.00% 0.00 0.00% 0.00 0.00

  • 8/12/2019 (Progress Invoice III)28 MAR

    11/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProgEvaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    TOTAL OF Building G+2 60,776 6.08% 35.95% 1,160.20 0.69% 1,582.80 0.94% 1,148.91 422.60

    Workshop

    C1B C1BW01 Preliminary Site Clearing and Leveling 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 0.00 0.00

    C1B C1BW02 Soil Investigation & Submittal of Reports 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 0.00 0.00

    C1B C1BW03 Survey & Layout Marking 69 0.01% 0.04% 55.20 80.00% 69.00 100.00% 0.00 13.80

    C1B C1BW04 Excavation for footing of the Steel Columns) 69 0.01% 0.04% 34.50 50.00% 62.10 90.00% 62.10 27.60

    C1B C1BW05 Compaction and FDT for Footing 139 0.01% 0.08% 0.00 0.00% 125.10 90.00% 139.00 125.10

    C1B C1BW06 Form & Pouring of Lean concrete for Footing 139 0.01% 0.08% 0.00 0.00% 125.10 90.00% 139.00 125.10

    C1B C1BW07 Form, Rebars & Pouring of Footing below GB 277 0.03% 0.16% 0.00 0.00% 249.30 90.00% 277.00 249.30

    C1B C1BW08 Water proofing of F & Backfilling comp for GB 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 277.00 0.00

    C1B C1BW09 Form & Pouring Lean conc. of GB 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 138.50 0.00

    C1B C1BW10 Form, Rebars & Pouring of GB & Footing 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BW11 Form, Rebars & Pouring of Pedestals W/ GIB for C 28 0.00% 0.02% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BW12 Water Proofing of GB & F 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BW13 Backfilling , Comp & FDTs for Grade slab 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BW14 Form, Rebar & Con Pour of Grade slab 14 0.00% 0.01% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BW15 Erection of Steel Columns 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BW16 Installation of Rafter , Purling & Tie Rods 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BW17 Final paint of Steel Structure 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BW18 Construction of CMU in Building Perimeter 2,079 0.21% 1.23% 0.00 0.00% 0.00 0.00% 0.00 0.00C1B C1BW19 Plastering & Painting of CMU 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BW20 Installation of Roof Sheet w/p for Ventilation 10,393 1.04% 6.15% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BW21 Installation of Wall Cladding 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BW22 Installation of Roll up shutters 2,771 0.28% 1.64% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Workshop 21,106 2.11% 12.48% 227.70 0.13% 768.60 0.45% 1,032.60 540.90

    External works

    C1B C1BE01 Emergency Access Stair & Monkey Ladder 12,471 1.25% 7.38% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BE02 Construction of Access Platforms 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BE03 Walk way w/Inter Locking conc. Paving Blocks 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BE04 6 Car Covered Parking 111 0.01% 0.07% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1B C1BE05 Green area with Grass and Irrigation system 443 0.04% 0.26% 0.00 0.00% 0.00 0.00% 0.00 0.00

    External works 13,330 1.33% 7.88% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TOTAL OF Building G+2, Workshop & External work 95,212 9.52% 56.32% 1,387.90 0.82% 2,351.40 1.39% 2,181.51 963.50

  • 8/12/2019 (Progress Invoice III)28 MAR

    12/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProgEvaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C 1S Scrap Handling Office G+1, TSD work Shop & External works

    Scrap Handling office G+1

    C1S C1SC01 Site Preparation Survey and Marking 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 69.00 0.00

    C1S C1SC02 Relocation of (T, F & other Utilities) 69 0.01% 0.04% 34.50 50.00% 34.50 50.00% 69.00 0.00

    C1S C1SC03 Excavation 69 0.01% 0.04% 6.90 10.00% 69.00 100.00% 69.00 62.10

    C1S C1SC04 Compaction and FDT 69 0.01% 0.04% 0.00 0.00% 69.00 100.00% 69.00 69.00

    C1S C1SC05 Survey and marking 69 0.01% 0.04% 0.00 0.00% 69.00 100.00% 69.00 69.00

    C1S C1SC06 Form & Pour Lean Concrete for footing 139 0.01% 0.08% 0.00 0.00% 139.00 100.00% 139.00 139.00

    C1S C1SC07 Re-Bars,Form & Pour Concrete for the Footing 275 0.03% 0.16% 0.00 0.00% 0.00 0.00% 275.00 0.00

    C1S C1SC08 Form & Pour Concrete of the Col below Grade Beam 69 0.01% 0.04% 0.00 0.00% 0.00 0.00% 69.00 0.00

    C1S C1SC09 Waterproofing & Backfilling below Grade Beam 69 0.01% 0.04% 0.00 0.00% 0.00 0.00% 69.00 0.00

    C1S C1SC10 Form & Pour Lean conc for GB 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 139.00 0.00

    C1S C1SC11 Re-Bars,Form &pour Conc for GB 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 81.08 0.00

    C1S C1SC12 Waterproofing & Backfilling below Grade slab 69 0.01% 0.04% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SC13 ReBar &Pour of Grade Slab 344 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SC14 Ground Floor Columns 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SC15 First Floor Slab with Sleeves of Sant,Plub&Elec 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SC16 First Floor Columns 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SC19 Roof Slab 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Civil Wok 4,360 0.44% 2.58% 110.40 0.07% 449.50 0.27% 1,117.08 339.10C1S C1SA01 Reinforced External CMU w/Parapet wall & coping 416 0.04% 0.25% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA02 Reinforce internal CMU 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA03 Internal Plastering 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA04 Gypsum Board Partition Dry Wall 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA05 Internal painting 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA06 Install ext Aluminum D & W 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA07 Install of int Wooden doors 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA08 Install 90m fr sp doors for Em & Ut 69 0.01% 0.04% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA09 Install Ceiling Grid & False Ceiling 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA10 Unglazed floor tiles for offices,aisles & toilet 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA11 Glazed wall tiles for Toilet Walls 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA12 Epoxy Paint of HVAC 69 0.01% 0.04% 0.00 0.00% 0.00 0.00% 0.00 0.00

  • 8/12/2019 (Progress Invoice III)28 MAR

    13/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProgEvaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C1S C1SA13 External plastering 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA14 External Painting 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA15 Roof Water Proofing 416 0.04% 0.25% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA16 Arch Cab & Hardware for Offices & Pantry 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SA17 Installation of Synthetic Gr Mar Counter Tops 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Arch Work 3,883 0.39% 2.30% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SP01 Installation of Potable water line 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SP02 Installation of Sanitary pipe line 69 0.01% 0.04% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SP03 Installation of Sanitary fittings 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Plumbing Work for G1 & Work Shop 1,039 0.10% 0.61% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SL01 Installation of Conduits 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SL02 Wire and Cable Pulling (Elec,Fire,HVAC& cat 6 ) 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SL03 Installation of Switches and Sockets 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SL04 Installation of Lighting Fixtures 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SL05 Installation of Panel Boards 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Electrical Work for G1 & Work Shop 1,801 0.18% 1.07% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SH01 HVAC ducting 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SH02 Insulation of Ducts 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SH03 Installation HVAC units 2,079 0.21% 1.23% 0.00 0.00% 0.00 0.00% 0.00 0.00

    HVAC Work for G1 & Work Shop 3,049 0.30% 1.80% 0.00 0.00% 0.00 0.00% 0.00 0.00C1S C1SF01 Installation of Detectors 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SF02 Installation of Fire Alarm System 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SF03 Installation of Fighting System(fire wl f H c) 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SF04 Installation of Fire Alarm Control Panels 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Fire Fighting & Detection System for G1 & Work Shop 1,872 0.19% 1.11% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1ST01 Installation of Telecom & Data Panels 1,663 0.17% 0.98% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Telecom & Data System for G1 & Work Shop 1,663 0.17% 0.98% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SO01 Electrical System 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SO11 HVAC System 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SO21 Fire Fighting & Alarm System 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SO31 Telecom & Data System 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Testing & Commissioning 1,108 0.11% 0.66% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TOTAL OF Scrap Handling office G+1 18,775 1.88% 11.11% 110.40 0.07% 449.50 0.27% 1,117.08 339.10

  • 8/12/2019 (Progress Invoice III)28 MAR

    14/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProgEvaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    TSD work Shop

    C1S C1SW01 Preliminary Site Clearing and Leveling 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 69.00 0.00

    C1S C1SW02 Soil Investigation & Submittal of Reports 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 69.00 0.00

    C1S C1SW03 Survey & Layout Marking 69 0.01% 0.04% 65.55 95.00% 69.00 100.00% 69.00 3.45

    C1S C1SW04 Excavation for footing(of the Steel Columns) 69 0.01% 0.04% 0.00 0.00% 69.00 100.00% 69.00 69.00

    C1S C1SW05 Compaction and FDT for Footing 69 0.01% 0.04% 0.00 0.00% 69.00 100.00% 69.00 69.00

    C1S C1SW06 Form & Pouring of Lean concrete for Footing 139 0.01% 0.08% 0.00 0.00% 139.00 100.00% 139.00 139.00

    C1S C1SW07 Form, Rebars & Pouring of Footing below GB 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 24.71 0.00

    C1S C1SW08 Water proofing of F & Backfilling comp for GB 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SW09 Form & Pouring Lean conc. of GB 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SW10 Form, Rebars & Pouring of GB & Footing 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00C1S C1SW11 Form, Rebars & Pouring of Pedestals W/ GIB for C 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SW12 Water Proofing of GB & F 69 0.01% 0.04% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SW13 Backfilling , Comp & FDTs for Grade slab 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SW14 Form, Rebar & Con Pour of Grade slab 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SW15 Dismantling of exiting ware H (sheets, steel ) 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SW16 Erection of Steel Columns 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SW17 Installation of Rafter , Purling & Tie Rods 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SW18 Final paint of Steel Structure 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SW19 Construction of CMU in Building Perimeter 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00C1S C1SW20 Plastering & Painting of CMU 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SW21 Installation of Roof Sheet w/p for Ventilation 2,079 0.21% 1.23% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SW22 Installation of Wall Cladding 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SW23 Installation of Roll up shutters 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TSD work Shop 11,365 1.14% 6.72% 203.55 0.12% 484.00 0.29% 508.71 280.45

    External works

    C1S C1SE01 Emergency Access Stair & Monkey Ladder 69 0.01% 0.04% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SE02 Construction of Access Platforms & Ramps 28 0.00% 0.02% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SE03 Walk way w/Inter Locking conc. Paving Blocks 554 0.06% 0.33% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SE04 9 Car Covered Parking 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1S C1SE05 Green area with Grass 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    External works 1,094 0.11% 0.65% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TOTAL OF Scrap Handling Office G+1, TSD work Shop & External works 31,234 3.12% 18.48% 313.95 0.19% 933.50 0.55% 1,625.79 619.55

  • 8/12/2019 (Progress Invoice III)28 MAR

    15/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProgEvaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C 1H Material Handling Office G & External works

    Material Handling Office G

    C1H C1HC01 Site Preparation Survey and Marking 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 0.00 0.00

    C1H C1HC02 Relocation of (T, F & other Utilities) 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 0.00 0.00

    C1H C1HC03 Excavation 139 0.01% 0.08% 139.00 100.00% 139.00 100.00% 0.00 0.00

    C1H C1HC04 Compaction and FDT 139 0.01% 0.08% 139.00 100.00% 139.00 100.00% 0.00 0.00

    C1H C1HC05 Survey and marking 139 0.01% 0.08% 139.00 100.00% 139.00 100.00% 139.00 0.00

    C1H C1HC06 Form & Pour Lean Concrete for footing 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 69.00 0.00

    C1H C1HC07 Re-Bars, Form & Pour Concrete for the Footing 139 0.01% 0.08% 139.00 100.00% 139.00 100.00% 139.00 0.00

    C1H C1HC08 Form & Pour Concrete of the Col below Grade Beam 277 0.03% 0.16% 277.00 100.00% 277.00 100.00% 277.00 0.00

    C1H C1HC09 Waterproofing & Backfilling below Grade Beam 139 0.01% 0.08% 69.50 50.00% 139.00 100.00% 139.00 69.50C1H C1HC10 Form & Pour Lean conc. for GB 277 0.03% 0.16% 0.00 0.00% 277.00 100.00% 277.00 277.00

    C1H C1HC11 Re-Bars,Form &pour Conc for GB 277 0.03% 0.16% 0.00 0.00% 277.00 100.00% 277.00 277.00

    C1H C1HC12 Waterproofing & Backfilling below Grade slab 277 0.03% 0.16% 0.00 0.00% 166.20 60.00% 277.00 166.20

    C1H C1HC13 ReBar &Pour of Grade Slab 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 346.00 0.00

    C1H C1HC14 Ground Floor Columns 139 0.01% 0.08% 0.00 0.00% 41.70 30.00% 139.00 41.70

    C1H C1HC15 Roof Floor Slab 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 18.47 0.00

    Civil Wok 2,772 0.28% 1.64% 1,109.50 0.66% 1,940.90 1.15% 2,097.47 831.40

    C1H C1HA01 Reinforced External CMU w/Parapet wall & coping 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA02 Reinforce internal CMU 277 0.03% 0.16% 0.00 0.00% 0.00 0.00%

    0.00 0.00

    C1H C1HA03 Internal Plastering 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA04 Gypsum Board Partition Dry Wall 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA05 Internal painting 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA06 Install ext Aluminum D & W 28 0.00% 0.02% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA07 Install of int Wooden doors 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA08 Install 90m fr sp doors for Em & Ut 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA09 Install Ceiling Grid & False Ceiling 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA10 Unglazed floor tiles for offices,aisles & toilet 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA11 Glazed wall tiles for Toilet Walls 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA12 Epoxy Paint of HVAC 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA13 External plastering 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA14 External Painting 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA15 Roof Water Proofing 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA16 Arch Cab & Hardware for Offices & Pantry 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HA17 Installation of Synthetic Gr Mar Counter Tops 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Arch Work 4,767 0.48% 2.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

  • 8/12/2019 (Progress Invoice III)28 MAR

    16/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProgEvaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C1H C1HP01 Installation of Potable water line 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HP02 Installation of Sanitary pipe line 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HP03 Installation of Sanitary fittings 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Plumbing Work 417 0.04% 0.25% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HL01 Installation of Conduits 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HL02 Wire and Cable Pulling (Elec,Fire,HVAC& cat 6 ) 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HL03 Installation of Switches and Sockets 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HL04 Installation of Lighting Fixtures 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HL05 Installation of Panel Boards 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Electrical Work 2,632 0.26% 1.56% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HH01 HVAC ducting 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00C1H C1HH02 Insulation of Ducts 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HH03 Installation HVAC units 2,770 0.28% 1.64% 0.00 0.00% 0.00 0.00% 0.00 0.00

    HVAC Work 3,324 0.33% 1.97% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HF01 Installation of Detectors 69 0.01% 0.04% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HF02 Installation of Fire Alarm System 69 0.01% 0.04% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HF03 Installation of Fighting System fire wl f H c) 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HF04 Installation of Fire Alarm Control Panels 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Fire Fighting & Detection System 1,663 0.17% 0.98% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HT01 Installation of Telecom & Data Panels 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Telecom & Data System 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HO01 Electrical System 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HO11 HVAC System 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HO21 Fire Fighting & Alarm System 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HO31 Telecom & Data System 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Testing & Commissioning 1,108 0.11% 0.66% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TOTAL OF Material Handling Office G 18,069 1.81% 10.69% 1,109.50 0.66% 1,940.90 1.15% 2,097.47 831.40

    External works

    C1H C1HE01 Emergency Access Stair & Monkey Ladder 485 0.05% 0.29% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HE02 Construction of Access Platforms & Ramps 42 0.00% 0.02% 0.00 0.00% 0.00 0.00% 0.00 0.00C1H C1HE03 Walk way w/Inter Locking conc. Paving Blocks 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1H C1HE04 6 Car Covered Parking 693 0.07% 0.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    External works 1,913 0.19% 1.13% 0.00 0.00% 0.00 0.00% 0.00 0.00

    19,982 2.00% 11.82% 1,109.50 0.66% 1,940.90 1.15% 2,097.47 831.40TOTAL OF Material Handling Office G & External works

  • 8/12/2019 (Progress Invoice III)28 MAR

    17/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProgEvaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C1T Material Transport Office, Electrial Room & External Work

    Material Transport Office,

    C1T C1TC01 Site Preparation Survey and Marking 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 0.00 0.00

    C1T C1TC02 Relocation of (T, F & other Utilities) 485 0.05% 0.29% 485.00 100.00% 485.00 100.00% 97.00 0.00

    C1T C1TC03 Excavation 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 29.57 0.00

    C1T C1TC04 Compaction and FDT 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 69.00 0.00

    C1T C1TC05 Survey and marking 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 69.00 0.00

    C1T C1TC06 Form & Pour Lean Concrete for footing 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 69.00 0.00

    C1T C1TC07 Re-Bars,Form & Pour Concrete for the Footing 346 0.03% 0.20% 346.00 100.00% 346.00 100.00% 346.00 0.00

    C1T C1TC08 Form & Pour Concrete of the Col below Grade Beam 346 0.03% 0.20% 346.00 100.00% 346.00 100.00% 346.00 0.00

    C1T C1TC09 Waterproofing & Backfilling below Grade Beam 69 0.01% 0.04% 48.30 70.00% 69.00 100.00% 69.00 20.70C1T C1TC10 Form & Pour Lean conc for GB 346 0.03% 0.20% 0.00 0.00% 346.00 100.00% 346.00 346.00

    C1T C1TC11 Re-Bars,Form &pour Conc for GB 139 0.01% 0.08% 0.00 0.00% 139.00 100.00% 139.00 139.00

    C1T C1TC12 Waterproofing & Backfilling below Grade slab 69 0.01% 0.04% 0.00 0.00% 41.40 60.00% 69.00 41.40

    C1T C1TC13 ReBar &Pour of Grade Slab 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 277.00 0.00

    C1T C1TC14 Ground Floor Columns 277 0.03% 0.16% 0.00 0.00% 83.10 30.00% 118.71 0.00

    C1T C1TC15 Roof Floor Slab 416 0.04% 0.25% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Civil Wok 3,115 0.31% 1.84% 1,570.30 0.93% 2,200.50 1.30% 2,044.28 547.10

    C1T C1TA01 Reinforced External CMU w/Parapet wall & coping 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA02 Reinforce internal CMU 277 0.03% 0.16% 0.00 0.00% 0.00 0.00%

    0.00 0.00

    C1T C1TA03 Internal Plastering 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA04 Gypsum Board Partition Dry Wall 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA05 Internal painting 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA06 Install ext Aluminum D & W 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA07 Install of int Wooden doors 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA08 Install 90m fr sp doors for Em & Ut 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA09 Install Ceiling Grid & False Ceiling 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA10 Unglazed floor tiles for offices,aisles & toilet 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA11 Glazed wall tiles for Toilet Walls 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA12 Epoxy Paint of HVAC 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA13 External plastering 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA14 External Painting 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

  • 8/12/2019 (Progress Invoice III)28 MAR

    18/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly ProgEvaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C1T C1TA15 Roof Water Proofing 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA16 Arch Cab & Hardware for Offices & Pantry 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TA17 Installation of Synthetic Gr Mar Counter Tops 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Arch Work 3,494 0.35% 2.07% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TP01 Installation of Potable water line 28 0.00% 0.02% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TP02 Installation of Sanitary pipe line 277 0.03% 0.16% 0.00 0.00% 55.40 20.00% 0.00 0.00

    C1T C1TP03 Installation of Sanitary fittings 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Plumbing Work for G & Electrical room 582 0.06% 0.34% 0.00 0.00% 55.40 0.03% 0.00 0.00

    C1T C1TL01 Installation of Conduits 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TL02 Wire and Cable Pulling (Elec,Fire,HVAC& cat 6 ) 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TL03 Installation of Switches and Sockets 14 0.00% 0.01% 0.00 0.00% 0.00 0.00% 0.00 0.00C1T C1TL04 Installation of Lighting Fixtures 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TL05 Installation of Panel Boards 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Electrical Work for G & Electrical room 708 0.07% 0.42% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TH01 HVAC ducting 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TH02 Insulation of Ducts 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TH03 Installation HVAC units 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    HVAC Work for G & Electrical room 1,664 0.17% 0.98% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TFI01 Installation of Detectors 14 0.00% 0.01% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TFI02 Installation of Fire Alarm System 139 0.01% 0.08% 0.00 0.00% 0.00 0.00%

    0.00 0.00

    C1T C1TFI03 Installation of Fighting System fire wl f H c) 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TFI04 Installation of Fire Alarm Control Panels 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Fire Fighting & Detection System for G & Eletrical room 431 0.04% 0.25% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TF01 Installation of Telecom & Data Panels 416 0.04% 0.25% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Telecom & Data System for G & Electrical room 416 0.04% 0.25% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TO01 Electrical System 138 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TO11 HVAC System 138 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TO21 Fire Fighting & Alarm System 138 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TO31 Telecom & Data System 138 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Testing & Commissioning 552 0.06% 0.33% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TOTAL OF Material Transport Office 10,962 1.05% 6.48% 1,570.30 0.93% 2,255.90 1.33% 2,044.28 547.10

    Electrial Room

    C1T C1ER01 Site Preparation Survey and Marking 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 0.00 0.00

    C1T C1ER02 Relocation of (T, F & other Utilities) 277 0.03% 0.16% 277.00 100.00% 277.00 100.00% 55.40 0.00

    C1T C1ER03 Excavation 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 69.00 0.00

    C1T C1ER04 Compaction and FDT 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 69.00 0.00

  • 8/12/2019 (Progress Invoice III)28 MAR

    19/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly Prog

    Evaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C1T C1ER05 Survey and marking 69 0.01% 0.04% 69.00 100.00% 69.00 100.00% 69.00 0.00

    C1T C1ER06 Form & Pour Lean Concrete for footing 139 0.01% 0.08% 139.00 100.00% 139.00 100.00% 139.00 0.00

    C1T C1ER07 Re-Bars,Form & Pour Concrete for the Footing 208 0.02% 0.12% 208.00 100.00% 208.00 100.00% 208.00 0.00

    C1T C1ER08 Form & Pour Concrete of the Col below Grade Beam 139 0.01% 0.08% 139.00 100.00% 139.00 100.00% 139.00 0.00

    C1T C1ER09 Waterproofing & Backfilling below Grade Beam 139 0.01% 0.08% 139.00 100.00% 139.00 100.00% 139.00 0.00

    C1T C1ER10 Form & Pour Lean conc for GB 139 0.01% 0.08% 0.00 0.00% 139.00 100.00% 139.00 139.00

    C1T C1ER11 Re-Bars,Form &pour Conc for GB 208 0.02% 0.12% 0.00 0.00% 208.00 100.00% 208.00 208.00

    C1T C1ER12 Waterproofing & Backfilling below Grade slab 139 0.01% 0.08% 0.00 0.00% 111.20 80.00% 139.00 111.20

    C1T C1ER13 ReBar &Pour of Grade Slab 139 0.01% 0.08% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1ER14 Ground Floor Columns 139 0.01% 0.08% 0.00 0.00% 27.80 20.00% 0.00 27.80

    C1T C1ER15 Roof Floor Slab 346 0.03% 0.20% 0.00 0.00% 0.00 0.00% 0.00 0.00C1T C1ER16 Reinfoced External CMU w/Parapet wall & coping 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1ER17 Reinforce internal CMU 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1ER18 Internal Plastering 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1ER19 Internal painting 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1ER20 Install ext Aluminum D & W 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1ER21 Install 90m fr sp doors for Em & Ut 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1ER22 Epoxy Floor Painting 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1ER23 External plastering 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1ER24 External Painting 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1ER25 Roof Water Proofing 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Electrial Room 4,101 0.41% 2.43% 1,178.00 0.70% 1,664.00 0.98% 1,373.40 486.00

    External Work

    C1T C1TE01 Emergency Access Stair & Monkey Ladder 277 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TE02 Construction of Access Platforms & Ramps 28 0.00% 0.02% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TE03 Walk way w/Inter Locking conc. Paving Blocks 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1T C1TE04 12 Car Covered Parking 166 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    External works 637 0.06% 0.38% 0.00 0.00% 0.00 0.00% 0.00 0.00

    15,700 1.53% 9.29% 2,748.30 1.63% 3,919.90 2.32% 3,417.68 1,033.10

    C1SS Siren Room & Siren system

    C1SS C1SS01 Survey & marking of Siren Room 208 0.02% 0.12% 0.00 0.00% 0.00 0.00% 208.00 0.00

    C1SS C1SS02 Excavation & compaction 485 0.05% 0.29% 0.00 0.00% 0.00 0.00% 485.00 0.00

    C1SS C1SS03 Form Rebar conc. pouring of footing 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 1386.00 0.00

    C1SS C1SS04 Super Structure 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 1293.60 0.00

    C1SS C1SS05 Finishing work 1,386 0.14% 0.82% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C1SS C1SS11 Installation of Siren System for all Buildings 2,078 0.21% 1.23% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Total of Siren Room & Siren system 6,929 0.69% 4.10% 0.00 0.00% 0.00 0.00% 3,372.60 0.00

    TOTAL OF ALL BUILDINGS & WORKSHOPS 169,057 16.86% 100.00% 5559.65 3.29% 9145.70 2.12% 12695.05 3447.55

    23.07% 0.76% 1.25%

    TOTAL OF Material Transport Office, Electrial Room& External Work

  • 8/12/2019 (Progress Invoice III)28 MAR

    20/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly Prog

    Evaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C 2 Improvement of Roads

    Road from E-Gate to Weighdridge 2

    Road from E- Gate to Hot Strip Hall 811.56 m

    C2E C2EH01 Survey & Marking 279 0.03% 0.13% 279.00 100.00% 279.00 100.00% 0.00 0.00

    C2E C2EH02 Relocate Elec,Camera Post & Sanitary WW Util. 2,771 0.28% 1.28% 1608.19 58.04% 2429.34 87.67% 395.86 821.21

    C2E C2EH03 Relocate Trees & Irrigation Facilities 2,771 0.28% 1.28% 2771.00 100.00% 2771.00 100.00% 2771.00 0.00

    C2E C2EH04 Relocate Street lighting, Road Sign & Survey P 2,771 0.28% 1.28% 2355.35 85.00% 2771.00 100.00% 2771.00 415.65

    C2E C2EH05 Sub Grade Preparation of Road ex 12m ep L 6m 2,079 0.21% 0.96% 1559.25 75.00% 2079.00 100.00% 1351.35 519.75

    C2E C2EH06 Place Aggregate Base Course 2,079 0.21% 0.96% 0.00 0.00% 2079.00 100.00% 831.60 2079.00

    C2E C2EH07 Place Asphalt Base Course 2,771 0.28% 1.28% 0.00 0.00% 0.00 0.00% 415.65 0.00

    C2E C2EH08 Place Asphalt Surface course 2,771 0.28% 1.28% 0.00 0.00% 0.00 0.00% 0.00 0.00C2E C2EH09 Construction of Aisle in Centre 2m 2,771 0.28% 1.28% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2E C2EH10 Construction of 4m Walkway With Interlock pavers 4,850 0.49% 2.25% 0.00 0.00% 485.00 10.00% 0.00 485.00

    Road from E- Gate to Hot Strip Hall 811.56 m 25,913 2.59% 12.00% 8572.79 3.97% 12893.34 5.97% 8536.46 4320.61

    Road along Hot Strip Mill Lay Down Area 293 m

    C2H C2HL01 Survey & Marking 139 0.01% 0.06% 139.00 100.00% 139.00 100.00% 139.00 0.00

    C2H C2HL03 ReHigh Voltage Elec Trench & Potable Water line 831 0.08% 0.38% 0.00 0.00% 0.00 0.00% 831.00 0.00

    C2H C2HL04 Relocate Road Sign, fire Hydrant & Survey P 831 0.08% 0.38% 0.00 0.00% 0.00 0.00% 831.00 0.00

    C2H C2HL05 Sub Grade Preparation of Road ex12m ep Bs 3m each 208 0.02% 0.10% 31.20 15.00% 31.20 15.00% 183.04 0.00

    C2H C2HL06 Place Aggregate & Asphalt Base Course 346 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2H C2HL07 Place Asphalt Base Course 346 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2H C2HL08 Place Asphalt Surface course 346 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2H C2HL09 Construction of Aisle in Centre 2m 139 0.01% 0.06% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2H C2HL10 Construction of 4m Walkway With Interlock pavers 1,109 0.11% 0.51% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Road along Hot Strip Mill Lay Down Area 293 m 4,295 0.43% 1.99% 170.20 0.08% 170.20 0.08% 1984.04 0.00

    Road along Scrap Yard Area 304 m

    C2SY C2SY01 Survey & Marking 139 0.01% 0.06% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2SY C2SY05 Sub Grade Preparation of Road ex10m ep R 8m 693 0.07% 0.32% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2SY C2SY06 Place Aggregate & Asphalt Course 970 0.10% 0.45% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2SY C2SY07 Place Asphalt Base Course 1,109 0.11% 0.51% 0.00 0.00% 0.00 0.00% 0.00 0.00C2SY C2SY08 Place Asphalt Surface course 1,109 0.11% 0.51% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2SY C2SY09 Construction of Aisle in Centre 2m 831 0.08% 0.38% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2SY C2SY10 Construction of 4m Walkway W/ Interlock pavers L 2,771 0.28% 1.28% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Road along Scrap Yard Area 304 m 7,622 0.76% 3.53% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2 E,H,SY& BW

  • 8/12/2019 (Progress Invoice III)28 MAR

    21/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly Evalu

    Actual % Progress Against Item

    Cummulative this monthCummulative last month

    wrt Weekly R

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    Road along Bar storage & weighbridge 294 mC2BW C2BW01 Survey & Marking 277 0.03% 0.13% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2BW C2BW02 Relocate Street Lightings, RS, Fire Hy & Survey 831 0.08% 0.38% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2BW C2BW03 Relocate Electrical Utilities 831 0.08% 0.38% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2BW C2BW04 Sub Grade Preparation of Road ex12m ep Bs 3m each 693 0.07% 0.32% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2BW C2BW05 Place Aggregate & Asphalt Course 1,663 0.17% 0.77% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2BW C2BW06 Place Asphalt Base Course 1,663 0.17% 0.77% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2BW C2BW07 Place Asphalt Surface course 1,663 0.17% 0.77% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2BW C2BW08 Construction of Aisle in Centre 2m 693 0.07% 0.32% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2BW C2BW09 Construction of 4m Walkway With Interlock pavers 693 0.07% 0.32% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Road along Bar storage & weighbridge 294 m 9,007 0.90% 4.17% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TOTAL OF Road from E-Gate to Weighdridge 2 46,837 4.68% 21.69% 8742.99 4.05% 13063.54 6.05% 10520.50 4320.61

  • 8/12/2019 (Progress Invoice III)28 MAR

    22/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly Prog

    Evaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    Road at Weighbridge 1 & LPF Dispatch Area

    Road along Bar Storage 130 m 0.00

    C2AB C2AB01 Survey & Marking 277 0.03% 0.13% 0.00 0.00% 277.00 100.00% 277.00 277.00

    C2AB C2AB02 Relocate Street Lightings & Road sign 2,079 0.21% 0.96% 0.00 0.00% 0.00 0.00% 2079.00 0.00

    C2AB C2AB03 Sub Grade Preparation of Road ex 8m ep R 5m 693 0.07% 0.32% 0.00 0.00% 0.00 0.00% 570.71 0.00

    C2AB C2AB04 Place Aggregate & Asphalt Course 2,771 0.28% 1.28% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2AB C2AB05 Place Asphalt Base Course 2,079 0.21% 0.96% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2AB C2AB06 Place Asphalt Surface course 2,079 0.21% 0.96% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2AB C2AB07 Construction of Aisle in Centre 2m 2,771 0.28% 1.28% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2AB C2AB08 Construction of 4m Walkway With Interlock pavers 9,838 0.98% 4.56% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Road along Bar Storage 130 m 22,587 2.26% 10.46% 0.00 0.00% 277.00 0.13% 2926.71 277.00Road along Finishing Bay 370 m

    C2FB C2FB01 Survey & Marking 139 0.01% 0.06% 0.00 0.00% 0.00 0.00% 139.00 0.00

    C2FB C2FB02 Relocate Street Lightings & Road sign 2,770 0.28% 1.28% 0.00 0.00% 0.00 0.00% 2770.00 0.00

    C2FB C2FB03 Sub Grade Preparation of Road ex 12m ep R 3m 624 0.06% 0.29% 0.00 0.00% 0.00 0.00% 99.84 0.00

    C2FB C2FB04 Place Aggregate & Asphalt Base Course 1,385 0.14% 0.64% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2FB C2FB05 Place Asphalt Base Course 1,385 0.14% 0.64% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2FB C2FB06 Place Asphalt Surface course 1,385 0.14% 0.64% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2FB C2FB07 Construction of Aisle in Centre 2m 693 0.07% 0.32% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2FB C2FB08 Construction of 4m Walkway With Interlock pavers 693 0.07% 0.32% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Road along Finishing Bay 370 m 9,074 0.91% 4.20% 0.00 0.00% 0.00 0.00% 3008.84 0.00

    Road along Coaster Bus Park 65 m

    C2CB C2CB01 Survey & Marking 139 0.01% 0.06% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2CB C2CB02 Sub Grade Preparation of Road New 12m 139 0.01% 0.06% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2CB C2CB03 Place Aggregate & Asphalt Course 208 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2CB C2CB04 Place Asphalt Base Course 208 0.02% 0.10% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2CB C2CB05 Place Asphalt Surface course 277 0.03% 0.13% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Road along Coaster Bus Park 65 m 971 0.10% 0.45% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Road to the Bar Storage 120 m

    C2TB C2TB01 Survey & Marking 277 0.03% 0.13% 0.00 0.00% 0.00 0.00% 0.00 0.00C2TB C2TB02 Demolish two bay of ex Bar Storage 693 0.07% 0.32% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2TB C2TB03 Sub Grade Preparation of Road ex 7m epd 19.2m w 1,386 0.14% 0.64% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2TB C2TB04 Place Aggregate & Asphalt Course 2,079 0.21% 0.96% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2TB C2TB05 Place Asphalt Base Course 2,079 0.21% 0.96% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2 AB,FB,CB,TB & WB

  • 8/12/2019 (Progress Invoice III)28 MAR

    23/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    MonthlyEvalu

    Actual % Progress Against Item

    Cummulative this monthCummulative last month

    wrt Weekly

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    C2TB C2TB06 Place Asphalt Surface course 2,079 0.21% 0.96% 0.00 0.00% 0.00 0.00% 0.00 0.00Road to the Bar Storage 120 m 8,593 0.86% 3.98% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Road along Bar storage going to WB (1) 65.5 m

    C2WB C2WB01 Survey & Marking 69 0.01% 0.03% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2WB C2WB02 Relocate Street Lightings & Road sign 69 0.01% 0.03% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2WB C2WB03 Sub Grade Preparation of Road ex 12m ep L 6m 69 0.01% 0.03% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2WB C2WB04 Place Aggregate & Asphalt Course 69 0.01% 0.03% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2WB C2WB05 Place Asphalt Base Course 139 0.01% 0.06% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2WB C2WB06 Place Asphalt Surface course 139 0.01% 0.06% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Road along Bar storage going to WB (1) 65.5 m 554 0.06% 0.26% 0.00 0.00% 0.00 0.00% 0.00 0.00

    41,779 4.18% 19.35% 0.00 0.00% 277.00 0.13% 5935.55 277.00TOTAL OF Road at Weighbridge 1 & LPF Dispatch Area

  • 8/12/2019 (Progress Invoice III)28 MAR

    24/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly Pro

    Evaluatio

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repo

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    Road from Mobile WS to Billet Bay 989.3m

    Road from Mobile WS to Billet Bay First Half

    C2M C2M01 Survey & Marking 139 0.01% 0.06% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2M C2M02 Relo or Pro Fire, Sanitary Waste & Potable W L 4,156 0.42% 1.93% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2M C2M03 Relo or Pro Oxygen & Nature G L & Comp Air Line 4,156 0.42% 1.93% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2M C2M06 Sub Grade Preparation of Road ex 12m ep R 3m 4,575 0.46% 2.12% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2M C2M07 Place Aggregate & Asphalt Base Course 5,196 0.52% 2.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2M C2M08 Place Asphalt Base Course 5,196 0.52% 2.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2M C2M09 Place Asphalt Surface course 5,196 0.52% 2.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2M C2M10 Construction of Aisle in Centre 2m 5,196 0.52% 2.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2M C2M11 Construction of 4m Walkway With Interlock pavers 5,196 0.52% 2.41% 0.00 0.00% 0.00 0.00% 0.00 0.00Road from Mobile WS to Billet Bay First Half 39,006 3.90% 18.07% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Road from Mobile WS to Billet Bay Second Half

    C2B C2B01 Survey & Marking 139 0.01% 0.06% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2B C2B02 Relo or Pro Fire, Sanitary Waste & Potable W L 4,157 0.42% 1.93% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2B C2B03 Relo or Pro Oxygen & Nature G L & Comp Air Line 4,157 0.42% 1.93% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2B C2B04 Relocate Portable Offices/Mosque 4,157 0.42% 1.93% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2B C2B05 Demolition of Conc & Steel Str. Buildings 4,157 0.42% 1.93% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2B C2B06 Sub Grade Preparation of Road ex 12m ep R 3m 5,197 0.52% 2.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2B C2B07 Place Aggregate & Asphalt Base Course 5,197 0.52% 2.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2B C2B08 Place Asphalt Base Course 5,197 0.52% 2.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2B C2B09 Place Asphalt Surface course 5,197 0.52% 2.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2B C2B10 Construction of Aisle in Centre 2m 5,196 0.52% 2.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2B C2B11 Construction of 4m Walkway With Interlock pavers 5,196 0.52% 2.41% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Road from Mobile WS to Billet Bay Second Half 47,947 4.79% 22.21% 0.00 0.00% 0.00 0.00% 0.00 0.00

    TOTAL OF Road from Mobile WS to Billet Bay 989.3m 86,953 8.70% 40.28% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2 M & B

  • 8/12/2019 (Progress Invoice III)28 MAR

    25/28

    Earned WBU Actual Prog % Earned WBU Actual Prog % Planned WBU Earned WBU

    N C E

    Date :7 APR -08

    HADEED - SAUDI IRON AND STEEL COMPANY

    HADEED LOGISTICS IMPROVEMENT PROJECT PHASE I

    PROGRESS MONITORING SHEET FOR THE MONTH OF MARCH CUT OFF DATE 28th MAR 08 ON WBU % WEIGHT

    This month

    Monthly Prog

    Evaluation

    Actual % Progress Against Item

    RCummulative this monthCummulative last month

    wrt Weekly Repor

    AL NABA

    WBU% Weight

    Vs. Project

    % Weight

    Vs. ItemITEM NO. Sch. ID ITEM DESCRIPTION

    Road Steel Plant Hadeed 1 to 2

    Road along Material Handling Area 329 m

    C2AMH C2AMH01 Survey & Marking 277 0.03% 0.13% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2AMH C2AMH02 Dem & Relo ex Wash Area & Wast Pit 693 0.07% 0.32% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2AMH C2AMH03 Demolish MTO/Mosque 693 0.07% 0.32% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2AMH C2AMH04 Demolition of Conc & Steel Str. Buildings 693 0.07% 0.32% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2AMH C2AMH05 SubGrade Preparation of Road 20m & 8m 1,524 0.15% 0.71% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2AMH C2AMH06 Place Aggregate & Asphalt Base Course 1,524 0.15% 0.71% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2AMH C2AMH07 Place Asphalt Base Course 1,524 0.15% 0.71% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2AMH C2AMH08 Place Asphalt Surface course 2,079 0.21% 0.96% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2AMH C2AMH09 Construction of 4m Walkway With Interlock pavers 2,079 0.21% 0.96% 0.00 0.00% 0.00 0.00% 0.00 0.00Road along Material Handling Area 329 m 11,086 1.11% 5.13% 0.00 0.00% 0.00 0.00% 0.00 0.00

    Road along Refractory & Reling Building

    C2RR C2RR01 Survey & Marking 139 0.01% 0.06% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2RR C2RR02 Relocate Street Lightings, ConcreteB & Road sign 692 0.07% 0.32% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2RR C2RR03 Sub Grade Preparation of Road ex 13m ep L 7m 346 0.03% 0.16% 0.00 0.00% 0.00 0.00% 0.00 0.00

    C2RR C2RR04 Place Aggregate & Asphalt Course 346 0.03% 0.16% 0.00 0.00