  • 3/24/2015 PEO Aircraft Carriers 1NAVSEA: Statement A: Approved for Release. Distribution is unlimited.

    Program Executive OfficerAircraftCarriers

    3/24/2015 PEO Aircraft Carriers

    State of the Carrier Program

    RADM Tom Moore17 March 2015

    NAVSEA: Statement A: Approved for Release. Distribution is unlimited.

  • 3/24/2015 PEO Aircraft Carriers 2NAVSEA: Statement A: Approved for Release. Distribution is unlimited.

    First of Class Comments

    Procurement nightmare

    The Navys billion-dollar hole in the water

    Another example of the Navy driving itself tothe poor house in a Cadillac.

    60 ships later..DDG 51 is doing pretty well!!

  • 3/24/2015 PEO Aircraft Carriers 3NAVSEA: Statement A: Approved for Release. Distribution is unlimited.

    GERALD R. FORD (CVN 78)Ship Construction

    March 2013 May 2013Hull structure

    complete.

    January 2013Island landing.

    August 2013Hull painting complete.

    October 2013Dry dock flooding complete.

    Aug 2011 Construction status

  • 3/24/2015 PEO Aircraft Carriers 4NAVSEA: Statement A: Approved for Release. Distribution is unlimited.3/24/2015 PEO Aircraft Carriers 4NAVSEA: Statement A: Approved for Release. Distribution is unlimited.

    My Favorite Headline

  • 3/24/2015 PEO Aircraft Carriers 5NAVSEA: Statement A: Approved for Release. Distribution is unlimited.3/24/2015 PEO Aircraft Carriers 5NAVSEA: Statement A: Approved for Release. Distribution is unlimited.

    GERALD R. FORD ClassThe Future is Now

    The Future is NowThe GERALD R. FORD Class brings new improvements over the Nimitz class, including:

    Increased flexibilityNearly 3 times the electric plant capacityRestored weight and stability service life allowances

    Increased capability33% increase in Sortie Generation Rates Increased space for flight deck operations and aircraft maintenance

    Increased affordabilityReduced manning and 20% reduction in maintenance costsDesigned for 43-month maintenance cycle and 12-year docking intervals

    The Future is NowThe GERALD R. FORD Class brings new improvements over the Nimitz class, including:

    Increased flexibilityNearly 3 times the electric plant capacityRestored weight and stability service life allowances

    Increased capability33% increase in Sortie Generation Rates Increased space for flight deck operations and aircraft maintenance

    Increased affordabilityReduced manning and 20% reduction in maintenance costsDesigned for 43-month maintenance cycle and 12-year docking intervals

  • 3/24/2015 PEO Aircraft Carriers 6NAVSEA: Statement A: Approved for Release. Distribution is unlimited.

    GERALD R. FORD (CVN 78)Current State

    Status 99% design complete 98% material procured 87.4% ship construction complete 1033 of 2608 compartments turned over to crew (39.2%) 9.5 million of 10.2 million feet of cable installed 37.5% overall shipboard testing complete Current EAC = $12,887M (at cost cap)

    Construction supports March 2016 Delivery. Closely managing remaining test risks.

    Accomplishments 9 of 9 new design air conditioning plants operational 4 of 11 Advanced Weapons Elevators (AWEs) in test Catapult installation on track (2 of 4 complete) Advanced Arresting Gear (AAG)

    Major components received Installation behind schedule

    Electromagnetic Aircraft Launch System (EMALS) Shipboard testing started on schedule, Aug 2014 8 of 12 motor generators energized Catapult testing started 16 Dec 2014, testing on schedule

    All Dual Band Radar (DBR) components received and installed Propulsion Plant

    Power units loaded Electric plant energized and operational Cold ops completed in both plants Hot ops ongoing in lead plant

    Upcoming Key Events Apr 2015: EMALS shuttle movement (no load testing) begins Jun 2015: EMALS deadload Testing begins Aug 2015: Crew move aboard Nov 2015: Combat Systems Trial Rehearsal

  • 3/24/2015 PEO Aircraft Carriers 7NAVSEA: Statement A: Approved for Release. Distribution is unlimited.

    Historical CVN Construction Man-Hours

    CVN 79 TO-GO(UNEXPENDED)

    + COST CHALLENGESCARRIER CONSTRUCTION RETURNING TO HISTORICAL LEVELS FOR MORE CAPABLE SHIP

    CVN 78 Class Capabilities

    33% greater Sortie Generation Rate

    Survivability and Damage Control improvements

    Increased magazine and JP-5 storage

    Greater Operational Availability

    Nearly 3X electric plant capacity

    Restoration of Service Life Allowances

    $4B Reduced Total Ownership Cost

  • 3/24/2015 PEO Aircraft Carriers 8NAVSEA: Statement A: Approved for Release. Distribution is unlimited.

    John F. Kennedy (CVN 79) Status

    Description Modified repeat of CVN 78, and second ship of the Gerald R. Ford class Force structure replacement for USS NIMITZ (CVN 68)

    Construction Preparation (CP) Long lead material procurement since FY07 Engineering / cost savings analyses; build strategy changes Advance construction since FY11

    662 units under contract; 570 units started; 405 complete 100% Product Model roll-over complete

    ~95% of direct-buy material under contract

    Detail Design & Construction (DD&C)) All Remaining construction units (1,109 Total) All Remaining erectables (452 Total) All Remaining construction material Manhours for integration and testing

    Key Construction Milestones Keel: Sep 2015; Launch: Feb 2020; Delivery: Jun 2022

  • PEO Aircraft CarriersNAVSEA: Statement A: Approved for Release. Distribution is unlimited.

  • 3/24/2015 PEO Aircraft Carriers 10NAVSEA: Statement A: Approved for Release. Distribution is unlimited.

    -20.0 -10.0 0.0 10.0 20.0 30.0 40.0 50.0

    RCOHYearsofServiceLife

    NIMITZClass:500totalcarrieryears,servingover84years,from1975until2059

    Only48%throughtheservicelifeoftheNIMITZClass 260carrieryearsremaining.

    FORDClass:10carriers,serving2016until2110

    DONTFORGETABOUTTHENIMITZCLASS

    CVN80

    CVN79

    CVN78