Program Design
Demand shifting program designed to reduce peak loads on summer weekdays
Program produces substantive and measurable impacts on peak demand
Program is successful in reducing demand without changing energy consumption
“Peak Rewards is not only effective, but happens at the optimal time of day.” Vern Porter, Manager of Power Supply Operations
2005 Program Details
Customers who have metered service points with >100 HP voluntarily sign up for program
Pre-programmed electronic timers installed on participants pumps
Pumps automatically interrupted during peak time of 4-8 pm on predetermined weekdays
Cycling period is from June 1st to August 31st
Program is available to Idaho rate 24 Agricultural Irrigation customers in 2005
Oregon customers will be eligible next year
Budget for program is $1.4 million
2005 Program Details (continued)
Irrigation customers receive credit against their demand charge.
Current demand charge for irrigation customers is $4.19 / kW
1 day option credit: $2.01 / kW
2 day option credit: $2.51 / kW
3 day option credit: $2.76 / kW
Most customers should expect to see an 8% savings per service point.
895 service points operated by 254 growers
Participants / Option
24% of eligible customers signed up
Option S P Qty. HP1 day / week 629 69,993
2 days / week 155 33,0343 days / week 110 25,700
Participants by Region
34%
56%
2%
8%
Southern
Eastern
Capital
Canyon/Payette
Average MW Reduction
Mon Tue Wed Thur Fri MW
(kW) (kW) (kW) (kW) (kW) AverageJune 16,975 40,323 39,944 39,111 16,394 30.55
July 15,914 37,803 37,447 36,667 15,370 28.64
August 12,885 29,691 30,088 28,763 12,058 22.70
1,800
2,000
2,200
2,400
2,600
2,800
3,000
10:00AM
11:00AM
12:00PM
1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM 10:00PM
11:00PM
12:00AM
Sy
ste
m L
oa
d (
MW
)
Thursday, July 7, 2005
Tuesday, July 12, 2005
Wednesday, July 13, 2005
Thursday, July 14, 2005
Demand Response Impact on Idaho Power Firm Load
4
6
8
10
12
14
16
8:38AM
10:33AM
12:28PM
2:24PM
4:19PM
6:14PM
8:09PM
10:04PM
12:00AM
1:55AM
MW
Feeder
JNCN 43
Julion Clawson
Minidoka County