Prof. Roy Levow Session 8. Steps in Closing a Project Getting Client Acceptance Installing...

23
Prof. Roy Levow Session 8

Transcript of Prof. Roy Levow Session 8. Steps in Closing a Project Getting Client Acceptance Installing...

Page 1: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Prof. Roy Levow

Session 8

Page 2: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Steps in Closing a Project Getting Client Acceptance Installing Project Deliverables Documenting the Project Post-Implementation Audit The Final Report Celebrating Success

Page 3: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Understand the steps needed to effectively close a project

Develop a closing strategy Identify the components of project

documentation Conduct a post-implementation audit Explain the significance of each post-

implementation audit question

Copyright 2007 John Wiley & Sons, Inc. Chapter 11 3

Page 4: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Getting client acceptance of deliverables Ensuring that all deliverables are

installed Ensuring that the documentation is in

place Getting client sign-off on the final report Conducting the post-implementation

audit Celebrating the success

Copyright 2007 John Wiley & Sons, Inc. Chapter 11 4

Page 5: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Ceremonial Acceptance Informal in that there is no accompanying sign-

off Two situations

Client has to accept deliverable by a certain date whether the deliverable meets specifications or not

Deliverable requires little or no checking Formal Acceptance

Inspection of deliverable expected Checklist

Formal sign-off before customer accepts deliverable

Copyright 2007 John Wiley & Sons, Inc. Chapter 11 5

Page 6: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

The product is turned on when it is delivered to the client

Copyright 2007 John Wiley & Sons, Inc. Chapter 11 6

Page 7: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Five Reasons for Documentation Reference for future changes in deliverables Historical record for estimating duration and

cost on future projects, activities, and tasks Training resource for new project managers Input for further training and development of

the project team Input for performance evaluation by the

functional managers of the project team members

Copyright 2007 John Wiley & Sons, Inc. Chapter 11 7

Page 8: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Project Overview Statement Project Proposal and backup data Original and revised project schedules Minutes of all project team meetings Copies of all status reports Design documents Copies of all change notices Copies of all written communications Outstanding issues reports Final report Sample deliverables (if appropriate) Client acceptance documents Post-implementation audit report

Copyright 2007 John Wiley & Sons, Inc. Chapter 11 8

Page 9: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Six Questions Was the project goal achieved?

Does it do what the project team said it would do? Does it do what the client said it would do?

Was the project work done on time, within budget, and according to specification?

Was the client satisfied with the project results? Was business value realized? (Check success

criteria) What lessons were learned about your project

management methodology? What worked? What didn’t?

Copyright 2007 John Wiley & Sons, Inc. Chapter 11 9

Page 10: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Overall success of the project Organization of the project Techniques used to get results Project strengths and weaknesses Project team recommendations

Copyright 2007 John Wiley & Sons, Inc. Chapter 11 10

Page 11: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

What Is the Critical Chain? Variation in Duration: Common Cause

versus Special Cause Statistical Validation of the Critical Chain

Approach The Critical Chain Project Management

Approach Buffers Track Record of Critical Chain Project

Management

Page 12: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Explain the difference between critical path and the critical chain

Identify resource constraints and know how to resolve them

Use the critical chain approach to project management for single projects

Copyright 2007 John Wiley & Sons, Inc. Chapter 12 12

Page 13: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

The longest path through the project that is both task-dependent and resource-constrained

Differs from the critical path, which is the path of the longest duration

Critical Chain Project Management is the planning, scheduling, and maintenance of the critical chain

Copyright 2007 John Wiley & Sons, Inc. Chapter 12 13

Page 14: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Common cause variation: “fluctuation in task duration that results from the capacity of that system affecting the task” Natural variations of the system Nothing can be done about this type of variation

Special cause variation: fluctuation is caused by a special cause external to the system Variations can be mitigated, planned for, or

avoided

Copyright 2007 John Wiley & Sons, Inc. Chapter 12 14

Page 15: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Calculate the 50% duration of a task Calculate the 90% duration of a task The difference between the two is the

contingency

Copyright 2007 John Wiley & Sons, Inc. Chapter 12 15

Page 16: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Step One – Create an Early Schedule Project Network Diagram

Copyright 2007 John Wiley & Sons, Inc. Chapter 12 16

Page 17: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Step Two – Convert the Early Schedule to the Late Schedule and Add Resources

Copyright 2007 John Wiley & Sons, Inc. Chapter 12 17

Page 18: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Step Three – Resolve Resource Conflicts

Copyright 2007 John Wiley & Sons, Inc. Chapter 12 18

One Solution Another Solution

Page 19: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

“Segments of time that are placed at the end of a sequence of tasks for the purpose of protecting the schedule of those tasks.”

Types of Buffers Project: Placed at the end of the critical chain to

protect the overall project schedule Feeding: Placed at the end of a sequence of

tasks that lead into the critical chain Resource: A flag that is placed to alert a resource

when it is needed. It has no time length.

Copyright 2007 John Wiley & Sons, Inc. Chapter 12 19

Page 20: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Copyright 2007 John Wiley & Sons, Inc. Chapter 12 20

Page 21: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Copyright 2007 John Wiley & Sons, Inc. Chapter 12 21

Page 22: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.

Successes Honeywell Defense Avionics Systems: Project

schedule reduced from 13 months to 6 months Lucent Technologies: Project completed within

one year despite estimates it would take longer Harris: Industry standard for factory built and

running at 90% capacity is 46 months. Harris factory built and running at 90% capacity in 13 months

Israeli aircraft industry: Reduced aircraft maintenance from three months to two weeks

Copyright 2007 John Wiley & Sons, Inc. Chapter 12 22

Page 23: Prof. Roy Levow Session 8.  Steps in Closing a Project  Getting Client Acceptance  Installing Project Deliverables  Documenting the Project  Post-Implementation.