Productivity Awards. Best Productivity Zone 1 - North Coast 14.85.
Productivity Outputs 1
-
Upload
leah-amor-mamanao -
Category
Documents
-
view
216 -
download
0
Transcript of Productivity Outputs 1
-
7/25/2019 Productivity Outputs 1
1/10
Page 1 of 10
MANPOWER AND EQUIPMENT PRODUCTIVITY OUTPUT
ITEM 100 CLEARING AND GRUBBING
1. Bush Clearance (LIGHT) 250 sq.m./man-day
2. Bush Clearance (MEDIUM) 125 sq.m./man-day3. Bush Clearance (DENSE) a) 65.50 sq.m/man-day
b) With chainsaw 200 sq.m/2 man gang/day4. Individual removal of trees (up to maximum of0.25m. diam.)
a) 1 tree per man dayb) With chainsaw 10 trees/2 man gang/day
5. Grubbing/top soil removal (sparce vegetation) 150.00 sq.m/man-day
6. Grubbing/top soil removal (dense vegetation) 80.00 sq.m/man-day7. Boulder removal (loose) 150.00 sq.m/man-day
NOTE: The outputs are up to a maximum disposal site distance of 10.00 meters.
ITEM 101 REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Reinforced Concrete Conc. Pvmt Aspalt pvmt
A. LABOR/man-day 0.50 cu.m 2.50 sq.m. 8.0 sq.m.
B. EQUIPMENTB.1 Air Compressor w/ jackleg 2.00 cu.m 50.00 sq.m
B.2 Road Grader Open-2,400 sq.mLimited-1,200 sq.m
C. REMOVAL OF SLIDES/LOADING OF WASTE MATERIALS
USING PAYLOADER
Disposal Distance (Meters) Capacity per Day (Cu.m)Rock Common Earth
7.5 300 43010 270 390
20 230 33025 200 280
30 180 260
40 160 23045 150 22050 140 210
55 130 19060 120 170
-
7/25/2019 Productivity Outputs 1
2/10
Page 2 of 10
NOTE:
1. Open refers to trafficless working and condition otherwise would be referred to as limited.
2. For A and B, consider waste disposal.3. For C
If necessary include bulldozer equipment.Beyond 60.0 meter use dump truck for disposal of waste and include time spotting calculation for
hauling in the detailed estimate.For heavy traffic areas, include the effect of traffic in the productivity output.
(Computation to be included in the detailed estimate)
ITEM 102: EXCAVATION
Daily output in cu.m.Common Earth Loose Rock
A. LABOR 3.00 0.50-0.75
B. EQUIPMENT (Bulldozer) based on a maximum disposal distance of 30 meters, if
Payloader is used refer to item 101 C.
Common EarthD4 210
D6 250D8 410
C. SOLID ROCK
C.1. ParticularsCap. Of 1 unit Air Compressor w/ jackhammers/day based
Based on perpindicular boring at a maximum height of150 meters 100 boreholes
Holes required for 1 cu.m. solid rock = 2 holes (1 m. deep)
Average no. of dynamite sticks per case = 330 (Mayon Brand)
= 316 (Power Jet Brand)
C.2. Blasting Requirements per Cu.m. of solid rock
3 4 sticks of dynamite per borehole2 pcs. Blasting caps per cu.m. of solid rock4 m. safety fuse per cu.m. of solid rock
C.3. Clearing provisions
Deduct 0.60 m. Free Haul DistanceRefer to item 101 C Removal of Slides
-
7/25/2019 Productivity Outputs 1
3/10
Page 3 of 10
C.4. Boring Crew Composition(Capacity of Crew 100 holes / day
1 Construction Foreman
2 Skilled Laborers2 Laborers
C. 5. Blasting Crew composition
(Capacity of crew 100 holes / day)1 licensed Blaster
2 Skilled Laborers2 Laborers
NOTES:
1. Consider reduction of manpower and equipment output for heights of more than1.50 meters and effect of heavy traffic.
2. Provide provisions of scaffolds and incidental expenses for height of more than
1.50 meters.3. All equipments except Dumptrucks and Road Rollers are to be assisted by by a
helper or laborer.
4. Beyond 30.0 meters include Payloader and Pumptruck for disposal of waste,attached the timespotting calculation for hauling in the detailed estimates and
the dumping area. B4065. For Rock excavation, using Bulldozer special equipment such as D155A-3,
D20P-7 etc., indicate the equipment output in the detailed estimate to justify thecosting; and provide equipment data/specification on output to support the
justification.
ITEM 103: STRUCTURE EXCAVATION
Daily Output in Cu.m.Common Excavation Loose Rock Hard Rock
A. Labor 1.50 0.50 0.30B. 0.225 cu.m Backhoe 120.00
C. Jackhammer 20 ft/hour 8 ft/Hr
NOTES:1. For instances where the excavated materials is to be disposed off to a specified
place (Dumping area) computations for such waste disposal shall be considered.
2. Above labor outputs are based on maximum depth excavation of 2.00 metersfor depths of excavation exceeding 2.00 meters, add provisions for hoisting ofdouble/ multiple handling.
-
7/25/2019 Productivity Outputs 1
4/10
Page 4 of 10
ITEM 104: EMBANKMENT
A. SHRINKAGE FACTOR 20% ( For common borrow only)
B. PLACING
B.1. LaborCommon Earth Hard rock
Daily output in cu.m./man-day 4 cu.m 2.50 cu.m
B.2. Equipment
Output of one unit Road grader 500.00 cu.m./day
C. COMPACTIONC.1. Labor (Tamping)
2 cu.m./Man-day (applicable to backfill for cross drains and retaining walls.
C.2. EquipmentPortable plate compactor 50 cu.m./Day
1 Tonner Road Roller 100 cu.m./day9 11 Tonner Road Roller 300 cu.m /day
Water Truck 8,000 sq.m./day
NOTE: For Hauling of embankment materials, attached timespotting calculation in thedetailed estimates.
ITEM 105: SUB-GRADE PREPARATION
A. EQUIPMENT(Using motorized road grader)
A.1. Reshaping and GradingPreparation of dirt/earth road for application of gravel
Item 200 or item 201 or 300 12, 500.00 sq.m/day
Preparation of gravel road for the construction of Asphalt Concrete pavement9,000.00 sq. m. /day
NOTE: 1. Compaction refer to Item 104
2. For heavy traffic, include the effect of traffic in the productivity output
computation to be included in the detailed estimate.
-
7/25/2019 Productivity Outputs 1
5/10
Page 5 of 10
SPL: AGGREGATE HAULING/TIMESPOTTING
A. QUARRYING
Output of one (1) D4 Bulldozer 210 cu.m./day of unprocessed matl.
B. SCREENING AND STOCKPILING
GENERAL FORMULAFor Wheel Loader:
Q = q x (60/CM) x E
Where:Q Hourly production in cu.m./Hourq Production per cycle
CM cycle time in minutesE Job efficiency
q = q1 x k
Where: q1 Heaped capacity of loader
k Bucket factor
CYCLE TIME (Cm) FOR LOADER1. In a cross loading
Cm = D/F + D/R + Z
2. For V Shaped loading
Cm = D/F + 2 + D/R + 2 + Z3. In Load and carry
Cm = D/F x Z
Where: Cm cycle time in minutes
D Hauling DistanceF Forward speed in meters/minute
R Reverse speed in meters/minutZ Fixed Time (minutes) sum of gear shifting, loading, turning,
dumping and waiting time
-
7/25/2019 Productivity Outputs 1
6/10
Page 6 of 10
Computation of screening and stockpiling output for wheel loaders (articulated), use job
efficiency (E) of 0.83 (83%) Cm = 1.00 Minute (Cycle time for screening 1 bucket ofunprocessed material)
GENERAL FORMULA:
Q = q x ( 60 / Cm) x E; use q = use struck bucket capacity= q x (60/1) x (0.83)
= 49.8 cm./hrwhere: q is the struck bucket capacity. However, for screening fine and course
aggregates, introduce (f) quarry factors to the general formula, therefore,1. For screening fine aggregates
Q = 49.8 qFf (cu.m./hour)
2. For screening course aggregatesQ = 49.8 qFc (cu.m./hr)
Where: Ff = quarry factor for fine aggregates
Fc = quarry factor for course aggregates
Moreover, in the screening process of fine and course aggregates, there is extra timerequired for stockpiling screened waste. Materials which needs to be determined as factor of
cycle time to be multiplied to the above formulas to arrive at the output.
C. LOADING AND UNLOADINGC.1. Loading and Unloading Time
a. Using payloader and dumptrucks1. Aggregates: a.1. Loading Time 5 min.
a.2. Unloading Time 1 min.
a.3 Slack time 2 6 min. Depending on the availability and location of maneuvering area:
2. Boulders 6 minnutes
b. Manual Loading (Crew of 6 laborers to fill one unit)
C2. Capacity of 1 unit Dumptruck 5 cu.m. 1 Hr.
D. SPEED 0F DUMPTRUCK
Speed in KPHBelow 7% Grade 7 12 Above 20%
Dirt Road Paved Dirt Rd Paved PavedLoaded Trip 15 25 10 15 5
W/o Load 20 30 15 20 10
-
7/25/2019 Productivity Outputs 1
7/10
Page 7 of 10
E. STOCKPILING OF BOULDERSE.1 From sideslope: (Barring down and stockpiling)
Labor Capacity 2.00 cu.m/man day
E.2. Picking and stockpiling from riverbedLabor capacity 2.00 cu.m/MD
ITEM 200 AND 201: AGGREGATE SUB-BASE COURSE AND AGGREGATE BASECOURSE RESPECTIVELY
A. SHRINKAGE FACTOR 15%
B. SPREADING CAPACITY OF 1 UNIT RD GRADER 500 cu.m./Day
NOTE: 1. Compaction, refer to item 104
2. For Pakyaw projects, include Civil Engineer and Lab Tech.
In the labor/supervision.C. LABOR/SUPERVISION
1 Foreman
2 Flagmen (Optional)1 Helper/Laborer for every equipment except for dumptrucks and rollers.
ITEM 311 PORTLAND CEMENT CONCRETE PAVEMENT
A. MATERIALSA.1. 9.10 bags of cement per cu. M. of concrete
A.2 Aggregates: Loose VolumeQuantity per cu. M. of concrete
Fine Aggrregates 0.50 cu.m.Coarse Aggregates 0.80 cu.m.
Include other miscellaneous accessories, e.g. dowel bars, joint fillers, curing compound, etc.
B. BATCHING AND CASTING IN PLACE
B.1. Using 2 units 1 - bagger concrete mixer (minimum)a. Capacity 150 bags / day (i.e. 75 bags per 1 bagger concrete mixer
b. Crew members
4 - Masons2 - Carpenters
24 - Laborers
1 - Foremanb.1. Consider water provision
b.2. For Pakyaw projects, include Civil Engineer and Lab tech.c. Equipment support for 2 units 1 bagger
c.1. Consider water provision
-
7/25/2019 Productivity Outputs 1
8/10
Page 8 of 10
c.2. 2 Portable concrete vibratorc.3. 1 Bar cutterc.4. 1 Concrete cutter
c.5. 2 Template depth min = 3c.6. steel forms gauge No. 18
B.2. Using Transit Mixer
1. For No. of trips/day, apply time spotting(Maximum distance of batching plant 10 km.)
2. Crew at Batching Plant3 - Laborers
3. Crew at Project Site1 Foreman
2 - Masons2 - Carpenters
6 - Laborers
4. Equipment RequirementTransit Mixer - quantity depends on the location of batching plant
1 Payloader / backhoe1 - Portable Concrete Vibrator
1 Water Truck1 Concrete Batching Plant (include labor for assembly batching and
lease of batching area)1 Bar cutter
1 Portable Concrete Cutter4 templates
1 Motorized Screeder
C. CURING PROVISIONC.1. Curing Compound, specify, liter additive/bag
C.2. PondingC.3. Combination of the above or any method specified under the 1995 DPWH Std.
Specs.
D. OTHERSD.1. Estimate for continuous 2 days operation.
D.2. Use steel forms gauge No. 18.
D.3. Consider provisions for used oil.D.4. Consider additional support materials for heavy downpour during pouring off
concrete.
D.5. Consider traffic/warning signs as safety measures.
-
7/25/2019 Productivity Outputs 1
9/10
Page 9 of 10
ITEM 400 PILING
CONDITIONS
1. Hammer THD 222. Piles are spotted
Capacity 6 8 meter/hr. depending on type of foundation
ITEM 404 REINFORCEING STEEL BARS
A. MATERIALS
A.1. Tie wires 15 kg wires per ton of steel bars
B. LABOR: (Cutting, bending, fabrication, installation and other miscellaneous works)B.1. Crew Composition: (Minimum Composition)
1 Construction Foreman
2 Skilled Laborers2 - Steelman6 - Laborers
For Pakyaw projects, include one Civil Engineer and Lab. Tech. In
C. EQUIPMENT REQUIREMENT PER GANG
1- unit Bar Cutter2- Bar Bender
ITEM 405 STRUCTURAL CONCRETE
A. MATERIALS
CLASS CEMENT FACTOR SAND FACTOR GRAVEL FACTOR(bags/cu.m.) (Loose vol./cu.m.) (Loose vol./cu.m.)
A 9.10 0.50 0.80B 8.00 0.45 0.85
C 9.50 0.55 0.75D 11.00 0.44 0.73
B. BATCHING AND CASTING IN PLACE
B.1. Crew for 1 bagger or 2 bagger concrete mixer and transit mixer is the same as
Item except for steelman which is included under Item 404 and Carpenterswhich is revised per section D of this Item.
B.2. Supporting equipments for Batching Plant same as Item 311.
C. CURING (Depends on the type of structure)
C.1. Either thru ponding use of curing compound or combination of both or asspecified in the 1995 Standard DPWH Specification.
-
7/25/2019 Productivity Outputs 1
10/10
Page 10 of 10
D. FORMWORKSD.1. Formworks
Minimum Crew Composition. Dependent on the type of structure
1 Construction Foreman2 Carpenters
4 LaborersCapacity: (DEPENDING ON THE TYPE OF STRUCTURE)
1. Fabrication and Installation 35 sq.m./day2. Stripping 60 sq.m./day
E. Include miscellaneous hardware materials in the estimates.
ITEM IV MASONRY WORKS
6 x 8 x 16 CHB
Capacity of Crew of 2 Masons and 3 Laborers 230 pcs./day
(Up to 2.0 m. height of structure
Capacity of crew of 2 Masons and 5 Laborers 230 pcs./day(Above 2.0 height of structure)
ITEM V FORMWORKS
TIMBER FORMS AND SCAFFOLDING1. Fabrication and Installation 35 sq.m./day
2. Removal 60 sq.m./day
Crew Composition1 Foreman
3 Laborers
ITEM 1003 CARPENTRY
1. Roof Framing (one storey building) 10 sq.m./day
2. Ceiling 15 sq.m./day3. Partition
a. Movable 3.5 sq.m/dayb. Fixed 7.0 sq.m/day
4. Exterior Walls 58.0 sq.m./dayCrew Composition
1 Foreman
2 - Carpenters1 Helper