Production Sampling and the Green Quadrant

26
Production Sampling and the Green Quadrant Selected Excerpts From 2009 AATCC Conference Dan Randall Colorways 3/11/2009

description

Production Sampling and the Green Quadrant. Selected Excerpts From 2009 AATCC Conference Dan Randall Colorways 3/11/2009. 2009 Color of the Year. +b*. -a*. +a*. -b*. Color Technologies that Save Money and the Planet. Shade Bands with fewer Hands The $15 Sample Garment - PowerPoint PPT Presentation

Transcript of Production Sampling and the Green Quadrant

Page 1: Production Sampling   and the Green Quadrant

Production Sampling and the Green Quadrant

Selected ExcerptsFrom 2009 AATCC Conference

Dan RandallColorways 3/11/2009

Page 2: Production Sampling   and the Green Quadrant

2009 Color of the Year

Page 3: Production Sampling   and the Green Quadrant
Page 4: Production Sampling   and the Green Quadrant
Page 5: Production Sampling   and the Green Quadrant

+a*

+b*

-b*

-a*

Page 6: Production Sampling   and the Green Quadrant

Color Technologies thatSave Money and the Planet

• Shade Bands with fewer Hands

• The $15 Sample Garment

• Virtual QC Check at the DC

Page 7: Production Sampling   and the Green Quadrant

Memories of Charleston

• Number of lab dips produced per year for Retail/Brand companies in the USA: 5,475,398

• Cost of producing these dips: • $481,835,024

• Cost of sending by courier: >$20,000,000

• Dips 5,475,398 x 4” size = 345 miles of dips end to end.

Page 8: Production Sampling   and the Green Quadrant

1 – Retailer A Production Sampling

• <2002 All SBs were sampled and expedited to Retailer’s Offices

• 2002-Present: Shift from Physical to Electronic Sampling

0

20

40

60

80

100

120

140

2002

2004

2006

2008

SBs

/1000

Page 9: Production Sampling   and the Green Quadrant

From Physical to Electronic

0

20

40

60

80

100

120

140

Phys

E SBs

Page 10: Production Sampling   and the Green Quadrant

SBE Process

Images courtesy of

Page 11: Production Sampling   and the Green Quadrant

2008 Shade Band results

• Total SBs tested: 104,529• Total Approved: 82,769 (~80%

passing)• SB Physicals : 22,250

• SBs not requiring physicals: 82,279• Savings in shipping costs: $2.9M

Page 12: Production Sampling   and the Green Quadrant

2002-Present

• Shade Bands – Electronic: 464,200• Saving to Suppliers, shipping: $16.3M

• Lab Dips – 9,500 /month = 114,000 / year– 40% electronic = 45,600 – Savings in shipping cost: $1.6M

• Total Cost Savings in Shipping: $27.5M

Page 13: Production Sampling   and the Green Quadrant

2 - The $15 Sample Garment

• Lifesize• Color Accurate• Realistic

Did I mention they are printed on paper?

Page 14: Production Sampling   and the Green Quadrant

Visualize the collection

Page 15: Production Sampling   and the Green Quadrant

Garment MappingWith just one suitable plain ‘donor’ garment ……

and a pattern repeat in an electronic file……

orStripe dimensions….

and the required shades…….

Page 16: Production Sampling   and the Green Quadrant

Virtual Garments, Savings in..

Transporting SamplesTime-consuming Admin.

Making-up into garments

Slides courtesy of

Page 17: Production Sampling   and the Green Quadrant

3 - Virtual QC Check at the DC

• Sampling garments that are not measurable

• Denim, prints, for example

Page 18: Production Sampling   and the Green Quadrant

Communicating Quality

Photos courtesy of

Page 19: Production Sampling   and the Green Quadrant

Environmental Benefits

• Difficult to calculate exactly

• Approximate by– Shipping Process– Fuel Consumption– GHG (CO2) output

Page 20: Production Sampling   and the Green Quadrant

One Package from Suzhou

All maps by GoogleEarth

Page 21: Production Sampling   and the Green Quadrant

One Package from Suzhou

• Shanghai to Anchorage – 4,331 miles – 8.75 hrs– 8,500 gal Fuel

Page 22: Production Sampling   and the Green Quadrant

One Package from Suzhou

• Anchorage to Memphis Superhub – 3,142 miles – 6.25 hrs– 4,700 gal Fuel

Page 23: Production Sampling   and the Green Quadrant

One Package from Suzhou

• Memphis to Tulsa – 411 miles – 0.9 hrs– 675 gal Fuel

• Tulsa to Retailer– 101 miles, Truck– 7 MPG = 14.4 gal

Page 24: Production Sampling   and the Green Quadrant

One Package from Suzhou

• Total: 8,035 miles• Fuel Consumption:

– 13,889 gallons

• 4.6B gallons annually for shipping• 2.5B US deliveries• 2.4B Tons CO2 from US deliveries

Page 25: Production Sampling   and the Green Quadrant

Just ask yourself….

• Do I really need that 3rd Lab Dip?

• Do I really need to dip every color in the palette?

• Am I working toward digital color processes that reduce physical sampling?

Page 26: Production Sampling   and the Green Quadrant