Production Planning Interview Questions and Answers for Experienced _ PP (Production Planning)...

download Production Planning Interview Questions and Answers for Experienced _ PP (Production Planning) Interview Questions _ STechies

of 7

Transcript of Production Planning Interview Questions and Answers for Experienced _ PP (Production Planning)...

  • 8/17/2019 Production Planning Interview Questions and Answers for Experienced _ PP (Production Planning) Interview Questio…

    1/7

    5/9/2016 Production Planning Interview questions and Answers for Experienced | PP (Production Planning) Interview Questions | STechies

    http://www.stechies.com/interview-questions-of-production-planning/ 1/7

    Feedback

    Download AppWrite

    New User?

    Production Planning Interview questions and Answers for Exper ienced

    By: rekha | Google  | 06 Feb 2008 9:34 am | 6322 times viewed | 0 Comments

     

    Q1: How to configure the planning calendar 

    for the ATP calculation where goods are

    shipped every other working day?

    Ans: Use Transaction MD25 and define

    calculation rule for every other working day.

    Check the lot size settings in OMI4 and

    maintain relevant data in MMR.

    Q2: We have two different production lines

    with different operations. One production

    line works 5 days a week and the other 7

    days a week. The factory calendar is

    assigned to the plant for 5 days a week.

    This calendar is checked when MRP is run.

    How can we assign 5 day a week and 7 days a week against a factory calendar to the related

    resources? Is it possible to have two types of calendars?

    Ans: Assign factory calendars to the work centers.

    Q3: What is the difference between by-product and co-product and how do you differentiate

    them in a BOM?

    Ans: In case of Co-product costs are settled with a apportionment structure. In case of By-product the

    price of this by-product is credited to the order or t he material stock account of the lead material being

    manufactured. Co-Product as well as by-product are defined as BOM Components/Items. Both of them

    have negative quantities. ( Not all negative quantity items fall under these categories!). When BOM is

    cr eated for FERT , you can see one indicator in COMPONENT DET AILS screen for co-product. You

    need to define the co-products with this special indicator .

    Q4: What are some important tables used in PP ?

    Ans: For orders:

    CUAFVD dialog structure for order headers and items

     AFPO - Order item

     AFFLD Order: Dialog table for order sequences (AFFL)

    MOPER Operation for production order 

    KBED Capacity requirements

     AFRU Order completion confirmations

    RESB Reservation/Dependent Requirements

     AFFHD Structure of PRT's in orders

    SOPER Sub-operations

    SAFRU Sub-operation confirmations

    SKBED Capacity requirements for sub-operation

    MRP table is MDTB.

    For PI:

    CAUFV - AFVC Operation within an order 

     AFFT Order Process Instructions

     AFFV Order process instruction values

    Some other tables of interest:

    PLKO, MAPL , PLAS.

    Bills Of Material

    PP (Production Planning)  » PP (Production Planning) Interview Questions Login To FollowTutorials

    Production Planning

    SAP Production Planning ( PP)

    Course, Fees, Career & Certification

    SAP PP (Production Planning) Course

    & Certification Fee

    Job Profile & Salary Package for SAP

    PP (Production Planning) Consultant

    WorkCenters and Routing in SAP PP

    Production Planning

    ForumsConversion of production plan

    Mass processing in Production

    Planning

    CBP PlanningSome training institutes which can

    help in Production Planning module.

    How to Fix Error in Editing Production

    (Planned) Key Figure?

    BE Mechanical Engineer Experienced

    with Production?

    What are the essential thing to be

    confogured in enterprise structure for 

    production planning

    Can we use the periodic billing plan

    type for sales products not a service?

    Function Materials Requirements

    Planning

    Standard Planning limits?????

    BooksProduction Planning with SAP APO

    Production Planning and Control with

    SAP ERP

    Search e.g. SAP ABAP

      1     0     0     0   Like

    ASK US !Get solutions from our experts!

    Register Login

    Tutorials Answers Books  Interview

    Questions  Jobs

      Courses &Institutes

    TransactionCodes

      Sam ple R es um e N ews   SAP Career Guidance

    http://www.stechies.com/production-planning_1/http://www.stechies.com/job-profile-salary-package-sap-pp-production-planning-cons/http://www.stechies.com/about-sap-production-planning-pp-course-fees-career-certif/http://www.stechies.com/login.php?refUrl=/interview-questions-of-production-planning/http://www.stechies.com/production-planning_2/http://www.stechies.com/tutorials/http://www.stechies.com/forums/http://www.stechies.com/pdf-books/http://www.stechies.com/interview-questions/http://www.stechies.com/jobs/http://www.stechies.com/courses/http://www.stechies.com/transaction-codes/http://www.stechies.com/sample-resumes/http://www.stechies.com/news/http://www.stechies.com/career-guidance/http://www.stechies.com/http://www.stechies.com/contactus.phphttp://www.stechies.com/home/new.phphttp://www.stechies.com/login.php?refUrl=/interview-questions-of-production-planning/https://accounts.google.com/o/oauth2/auth?response_type=code&redirect_uri=http://www.stechies.com/googleconnect/login.php&client_id=33012380205-ukj5r00h0trsgfj25vb8bkikfcqnd2kb.apps.googleusercontent.com&scope=https%3A%2F%2Fwww.googleapis.com%2Fauth%2Fuserinfo.email+https%3A%2F%2Fwww.googleapis.com%2Fauth%2Fplus.me&access_type=offline&approval_prompt=forcehttp://www.stechies.com/linkedinConnect/auth.php?refUrl=interview-questions-of-production-planning&login=1http://www.stechies.com/hello-experts-have-question-about-periodic-billing-plan-per/http://www.stechies.com/hello-experts-have-question-about-periodic-billing-plan-per/http://www.stechies.com/techanical-associtate/http://www.stechies.com/techanical-associtate/http://www.stechies.com/techanical-associtate/http://www.stechies.com/standard-planning-limits/http://www.stechies.com/function-materials-requirements-planning/http://www.stechies.com/career-guidance/http://www.stechies.com/news/http://www.stechies.com/sample-resumes/http://www.stechies.com/transaction-codes/http://www.stechies.com/courses/http://www.stechies.com/jobs/http://www.stechies.com/interview-questions/http://www.stechies.com/pdf-books/http://www.stechies.com/forums/http://www.stechies.com/tutorials/http://www.stechies.com/production-planning-control-sap-erp/http://www.stechies.com/production-planning-sap-apo/http://www.stechies.com/standard-planning-limits/http://www.stechies.com/function-materials-requirements-planning/http://www.stechies.com/hello-experts-have-question-about-periodic-billing-plan-per/http://www.stechies.com/production-planning_1/http://www.stechies.com/mechanical-enigineer-having-4-years-experience-production-o/http://www.stechies.com/fix-error-editing-production-planned-key-figure/http://www.stechies.com/techanical-associtate/http://www.stechies.com/cbp-planning/http://www.stechies.com/mass-processing-in-production-planning/http://www.stechies.com/conversion-of-production-plan/http://www.stechies.com/workcenters-and-routing-in-sap-pp-production-planning/http://www.stechies.com/job-profile-salary-package-sap-pp-production-planning-cons/http://www.stechies.com/sap-pp-production-planning-course-certification-fee/http://www.stechies.com/about-sap-production-planning-pp-course-fees-career-certif/http://www.stechies.com/production-planning_2/http://www.stechies.com/login.php?refUrl=/interview-questions-of-production-planning/http://www.stechies.com/pp-production-planning-interview-questions/http://www.stechies.com/pp-production-planning/http://www.stechies.com/bill-of-material-bom/https://plus.google.com/101501905990081907259?rel=authorhttp://www.stechies.com/linkedinConnect/auth.php?refUrl=interview-questions-of-production-planning&login=1https://accounts.google.com/o/oauth2/auth?response_type=code&redirect_uri=http://www.stechies.com/googleconnect/login.php&client_id=33012380205-ukj5r00h0trsgfj25vb8bkikfcqnd2kb.apps.googleusercontent.com&scope=https%3A%2F%2Fwww.googleapis.com%2Fauth%2Fuserinfo.email+https%3A%2F%2Fwww.googleapis.com%2Fauth%2Fplus.me&access_type=offline&approval_prompt=forcehttp://www.stechies.com/login.php?refUrl=/interview-questions-of-production-planning/http://www.stechies.com/home/new.phphttps://play.google.com/store/apps/details?id=app.stechies.comhttp://www.stechies.com/contactus.phphttp://www.stechies.com/

  • 8/17/2019 Production Planning Interview Questions and Answers for Experienced _ PP (Production Planning) Interview Questio…

    2/7

    5/9/2016 Production Planning Interview questions and Answers for Experienced | PP (Production Planning) Interview Questions | STechies

    http://www.stechies.com/interview-questions-of-production-planning/ 2/7

    Q5: We have a BOM - 'A' with two packing materials 'X' and 'Y'. For 1000 units of 'A', 1 packing

    material of 'X' is required and for 50 units of 'A', 1 packing material of 'Y' is required. Base

    quantity of 'A' is defined as 1000. How can I define 'X' & 'Y' or in fact 'A'?

    Ans: Make the base quantity of 'A' as 5000. The resulting component quantities would be 5 of 'X' and

    100 of 'Y'.

    Work Centers

    Q6: Can we have more than 6 standard values in standard value key?

    Ans: One way to achieve this is to create another operation step using the same work center. However 

    this shall be with a control key that is not a milestone. When the milestone operation is confirmed, theprevious operations up to the next milestone are automatically confirmed. To get the desired number of 

    standard values , all the 'non milestone' steps can be built depending on the need.

    Routing

    Q7: Can we use same routing for materials undergoing the same process/operations? Can we

    avoid separate routing for each and every material produced?

    Ans: Presume that there are 50 products and the fabrication shop uses a set of 10 machines. If all

    these products use the same settings of the machines, Reference Operation Sets (task list type S) can

    be setup for common processes that use the same work centers. However costing, scheduling and

    capacity will be affected if each product has different setup time and Reference Operation sets can not

    be used.

     A routing for each material number ( type N or R) has to be set up and within that routing, theReference Operation Set can be used.

    However you can by try utilizing the KMAT material and product variants invariant configuration to avoid

    separate routing for each material.

    Ans: You may create a routing group. Go into routing creation and enter the plant and the group name.

    If you want you may name the group , else name is assigned by internal counter). Create the routing

    with the work centers, operation times, etc. Go to the "Header overview" screen and click on the "Mat

     Alloc" screen. Fill in the blanks with all the material masters that use this routing.

    Q8: Scheduling times can be defined in the material master record by;

    # entering the in-house production time. This value can be updated from the routing by the

    system.

    # entering the setup, tear down, processing, and interoperation times. If these values are

    maintained, the system determines the in-house production time on the basis of lot size.

    How do you get the system to update this value from the routing?

    Ans: In routing, carry out scheduling. Go into the routing operation overview and follow Extras ->

    Scheduling -> Results. The pop-up window displays the scheduling data. At the bottom there is a

    pushbutton to copy the scheduling data to the material master Check this push button to update master 

    data.

    Q9: We have deleted a group key in an operation in routing and the same does not appear for 

    this routing (CA02). But we noticed that entries are maintained in table PLPO and the deletion

    indicator is not set. How does the system remember this deletion of group key?

    Ans: You may look at the tables PLKO, MAPL and PLAS.

    Sales & Operations Planning

    Q10: We defined SOP in months. However during SOP transfer to demand management, our independent requirements are appearing in weeks. How can we correct this from weeks into

    months ?

    Ans: Check transaction OMPA for general split. OMPS - based on the MRP group. Ensure that MRP

    group assigned to the material. Delete any allocations in these tables. Then periods will be transferred

    to Demand Management with the same splits as in SOP. Also check whether the value of period is set

    as "month" at your plant level in Transaction 'OMP7'

    Demand Management

    Q11: Sales quantities in SOP for certain days are transferred into Demand Management and are

    shown as planned independent requirements. We need to keep the settings in SOP and change

    the periods in Demand Management? We would like to have a rolling horizon, for ex: the

    following 4 weeks on a daily basis, after that on a monthly basis. What is the best way to do

    this?

    Ans: Use the automatic period split function.

    M R P

    Q12: We have a lot size procedure here which is creating more order proposals. How do you set

    Materials Planning with SAP

    SAP Product Costing Configuration

    SAP product costing master data

    R/3 System Product Costing

    Sales and Inventory Planning with

    SAP APO

    SAP Business Planning and

    Consolidation

    SAP BusinessObjects Planning and

    Consolidation

    Characteristic Based Planning with

    mySAP SCM

    Jobs

    System Software Engineer | 0 - 1 yrs | Bengaluru /

    Bangalore

    Exp :0 - 1 years | City : Bangalore

    Software Developer | 0 - 1 yrs | Bangalore | Oracle

    Exp :0 - 1 years | City : Bangalore

    SAP Fresher 

    Exp :0 - 1 years | City : Mumbai

    SAP Design Build Project Manager | 3 - 8 Years |Kolkata | I

    Exp :3 - 8 years | City : Kolkata

    SAP Basis Administrator - GTS - SD | 4 - 7 Years |

    Chennai |

    Exp :4 - 7 years | City : Chennai

    SAP Basis Consultant

    Exp :3 - 8 years | City : Gurgaon

    SAP HANA COE Manager Opening | 12 - 15 Years |

    Hyderabad | Z

    Exp :12 - 15 years | City : Hyderabad

    Scrum Management | 2 - 5 Years | Gurgaon |

    Accenture

    Exp :2 - 5 years | City : Gurgaon

    Customer Support Voice | 1 - 3 Years | Noida |

    Accenture

    Exp :1 - 3 years | City : Noida

    Automated Functional Test Planning-preparation-

    execution1 |

    Exp :2 - 5 years | City : Bangalore

    http://www.stechies.com/automated-functional-test-planningpreparationexecution1-2_job/http://www.stechies.com/customer-support-voice-1-3-years-noida-accenture_job/http://www.stechies.com/scrum-management-2-5-years-gurgaon-accenture_job/http://www.stechies.com/sap-hana-coe-manager-opening-12-15-years-hyderabad-zens_job/http://www.stechies.com/sap-basis-consultant_10_job/http://www.stechies.com/sap-basis-administrator-gts-sd-4-7-years-chennai-ibm_job/http://www.stechies.com/sap-design-build-project-manager-3-8-years-kolkata-ibm_job/http://www.stechies.com/sap-fresher_job/http://www.stechies.com/software-developer-0-1-yrs-bangalore-oracle_job/http://www.stechies.com/system-software-engineer-0-1-yrs-bengaluru-bangalore-h_job/http://www.stechies.com/characteristic-based-planning-mysap-scm/http://www.stechies.com/sap-businessobjects-planning-consolidation/http://www.stechies.com/sap-business-planning-consolidation/http://www.stechies.com/sales-inventory-planning-sap-apo/http://www.stechies.com/r3-system-product-costing/http://www.stechies.com/sap-product-costing-master-data/http://www.stechies.com/sap-product-costing-configuration/http://www.stechies.com/materials-planning-sap/

  • 8/17/2019 Production Planning Interview Questions and Answers for Experienced _ PP (Production Planning) Interview Questio…

    3/7

    5/9/2016 Production Planning Interview questions and Answers for Experienced | PP (Production Planning) Interview Questions | STechies

    http://www.stechies.com/interview-questions-of-production-planning/ 3/7

    the limit value for maximum number of MRP order proposals per date in IMG?

    Ans: Under customization, try materials management->consumption based planning->maintain all

    plants

    Q13: What is the difference between "planned consumption" and "Unplanned consumption"?

    Can safety stock calculation be done on either of these?

    Ans: While customizing movement types (OMJJ) it is defined as to which set of consumption values

    gets posted during the material movement. For some it may always be the total consumption and for 

    some it is always the unplanned one and for some it is dependent on whether the issues were done

    with reference to a reservation ie., a planned consumption. The way these consumption values are

    taken into account in MRP is defined in the customizing of MRP types.

    For Reorder point planning (VM) the total consumption is used to calculate the safety stock and the

    reorder point.

    For Forecast based planning (VV) the total consumption is used to build the forecast which will be used

    to compile the order proposals.

    For Deterministic MRP (PD) the unplanned consumption is used to calculate the forecast which in turn

    is added to the actual demand.

    Q14: We want the system to run a single level MRP automatically on receipt of sales order. How

    to configure triggering event based MRP?

    Ans: This can only be run if material master has planning strategy 41 (made-to-order) in the MRP2

    view. We need to run for other MRP types. We have to create a user exit in the sales order processing

    (VA01) to start MRP based on data from our sales transaction.

    Q15: We have an assembly 'A' using a subassembly 'B'. 'B' in turn uses raw material 'C'. Item 'A'is an MPS and is duly marked in Material Master. Item 'B' and 'C' are marked as 'PD'. When

    demand for 'A' is entered and MPS is run , upto which level the requirements are taken care of?

    Ans: MRP can be run depending on your requirement. For example:

    Single Item / Single Level from MPS - Transaction Code MD42 - Only the top MPS item ( 'A' in this

    case) is planned and dependent requirements will be passed to MRP item ( 'B' ) . Run MRP,

    Transaction MD02 on 'B' to plan it and all MRP items below .

    Single Item / Multi Level from MPS - Transaction Code MD41 - All levels are planned - A , B & C

    Read Here for more SAP PP (Production Planning) Transaction Codes.

    Total Planning from MPS online or background - Transaction Code MD40 or MDBS

    Without marking the checkbox " Process MRP materials" is like case ( 1) above and with the checkbox

    marked is like case (2 ).

    Production Orders

    Q16: We get an error message "Control parameters for scheduling not defined" while creating

    test production Orders. Why?

    Ans: Before you attempt creating Production orders, configure your 

    Order types- Transaction Code OPHJ

    Order type Dependent parameters - Transaction Code OPL8

    Backorder Scheduling - Transaction Code OMIH

    Scheduling Levels - Transaction Code OMIF

    Q17: We are trying to create Purchase Requisition from MRP run. We have material , info

    Record, Source list , Demand in place. MRP is always creating plan order. Why?

    Ans: Check the procurement type in MRP view of material master. Check 'Create Purchase requisition'

    indicator while running MRP. If you want purchase requisitions to be created in the opening period,

    select the for MRP control parameter 'create purchase requisitions' as '1'.

    Q18: what is the option "Documented goods movements" on Selection of Individual Object

    Lists (transaction code CO28)?

    Ans: Use Transaction code OPL8 to customize by choosing the order type, select all the checkbox

    under "Documentation of goods movements" at the bottom of the page. Create a new Production order,

    make GI to it, and run the report.

    Q19: We would like to have a report/inquiry that would indicate variances (materials, material

    quantities) between material recipe and actual process orders. We tried ME2M but this gives us

    a list of purchasing documents and not the consumption deviation. Where can I get such

    consumption deviation (master recipe Vs. Process> Orders)?Ans: Do a data collection first.

    Menu Path - Accounting->Controlling->Product cost acctg->Process mfg->Information system->Cost

    object hierarchy->data collection

    (If you are using order hierarchy you would select order hierarchy in place of cost object hierarchy in

    the menu path.)

    Then,

    http://www.stechies.com/pp-production-planning-transaction-codes/

  • 8/17/2019 Production Planning Interview Questions and Answers for Experienced _ PP (Production Planning) Interview Questio…

    4/7

    5/9/2016 Production Planning Interview questions and Answers for Experienced | PP (Production Planning) Interview Questions | STechies

    http://www.stechies.com/interview-questions-of-production-planning/ 4/7

     Accounting->Controlling->Product Cost Accounting->Order Related Production->Information System

    Choose Report Period Costing - Target/Actual production variance

    Q20: We have two components ( 'X' & 'Y' ) in a production order in a process oriented

    production process. When 50 numbers of component 'X' are issued, we need the system to

    automatically issue 100 numbers of component 'Y' based on ratio of 1 to 2. Where do I specify

    these ratios?

    Ans: You can define the ratio in BOM and material may be issued with reference to BOM.

    Q21: We have two storage locations are '0001' and '0600'. Default storage location in Process

    order is always '0001' What determines this default location?

    Ans: Look into OSS notes: 100757, 63493, 96262, 87843, 82033, 64946.

    The Storage location as configured in the Supply area has the highest priority.

    Q22: We need to do GI of components to production order using Back-flush. The component

    stock is managed in Batches. The Batch to be back-flushed

    Ans: With the following settings, the batches are selected the moment the production order is released.

    1: Set up batch determination the way that the batches in batch selection are sorted the right way. e.g.

    sorted by expiry date

    2: Use automatic batch selection in disp view.

    3: Ensure that the components are allowed to be back-flushed (material master / work center) is

    selected by FIFO from the issue storage location. How can we set this up?

    Q23: We want to report on several status combinations like each order that has status 'Not

    deleted' and 'Not technically completed'. What set up is required?Ans: Check transaction CO28. In the selection screen note the possible selection 'System Status' . You

    can select TECO for technically complete an DLT for deleted from the list. Select the Excl. indicator 

    also.

    You may also try transaction CO26 (Logistics -> Production -> Production control -> Control ->

    Information systems -> Order Info System -> Object overview). Before executing the transaction report,

    combinations of statuses can be selected or exclude them.

    Q24: How can we shut off the "automatic costing indicator" and the "automatic scheduling

    indicator" which go on when the production order is released?

    Ans: For "no automatic costing" follow the IMG path

    Production -> Production orders ->Master data -> Order - >Define order type dependent parameters

    Select the order type for which u automatic costing is not required. In the controlling settings, select "no

    automatic costing"

    For "no automatic scheduling" , follow the IMG path :Production ->Operations - >Scheduling -> Define control parameters

    Select the order type and go to details. Deselect " automatic dates "

     Alternatively, you can find indicators in the control key, which is in the routing. Transaction OPL8 gives

    you costing indicators (Order type dependent parameters), and OPJU (control table for scheduling)

    gives some scheduling options.

    Variable Size

    Q25: How can I use variable size items?

    Ans: For example, consider an item A with 'kg' as base Unit Of Measurement(UOM) and 'm3' as stock

    keeping/issue unit. Conversion factor is 1kg = 2.4 m3.

    In the BOM of 'B' ,number of A required are specified (say 5).

    Specify the 3 variable dimensions i.e. length, width & thickness- say 2000mm X 3000mm X 4mm =0.024 m3

     As per BOM - 'B' , the quantity of A required is 0.024 X 5 = 0.120 m3

    If a production Order is released for 15 numbers of 'B' , the quantity of variable size unit will be 1.20 m3.

    You can change the length, width or thickness in the production order & check the resulting variable

    size item quantity. At the same time this requirement can be seen in 'kg' in stock/requirement list.

    Q26. Can MRP be carried out for one particular level of a bom ( Level code : 0001/0002 etc).

    Ans: Yes it can be done by running for specific materials (Single Material Single Level)

    Q27. How Requiements( PIR,Sles Order, Customer Requirement) are reduced after they are

    produced?

    Ans: Reqmts are reduced automatically after Delivery is made to the Particular Order 

    (In case of Strategy 11, the PIRs are consumed after the GR for Production Order)

    Q28. Can't one material be assigned to more than one operation in a routing?

    Ans: One material from a BOM CANNOT be assigned to different Operations.

    It can be done by defining the material for so many times as required in the BOM

    Q29. How to insert an inspection checkpoint at the end of an operation?

  • 8/17/2019 Production Planning Interview Questions and Answers for Experienced _ PP (Production Planning) Interview Questio…

    5/7

    5/9/2016 Production Planning Interview questions and Answers for Experienced | PP (Production Planning) Interview Questions | STechies

    http://www.stechies.com/interview-questions-of-production-planning/ 5/7

    Sign up for STechies

    Add Answer

    SAP comes to Rescue Indian RailwaysIndian railways were originally founded in the year 1853 and now areknown as the largest rail network in Asia. It is interesting to know thatthere are more than 6000 stations and almost 20 million passengerstravel daily through trains. Apart from being a favored mode of transport,the railways...

    Top 10 Highest Paid SAP Companies in UK in 2015Though there are numerous companies in the industry that provide SAPsolutions and other related services to their global clients, not all of them

    shine equally in the field. The major reason is variation in the efficiency of the employees and working flexibility. The organizations which are able...

    Important SAP KEYBOARD SHORTCUTS ListKEYBOARD SHORTCUTS Instead of an SAP icon button, you can use a keyboard shortcut. Akeyboard shortcut is a key or combination of keys that you can use to access icon button functions

    Ans: If in process sample is to be defined, assign inspection type 03 in the Material Master.

    Then create MICs and assign them in the Routings.

    System automatically generates the Inspection Lots

    Q30. Where we have to specify the teardown time in one operation?

    Ans: Teardown time can be defined as one of the Standard Parameters...

    Q31. How the process time is calculated in a WC when both labour, Machine categories exist?

    Ans: Scheduling is done based on the Capacity Category we define in the Workcenter 

    Q32. How to create opbject dependencies in a BOM FOR A CONFIGURABLE MATERIAL?

    Ans: Go to Extras -> Object Dependency -> Assign

    For this you need to create Characteristics and Class (of Class Type 300) earlier 

    Q33. Can any body explain me why work scheduling view is required for semi finished and

    finished products? (Because we'll mention all details in MRP views)

    Ans: We need to maintain working scheduling view in order to make that finished or semi finished

    goods available for production as we assign production scheduler and production scheduler profile in

    this view, if not maintained conversion of planned order to production will not be possible.

    Get More Questions and Answers with Explanation at SAP PP (Production Planning) Forums.

    Comments

    No Comments Posted for this Article.

     Add your Answer...

    Next Story

    http://www.stechies.com/pp-production-planning-forums/http://www.stechies.com/keyboard-shortcuts/http://www.stechies.com/top-10-highest-paid-sap-companies-uk-2015/http://www.stechies.com/top-10-highest-paid-sap-companies-uk-2015/http://www.stechies.com/sap-comes-rescue-indian-railways/http://www.stechies.com/sap-comes-rescue-indian-railways/http://www.stechies.com/login.php?refUrl=/interview-questions-of-production-planning/https://accounts.google.com/o/oauth2/auth?response_type=code&redirect_uri=http://www.stechies.com/googleconnect/login.php&client_id=33012380205-ukj5r00h0trsgfj25vb8bkikfcqnd2kb.apps.googleusercontent.com&scope=https%3A%2F%2Fwww.googleapis.com%2Fauth%2Fuserinfo.email+https%3A%2F%2Fwww.googleapis.com%2Fauth%2Fplus.me&access_type=offline&approval_prompt=forcehttp://www.stechies.com/login.php?refUrl=/interview-questions-of-production-planning/

  • 8/17/2019 Production Planning Interview Questions and Answers for Experienced _ PP (Production Planning) Interview Questio…

    6/7

    5/9/2016 Production Planning Interview questions and Answers for Experienced | PP (Production Planning) Interview Questions | STechies

    http://www.stechies.com/interview-questions-of-production-planning/ 6/7

    while you are working in SAP. On a PC, the icon name and keyboardshortcut are displayed when you place the mouse...

    SAP's Partnership with Apple Makes Way for the DynamicCombination of HANA-iOS

     Apple Inc is teaming up with the wor ld’s software giant SAP to enter thecorporate computing world. This news has been confirmed by both thecompanies on Thursday.The American multinational technology company,

     Apple INC has in the past couple of years teamed up with the well-knownbrands like...

    Top 10 Tips to make Your SAP Implementation SecuredDevoid of clear ownership of security for a serious business platform likeSAP, it should come as no wonder that SAP cyber security endures to fallthrough the cracks among IT, admin, and security and InfoSec teams.Tip1: Recognize the RiskThe first tip is to recognize the risk. Same like theother...

    Related

    Production Planning

      Production Planning (PP) Work center CRHH Work center hierarchy ...

    SAP Production Planning ( PP) Course, Fees, Career & Certification

    SAP Production Planning ( PP) generally encompasses the integration and streamlining of thevaried needs of a manufacturing enterprise and takes care of the proper planning of its alliedprocesses...

    Conversion of production plan

      My Question is that can some body explain that how to enter the production plan in pp. And theworking after that (work center, capicty planning etc).can some body will provide the...

    SAP PP (Production Planning) Course & Certification Fee

    Basic and advance level SAP PP training can be under taken by the interested candidates fromreputed institutes world wide. The duration of the course varies from the level of competencies...

    Job Profile & Salary Package for SAP PP (Production Planning) Consultant

    Still this sector needs good number of Indian professionals. Currently 7 out of 10,000 of all Indianprofessionals are having expertise in SAP PP.The demand is huge and thus this is a goodcourse...

    Production Planning with SAP APO

    Contents t tt tttIntroduction ............................................................................... ttt13 tt tt ttt1 AnOverview of Planning with SAP SCM...

    WorkCenters and Routing in SAP PP Production Planning

    For SAP PP consultants, it is very important to understand the concept of SAP workcenters aswell as routings in SAP. Workcenters are an important part of production planning in SAP. In thesimplest...

    SAP Production Planning Table

    Demand Management PBED Independent Requirements Data PBIM Independent Requirementsby Material Repetitive Manufacturing SAFK RS Header Master Data S025...

    Production Planning Transaction Codes

    Transaction Activity Master Data MD25 Create planning calendar MD26 Change planningcalendar MD27 Display planning calendar MDSA Display BOM explosion number MDSP EditBOM explosion...

    APO - R/3 Integration in Production Planning

    Transferring Sales Orders from R/3 to APO Purpose If APO is used as a planning system for aproduct, planning may only be carried out in the APO System. Planning in R/3 and APO willreact...

    Production Planning and Control with SAP ERP

    Contents t tt tttForeword ...................................................................................... ttt13 tt tt ttt1Introduction...

    Production Planning - Production Control System Messages

    You can manage the production control system messages with transaction OPJB. In this step youcan specify whether the SAP System will :- - suppress this information - displays it as a...

    SAP PRODUCTION & PLANNING PDF MATERIAL.

    hi all, I am kishore with more than 7 years experience in manufacturing,production planning. Iwould like to learn sap pp module. Can anyone help me out to find SAP PP MODULE PDF files...

    Mass processing in Production Planning

    Why we are getting a message "No elements exist for the selection" while executing transactioncode COHV for shop floor paper printing .

    SAP HR Interview Questions for Experienced

    SAP HR Questions by [email protected] characteristics does a day with day type 1

    http://www.stechies.com/saphr-interview-questions-by-smdsirajwiprocom/http://www.stechies.com/mass-processing-in-production-planning/http://www.stechies.com/sap-production-planning-pdf-material/http://www.stechies.com/production-planning-production-control-system-messages/http://www.stechies.com/production-planning-control-sap-erp/http://www.stechies.com/apo-r3-integration-production-planning/http://www.stechies.com/production-planning/http://www.stechies.com/sap-production-planning-table/http://www.stechies.com/workcenters-and-routing-in-sap-pp-production-planning/http://www.stechies.com/production-planning-sap-apo/http://www.stechies.com/job-profile-salary-package-sap-pp-production-planning-cons/http://www.stechies.com/sap-pp-production-planning-course-certification-fee/http://www.stechies.com/conversion-of-production-plan/http://www.stechies.com/about-sap-production-planning-pp-course-fees-career-certif/http://www.stechies.com/production-planning_2/http://www.stechies.com/top-10-tips-make-your-sap-implementation-secured/http://www.stechies.com/top-10-tips-make-your-sap-implementation-secured/http://www.stechies.com/saps-partnership-apple-makes-way-dynamic-combination-hanaio/http://www.stechies.com/saps-partnership-apple-makes-way-dynamic-combination-hanaio/http://www.stechies.com/keyboard-shortcuts/

  • 8/17/2019 Production Planning Interview Questions and Answers for Experienced _ PP (Production Planning) Interview Questio…

    7/7

    5/9/2016 Production Planning Interview questions and Answers for Experienced | PP (Production Planning) Interview Questions | STechies

    http://www.stechies.com/interview-questions-of-production-planning/ 7/7

    have? Its OFF and PaidCan a posting run be deleted? Yes It can be reversed before the Banktransfer.Once the...

    Qualifications and Skills requires to become a SAP PP (Production Planning) Consultant

    Thus the basic skills required are: Good educational background, with a degree from reputedinstitute or university Basic knowledge of computers and information technology ...

    PP - The Common Planning Strategy used

    The planning strategies are maintained in Customizing for Demand Management in SM30 -V_T461S. Define the Planned Requirement Type and assign the requirement class in OMP1.Define the...

    SAP PROJECT SYSTEMS AND PRODUCTION PLANNING TRAINER- SAP CERTIFIED

    My name is Suresh, having 12 years of SAP R/3 Consulting experience in Project Systems,

    Production Planning and Variant Configuration Modules and 6 years of Industry experience in thecore areas of...

    Compare Production Confirmation against Planned by Work Centre

    * * Compare Production Confirmation against Planned by Work Centre * REPORTZASSEMBLY_EFFICIENCY LINE-SIZE 255 NO STANDARD PAGE HEADING LINE-COUNT065(001). TABLES: AFKO...

    Home   Tutorials   Answers   Books   Interview Questions   Transaction Codes   Jobs   Classifieds   News   Announcements

    Contact Us  Terms Of Use  Terms & Conditions   Site Map  We are Hiring

    All the site contents are Copyright © www.stechies.com and the content authors. All rights reserved. All product names are trademarks of their respectivecompanies. The site www.stechies.com is in no way affiliated with SAP AG. Every effort is made to ensure the content integrity. Information used on this

    site is at your own risk. The content on this site may not be reproduced or redistributed without the express written permission of www.stechies.com or the contentauthors.

    http://www.stechies.com/careers.phphttp://www.stechies.com/sitemap.phphttp://www.stechies.com/terms-conditions.phphttp://www.stechies.com/terms-of-use.phphttp://www.stechies.com/contactus.phphttp://www.stechies.com/announcements/http://www.stechies.com/news/http://www.stechies.com/classifieds/http://www.stechies.com/jobs/http://www.stechies.com/transaction-codes/http://www.stechies.com/interview-questions/http://www.stechies.com/pdf-books/http://www.stechies.com/forums/http://www.stechies.com/tutorials/http://www.stechies.com/http://www.stechies.com/compare-production-confirmation-against-planned-by-work-centre/http://www.stechies.com/sap-project-systems-and-production-planning-trainer-sap-cert/http://www.stechies.com/pp-the-common-planning-strategy-used/http://www.stechies.com/qualifications-skills-requires-become-sap-pp-production-pla/