Procurement! Observer’s! Guide! - World...

55
Procurement Observer’s Guide 2014

Transcript of Procurement! Observer’s! Guide! - World...

 

Procurement  Observer’s  Guide  

2014  

TABLE  OF  CONTENTS  

Introduction................................................................................................................................. 1  

Chapter  1  Who  Can  Observe  Government  Procurement  Activities?...................................................................................................................................... 5  

Chapter  2  What  to  Observe? .................................................................................................10  

Chapter  3  Why  Report? ..........................................................................................................33  

Chapter  4  Code  of  Conduct  for  Observers ........................................................................36  

Chapter  5  Tools  and  Instruments .......................................................................................40  

Chapter  6  Other  Suggested  Activities ................................................................................45  

Annex  A  Sample  Form  of  Confidentiality  Agreement...................................................50  

 

INTRODUCTION  

The  Philippine  Government  spends  hundreds  of  billions  of  pesos  on  the  procurement  of   goods,   infrastructure   projects,   and   consulting   services   on   a   regular   basis.   This  money  comes  from  the  budget  that  the  Philippine  Government  appropriates  out  of  its  own   revenues   and   from   loans   and   grants   extended   by   foreign   sources   such   as  multilateral   development   banks   and   bilateral   donors.   This   amount   of   public  expenditures  alone  underscores  the  need  to  ensure  that  public  contracts  are  procured  competitively  with  due  consideration  to  economy  and  efficiency  in  a  transparent  and  fair   process   free   from   any   form   of   anomalies   and   irregularities   attributed   to   the  commission  of  graft  and  corruption.      In  2001,  the  Office  of  the  Ombudsman  (Omb)  estimated  that  USD48  billion  had  been  lost   to   corruption   in   the   last  20  years,   an  amount   that   could  have  paid   for   the   total  debt   of   the   Philippines   for   the   same   period.   The   Commission   on   Audit   (COA)  conservatively   estimates   corruption   loss   at   P2   billion   per   year.   (World  Bank,   2001;  Thomton,  2006).      In   the  area  of  public  procurement,   leakage   is  estimated  by  Procurement  Watch,   Inc.  (as  of  2001)  at  P95  billion  or  68%  of  the  budget  deficit.  Another  study  has  said  that  20%  of   the  Philippine  budget   is   lost   to   corruption   each   year.   If   translated   to   actual  impact,  in  2010,  for  instance  when  the  country  had  1.54  trillion  budget,  the  20%  loss  would  be  equivalent   to  P308.2  billion  on  an  annual  basis  or  P843  million  on  a  daily  basis.  The  amount  could  have  been  used  to:    

• Build  an  additional  598,446  classrooms;  • Hire  an  additional  1.6  million  teachers;  or  • Construct  127.78  kilometers  of  roads.  

 The   table   below   shows   that   in   a   survey   conducted   by   Social   Weather   Station,   the  respondents  viewed  that  although  public  corruption  was  prevalent  in  revenue-­‐raising  functions   of   the   government,   a   significant   percentage   viewed   that   the   same   is   also  true  in  government  spending.    Areas  of  Public  Sector  Corruption  and  Corresponding  Percentage  of  Respondents:    Number  of  people  that  think  public  sector  corruption  is:    Due  more  to  bad  regulations   1  Due  more  to  bad  implementation   45  Equally  due  to  bad  regulations  and  bad  implementation   47  Due  neither  to  bad  regulations  nor  bad  implementation   7  Number  of  people  that  think  public  sector  corruption  is:    More  prevalent  in  government  revenue-­‐raising   3  

2  |  P a g e    Number  of  people  that  think  public  sector  corruption  is:    More  prevalent  in  government  spending   27  Equally  prevalent  in  government  revenue-­‐raising  and  spending   67  Found  neither  in  government  revenue-­‐raising  nor  spending   3  (Source:  WB,  2001)  SWS  Enterprise  Survey,  August-­‐  October  2000    The   occurrence   of   corruption   in   public   procurement   remains   prevalent   despite   the  existence  of  public  procurement  related  laws1  and  the  participation  of  the  public  for  increased   transparency.  Although   several   statutes  provide   for   citizens’  participation  in   public   procurement   exist,   what   was   common   in   these   laws   was   that   Observers  were  made  non-­‐voting  members  of  the  Pre-­‐qualification  Bids  and  Awards  Committee  (PBAC),  except  in  the  PBAC  of  LGUs.    Despite  the  space  given  to  CSOs  by  these  laws,  the  following  were  issues  that  had  to  be  dealt  with:    

• Familiarity,  closeness  and  regular  interrelation  of  Observers  with  the  members  of  the  PBAC;  

• Lack  or  absence  of  independent  Observers;  and  • Non-­‐mandatory  nature  of  the  submission  of  reports  by  Observers.  

 To   address   these   concerns,   Republic   Act   (R.A.)   No.   9184,   otherwise   known   as  “Government  Procurement  Reform  Act”   (GPRA)  was  enacted   into   law   in  2003.    The  new   public   procurement   legal   framework   provides   for   an   enhanced   citizens’  participation   to   ensure   that   the   procurement   process   is   transparent,   efficient   and  honest.  Although  observers  are  no  longer  part  of  the  BAC,  the  law  has  emphasized  and  provided   for   increased   accountability   and   wider   CSO   participation,   alongside   the  principle   of   public   monitoring.   The   GPRA   is   a   remarkable   legislative   improvement  from   the   plethora   of   laws   that   used   to   govern   the   Philippine   Government  procurement  system.      Consistent   with   the   principles   of   transparency   and   public   monitoring,   the   GPRA  allowed  third  party  observers  to  monitor  how  government  units  and  agencies  conduct  their  procurement  activities.    Thus,   to  enhance  transparency,   the  BAC   is  required  to  invite  at   least  two  (2)  observers  -­‐  one  (1)  from  a  duly  recognized  private  group  in  a  sector  or  discipline  relevant   to   the  procurement  at  hand,  and   the  other   from  a  non-­‐government  organization  to  sit  in  all  stages  of  the  procurement  process  -­‐  in  addition  to   the   representative   of   the   Commission   on   Audit.   The   law   likewise   requires   that  observers  must  not  have  any  direct  or  indirect  interest  in  the  contract  to  be  bid.    The  opportunity   for   citizens   to  participate   in   government  procurement   activities   as  observers   has   been   considered   a   key   development   in   the   Philippine   Government  procurement  system.  It  is  a  unique  feature  of  the  GPRA  that  the  country  takes  pride  in,  as   much   as   it   takes   pride   in   the   vibrant   community   of   civil   society   organizations                                                                                                                  1 Presidential  Decree  No.  1594  and  its  IRR;  Republic  Act  No.  7160  or  the  Local  Government  Code  of  the  Philippines;  Executive  Order  No.  262,  S.  2000  and  its  IRR;  and  Executive  Order  No.  40,  S.  2001  and  its  IRR.

 

(CSOs)   and   non-­‐governmental   organizations   (NGOs).   This   development   can   be  attributed   to   recognition   by   the   government,   its   development   partners   and   civil  society   that   citizens   and   communities   have   important   roles   in   enhancing  accountability   of   public   officials,   reducing   corruption   and   improving   efficiency   and  effectiveness  in  the  delivery  of  public  service.    The  participation  of  independent  CSO  observers   to   enhance   transparency   and   public   monitoring   of   government  procurement   activities   is   a   tool  under   the  broader   concept  of   “Social  Accountability  that  has  become  an  attractive  approach  to  both  the  public  sector  and  civil  society  for  improving  governance  processes,  service  delivery  outcomes,  and  improving  resource  allocation   decisions.   Over   the   last   decade,   numerous   examples   have   emerged   that  demonstrate   how   citizens   can   make   their   voice   heard   and   effectively   engage   in  making   the   public   sector  more   responsive   and   accountable.”     (Social   Accountability  Sourcebook,   World   Bank).   It   was   observed,   however,   that   the   presence   of   so   many  CSOs  and  NGOs  is  still  insufficient  to  supply  the  demand  for  procurement  observers.        Aside   from   the  high  demand  given   the  number  of  agencies,   the   lack  of  observers   to  cover   the   procurement   of   agencies   is   also   due   to   the   need   for   CSOs   to   fulfill   the  requirements  of   the   law  before  becoming  observers.  Under   the   law,  observers   shall  come   from   an   organization   duly   registered   with   the   Securities   and   Exchange  Commission  (SEC)  or  the  Cooperative  Development  authority  (CDA).    The  law  further  requires   that   the   observers   should   meet   the   following   criteria:   a)   knowledge,  experience  or  expertise  in  procurement  or  in  the  subject  matter  of  the  contract  to  be  bid;  b)  absence  of  actual  or  potential  conflict  of  interest  in  the  contract  to  be  bid;  and  c)  any  other  relevant  criteria  that  may  be  determined  by  the  BAC.  (Section  13.2  of  the  revised  Implementing  Rules  and  Regulations  (IRR)  of  R.A.  9184)    As  stated,  the  CSOs  or  NGOs  need  not  only  be  registered  with  SEC  or  CDA  but  should  also   be   knowledgeable   in   the   procurement   process   or   in   the   subject  matter   of   the  contract   to   be   bid.   To   be   knowledgeable   in   the   procurement   process,   the   CSOs   or  NGOs  must  necessarily  undergo  training  in  R.A.  9184  and  its  IRR.  It  is  to  this  end  that  this  Procurement  Observers  Guide  (POG)  seeks  to  contribute  to  that  need  for  training  of  CSOs.  Although  the  law  can  always  be  read  and  interpreted  on  its  own,  learning  and  having   a   clearer   interpretation   of   each   provision   are   better   facilitated   through  translation  into  simpler  terms  in  the  form  of  a  guide.      Accordingly,   this   Guide   seeks   to   simplify,   in   terms   of   presentation,   the   content   of  GPRA   and   its   IRR  with   the   aim   that   observers   can   understand   the   law   easily.   It   is  therefore  to  be  used  and  read  in  conjunction  with  the  GPRA  IRR.      This  publication  mainly  addresses  members  of  different  CSOs  and  NGOs  who  intend  to  participate  in  the  government  procurement  activities  as  observers.  This  POG  likewise  seeks  to  describe  procurement  principles  and  standards  in  a  simple  and  clear  manner,  for   those   who   are   interested   in   getting   involved   in   the   government   procurement  activities  but  are  not  yet  affiliated  with  any  organization  and  for  all  those  who  intend  to   learn   more   about   government   procurement.   Ultimately,   this   Guide   presents   an  opportunity   for   responsible   citizens   and   CSOs   to   put   into   practice   the   fundamental  principle   of   democracy   that   citizens   have   the   right   to   demand   accountability   and  public  officials  have  an  obligation  to  be  accountable.  

4  |  P a g e    

                                                                 

CHAPTER  1  WHO  CAN  OBSERVE  GOVERNMENT  PROCUREMENT  

ACTIVITIES?  

Section  16,  Article  XIII  of  the  1987  Philippine  Constitution  ensures  that  “the  right  of  the   people   and   their   organizations   to   effective   and   reasonable   participation   at   all  levels   of   social,   political,   and   economic   decision-­‐making   shall   not   be   abridged.   The  State  shall,  by  law,  facilitate  the  establishment  of  adequate  consultation  mechanisms.”    This   constitutional   guarantee   has   been   the   basis   for   the   creation   of   various  development   councils   at   the   local   level   and   the   framework   for   the   participation   of  third  party  observers  in  the  government  procurement  system.    This   idea   of   citizen’s   participation   is   consistent   with   the   Government   Procurement  Reform   Act’s   (GPRA)   general   principle   and   policy   of   promoting   transparency,  accountability,   efficiency,   and   public   monitoring   in   government   procurement.  Accordingly,  the  presence  of  observers  in  the  procurement  process  is  a  way  to  ensure  adherence  to  the  law  and  the  prevention  of  graft  and  corruption.      A. Who  can  be  Procurement  Observers?      

Under   R.A.   9184   and   its   IRR,   there   are   three   kinds   of   observers:   (1)   a  representative   of   the   Commission   on   Audit;   (2)   an   observer   from   a   duly  recognized  private  group  in  a  sector  or  discipline  relevant  to  the  procurement  at  hand  (e.g.,  Philippine  Contractors  Association  for  infrastructure);  and  (3)  an  observer  from  a  non-­‐government  organization  (NGO).  (Section  13  of  R.A.  9184  and  its  IRR)    This  Guide  shall  use  the  term  NGO  in  the  same  context  as  the  term  CSO,  which  is   defined   in   National   Budget   Circular   No.   5392   to   include   NGOs,   people’s  organizations,   cooperatives,   trade   unions,   professional   associations,   faith-­‐based   organizations,   media   groups,   indigenous   peoples   movements,  foundations  and  other  citizen  groups  formed  primarily  for  social  and  economic  development,  to  monitor  government  programs  and  projects,  engage  in  policy  discussions,   and   actively   participate   in   collaborative   activities   with  Government.        

                                                                                                               2 Guidelines  on  Partnership  With  Civil  Society  Organizations  and  Other  Stakeholders  in  the  Execution  of  the  National  Budget  issued  on  21  March  2012.

6  |  P a g e    

This  Guide  may  be  used  by  observers  from  recognized  private  groups  insofar  as  it  is  applicable.  

 

REMINDERS  

It   should   be   noted   that   the   IRR   of   R.A.   9184   recognizes   two   (2)   modes   of   NGO  “participation”   in   public   procurement,   as   shown   in   the   following   pertinent  provisions:  

 1. Section  13  requires  the  presence  of  third-­‐party  NGO  observers  in  all  stages  of  the  

procurement   process   to   enhance   transparency   and   thereby   promote  accountability  and  public  monitoring.      

2. Section   53.11   allows   procuring   entities   to   contract   with   NGOs   through   public  bidding   or   negotiated   procurement   when   an   appropriation   law   or   ordinance  earmarks  amounts  to  be  specifically  used  for  such  purpose.  

 Awareness   of   this   dual   role   of   NGOs   as   independent   third   party   observers   of   the  procurement   process   and   as   bidders   or   providers   of   goods   and   services   for  government   projects   will   allow   better   focus   for   the   POG   and   prevent   potential  conflicts   of   interest   among   NGOs   who   are   engaged   to   participate   in   public  procurement.  

 In   order   to   promote   greater   awareness   and   a   more   empowering   participation   of  citizen  stakeholders,  qualified  NGOs  based  in  communities  of  project  beneficiaries  are  encouraged  to  volunteer  as  observers  in  procurement  activities  in  their  localities.    1. Qualifications  of  an  Observer  

 a. Member   of   an   organization   duly   registered   with   the   Securities   and  

Exchange  Commission  (SEC)  or  the  Cooperative  Development  Authority  (CDA);  

 

REMINDERS  

To  encourage  the  participation  of  community-­‐based    procurement  observers,  they  may  affiliate  themselves  with    registered  NGOs.  

 b. Should  have  knowledge,  experience  and/or  expertise  in  procurement  or  

in  the  subject  matter  of  the  contract  to  be  bid;      

c. Should  have  no  actual  or  potential  conflict  of  interest  in  the  contract  to  be  bid;  and  

   

7  |  P a g e    

Procurement  Observer’s  Guide  

 d. Should  possess   other   relevant   criteria   that  may  be  determined  by   the  

Bids   and  Awards  Committee   (BAC)  of   the  procuring   entity   concerned.  (Section  13.2  of  the  IRR  of  R.A.  9184)  

 2. Observer’s  Responsibilities    

 a. To   familiarize   himself/herself   or   to   have   sufficient   knowledge   of   R.A.  

9184  and  its  IRR;        

b. To  observe  all  stages  of  the  procurement  process;  and    

c. Under  Sec.  13.4  of  the  IRR  of  the  GPRA,  observers  should:    

a. Prepare   a   report   either   jointly   or   separately   indicating   their  observations  made  on   the  procurement  activities   conducted  by  the   BAC   for   submission   to   the   Head   of   the   Procuring   Entity  (HOPE),  copy  furnished  the  BAC  Chairman;  

 b. Submit  their  report  to  the  procuring  entity  and  furnish  a  copy  of  

to   the   GPPB   and   the   Office   of   the   Ombudsman/Resident  Ombudsman;  and  

 REMINDERS  

The   primary   responsibility   of   the   NGO   observer   is   to  prepare   a   report   of   his   or   her   observations   assessing   the  extent  of   the  BAC’s   compliance  with   the  provisions  of   the  IRR   of   R.A.   9184   and   areas   of   improvement   in   the   BAC  proceedings,   in   line   with   the   principles   and   intent   of   RA  9184   to   promote   public   monitoring   of   the   procurement  process.        

The  report  shall  assess  the  extent  of  the  BAC’s  compliance  with  the  provisions  of  the  IRR  and  areas  of  improvement  in  the  BAC’s  proceedings.  See  Section  13.4(a)    

If   no   report   is   submitted   by   the   observer,   then   it   is  understood  that  the  bidding  activity  conducted  by  the  BAC  followed  the  correct  procedure.  See  Section  13.4(c)    

Refer  to  Section  D.  Procurement  Observer’s  Report  (POR)  on  page  42.  

 c. Immediately   inhibit   and   notify   in   writing   the   procuring   entity  

concerned   of   any   actual   or   potential   conflict   of   interest   in   the  contract  to  be  bid.  

8  |  P a g e    

 

REMINDERS  

Section   13   of   R.A.   9184   prohibits   observers   of   the  procurement   process   from   having   direct   or   indirect  financial  or  material  interest  in  the  contract  to  be  bid  out  to  prevent   “conflict   of   interest”   on   the   part   of   the   observer.  When   the  NGO  observer   is   “involved   in  multiple   interests  which  prevents  an  unbiased  and  impartial  attitude  toward  the  work  to  be  done”,  conflict  of  interest  occurs.  (Conflict  of  Interest,  Definition  of  Terms,  NBC  No.  539).    

The  actual  or  potential  conflict  of  interest  is  personal  to  the  representative   of   the   organization.   It  may   not   necessarily  prohibit  the  same  organization  from  sending  a  different  but  disinterested  representative.    

 3. Observer’s  Rights  

 Upon  invitation  by  the  concerned  procuring  entity’s  BAC:    

a. Attend  any  or  all  stages  of  the  procurement  process;    b. Record  what  they  have  observed  during  any  of  the  procurement  

proceedings;      c. Access   the   following   procurement   related   documents   upon  

request   and   subject   to   signing   of   a   Confidentiality   Agreement3  (See  Annex  A.  Sample  Form  of  Confidentiality  Agreement):  

 • Annual  Procurement  Plan  (APP)  and  Project  Procurement  

Management  Plan  (PPMP);    

• Minutes  of  the  BAC  Meetings;      • Abstract  of  Bids;    

 • Opened  Proposals.    (Section  13.5  of  the  IRR  of  R.A.  9184);  

and                                                                                                                        3Confidentiality   Agreement   also   known   as   a   nondisclosure   agreement   (NDA),   confidential  disclosure  agreement  (CDA),  proprietary  information  agreement  (PIA),  or  secrecy  agreement,  is  a   legal   contract   between   a   government   procuring   entity   and   a   volunteer   or   team   of   volunteer  procurement  observers  that  outlines  confidential  material,  knowledge,  or  information  that  the  parties  wish  to  share  with  one  another  for  certain  purposes,  but  wish  to  restrict  access  to  by  third  parties.  It  is  a   contract   through  which   the   parties   agree   not   to   disclose   procurement   information   covered   by   the  agreement.  Section  13.5  of  the  IRR  of  RA  9184  requires  that  Observers  sign  a  confidentiality  agreement  before  they  are  allowed  access  to  certain  documents.  

9  |  P a g e    

Procurement  Observer’s  Guide  

 • Post  Qualification  Summary  Report.    

 4. Observer’s  Accountability  

 While  R.A.   9184   and   its   IRR   are   silent   on   observers’   accountability   in  case  of  failure  to  perform  their  duties  and  responsibilities  or  in  case  of  inappropriate  behavior  during   the  bidding  process,  observers,  and  the  organizations  they  represent,  remain  accountable  and  liable  for  any  or  all  actions  in  violation  of  the  procurement  law,  its  associated  rules,  and  other   procurement-­‐related   statutes,   rules,   and   regulations   during   the  procurement  process.          Observers   are   accountable   to   the   organizations   they   represent.   Being  authorized   agents   and/or   members,   they   are   bound   by   the   internal  rules  and  procedures  of  the  organizations  to  which  they  belong.  Hence,  they   are   subject   to   such   disciplinary   actions   and   sanctions   their  respective   organizations   may   mete   out,   when   circumstances   so  warrant.    In   as  much   as   the   law   requires   that   observers  must   have   knowledge,  experience  and  expertise  in  procurement  or  in  the  subject  matter  of  the  contract   to   be   bid,   NGOs   are   encouraged   to   provide   the   necessary  training   and   orientation   to   their   members   before   deploying   them   as  observers.   It   is   strongly   recommended   that   a   thorough   and   rigid  screening  be  performed  to  ensure  the  integrity  of  the  NGO  observer.    One  possible  consequence  against  errant  observers  is  being  disqualified  from  participating  in  the  procurement  process.  Procuring  Entities  (PEs)  may   disqualify   observers,   or   the   NGO   they   represent   under   Section  13.2(c)   of   the   IRR  wherein   the   BAC   of   the   PE   concerned  may   impose  any   other   relevant   criteria   applying   R.A.   9184,   which   the   observers  shall  meet  before  being  able  to  participate  as  an  observer.    Moreover,  errant  observers  are  not  precluded  from  being  charged  with  a  civil  or  criminal  case,  when  the  circumstances  so  warrant  and  all  the  requisites  are  present,  under  existing  civil  and  criminal  laws.    In   spite  of   the  challenges   that  accountability  poses  on  Observers,   they  should  be  fortified  by  the  empowering  thought  that  they  are  fulfilling  an  important  and  noble  role  as  mature  responsible  citizens  to  bring  about  a  strong,  vibrant  and  functioning  democracy  that  we  all  aspire  for  as  a  people.      

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

CHAPTER  2  WHAT  TO  OBSERVE?  

R.A.  9184  and  its  IRR  states  that  Observers  should  be  invited  by  the  BAC  in  all  stages  of   the   procurement   process.   It   mandates   the   presence   of   Observers   in   monitoring  procurement   and   contract   implementation   as   a   means   of   improving   transparency,  accountability,   public   monitoring,   and   governance.   Observers   are   now   invited   to  monitor  all  stages  of  the  procurement  process.    A. Competitive  bidding  process    

In  accordance  with  Section  10  of  RA  9184  and  its  IRR,  Procuring  Entities  shall  adopt  competitive  bidding  as  the  primary  mode  of  procurement.      

 1. Procurement   of   Goods   and   Infrastructure   Projects   (showing   the  

latest  allowable  time)                                            o        

7  cd  for  goods  and  4  cd  for  infra  with  an  ABC  amounting  to  P  50M   3  cd  for  goods  and  2  cd  for  infra  with  

an  ABC  amounting  to  P  50M              10  cd  

 

Issuance  of  a  Notice  to  Proceed  

 

 Contract  Signing  

 Issuance  of  

Notice  of  Award  

7  cd  (goods)  and  infra  w/  an  ABC  above  P50M    from  deadline  for  receipt    of  proposals  (5  cd    for  infra  w/  an  ABC  amounting  to  P  50M  and  below)                7  cd  to  30  cd  

12  cd  to  30  cd                      1  cd  

1  cd                    7  cd  From  1st  day  of  posting  to  bid  submission  

 

Detailed  Bid  Evaluation  

 Post-­‐Qualification  

 Bid  Submission  

 

Opening  of  Technical  Proposal  (incl.  eligibility  docs)  

 Opening  of  

Financial  Proposal  

Advertisement/  Posting  

 Pre-­‐Bid  

Conference  

 Distribution/Sale  of  Bidding  Documents  

1  

1  

11  |  P a g e    

Procurement  Observer’s  Guide  

2. Procurement  of  Consulting  Services    

Quality-­‐Based  Evaluation  Procedure  (showing  the  latest  allowable  time)      

                   

 b.  

       

   Quality-­‐Cost  Based  Evaluation  Procedure  (showing  the  latest  allowable  time)    

                                 

         

Opening  of  Financial  Proposal   Negotiation   Post-­‐qualification  Proposal  Evaluation  

and  Ranking  

Award  of  Contract  

Submission  of  Proposals  

Opening  of  Technical  Proposal  &  Preliminary  Examination  

Pre-­‐Bid  Conference  

Advertisement  /Posting  

 

Submission  of  LOI  together  with  the  application  for  eligibility  

Submission  of  Eligibility  

Requirements  

Opening  of  Eligibility  Envelope,  

Eligibility  Check  

7  cd  

not  later  than  7  cd   not  to  exceed  20  cd  

1  cd  

Shortlisting   HOPE  Approval  

1  cd  

at  least  12  cd  

1  cd   10  cd   7  cd  not  more  than  21  cd  +  2  cd  for  HOPE  approval  

Negotiation   Post-­‐qualification  Proposal  Evaluation  and  Ranking  

Award  of  Contract  

Submission  of  Proposals  

Opening  of  Technical  Proposal  &  Preliminary  Examination  

Pre-­‐Bid  Conference  

Advertisement  /Posting  

Submission  of  LOI  together  with  the  application  for  eligibility  

Submission  of  Eligibility  

Requirements  

Opening  of  Eligibility  Envelope,  

Eligibility  Check  

7  cd  

not  later  than  7  cd   not  to  exceed  20  cd  

1  cd  

Shortlisting   HOPE  Approval  

1  cd  

at  least  12  cd  

10  cd   7  cd  not  more  than  21  cd  +  2  cd  for  HOPE  approval  

Opening  of  Financial  Proposal  

12  |  P a g e    

Observers   are   invited   to  participate   in   all   stages  of   the  procurement  process  starting  from  Pre-­‐Bid  Conference  until  the  award  of  the  contract  and  contract  implementation.    

 Below   is   a  more   detailed   discussion   of   each   procurement   stage/activity   and  the  corresponding  responsibilities  and  reminders   that  Observers   should   take  into  consideration:  

   

STAGE/ACTIVITY   DESCRIPTION  

ADVERTISEMENT  OF  THE  

INVITATION  TO  BID  (IB)  OR  REQUEST  FOR  EXPRESSION  OF  INTEREST  (REI)  

(Section  21,  RA  9184  and  its  IRR)  

As   mandated   by   law,   the   IB/REI   should   be   advertised   and  posted.      Except  otherwise  provided  in  Sections  21.2.2  and  54.2  of  the    IRR   of   R.A.   9184   and   for   the   procurement   of   common-­‐use  goods  and  supplies,  the  IB/REI  shall  be  advertised  or  posted  in  the  following  manner:    

Medium  

ABC  

Newspaper  of  general  nationwide  circulation  

PhilGEPS  Website  of  PE  

Conspicuous  Place  

Goods  ≤  2M          

Infra  ≤  5M          

Consulting  ≤  1M  and/or  ≤  4  months  

       

Goods  >  2M          

Infra  >  5M          

Consulting  >  1M  and/or  >  4  months  

       

 

STAGE/ACTIVITY   DESCRIPTION  

13  |  P a g e    

Procurement  Observer’s  Guide  

Receipt  of  Invitation  from  the  Procuring  Entity  for  Any  Stage  of  the  Bidding  Process  

(Section  13,  R.A.  9184  and  its  IRR)  

To  enhance  the  transparency  of  the  process,  the  BAC  shall,  in  all   stages   of   the   procurement   process,   invite,   in   addition   to  the  COA  representative,  at  least  two  (2)  observers,  who  have  no  right  to  vote,  one  from  a  duly  recognized  private  group  in  a   sector   or   discipline   relevant   to   the   procurement   at   hand,  and  the  other  from  a  non-­‐government  organization.      

REMINDERS  

• Implementing  Agencies   (IA)   or   Procuring   Entities   (PE)   are   required   by   law   to  invite  Observers  in  writing  at  least  three  (3)  calendar  days  before  the  date  of  the  procurement  activity.  

 • The   absence   of   Observers  will   not   nullify   the   BAC   proceedings,   provided   that  

they  have  been  duly  invited  in  writing.    • The  BAC  observer  should:    

Upon    receipt  of  the  invitation  personally  or  through  mail,  acknowledge  receipt  by  indicating  the  name  of  the  recipient;  date  of  receipt;  and  by  affixing  her  signature  on  the  receiving  copy;  or    

  If  the  invitation  is  received  through  fax,  the  BAC  observer  should  

acknowledge  receipt  in  the  same  manner  by  sending  the  facsimile  copy  to  the  procuring  entity  with  the  abovementioned  details;  or      

Call  the  procuring  entity  upon  receipt  of  invitation  to  inform  them    that  the  same  was  already  received.  ,    

• Inform  the  procuring  entity  if  a  representative  will  be  sent,  stating  the  name  and  her  position  in  the  organization.  Observer  should  inquire  about  what  transpired  during   the   previous   stage(s),   and   request   for   documents   and   list   of   Observer  invitees  (attended/unable  to  attend)  in  the  stage(s)  to  be  guided  accordingly.    

 • Secure  a  copy  of  the  bidding  documents  from  the  the  Procuring  Entity  (PE).  

   • Whether   invited   or   not,   the   Observer   may   get   hold   of   a   copy   of   the   Annual  

Procurement   Plan   (APP)   to   check   if   the   procurement   activity   is   indicated  therein.    The  APP  should  be  available  on  the  website  of  the  government  agency.    There  are  now  transparency  provisions  under  the  General  Appropriations  Acts  (GAA).      In  the  case  of  local  government  units,  the  APP  is  also  required  to  be    posted  in  at  least   3   publicly   accessible   and   conspicuous   places   or   newspaper   of   general  circulation   in   their   locality,   as   required   by   laws,   rules   and   regulations   on  

14  |  P a g e    

transparency  and  disclosure  such  as:    − DILG  Memorandum  Circular  2011-­‐95  Seal  of  Good  Housekeeping   for  Local  

Governments  CY  2011  Implementation,    − MC   2011-­‐134   Amending   DILG   MC   2011-­‐08,   Series   2010   Titled   Full  

Disclosure   of   Budget   and   Finances   and   Bids   and   Public   Offerings,   As  Amended.  

   

• Write  your  comments/remarks/observations  in  the  Observer’s  Report.    

Inquire   for   the   PhilGEPS   reference   number   and   check   for   posting   in   the  PhilGEPS   Website   (www.philgeps.net)   and   the   number   of   calendar   days  required  for  its  posting/advertisement  [seven  (7)  calendar  days  or  longer].    

Verify  whether  the  IB/REI  is  posted  in  the  Procuring  Entity’s  Bulletin  Boards  (conspicuous  place)  reserved  for  this  purpose.    

In  order  to  validate  whether  the  bid  notice  was  published  and/or    posted,  the  Observer  can  request   for   the  date  when   the  opportunity  was  advertised  or  posted.  In  case  the  bid  notice  is  required  to  be  advertised  in  a  newspaper,  the  Observer,   whenever   applicable,   may   request   for   a   copy   of   the   newspaper  advertisement.    

Upon   seeing   a   copy   of   the   advertised   or   posted   bid   notice,   the   Observer  should   also   determine   the   completeness   of   the     information   indicated  therein.  (Rule  VII,  Section  21,  IRR  of  RA  9184)  provided  in  the  IB/REI.  

15  |  P a g e    

Procurement  Observer’s  Guide  

 What  is  PhilGEPS?    The   Philippine   Government   Electronic   Procurement   System   serves   as   the   primary  and   definitive   source   of   information   on   government   procurement.   All   procuring  entities   are   required   to   utilize   the   system   for   the   procurement   of   common   use  supplies  and  to  post  all  procurement  opportunities  and  results  therein.    Some  of  its  features  include:    

• Electronic  Bulletin  Board  • Registry  of  Suppliers,  Contractors  and  Consultants  • Electronic  Catalogue  • Virtual  Store  • Electronic  Payment  • Electronic  Bid  Submission  

 What  information  should  be  included  in  the  Invitation  to  Bid  (IB)?    For  the  procurement  of:    

• Goods,  the  name  of  the  contract  to  be  bid  and  a  brief  description  of  the  goods  to  be  procured;  

 • Infrastructure  projects,   the  name  and   location  of   the   contract   to  be  bid,   the  

project   background   and   other   relevant   information   regarding   the   proposed  contract  works,   including   a   brief   description   of   the   type,   size,  major   items,  and  other  important  or  relevant  features  of  the  works;  and  

 • Consulting  services,  the  name  of  the  contract  to  be  bid,  a  general  description  

of  the  project  and  other  important  or  relevant  information.    For  all  types  of  procurement:    

• A  general  statement  on  the  criteria  to  be  used  by  the  procuring  entity  for  the  eligibility   check,   short   listing   of   prospective   bidders,   in   the   case   of   the  procurement  of   consulting  services,   the  examination  and  evaluation  of  bids,  post  qualification,  and  award;  

• The   date,   time   and   place   of   the   deadline   for   the   submission   and   receipt   of  eligibility   requirements,   the   pre-­‐bid   conference,   if   any,   the   submission   and  receipt  of  bids,  and  the  opening  of  bids;  

• Approved  Budget  for  the  Contract  (ABC)  or  the  Estimated  Project  Cost  (EPC)    as  the  case  may  be,  for  the  items,  infrastructure  projects  or  consulting  service  to  be  bid;  

• The  source  of  funding;  • The  period  of   availability   of  Bidding  Documents,   the  place  where   it  may  be  

secured,  the  website  where  it  may  be  downloaded,  and  where  applicable,  its  price;  

• The  contract  duration  or  delivery  schedule;  

16  |  P a g e    

• The  names,  address,  telephone  number,  facsimile  number,  e-­‐mail  and  website  addresses  of  the  concerned  procuring  entity,  as  well  as  its  designated  contact  person;  and  

• Such  other  necessary  information  deemed  relevant  by  the  procuring  entity.      

STAGE/ACTIVITY   DESCRIPTION  

PRE-­BID  CONFERENCE  

(Section  22,  RA  9184  and  its  IRR)  

The   pre-­‐bid   conference   is   an   opportunity   for   the   potential  bidders   to   seek   clarification   and   for   the   BAC   to   explain   the  eligibility   requirements   and   the   technical   and   financial  components  of  the  contract  to  be  bid.    

MANDATORY   DISCRETIONARY  

For   contracts   with   an   ABC  of   One   Million   Pesos  (P1,000,000.00)   or   more,  the   BAC   shall   convene   at  least   one   pre-­‐bid  conference.  

For   contracts   with   an   ABC  of   less   than   One   Million  Pesos  (P1,000,000.00),  pre-­‐bid   conferences   may   be  conducted  at  the  discretion  of  the  BAC.  

Subject   to   the   approval   of   the   BAC,   additional   pre-­‐bid  conference  may  also  be  conducted  upon  written  request  of  any  prospective  bidder.  

 Attendance  of  bidders  is  NOT  mandatory.      At   the   option   of   the   Procuring   Entity,   only   those   who   have  purchased   the   Bidding   Documents   shall   be   allowed   to  participate   in   the   pre-­‐bid   conference   and   raise   or   submit  written  queries  or  clarifications.    Statements  made  during  the  conference  shall  not  modify  the  terms   of   the   Bidding   Documents,   unless   it   is   specifically  identified   in   writing   as   an   amendment   and   issued   as   a  Supplemental/Bid  Bulletin.    Supplemental/Bid   Bulletins   may   be   issued   upon   the  procuring   entity’s   initiative   for   purposes   of   clarifying   or  modifying  any  provision  of  the  Bidding  Documents  at  least  7  calendar   days   before   the   deadline   for   the   submission   and  receipt  of  bids.  

REMINDERS  

• Conduct  research  on  the  procurement  project  involved  and  identify  the  items  to  watch  out   for,   such  as   reasonableness  of   the  Approved  Budget   for   the  Contract  

17  |  P a g e    

Procurement  Observer’s  Guide  

(ABC)  or  Estimated  Project  Cost  (EPC)  as  the  case  may  be,  generality  of  technical  specifications/scope  of  work/terms  of  reference,  and  conformity  of   the  Bidding  Documents  with  RA   9184   and   its   IRR,   its   associated   rules   and   procedures,   the  standardized   Philippine   Bidding   Documents,   and   the   Generic   Procurement  Manuals.  

 • Pre-­‐bid  conference  (PBC)  must  be  held  at  least  twelve  (12)  calendar  days  before  

the   deadline   for   the   submission   and   receipt   of   bids,   or   at   least   thirty   (30)  calendar   days   before   the   deadline   for   the   submission   and   receipt   of   bids   if   a  longer  period   is   determined  by   the  Procuring  Entity   as   necessary  by   reason  of  the  method,  nature,  or  complexity  of  the  contract  to  be  bid  or  when  international  participation  will  be  more  advantageous  to  the  government.    

• Check  if:    

Pre-­‐bid  conference  is  mandatory  based  on  the  ABC  or  EPC,  as  the  case  may  be.    

All   the   bidders   who   have   expressed   their   interest   to   participate   (either   by  downloading  the  bidding  documents  from  the  PhilGEPS  website  or  those  who  purchased   the   bid   documents)   were   invited   in   cases   where   a   PBC   is   not  mandatory  but   the  BAC  decides   to  hold  one.  Take  note   that   the  presence  of  bidders  is  not  required.    

The   eligibility,   technical,   and   financial   requirements   of   the   procurement   at  hand  were  thoroughly  discussed.    

Clarifications  and  questions  were  encouraged  and  entertained.    

Clarifications   and   questions   not   immediately   addressed   during   the  conference   were   answered   through   the   issuance   of   a   supplemental/bid  bulletin.      

• If  there  is  any  Supplemental/Bid  Bulletin,  check  if:      

It  was  posted  on  the  PhilGEPS  and  the  PE’s  website.    

It  was  issued  not  later  than  seven  (7)  calendar  days  before  the  deadline  of  the  submission  of  bids.    

It   was   provided   to   all   prospective   bidders   who   had   bought   bidding  documents.      

• The   Pre-­‐bid   Conference   proceedings   should   be   recorded   and  minutes  must   be  made  available  to  all  participants  not  later  than  three  (3)  calendar  days  after  the  conference.    

• Bidders   who   have   submitted   their   bids   prior   to   the   issuance   of   the  supplemental/bid   bulletin   should   be   informed   and   allowed   to   modify   or  withdraw  their  bids.  

   

18  |  P a g e    

STAGE/ACTIVITY   DESCRIPTION  

RECEIPT  AND  OPENING  OF  BIDS  (Section  25,  RA  9184  and  

its  IRR)  

Bidders   shall   simultaneously   submit   their   bids   in   two   (2)  separate   sealed   envelopes,   on   the   date,   time   and   place  specified  in  the  IB.    The  BAC  shall   immediately  open  the  bids  after  the  deadline  for  submission.    Two-­Envelope  System      1st  Envelope  

Eligibility  requirements:  Class  “A”  Documents  − Legal  (Registration  certificate  ,  

Mayor’s  permit,  Tax  Clearance)  − Technical  (Statement  of  all  on-­‐going  

and  completed  contracts,  PCAB    license  and  registration  for  infrastructure  projects,  statement  of  consultant’s  nationality,  professional  registration,  curriculum  vitae  for  consulting  services)  

− Financial  (audited  financial  statement,  NFCC).  

Class  “B”  Document  − Valid  joint  venture  agreement  (JVA)    − For  foreign  bidders,  Class  “A”  

Documents  may  be  substituted  by  the  appropriate  equivalent  documents,  if  any,  issued  by  the  country  of  the  foreign  bidder  concerned.  

Bid  security   Technical  

specifications/Project  Requirements  

Omnibus  sworn    statement  

   

2nd  Envelope  

Financial  Bid  Form  

 

REMINDERS  

Review  the  Bidding  Documents.      

Review  Rule  VIII  (Receipt  and  Opening  of  Bids)  of  the  IRR  of  R.A.  9184.  

19  |  P a g e    

Procurement  Observer’s  Guide  

  Make  sure  to  be  present  before  the  scheduled  opening  of  bids.    

 • Check  if:      

All  the  bids  were  submitted  on/before  the  published  deadline.    

The  BAC  did  not  accept  late  bids.      

The   following   periods   from   the   last   day   of   posting   of   IB/REI   up   to   the  submission  and  receipt  of  bids  have  been  observed  by  the  BAC:  

 Type  of  Procurement   Maximum  Period  Goods   Forty  five  (45)  calendar  days  Infrastructure  Projects:  Fifty  (50)  million  and  below  ABC  Above  fifty  (50)  million  ABC  

 Fifty  (50)  calendar  days  Sixty  Five  (65)  calendar  days  

Consulting  Services   Seventy  five  (75)  calendar  days  

 In  the  case  of  projects  funded  by  the  ADB  and  the  WB,  a  minimum  (instead  of  a  maximum)  period  for  the  preparation  of  bids  is  required.      In   the   case   of   ADB   funded   projects   bidders   shall   be   given   a   minimum  period   to  prepare  and  submit  bids  of  4  weeks,   counted   from  the  date  of  invitation   to   bid   or   the   date   of   availability   of   bidding   documents,  whichever  is  later.      For   WB   assisted   projects,   a   period   of   at   least   thirty   (30)   days   for   bid  preparation   shall   be   required   from   the   date   of   invitation   to   bid   or   the  date  of  availability  of  of  bidding  documents,  whichever  is  later.    As  a  general  rule,   the  earliest  possible   time  for  bid  preparation   is   less  than   30   days.   However,   if   the   procuring   entity   determines   that   by  reason  of  the  method,  nature,  or  complexity  of  the  contract  to  be  bid  or  when  international  participation  will  be  more  advantageous  to  the  GOP,  the  time  for  bid  preparation  may  be  more  than  30  days.  

  The  bid  box  was  properly   sealed/locked  so   that  no  one  can  easily  open  or  

have  access  to  it.    

The  BAC  members  comprising  a  quorum  were  present  before  the  start  of  the  bidding.  

  The  checklist  on  the  required  documents  for  the  eligibility  check  is  reflected  

on  the  board  and/or  in  a  document  prepared  and  distributed  to  members  of  the  BAC,  BAC  Secretariat,  the  TWG,  and  Observers.  

  Prospective   bidders   submitted   their   eligibility   envelopes   along   with   their  

technical  and  financial  envelopes  properly  sealed  and  duly  marked.    

20  |  P a g e    

All  bids  are  still  properly  sealed  before  opening.    

  The  BAC  used  non-­‐discretionary   “pass  or   fail”   criterion   in  determining   the  

completeness  of  each  bidder’s  eligibility  requirements  or  statements.    

Remaining  bid    envelopes  of  bidder/s  declared  ineligible  by  the  BAC,  when  one  or  more  of  the  required  documents  was  found  to  be  missing,  incomplete  or  patently  insufficient,  shall    have  been  immediately  returned  to  the  bidders  unopened.  

 For  ADB  assisted    projects  the  following  rule  applies:    ITB  Clause  24.2  -­  During  Bid  opening,  if  the  first  bid  envelope  lacks  any  of  the  documents  listed  in  the  ADB  BDS  12.1(a),  the  bid  shall  be  declared  non-­responsive  but   the  documents  shall  be  kept  by   the  Procuring  Entity.    Only  the  unopened  Price  Proposal  shall  be  returned  to  the  Bidder.    For  WB  assisted  projects  the  following  rule  applies:  ITB  Clause  24.2  -­  During  Bid  opening,  if  the  first  envelope  lacks  any  of  the  documents  listed  in  World  Bank  BDS  12.1(a),  the  bid  shall  be  declared  non-­responsive   but   the   documents   shall   be   kept   by   the  Procuring  Entity.     The  financial  proposals   in   the  second  envelope  of  all   the  bidders   shall  be  read  for  record  purposes.    The  first  and  second  envelopes  shall  not  be  returned  to  the  bidders.    

If   a   bidder   modifies   its   bid,   it   must   be   done   before   the   deadline   for  submission  and  receipt  of  bids.  Modification  shall  be  done  through  sending  of  another  bid  equally  sealed,  properly   identified,   linked  to  the  original  bid  and  marked  as  “modification”,  and  stamped  “received”  by  the  BAC.  

  A   bidder   may   be   through   through   a   letter,   withdraw   its   bid,   before   the  

deadline  for  the  receipt  of  bids.  The  bidder  shall  not  be  permitted  to  submit  another  bid,  directly  or  indirectly,  for  the  same  contract.  

  In  case  the  BAC  declares  a  failure  of  bidding  in  this  stage  of  the  procurement  

process,   the  BAC’s  declaration  of   failure   should  be    based  on   the   following  grounds:  

 

− No  prospective  bidder   submits  a  Letter  of   Intent   (in   the   case  of   consulting  services)  or  no  bids  are  received;  or  

 − All  prospective  bidders  are  declared  ineligible.  

         

STAGE/ACTIVITY   DESCRIPTION  

21  |  P a g e    

Procurement  Observer’s  Guide  

BID  EVALUATION  (Section  30,  RA  9184  and  

its  IRR)  

To   determine   the   Lowest   Calculated   Bid   (LCB)   or   Highest  Rated  Bid  (HRB),  the  BAC  shall  conduct  a  detailed  evaluation  using     non-­‐discretionary   criteria   in   considering   the  completeness  of  bids  and  arithmetical  corrections.      Bids  shall  be  evaluated  on  an  equal  footing  to  ensure  fair  and  competitive  bid  comparison.    A  NO  CONTACT  RULE  shall  be  observed  (Refer  to  Rule  IX,  Sections  32  &  33  of  the  IRR  of  R.A.  9184).    Generally,   members   of   the   BAC,   including   its   staff   and  personnel,  as  well  as  its  Secretariat  and  TWG,  are  prohibited  from   making   or   accepting   any   communication   with   any  bidder   regarding   the   evaluation   of   their   bids   until   the  issuance   of   the  Notice   of   Award   (NOA).   However,   the   BAC,  through  its  Secretariat,  may  ask  the  bidder  in  writing  for  the  clarification   of   its   bid.   All   responses   to   requests   for  clarification  shall  be  likewise  in  writing.4    The  BAC  shall  prepare  an  Abstract  of  Bids   for  procurement  of   goods   and   infrastructure,   or   a   ranking   of   short-­‐listed  bidders   in   the   case   of   procurement   for   consulting   services,  as  calculated,  which  shall  be  signed  by  all  the  members  of  the  BAC  who  are  present.  

REMINDERS  

• Invitation   to   attend   the   Bid   Evaluation   process   should   have   been   received   at  least  three  (3)  calendar  days  prior  to  the  activity.    

• Documents  pertinent  to  the  evaluation  should  have  been  received  together  with  the  invitation.    

• All   bids   must   be   accompanied   by   a   bid   security   in   the   form   and   amount  prescribed   in  Section  27.2  of   the  revised   IRR  of  R.A.  9184.  Otherwise,   the  BAC  must  automatically  disqualify  the  bid.  

 • Observe  the  processes  and  procedures  employed  by  the  BAC  and  follow  closely  

the  manner  by  which  each  bidder  is  assessed.    • The   evaluation   of   bids   was   completed   no   later   than   seven   (7)   calendar   days  

from  the  deadline  of  the  receipt  of  the  proposals.    • Review  the  accuracy  of  the  computations.    

                                                                                                               4 Section 32.1 of the IRR of R.A. 9184

22  |  P a g e    

• In  case  of  discrepancies,  the  following  shall  prevail:    -­‐ Words  over  figures;      -­‐ Unit  prices  over  total  prices;    -­‐ Actual  Sum  of  prices  of  component  items  over  stated  total  price;  and  -­‐ Bill  of  quantities  over  detailed  estimate.  

 • Indicating  no  price  is  considered  as  non-­‐responsive.  

 • Specifying  a  “0”  or  “-­‐”  means  it  is  offered  for  free.    • Unless  the  Instruction  to  Bidders  (ITB)  specifically  allows  partial  bids,  those  not  

providing  all  required  items  shall  be  considered  non-­‐responsive.    

• In   case   the  BAC  declares   a   failure   of   bidding   at   this   stage   of   the  procurement  process,  it  shall  be  by  reason  of  failure  by  all  the  bids  to  comply  with  all  the  bid  requirements,   or   in   the   case   of   consulting   services,   there   is   no   successful  negotiation.  

 • Observers  should  also  follow  the  NO  CONTACT  RULE.  

 Bid  Security    Form  of  Bid  Security   Amount  of  Bid  Security    

(Equal  to  Percentage  of  the  ABC)  a) Cash  or  cashier’s/manager’s  check  

issued  by  a  Universal  or  Commercial  Bank  

b) Bank  draft/guarantee  or  irrevocable  letter  of  credit  issued  by  a  Universal  or  Commercial  Bank5  

     Two  percent  (2%)  

c) Surety  bond  callable  upon  demand  issued  by  a  surety  or  insurance  company  duly  certified  by  the  Insurance  Commission  as  authorized  to  issue  such  security  

Five  percent  (5%)  

d) Any  combination  of  the  foregoing   Proportionate  to  share  of  form  with  respect  to  total  amount  of  security.  

 For  biddings  conducted  by  local  government  units  (LGUs),  the  prospective  bidder  may  also  submit  bid  securities  in  the  form  of  casher’s/manager’s  check,  bank    draft/guarantee,  or  irrevocable  letter  of  credit  from  other  banks  certified  by  the  BSP  as  authorized  to  issue  such  financial  instrument.    A  bidder  may  submit  a  Bid  Securing  Declaration  in   lieu  of  a  bid  security   if  allowed  in  the  Bidding  Documents.     A   Bid   Securing   Declaration   is   an   undertaking   which   states,   among   others,   that   the  bidder   shall   enter   into   contract  with   the   procuring   entity   and   furnish   the   required   performance  security  within  ten  (10)  calendar  days,  or  less,  as  indicated  in  the  Bidding  Documents,  from  receipt  of  the  Notice  of  Award  (NOA).  The  bidder  commits  to  pay  the  corresponding  fine  and  be  suspended  for  a  period  of  time  from  being  qualified  to  participate  in  any  government  procurement  activity  in  the  event  it  violates  any  of  the  conditions  stated  therein  as  required  by  the  Guidelines  issued  by  the  

                                                                                                               5 If  issued  by  a  foreign  bank,  that  it  shall  be  confirmed  or  authenticated  by  a  Universal  or  Commercial  Bank. 6 Section 27.5 of the revised IRR of RA 9184

23  |  P a g e    

Procurement  Observer’s  Guide  

GPPB.6        

STAGE/ACTIVITY   DESCRIPTION  

POST-­QUALIFICATION  

(Section  34,  RA  9184  and  its  IRR)  

Three  (3)  days  after  receiving   the  notice   from  the  BAC  that  the   bidder   has   the   LCB/HRB,   the   bidder   shall   submit   the  following:    a) Latest  income  and  business  tax  returns;    b) Certificate  of  PhilGEPS  registration;  and    c) Other  appropriate  licenses  and  permits  required  by  law  

and  stated  in  the  Bidding  Documents.    Note  that   failure  to  submit   the  above  requirements  on  time  or  a  finding  against  the  veracity  of  such  shall  be  a  ground  for  the   forfeiture  of   the  bid   security   and  disqualification  of   the  bidder  for  award.  The  BAC  shall  validate  and  ascertain  all  the  statements  and  documents  submitted  by  the  LCB.7    The  BAC  shall  declare  the  LCB  as  the  LCRB  or  the  HRB  as  the  HRRB  if  it  passes  post  qualification.    

REMINDERS  

Be  prepared  to  join  members  of  the  BAC,  TWG,  and  BAC  Secretariat  in  going  to  the   appropriate   place   where   they   need   to   verify,   validate,   or   ascertain   the  veracity  of  statements  and  documents  submitted  by  the  bidder;  this  includes  the  sworn  affidavit  or  Omnibus  Sworn  Statement    required  under  Section  47,  Rule    XV,  of  the  IRR  with  regard  to  the  disclosure  of  relations  by  bidders.    

• If  the  situation  warrants,  conduct  additional  research  to  ascertain  questionable  statements  and  documents  submitted  by  the  bidder.  

 • The  BAC  should  verify,  validate  and  ascertain  the  following:  

  That   the   bidder   with   the   LCB   was   not   included   in   any   government  

Blacklist.    

The  BAC  should  undertake  verification  and  validation  on  the  sufficiency  of  the  bid  security  as  to  type,  form,  amount,  wording  and  validity  period.  

  The  BAC  should  verify,  validate  and  ascertain  the  legality  of  the  licenses  

and  agreements,  among  others,  submitted  by  the  bidder  with  the  LCB.    

• The   Procuring   Entity   as   well   as   the   bidders,   suppliers   and   consultants   shall  

                                                                                                               7 Refer to the Public Bidding Checklist for a detailed manner on conducting post-qualification.

24  |  P a g e    

observe  the  highest  standard    of  ethics  during  the  procurement  and  execution  of  the  contract.      Clause  3,  Instruction  to  Bidders  (ITB),  Philippine  Bidding  Documents  (PBD)  for  Goods,   Infrastructure   Projects   and   for   Consulting   Services   4th   Edition,   defines  “corrupt   practice”,   “fraudulent   practice”,   “collusive   practices”,   “coercive  practices”,  and  “obstructive  practice”.  The  PE  will  reject  a  proposal  for  award  if  it  determines  that  the  Bidder  recommended  for  award  has  engaged  in  any  of  the  practices  mentioned  in    Clause  3  of  the  PBDs  for  purposes  of  competing  for  the  contract.  

 • If  the  bidder  with  the  LCB/HRB  fails  the  criteria  for  post-­‐qualification,  the  BAC  

should  immediately  notify  the  bidder  in  writing  of   its  post-­‐disqualification  and  the  grounds  therefor.    

• The   same  post-­‐qualification  process   should  be  done  by   the  BAC   to   the  bidder  with  the  next  LCB/HRB  until  the  LCRB/HRRB  is  determined  for  the  award.  

 • At  this  stage,  the  failure  of  bidding  may  only  occur  if  no  bidder  passed  the  post  

qualification   stage.   Other   than   that,   there   should   be   no   other   reason   for   the  declaration  of  a  failure  of  bidding.    

     

STAGE/ACTIVITY   DESCRIPTION  

AWARD  OF  CONTRACT  

(Section  37,  RA  9184  and  its  IRR)  

The   BAC   recommends   to   the   Head   of   the   Procuring   Entity  (HOPE)  that  the  contract  be  awarded  to  the  bidder  with  the  Lowest   Calculated   and   Responsive   Bid   (LCRB)   or   Highest  Rated  and  Responsive  Bid  (HRRB).    In   case   of   approval,   the   HOPE   issues   the   Notice   of   Award  (NOA).  The  NOA  should  be  posted  in  the  PhilGEPS’  website,  PE’s   website,   and   in   conspicuous   places   within   the   PE’s  premises  within  three  (3)  calendar  days  from  its  issuance.      Within  ten  (10)  calendar  days  from  receipt  of  the  NOA,  the  winning  bidder  shall  submit  the  Joint  Venture  Agreement,  if  applicable;  post  the  required  Performance  Security  and  both  parties  shall  enter  into  contract  provided  that  all  the  documentary  requirements  are  complied  with.  Refer  to  Sec.  39  of  the  IRR  of  R.A.  9184  for  a  more  detailed  description  of  the  requirements  for  a  Performance  Security.    The   Notice   to   Proceed   (NTP),   together   with   a   copy   of   the  approved   contract,   shall   be   issued   to   the   successful   bidder  within  three  (3)  calendar  days   from  the  date  of  approval  of  the   contract   by   the   appropriate   government   approving  

25  |  P a g e    

Procurement  Observer’s  Guide  

authority.      The   contract’s   effectivity  date   shall   be  provided   in   the  NTP  by  the  PE.  The  effectivity  date  should  not  be  later  than  seven  (7)  calendar  days  from  its  issuance.    Through  the  BAC  Secretariat,  the  PE  shall  post  a  copy  of  the  NTP   and   the   approved   contract   in   the  PhilGEPS  website   or  PE’s  website  within   15   calendar   days   from   the   issuance   of  the  NTP.  

REMINDERS  

• Check   if   the  NOA  and  NTP  were  posted   in   the  PhilGEPS  website,  PE’s  website,  and  in  conspicuous  places  within  the  PE’s  premises  within  the  required  calendar  days  after  its  issuance.  

 • The  decision  of  the  HOPE  or  his/her  duly  authorized  representative  whether  or  

not   to   award   the   contract  was  made  within   seven   (7)   calendar  days   from   the  determination  and  declaration  by  the  BAC  of  the  LCRB.  

 • The  BAC  should  notify  all   losing  bidders  of  their  decision  in  writing  within  the  

same  period.    

• Failure  of  bidding  at  this  stage  of  the  procurement  process  may  be  declared  by  the  BAC   in  case  the  bidder  with  the  LCRB  or  HRRB  refuses,  without   justifiable  cause,  to  accept  the  award  of  contract,  and  no  award  is  made  in  accordance  with  Section  40  of  R.A.  9184  and  its  revised  IRR.  

 • If   the   organization’s   monitoring   work   extends   to   project   implementation,  

compile   all   documentation/reports   on   procurement   observation   work   and  transfer  these  to  the  person/s  in  charge  of  monitoring  project  implementation.    

   Performance  Security    Forms  of  Performance  Security   Amount  of  Performance  Security  

(Equal  to  percentage  of  the  total  contract  price)  a)  Cash,  cashier’s/  manager’s  check,  bank  draft/  guarantee  confirmed  by  a  universal  or  commercial  bank  b)  Irrevocable  letter  of  credit  issued  by  a  Universal  or  Commercial  Bank8    

   Goods  and  Consulting  Services-­‐  five  percent  (5%)    Infrastructure  Projects-­‐  Ten  percent  (10%)  

c)  Surety  bond  upon  demand  issued  by  a  surety  or  insurance  company  duly  certified  by  the  Insurance  Commission  

Thirty  percent  (30%)  

d)  Any  combination  of  the  foregoing.     Proportionate  to  share  or  form  with  respect  to  total  

                                                                                                               8 If  issued  by  a  foreign  bank,  that  it  shall  be  confirmed  or  authenticated  by  a  Universal  or  Commercial  Bank.

26  |  P a g e    

amount  of  security.    For  biddings  conducted  by  local  government  units  (LGUs),  the  prospective  bidder  may  also  submit  performance  securities  in  the  form  of  cashier’s/manager’s  check,  bank  draft/guarantee,  or  irrevocable  letter  of  credit  from  other  banks  certified  by  the  BSP  as  authorized  to  issue  such  financial  instrument.        B. Procurement  Timelines  

 Timelines   for   the   Procurement   of   Goods   and   Infrastructure   Projects   and  Consulting  Services    (Annex  C  of  the  IRR)  

 • Earliest  Allowable  Time-­  Goods  

     

• Latest  Allowable  Time-­Goods  

       

Procurement  of  Infrastructure  Projects  with  an  ABC  of  PhP  50  Million  and  below-­  Latest  Allowable  Time    

27  |  P a g e    

Procurement  Observer’s  Guide  

 

     

     

Procurement   of   Infrastructure   Projects   with   an   ABC   of   above   PhP   50   Million-­  Latest  Allowable  Time    

 

   

           

 • Earliest  Allowable  Time-­Consulting  Services    

   

28  |  P a g e    

   

 • Latest  Allowable  Time  –  Consulting  Services  

   

                   

C. Alternative  Methods  of  Procurement    

29  |  P a g e    

Procurement  Observer’s  Guide  

Observers  are  required  to  be  invited  in  the  conduct  of  alternative  procurement  methods  of  Limited  Source  Bidding  and  Negotiated  Procurement  (in  the  case  of  two  failed  biddings).    

 Below  is  a  more  detailed  discussion  of  each  alternative  method  of  procurement  and   the   corresponding   responsibilities   and   reminders   that  Observers   should  take  into  consideration:      

ALTERNATIVE  MODE   DESCRIPTION  

LIMITED  SOURCE  BIDDING  

As  defined  under  Section  49  of  the  IRR  of  RA  9184,  Limited  Source  Bidding,  otherwise  known  as  selective  bidding,   is  a  method   of   procurement   of   goods   and   consulting   services  that  involves  direct  invitation  to  bid  by  the  procuring  entity  from  the   list  of  pre-­‐selected  suppliers  or  consultants    with  known   experience   and   proven   capability   on   the  requirements   of   the   particular   contract.     This   alternative  method  of  procurement  may  be  employed  under  any  of  the  following  conditions:    a)  Procurement   of   highly   specialized   types   of   goods   (e.g.,  sophisticated  defense  equipment,  complex  air  navigation  systems,   coal)  and  consulting   services  where  only  a   few  suppliers  or  consultants  are  known  to  be  available,  such  that  resorting  to  the  public  bidding  method  will  not  likely  result   in   any   additional   suppliers   or   consultants  participating  in  the  bidding;  or      

 b)  Procurement   of   major   plant   components   where   it   is  deemed   advantageous   to   limit   the   bidding   to   known  qualified   bidders   in   order   to   maintain   uniform   quality  and  performance  of  the  plant  as  a  whole.  

 The   pre-­‐selected   suppliers   or   consultants   shall   be   those  appearing   in  a   list  maintained  by   the  relevant  government  authority   that   has   expertise   in   the   type   of   procurement  concerned.  The  list  of  pre-­‐selected  suppliers  or  consultants  shall   be   updated   periodically.   A   copy   of   the   list   shall   be  submitted  to,  and  maintained  updated  with,  the  GPPB.    According  to  Section  49.4  of  the  IRR  of  RA  9184,  “all  other  procedures   for   competitive   bidding   shall   be   undertaken,  except   for   the   advertisement   of   Invitation   to   Bid/Request  for   Expression   of   Interest   under   Section   21.2.1   of   this  IRR.)”.   This   means   that   the   requirement   to   invite  independent  observers  from  COA,  and  two  (2)  others  from  a   duly   recognized     private   group   in   a   sector   or   discipline  

30  |  P a g e    

relevant  to  the  procurement  at  hand  and  a  non-­‐government  organization   (NGO)   shall   apply   to   all   the   other  stages/procedures.    Note:    For   a   complete   understandin   of   the   requirements   for   the  conduct   of   Limited   Source   Bidding,   please   refer   to   the  “Guidelines   Amending   the   Pre-­‐Selection   Procedure   in   the  Conduct   of   Limited   Source   Bidding”,   GPPB   Resolution   No.  06-­‐2012  dated  30  March  2012.  

REMINDERS  

• The   Procuring   Entity   through   the   BAC   shall   request   the   presence   of   the  Observers   by   sending   them   invitation   letters   at   least   three   (3)   calendar   days  before  the  date  of  the  procurement  stage/activity.    In  the  case  of  limited  source  bidding  this  should  be    at  least  three  (3)  days  before  the  direct  invitation  to  bid  is  issued  by  the  procuring  entity  to  prospective  bidders  drawn  from  the  list  of  pre-­‐selected  suppliers  or  consultants.        

• Observers   should   be   vigilant   and   verify   whether   the   conditions   for   limited  source   bidding   as   established   in   the   IRR   of   R.A.   9184  were  met   and   that   the  resort  to  such  method  was  justifiable.      

• Observers   should   also   determine   whether   the   pre-­‐selection   of   suppliers   and  consultants  are  in  accordance  with  the  procedures  provided  for  in  the  IRR  and  the  Guidelines.    

• Observers   should   be   guided   by   procedures   applicable   to   procurement   stages  for  competitive  bidding   from  the  conduct  of  a  pre-­‐bid  conference   to  award  of  the  contract.      

• The   Procuring   Entity   as   well   as   the   bidders,   suppliers   and   consultants   shall  observe  the  highest  standard    of  ethics  during  the  procurement  and  execution  of  the  contract.    

 • The  BAC   should   ascertain   that   all   Bidders   found   to   have   conflicting   interests  are   disqualified   to   participate   in   the   procurement   at   hand.   (Paragraph   4,  Instruction  to  Bidders,  PBDs  for  Goods,  and  Paragraph  2,  Instruction  to  Bidders,  PBDs  for  Consulting  Services).    

• It  should  be  verified  by  the  BAC  that  the  requirements  of  Section  47  of  the  IRR  with   regard   to   the   disclosure   of   relations   by   bidders   are   complied  with.   The  Observer  should  satisfy  himself   that  any  bidders  related  within   the   third  civil  degree  of  consanguinity  or  affinity  to  the  HOPE,  members  of  the  BAC,  the  TWG,  and   the   BAC   Secretariat,   the   head   of   the   PMO   or   the   end-­‐user   unit,   and   the  project  consultants,  are  automatically  disqualified.    

31  |  P a g e    

Procurement  Observer’s  Guide  

 Clause  3,  Instruction  to  Bidders  (ITB),  Philippine  Bidding  Documents  (PBD)  for  Goods,   Infrastructure   Projects   and   for   Consulting   Services   4th   Edition,   defines  “corrupt   practice”,   “fraudulent   practice”,   “collusive   practices”,   “coercive  practices”,  and  “obstructive  practice”.  The  PE  will  reject  a  proposal  for  award  if  it  determines  that  the  Bidder  recommended  for  award  has  engaged  in  any  of  the  practices  mentioned  in    Clause  3  of  the  PBDs  for  purposes  of  competing  for  the  contract.  

       

ALTERNATIVE  MODE  

DESCRIPTION  

NEGOTIATED  PROCUREMENT  –  TWO  FAILED  BIDDINGS  

Negotiated  Procurement    is    a  method  of  procurement  that  may  be  resorted  to  under  the  extraordinary  circumstances  provided  in  Section  53  of  RA  9184  and  its  IRR,  whereby  the  PE  directly  negotiates  a  contract  with  a  technically,   legally,  and  financially  capable  supplier,  contractor,  or  consultant.    The   alternative     method   of     negotiated   procurement   is  allowed  in  a  case  of  two  failed  biddings.    This  occurs  when  there  has  been  failure  of  public  bidding  for  the  second  time  as  provided  in  Section  35  of  the  Act  and  the  IRR.    In   the  conduct  of  a  negotiated  procurement   in  case  of   two  (2)   failed   biddings,   Section   53,   Para   53.1.6   requires   that  observers  shall  be  invited  in  all  stages  of  the  negotiations.  

REMINDERS  

• The   Procuring   Entity   through   the   BAC   shall   request   the   presence   of   the  Observers   by   sending   them   invitation   letters   at   least   three   (3)   calendar   days  before   the   date   of   the   procurement   stage/activity.     In   the   case   of   negotiated  procurement  after  two  (2)  failed  biddings  this  should  be    at  least  three  (3)  days  before  the  direct  invitation  to  engage  in  negotiations    is  issued  by  the  procuring  entity   to  a   short   list  of   selected  suppliers,   contractors  or   consultants  potential  bidders  who  shall  be  of  sufficient  number  to  ensure  effective  competition.    

• Observers  should  be  vigilant  and  ascertain  whether  the  BAC’s  declaration  of  two  (2)  failed  biddings  are  in  accordance  with  Section  35  -­‐  Failure  of  Bidding  of  the  IRR  of  RA  9184.        

• Observers  should  also  review  and  verify  from  the  Minutes  of  the  Meeting  and/or  Bid   Evaluation  Reports   of   the   previous   two   (2)   failed   biddings  whether   these  were  conducted  in  accordance  with  the  bidding  procedures  specified  in  the  IRR  of  RA  9184,  especially  if  no  independent  CSO  Observers  were  previously  invited.  

32  |  P a g e    

 • The   BAC   shall   conduct   a   mandatory   review   of   the   terms,   conditions,  

specifications   and   cost   estimates   as  prescribed   in   Section  35  of   the   IRR  of  RA  9184   and   agree   on  minimum   technical   specifications,   and   if   necessary,   adjust  the   ABC,   subject   to   the   required   approvals..   However,   the   ABC   cannot   be  increased   by   more   than   twenty   percent   (20%)   of   the   ABC   for   the   last   failed  bidding.  

 • In   the   case   of   infrastructure   projects,   bona   fide   contractors   licensed  with   the  

CIAP   whose   eligibility   documents   are   on   file   with   the   procuring   entity  concerned   or   the   Department   of   Public   Works   and   Highways   (DPWH)  Contractors’  Registry,  as   the  case  may  be,  and  who  have  been  classified  under  the   type   of   contract/project  where   the   subject   contract   falls   are   eligible   to   be  invited   for   negotiation.   Other   contractors   not   previously   deemed   eligible  may  also  apply  for  eligibility.  

 • Observers   should   ascertain   that   the   Procuring   Entity   maintains   a   registry   of  

suppliers,  contractors,  and  consultants  which  shall  be  the  basis  for  drawing  up  the   short   list   and/or   selecting   the   suppliers,   contractors,   and   consultants   for  negotiations.    

• The  procuring  entity  should  see  to  it  that  any  and  all  information  relative  to  the  negotiations   that   are   communicated   on   an   equal   basis   to   all   other   suppliers,  contractors,   or   consultants   engaging   in   negotiations  with   the   procuring   entity  relative  to  the  procurement.  

 • The  procuring  entity  shall  select  the  successful  offer  on  the  basis  of  the  best  and  

final   offers   of   the   suppliers,   contractors   or   consultants   remaining   after  negotiation  proceedings  which  meets  the  PE’s  minimum  technical  requirements  without  exceeding  the  ABC.  

 • The  Procuring  Entity  as  well  the  suppliers,  contractors  and  consultants  selected  

for  negotiations  observe  the  highest  standard  of  ethics  during  the  procurement  and   execution   of   the   contract,   and   that   the   principles   of   transparency,  accountability,  economy  and  efficiency  are  followed.  

 

   

CHAPTER  3  WHY  REPORT?  

As  mentioned   in   the   introduction   to   this  Guide,   the   provision   allowing  Observers   in  government   procurement   activities   has   been   considered   a   noble   and   exceptional  feature   of   the   GPRA   that   other   countries   admire.   It   was   intended   to   enhance   and  promote  transparency,  accountability  and  efficiency  in  procurement.  The  presence  of  CSOs   and   other   stakeholders   in   the   procurement   activities   ensures   public   oversight  and  monitoring  of  the  procurement  process.      A. Significance  of  an  Observer’s  Report    

Preparing  and  filing  an  Observer’s  Report  is  significant  in  so  many  ways.    

1. Feedback  to  the  Procuring  Entity      

Aside  from  serving  as  documentation  of  the  conduct  of  the  procurement  process,  including  any  irregularities  committed  therein,  the  filing  of  the  Observer’s  Report  is  a  means  for  the  government  agencies  concerned  to  improve  their  processes  with  regard  to  gaps  and  deficiencies  observed.  Reports   and   feedbacks   from   observers,   whether   positive   or   negative,  would   give   procuring   entities   an   opportunity   to   address   identified  challenges  and  sustain  observed  strength.    

 2. Ensuring  Integrity    

 The   filing   of   an   Observer’s   Report   can   result   to   the   filing   of   the  corresponding   administrative   or   criminal   complaint   against   BAC  Members,   the   BAC   Secretariat   or   TWG,   or   anyone   involved   in   the  procurement  process  found  violating  any  provision  of  R.A.  9184  and  its  revised   IRR,  R.A.  3019   (“Anti-­‐Graft  and  Corrupt  Practices  Act”),  or  R.A.  6713   (“Code   of   Conduct   and   Ethical   Standards   for   Public   Officials   and  Employees”).     A   bidder   who   commits   a   violation   of   RA   9184   and   its  revised   IRR  may   be   held   criminally   liable   and  may   also   be   blacklisted  from  participating  in  all  government  procurement  activities.      Accordingly,   those   who   do   not   deserve   to   be   involved   in   government  procurement   are   effectively   weeded   out   from   the   process.   Since   the  Office  of   the  Ombudsman   is   furnished  a  copy  of   the  Observer’s  Report,  administrative   or   criminal   complaints   against   erring   procurement  officials  and  private  entities  colluding  with   them  can  be  acted  upon  by  

34  |  P a g e    

the   authorities   concerned.   With   the   presence   of   Observers   in   the  procurement   activities,   officials   may   capitalize   on   this   opportunity   to  improve   their   procurement   processes   and   strengthen   their   capacity  towards   a   more   efficient,   transparent,   competitive   and   accountable  procurement  regime.  

 3. Policy  Changes  and  Improvements  

 Since   a   copy  of   the  Observer’s  Report   is   likewise   given   to   the  GPPB,   it  can   also   serve   as   an   effective   tool   for   procurement   policy   change,  enhancement  and  development.    R.A.  9184,  including  its  revised  IRR  and  other   associated   rules   and   procedures,   like   any   other   law,   needs  constant   study  and   review   to  ensure   that   the  policies   the   law  seeks   to  enforce  are  still  attuned  with  the  times  and  the  needs  of  the  government.  Through   the  accurate  documentation  made  by   independent  Observers,  policy  changes  and  improvements  can  be  effected  to  make  R.A.  9184  and  its   revised   IRR  more   reflective  of   the  needs   in   the   government   and   its  citizens.  

   B. Challenges  in  Filing  Observer’s  Report    

As  early  as  2006,   the  Office  of   the  Ombudsman  crafted  Department  Order  No.  66,  which  institutionalized  a   feedback  and  complaints  mechanism  designed  to  specifically   address   procurement-­‐related   cases.   Notwithstanding   such  mechanism,  available  reports  have  it  that  Observers  failed  to  effectively  utilize  such  feedback  mechanism  due  to  the  apparent  comfort  to  provide  only  verbal  feedback  to  agencies.    The  Bureau   of  Resident  Ombudsman   (BRO)   has   since   been   the   keeper   of   the  procurement  reports  filed  by  Observers  or  CSOs.  However,  exact  figures  on  the  number   of   reports   filed   in   the   Ombudsman   are   not   available.   It   was   even  reported   that  only   two   (2)   reports  have  been  received  by   the  Ombudsman   in  2008,   and   the   reports   are   not   even   substantial.   On   the   other   hand,   the  GPPB  receives   a   very   small   number   of   Observer’s   Reports   every   year.   The   GPPB  received  only  four  (4)  reports  in  2010,  eight  (8)  in  2011,  and  one  (1)  to  date.    The   figures   above   glaringly   shows   that   if   we   truly   want   to   achieve  transparency,   accountability,   and   efficiency   in   government   procurement,  gathering  of   information  and   filing  of  Observer’s  Reports   is  one  area   that   the  CSOs  or  NGOs  must  develop  and  improve.  While  preparation  and  submission  of  reports   may   be   tedious   and   cumbersome,   continuous   training   and   capacity  building  would  address  these  weaknesses.      Another  challenge  faced  by  Observers  in  filing  Observer’s  Reports  is  the  power  and  authority  given  to  them  by  law.    It  has  been  cited  that  the  ability  to  disclose  or   hide   irregularities   immediately   bestows   Observers   with   significant  responsibility   and   this   potentially   opens   up   new   avenues   for   corruption   or  threats.  This  threat  however,  is  mitigated  by  safeguards  such  as  the  Observer’s  execution  of  a  Conflict  of   Interest  Form  and  by  the  fact   that   in  addition  to  the  

35  |  P a g e    

Procurement  Observer’s  Guide  

two  (2)   independent  observers  a  duly  recognized  private  group  in  a  sector  or  discipline  relevant  to  the  procurement  at  hand,  a  representative  from  the  COA  shall  likewise  be  invited.  

CHAPTER  4  CODE  OF  CONDUCT  FOR  OBSERVERS  

A. Code  of  Conduct    

Aside   from   being   keen   on   the   procurement   process   and   taking   note   of   how  consistent   the   procuring   entity   relative   to   compliance  with   the   procurement  law,  rules,  and  regulations,  it  is  also  important  for  an  Observer  to  follow  a  Code  of  Conduct:    

 1. Respect  for  the  Rule  of  Law.    

 In   the   performance   of   their   duties,   and   at   all   times,   Observers   must  respect   the   laws   and   the   authority   of   the   agencies   charged   with  administering   the   procurement   process.   Observers   must   likewise  maintain  a  respectful  and  cordial  attitude  toward  procurement  officials  and  other  government  officials.    

 2. Professionalism.    

 Observers   should   conduct   themselves   with   a   high   degree   of  professionalism  at  all   times.  Observers  must  undergo  training  so  as   to  acquire   the  degree  of   procurement   expertise   and  knowledge   required  by   the   law.   They   must,   at   all   times,   uphold   their   ethical   and   moral  obligations  as  Procurement  Observers.    

 3. Competence.    

 Observers   must   exercise   utmost   efficiency   and   effectiveness   in   the  performance  of  their  duties  and  responsibilities.  Observers  must  ensure  that  all  of  their  observations  are  true,  accurate  and  well-­‐documented  for  the  effective  monitoring  of  the  procurement  process.  

 4. Dedication.    

 Observers  must  show  the  highest  degree  of  commitment  and  dedication  in   the   performance   of   their   duties   and   responsibilities.     They   should  uphold  the  guiding  principles  of  R.A.  9184   in   the  performance  of   their  duties,   i.e.   accountability,   transparency,   efficiency,   etc.,   and   encourage  adherence  by  others  as  well.      

 

37  |  P a g e    

Procurement  Observer’s  Guide  

 5. Honesty  and  Integrity.    

 Observers  should  conduct  themselves  with  utmost  integrity.    They  must  have  the  trust  and  confidence  of  the  BAC.  In  so  doing,  they  should  help  maintain   and   enhance   public   confidence   in   the   integrity   of   the  procurement  process  and  advance  the  good  of  the  community  by  being  objective  and  acting  in  accordance  with  the  spirit  and  letter  of  the  law.    

   6. Diligence.    

 Observers   should   exercise   proper   diligence   and   attention   in   the  performance  of  their  duties  and  obligations.  

 7. Accountability.    

 Observers  should  be  answerable  or  responsible  to  the  public,  as  well  as  to  the  organization  they  represent,  for  their  actions  and  decisions,  and  the   consequences   thereof,   in   the   performance   of   their   duties   and  obligations  as  Observers.    

 8. Punctuality.    

 Observers  must  be  punctual  in  their  attendance  in  the  bidding  activities.    They  must  fulfill  their  reportorial  obligations  on  time  so  as  not  to  delay  any   action   on   the   part   of   the   agencies   in   charge   of   monitoring  compliance  and/or  investigating  irregularities  and  violations  of  the  law.  Non  submission  of  report  by   the  observer  shall  mean  that   the  bidding  activity  conducted  by  the  BAC  followed  the  correct  procedure.  

 9. Impartiality.    

 Observers’   judgments   must   be   based   on   the   highest   standards   for  accuracy  of   information  and  impartiality  of  decision-­‐making.  CSOs  and  NGOs   to  which   the  Observers  belong  must  ensure   their  neutrality  and  independence   at   all   times.   Observers  must   always   be   objective   in   the  appreciation  of  facts,  letting  go  of  personal  beliefs  and  biases.  Potential  and   actual   conflicts   of   interest   must   always   be   disclosed   by   the  Observer’s  to  the  Procuring  Entity  concerned.  

 10. Proper  Personal  Behavior.    

 Observers   must   maintain   proper   personal   behavior   at   all   times.  Observers   must   always   exercise   sound   judgment   in   their   personal  interactions  with  BAC  Members,  Secretariat,  TWG  and  other  officials  of  the   Procuring   Entity   concerned.   Proper   attire   and   decorum   must   be  followed  while  performing  their  duties.  

38  |  P a g e    

     

B. Prohibited  Acts    

1. Prohibition  on  Conflict  of  Interest    

The   Observer   has   the   duty   to   be   honest   about   his/her   qualifications,  and   about   any   circumstance   that   may   lead   to   a   conflict   of   interest.  Protocols  must   be   laid   down  within   the   CSOs   or   NGOs   on   preserving  their  neutrality  and  independence.  

 2. Prohibition  on  Kickbacks  and  Acceptance  of  Gratuities      

Observers  are  prohibited  to  solicit  or  assist  in  securing  a  contract  for  a  commission,   brokerage   or   contingent   fee   or   the   promise   of   such  payments,   or   non-­‐monetary   benefits   or   the   promise   of   such   benefits.  Observers  are  likewise  prohibited  to  solicit  and  accept  gratuities,  favors  or  anything  of  monetary  and  non-­‐monetary  value,  including  meals  and  rides,   from   contractors,   potential   contractors,   or   parties   to   sub-­‐agreements.  Taking  bribes  is  not  only  strictly  prohibited,  but  it  is  evil  in  itself,   and     Observers   must   always   be   firm   in   refusing   bribes   and  steadfast  in  not  accepting  them.  

 3. Prohibition    on  Discussing    Detailed  Information        

Observers   are   prohibited   to   formally   or   informally   discuss   with   the  bidders,  detailed  information  related  to  the  procurement  once  the  bids  are  opened  until  the  issuance  of  the  Notice  of  Award,  in  support  of  the  “no   contact   rule”   under   R.A.   9184   and   its   revised   IRR.   The  Observers  shall  not  allow  themselves  to  be  used  to  circumvent  the  law.  

 

REMINDERS  

Detailed  information  includes,  but  is  not  limited  to,  the  following:  a. Advance  Information  ;  b. Confidential  or  proprietary  information  about  other  bidders;  c. Technical  information;  and  d. Updates  on  decisions  made  by  the  BAC.  

 C. Observer’s  Dos  and  Don’ts    

Below  is  a  simple  checklist  following  the  Code  of  Conduct  for  Observers:      

DO’s:     DON’Ts:  

39  |  P a g e    

Procurement  Observer’s  Guide  

• Acknowledge  receipt  of  invitation.  Be  on  time.  

  • Don’t  come  unprepared.  

• Know  your  role  and  rights  as  observer.  

  • Don’t  engage  in  a  debate  with  the  BAC.    

• Bring  references  that  you  may  need.     • Don’t  express  your  own  opinion.  

• Disclose  conflict  of  interest.     • Don’t  be  combative.  

• Politely  call  the  attention  of  BAC.  Cite  the  applicable  laws  and  rules.  

  • Don’t  be  complacent.  

• Be  assertive  and  persuasive.     • Don’t  engage  in  fishing  expedition.  

• Strictly  observe  and  comply  with  the  confidentiality  agreement.  

  • Don’t  accept  favors/gifts  from  the  BAC  or  supplier  or  from  anyone  involved  in  the  bidding.  

• Refuse  to  accept  monetary  consideration  or  any  form  of  favor  or  gift  or  token.  

• Prepare  reports.  Take  note  of  critical  observations.  

 

• Inhibit  oneself  in  case  of  a  possible  conflict  of  interest  in  the  event  that  one  is  related  to  any  of  the  bidder  or  one  has  a  personal  interest  in  the  item  to  be  bid  out  or  if  in  case  there  is  a  personal  relationship  with  the  BAC  members.  

 

CHAPTER  5  TOOLS  AND  INSTRUMENTS  

Chapter   5   features   some   tools   and   instruments   related   to   procurement   that   can  further   assist   Observers   in   their   work   that   contributes   to   the   larger   goal   of  maintaining   integrity   and   improving   efficiency,   transparency,   competition   and  accountability  in  government  procurement.    A. Copy   of   Republic   Act   No.   9184   and   its   Implementing   Rules   and  

Regulations    

Bring  a  copy  of  the  RA  9184  and  its  IRR.  Observers  are  not  expected  to  be  legal  nor  procurement  experts.  Hence,  it  is  imperative  that  Observers  have  a  copy  of  the  law  that  is  handy.  This  way,  the  Observer  can  always  refer  to  it  in  cases  of  doubt  in  his  own  judgment.  

 B. Checklist  of  Basic  Documents    

Use  a  checklist.  It  will  serve  as  a  guide  to  make  sure  the  Observer  does  not  miss  anything.   The   checklist   determines   the   presence   or   absence   of   important  documents  as  shown  in  the  table  below.  This  may  be  expanded  depending  on  what  can  help  you  best.    Sample   Checklist:   Presence   or   Absence   of   Documents   (put   a   check   if   available;  cross  if  unavailable)      

Annual  Procurement  Plan    and  Project  Procurement  Management  Plan      

Minutes  of  BAC  Meetings    

Abstract  of  Bids  as  Read  and  Abstract    of  Bids  as  Evaluated    

Opened  Proposals    

Post-­qualification  Summary  Report    

     

41  |  P a g e    

Procurement  Observer’s  Guide  

 C. Conflict  of  Interest  Form    

The   Observer   must   complete   a   Conflict   of   Interest   Form,   indicating,   among  others,   the   areas   of   conflict,   if   any.   The   BAC   should   prepare   the   Conflict   of  Interest  Form.  If  the  BAC  does  not  prepare  a  Conflict  of  Interest  Form,  the  CSO  Observer   may   prepare   one   following   the   Sample   Form   provided   below.   An  observer   may   indicate   in   one   Conflict   of   Interest   Form   several   contracts   or  projects  for  procurement  for  which  an  Invitation  has  been  extended.    Below  is  a  Sample  Conflict  of  Interest  Form  that  the  Observer  may  use.  

 Name:    

Date:  

Civil  Society  Organization/Non-­‐governmental  organization:    Procuring  Entity:    Project  Name:    1. Do   you   have   any   relationship   with   the   Head   of   the   Procuring   Entity,   BAC   Member,  

Secretariat,  TWG,  Head  of   the  PMO  or  end-­‐user  unit,   or  project   consultants  within   the  3rd  degree  of  consanguinity  or  affinity?  

       

2. Do  you  have  any  significant  financial  or  business  interests  that  would  reasonably  appear  to   be   affected   by   the   activities   you   would   undertake   as   an   Observer?   If   yes,   provide  additional  information.  

   

   

3. Explain  the  nature  of  any  potential  conflict  of   interest  that  you  may  have  in  relation  to  the  activities  you  would  undertake  as  an  Observer.  Use  additional  sheets,  if  necessary.  

   

   

 Signature:    

Date:    

     

REMINDERS  

• The  Conflict   of   Interest   Form  must   be   filled   up   accurately,   and  must   be  updated  when  any  change  in  the  circumstances  of  the  Observer  occurs.      

• The  BAC  must  review  the  statements  declared   in   the  Conflict  of   Interest  

42  |  P a g e    

Form  prior  to  the  Observer’s  participation  in  the  procurement  process  to  ensure  that  any  actual  or  potential  conflict  of  interest  has  been  properly  identified  and  addressed.  

 • The  Observer  shall  be  prohibited  from  participating  in  the  procurement  

process   in   the  particular  project   to  be  procured,   in   the  event   that   there  exists  an  actual  or  potential  conflict  of  interest  on  the  Observer’s  part  as  properly  identified  by  the  BAC.    The  CSO/NGO  invited  shall  send  another  Observer,  with  no  conflict  of   interest,  as   temporary  replacement   for   the  procurement  of  the  item  concerned.  

 • The  Procuring  Entity  may  provide  additional  prohibitions  and  sanctions  

relative  to  actual,  apparent,  or  potential  conflict  of  interest.      

     D. Procurement  Observer’s  Report  (POR)      

Fill   out   the   Observer’s   Report.   The   Observer   may   use   this   to   determine  compliance   by   the   Procuring   Entity   with   procurement   processes   and  procedures  and  to  analyze  data  gathered  during  each  bidding  stage.  You  may  also   expand   the   POR   depending   on   what   can   help   best   evaluate   the  effectiveness   of   procurement   practices   of   various   government   agencies.  Observers,   in  cooperation  with  an  agency,  may  assist   in  validating  the  results  of  this  self-­‐assessment  tool.        

 Sample  POR  template  

   

OBSERVER’S  REPORT    “[Observer’s]  report  shall  assess  the  extent  of  the  BACs  compliance  with  the  provisions  of  this  IRR  and  areas  for  improvement  in  the  BAC’s  proceedings.”    (Sec.  13.4)      Procuring  Entity    

Head  of  Procuring  Entity    

BAC  Chairman    

Project  Name  (ID  No.)    

PhilGEPS  Reference  No.    

Approved  Budget    

 I. Bidding  Procedures  

 

43  |  P a g e    

Procurement  Observer’s  Guide  

 Procurement  Type  (Goods,  Infra,  Services)  

 

 Procurement  Process  Method  (Public  Bidding  or  Alternative  Mode)  

 

 II. Details  of  Procurement  Stage  Attended  and  Observations  Made    Date   Time   Place   Procurement  Stage   Where  there  

any  deviations  observed?  (Yes  or  No)  

GPRA/IRR  Provisions  Violated  (if  any)  

      Advertisement             Pre-­‐Bid  Conference             Bid  Submission  &  Opening             Post-­‐Qualification             Awarding  of  Contract        III. Highlights  of  Each  Stage  of  Procurement    

 Stages  of  Procurement  

 

 Notes  

Advertisement    

 Pre-­‐Bid  Conference  

     

 Bid  Submission  &  Opening  

     

 Post-­‐Qualification  

     

 Awarding  of  Contract  

     

 IV. Other  Details  of  the  Procurement  Process      Average   Number   of   Bidders  Acquiring   Bidding   Documents  (Those  that  have  bought  bidding  documents)  

 

Average   Number   of   Bidders  submitting  bids  

 

44  |  P a g e    Average   Number   of   Bidders  passing  preliminary  examination  of  bids  

 

Average   Number   of   days   from  posting  to  Contract  award  

 

(Average)   Number   of   days   to  resolve   request   for  reconsideration/protest   (If  applicable)  

 

   Respectfully  submitted  by:                  Observer      Date:                  Cc.:        BAC  Chairman                    Head  of  Procuring  Entity        E. Agency  Procurement  Compliance  and  Performance  Indicators  (APCPI)    

The   GPPB   approved   the   use   of   a   tool   called   APCPI   to   assess   a   government  agency’s   performance   in   its   procurement   activities   and   compliance   with  national  procurement  systems  and  international  best  procurement  practices.      The  APCPI  is  derived  from  the  Baseline  Indicator  System  (BLI)  and  Compliance  and   Performance   Indicator   (CPI)   System   prescribed   under   OECD-­‐DAC  Methodology  for  the  Assessment  of  National  Procurement  Systems  where  the  Philippines   served   as   a   pilot   country.   It   is   also   a  modification   of   the   Agency  Procurement   Performance   Indicators   (APPI)   and   the   Online   Monitoring   and  Evaluation   System   (OMES)   previously   used   by   the   GPPB   to   evaluate   the  effectiveness   of   procurement   practices   of   various   government   agencies.   The  APCPI  System  was  adopted  by  the  GPPB  for  use  by  government  agencies,  as  set  forth  in  GPPB  Resolution  No.  10-­‐2012,  dated  June  1,  2012  

   

The   confirmation   process   is   an   important   feature   of   the   APCPI   Assessment  which   highlights   procurement   transparency,   public   monitoring   and  accountability.     Observers  may   join   the   Confirmation   Team  which   shall   take  the  role  of  an  independent  entity  that  will  carry  on  the  task  of  confirming  the  assessment   results   of   the   PE.     This   Team   shall   be   responsible   to   check   the  APCPI   results   of   the   procuring   entity   in   terms   of   completeness,   correctness,  consistency  and  responsiveness.  

CHAPTER  6  OTHER  SUGGESTED  ACTIVITIES  

Although   the  most   important   and  primary   task   of   an  Observer   is   to   record   his/her  accounts  of  the  manner  by  which  a  procuring  entity  conducted  its  procurement,  there  are  other  efforts  that  the  organization  may  want  to  do  to  be  more  effective  in  its  effort  to  contribute  to  procurement  reform.    This  Chapter  enumerates  some  of  these  activities  which  are  mostly  organizational  or  administrative.    A. Tracking  System    

Organizations  must  validate  the  accuracy  and  completeness  of  the  observation  reports  before  submitting  a   copy   to   the  head  of   the  procuring  entity  and   the  agency’s   resident   Ombudsman   or   the   Ombudsman   for   Luzon,   Visayas,  Mindanao   depending   on   its   location.     Tracking   is   important   to   record   all  correspondences/  communications  with  government  and  the  actions  taken.  It  is   also   useful   for   purposes   of   recording   the   organization’s   activities   and  progress  in  its  procurement  monitoring  work.  

 You  can  use  the  sample  template  below  in  tracking  the  reports.    Sample  Tracking  List:  

 Reference/  Report  No.  

Agency   Summary   Status/Date  

0001   Procurement  City  

alleged  overpriced  lamp  posts  

7  March  2009  –  letter  of  inquiry  sent  to  the  Mayor’s  office  

 Keep  the  tracking  simple.  Include  a  reference  number,  name  of  agency,  a  brief  summary  of  the  issue  or  concern,  and  important  dates,  particularly,  the  report  submission  and  reply  of  the  PE.    

 If   the   organization   is   satisfied   with   the   PE’s   reply,   it   may   send   a   thank   you  letter.  Otherwise  continue  to  follow-­‐up  until  the  issue  is  resolved.    

 It  will  also  help  if  tracking  lists  are  copy-­‐furnished  to  the  GPPB  for  appropriate  guidance  and/or  action.  

46  |  P a g e    

 B. Record  Keeping    

The  organization  will  collect  and  generate  various  types  of  information  in  the  process  of  participating  in  the  different  stages  of  procurement  and  establishing  networks.   It   must   be   kept   to   provide   quick   and   easy   reference   for   reviews,  studies,  performance  benchmarking,  and  decision-­‐making.    The  system  of  recording  and  managing  of  information  may  be  done  as  follows:  

 

Type  of  information  

Description  of  

information  Origin   Receiver   Custody   Storage   Retention  

Period  

             

 C. Disclosure  Policy    

Some   information   may   be   sensitive,   confidential,   or   sourced   through  unconventional  means.  The  organization  must  exercise  prudence   in  releasing  the  information  to  the  public.  As  a  matter  of  policy,  it  should  be  released  only  after   a   thorough   verification   and   deliberation   by   the   organization   of   the  possible  impact  of  releasing  the  same.    

 D. Reporting  to  the  Public    

CSOs  have  to  regularly  engage  the  public  at  large  to  share  relevant  information  obtained   in   the   course  of   procurement  observation.   In   addition,   reporting   to  the  public  may  encourage  more  volunteers  to  step  up  and  participate.    The   following   methods   may   be   utilized   by   CSOs   to   disseminate   relevant  information  to   the  general  public  aside   from  means   they  are  already   familiar  with:  

 1. Communicating  messages   via   press   statements   is   a   good   strategy.   An  

organization  who  would  like  to  do  this  should  first  consult  its  partners,  validate   information   that  will  be  released  and  cite  provisions  of   law   if  necessary.    

 It   should   also   take  note   of   the   following  when  drafting   a  PR   and  may  look  at  the  sample  PR  below,  thus  the  PR  must  contain:    

 a. Factual  and  objective  information          b. Constructive  feedbacks  c. Identifiable  contact  information    d. Simple  language  

47  |  P a g e    

Procurement  Observer’s  Guide  

e. Exact  quotes    

SAMPLE  PRESS  RELEASE    Philippine  Procurement  Network-­  BISDAK  Group  September  1,  2010    Anti-­corruption   advocates   cry   foul   over   medicine   scam,   vows   to   file  charges  to  LGU  Execs/Contractors    Anti-­‐corruption   advocates   in   Mindanao   recently   vows   to   file   corruption  charges   to   LGU   execs   in   General   Santos   City   and   business   contractors  following   accusations   of   anomalous   public   bidding   involving   hundreds   of  thousands  of  pesos  worth  of  medicines  for  the  General  Santos  City  Hospital.  According  to  Mr.  Geroncio  Ohayas,  Coordinator  of  the  P2N  BISDAK  Group,  the  anomaly   includes   the  procurement  of  gentamicin   sulfate   and  cloxacillin  sodium  drugs  amounting  to  150,000  pesos  which  the  General  Santos  Medical  Society  President  Dr.  Cristita  Epal  considers  as  fake.  BAC  Observer  and  P2N  affiliate  Ms.  Lota  Agbulos   claims   that   there  are  violations  committed  both  by  the  Supplier-­‐  DMI  Medical  Supplies  and  the  LGU  BAC  on  the  provisions  of  the  RA  9184  particularly  on  the  specifications  of  goods  as  per  reflected  in  the  original   bid/contract   documents.   The   P2N   Bisdak   Group   is   a   network   of  citizen   volunteers   observing   the   compliance   of   government   agencies   to  procurement  laws  in  Mindanao.      Contact:  Ms.  Ann  Patricia  Felicio  Media  Officer,  P2N  Bisdak  Group  Contact  Number:  0900-­000-­00-­00  

 2. Broadcasting  messages   through  radio  and   television  may  also  be  used  

by  CSOs  making  sure  that  their  messages  are  :    

a. Short   and   concise   so   as   not   to   confuse   audience   with   too   much  information.  

b. Using  simple  and  straightforward  language.  c. Offers  specific  and  practical  suggestions  or  options.  d. Organized  clearly  and  logically.  

 3. Conducting   symposiums,   forums,   conferences,   and   similar   activities  

may   also   be   done   to   increase   local   awareness   and   attract   people   to  become  actively  involved  as  procurement  Observers.  

 4. Messages  may   also   be   disseminated   using   the   Internet   through   social  

networking  sites  and  other  websites  to  promote  information  on  public  procurement  reforms.  

48  |  P a g e    

 5. Other   mechanisms   can   also   be   put   in   place   such   as   designating   a  

spokesperson   or   forming   a   public   relations   committee   to   facilitate  better  media  relations  in  the  future.  All  in  all,  public  reporting  becomes  a   critical   if   not   an   integral   part   of   an   organizations’   involvement   in  public  procurement  activities  as  it  helps  strengthen  efforts  to  maintain  transparency  and  accountability  of  all  those  involved.    

   The  Baba’s  Foundation  Experience    Information    CSO:   Baba’s   Foundation   Inc.   (BFI)   is   currently   heading   the   Secretariat   for   the   Davao   Procurement  Transparency  Core  Group  (DPTCG)  Years:  2009-­‐2010  Country:  Mindanao,  Philippines  Amount:    Sector:  Civil  Society  Monitoring  of  Public  Procurement  and  Auctions  Corruption  Problem:  Widespread  corruption  in  government  procurement  throughout  the  Philippines  Tools   employed:   Capacity   Building,   Third   Party   Monitoring,   Constructive   Engagement,   Coalition  Building,  Community  Mobilization,  Structured  Consultation  Process    To  help  curb  –  if  not  stop  this  type  of  corruption  –  DPTCG  is  organizing  and  enhancing  the  capacity  of  civil  society  organizations  (CSOs)   in   the  Davao  Region  of  Mindanao,  by  mobilizing  them  as  observers  during  bidding  and  procurement  processes   carried  out  by  government  agencies.  As  mandated  under  the  Philippine’s  Government  Procurement  Reform  Act,   CSOs  may  designate   observers   to  monitor   all  phases  of  the  bidding  procurement  process,  including  contract  implementation  by  winning  bidders.    Actions  Taken  by  BFI    The   engagement   of   CSOs   as   observers   during   all   stages   of   government   procurement   processes   is  DPTCG’s  principal  approach  toward  addressing  corrupt  practices.   In  the   initial  phase  of  the  program,  there   was   resistance   on   the   part   of   government   entities   to   invite   civil   society   organizations   as  observers,  even  if  the  Government  Procurement  Reform  Act  required  them  to  do  so.    To  soften  any  resistance,  several  dialogues,  fora  and  other  interface  activities  were  initiated  by  DPTCG,  inviting  server  heads  and  key  personnel  of  different  government  agencies.    Through   these   activities,   the   efforts   of   the   CSOs   were   appreciated   by   the   attending   government  agencies,  and  both  CSOs  and  government  agency  representatives  came  up  with  their  ideal  concepts  of  “good  government”,  which  included  the  goal  of  a  corruption-­‐free  nation.  The  participation  of  academia  and  the  private  sector  proved  to  be  an  effective  strategy  to  facilitate  dynamic  and  progressive  thinking  and  the  development  of  action  steps  to  combat  corruption  in  the  procurement  system.  In  order  to  elicit  government  agencies   to  commit   to   the  path  of  good  governance  chosen,  DPTCG   initiated   the  crafting  and  signing  of  a  Memorandum  of  Agreement,  an  ethical  code  to  be  adopted  by  participating  entities.    When,  as  a  result  of  volunteer  monitoring,  a  case  of  corruption  had  been  discovered,  DPTCG  submitted  its  report  to  the  Office  of  the  Ombudsman.    Impact  and  Results  Achieved    As   a   result   of   the   participation   of   CSOs   and   pressure   exerted   to   assert   due   diligence   in   government  procurement,  procurement  has  become  more  transparent  and  most  of  the  agencies  are  now  following  proper  procedures.  In  some  agencies,  CSO  observers  reported  that  there  is  a  considerable  decrease  in  the  complaints  about   “syndicated”  bidding  procedures,   reducing   the  prevalence  of  bidders  who  have  

49  |  P a g e    

Procurement  Observer’s  Guide  

already   been   awarded   with   a   procurement   contract   long   before   the   bidding   processes   has   actually  finished.    Several   CSOs   reported   that   as   a   result   of   their   vigilance   in   the   monitoring   of   the   construction   of   a  government  building,  the  budget  had  been  utilized  as  laid  out  in  the  original  project  plan,  resulting  in  better  quality  of  construction  and  –  in  other  instances  –  in  better  services  for  the  population.    Another   observed   impact,   has   been   the   growing  number   of   government   procuring   agencies   that   are  open  to  the  presence  and  participation  of  CSOs  as  observers  of  the  Bids  and  Awards  Committees  (BAC).  In  the  initial  phase  of  the  project,  only  7  government  agencies  were  receptive,  most  of  them  from  Davao  City.   Currently,   some   18   government   agencies   are   inviting  DPTCG   to   send   BAC   observers   during   all  phases  of   the  bidding  process,  and  several   invitations  have  been  received  from  provinces  around  the  Davao  Region.  DPTCG  currently  prioritized  third  party  monitoring  of  the  five  top  procuring  entities  and  local  government  units  in  each  city  or  province  within  the  Davao  Region  to  guarantee  focus,  results  and  in-­‐depth  participation.    Another  achievement  of  the  project  is  the  creation  of  city  and  provincial  integrity  boards,  initiatives  for  collaboration  amongst  CSOs,  local  government  units  and  other  stakeholders  in  each  locality  to  maintain  and  sustain  the  mechanisms  of  combating  corruption.                                  

ANNEX  A  SAMPLE  FORM  OF  CONFIDENTIALITY  AGREEMENT  

   

CONFIDENTIALITY  AGREEMENT    

 This   CONFIDENTIALITY   AGREEMENT   (hereinafter   “Agreement”)   is   made   and   entered   into  this  [date]  day  of  [month],  [year],  by  and  between:      

[First  party’s  details]      

and      

[Second  party’s  details].    

DEFINITION  OF  CONFIDENTIAL  INFORMATION  1. As  used  in  this  Agreement,  “confidential   information”  shall  mean  all   information  and  

materials   including,   without   limitation,   market   analyses,   cost   estimates,   technical  specifications,   evaluation   criteria   and   results,   and   any   documentation,   analyses,  compilations,   forecasts,   studies   or   other   procurement-­‐related     documents   prepared  based   on   any   of   the   foregoing   that   is   provided   by   the   party   disclosing   (“Disclosing  Party”)  to  the  party  receiving  (“Receiving  Party”)   information  under  this  Agreement,  whether  oral,  written,  or  in  any  other  medium.    

HANDLING  OF  CONFIDENTIAL  INFORMATION    2. The  Receiving  Party  shall  maintain   the  secrecy  of   the  Disclosing  Party’s  Confidential  

Information  and  shall     exert  all   reasonable  efforts   to  preserve   the     confidentiality  of    such   information,   including,     but   not   limited   to,   the   implementation   of     reasonable  physical  security  measures  and  operating  procedures.      

 3. The  Receiving  Party  agrees  that  at  all   times  and  notwithstanding  any  termination  or  

expiration  of   this  Agreement,   it  will  hold   in  strict  confidence  and  not  disclose  to  any  third  party    all  Confidential  Information  received  from  the  Disclosing  party,  except  as  approved  in  writing  by  the    latter.  The  receiving  party  shall  be  prohibited  from  using  the    Confidential  Information  for    purposes  other  than    compliance  with  its  obligations  as  an  Observer  under  Republic  Act  9184  and  its  Implementing  Rules  and  Regulations.      

4. Access  to  Confidential  Information  of  the  Disclosing  Party  shall  only  be  granted  by  the  Receiving   Party   to     its   employees   or   authorized   representatives,   when   their  knowledge  of  such  information  becomes  necessary,  provided  that  such  persons    have  signed   confidentiality   agreements   or   are   otherwise   bound   by   confidentiality  obligations    which  contain  the  minimum  terms,  restrictions  and  limitations    provided  herein.  

   

   

 

PERIOD  AND  TERMINATION    

5. This   Agreement   shall   be   effective   for   a   period   of   ____,   and   shall   automatically  terminate   thereafter.     Notwithstanding   the   termination   or   expiration   of   this  agreement,   all   obligations   contained  herein   shall   remain  valid,   effective  and  binding  upon  the  Receiving  Party,  his  successors  and  assigns.      

6. Upon    termination  or  expiration  of  this  Agreement,  or  otherwise  upon  the  Disclosing  Party’s  request,  all  Confidential  Information  furnished  to  the  Receiving  Party    shall  be  promptly   returned   to   the   Disclosing   Party,   or   at   the   Disclosing   Party’s   express  request,     shall   be   destroyed.     In   case   of   destruction   as   requested   by   the   Disclosing  Party,    the  same  shall  be  confirmed  in  writing  by  the  Receiving  Party.    

 EQUITABLE  REMEDIES  

 7. The   Receiving   Party   acknowledges   that   any   breach   of   this   Agreement   may   cause  

irreparable  harm  to  the  Disclosing  Party  for  which  the  latter  is  entitled  to  seek,  among  others,  indemnification  for  damages,  as  well  as  injunctive  or  other  equitable    remedies  as  may  be  allowed  by  law.  

 MISCELLANEOUS  

 8. The  Receiving  Party  shall  not  transfer  or  assign  this  Agreement  to  any  other  person  or  

entity,  whether  by  operation  of  law  or  otherwise,  without  the  prior  written  consent  of  the  Disclosing  Party.  Any  such  attempted  assignment  shall  be  void  and  of  no  effect.      

9. In   case   any  provision   of   this  Agreement   is   declared  by   a   competent   authority   to   be  unenforceable   or   invalid,   such   declaration   shall   not   render   this   Agreement  unenforceable  or  invalid  as  a  whole.    The  unenforceable  or  invalid  provision  shall  be  changed   and   interpreted   so   as   to   best   accomplish   the   objectives   of   such   provision,  subject  to  existing  laws,  rules  and  regulations.    

10. This  Agreement  is  the  complete  and  exclusive  agreement  regarding  the  disclosure  of  Confidential  Information  between  the  parties,  and  replaces  or  supersedes  any  and  all  prior  oral  or  written  communications  and  agreements  between  the  parties  regarding  Confidential   Information  without   prejudice   to   the   rules   and   regulations   concerning  restrictions   on   disclosure   of   information   such   as   on   matters   involving   national  security,  diplomatic  or  foreign  relations,  intelligence  and  other  classified  information.  

   

IN   WITNESS   WHEREOF,   the   parties   hereto   have   executed   this   Confidentiality  Agreement  as  of  the  date  and  year  first  above  written.  

   

_______________________ ________________________

 SIGNED IN THE PRESENCE OF:

_______________________ ________________________  

 [ACKNOWLEDGMENT]  

52  |  P a g e    

Procurement  Observer’s  Guide