Procurement Approaches
-
Upload
husni-n-abdulhadi -
Category
Documents
-
view
216 -
download
0
Transcript of Procurement Approaches
-
7/24/2019 Procurement Approaches
1/18
PROCUREMENT
APPROACHES
-
7/24/2019 Procurement Approaches
2/18
Procurement is the process of selecting a team for successfully
conducting a construction project.
There are three main ways in which owners procure construction
services: in-house capability, appointment and competition.
-
7/24/2019 Procurement Approaches
3/18
IN-HOUSE
The in-house capability is extensively used by owners who
undertake large volumes of work, such as large private
developers and state agencies. The functions usually handled in-
house are related to design and facility management, because
there has been a shift towards outsourcing most project functionsin recent years.
-
7/24/2019 Procurement Approaches
4/18
There are a number of important advantages offered by the in-house
capability option, including:
no need for a complete contract prior to starting the project
extensive administrative audit capability for the owner
minimal risk of opportunistic profiteering at the owner!s expense.
"owever, there are also important disadvantages of this option:
possible diversion from the owner core business
expensive to maintain in-house capability for small number of projects
possible production inefficiencies because of lack of competition.
-
7/24/2019 Procurement Approaches
5/18
APPOINTMENT
#ppointment is often used for design and project management
services.
"owever, in many $uropean countries, appointment for public
projects is limited to a pre-established maximum contract value%
above that value a tender procedure is re&uired.
#ppointment may also be used when the project re&uirements are
so specific that only one entity can fulfil them or when the
re&uirement to mobilise resources is so urgent that there is no
time to go through a tendering process 'e.g. urgent repair of a
wall at risk of collapsing(.
-
7/24/2019 Procurement Approaches
6/18
The advantages of appointment are:
restricted search of suppliers with lower costs and reduced risks
high-trust relationships built up between the client and the
supplier.
Possible disadvantages are:
lower levels of production efficiency and effectiveness due to
the lack of competition
lack of transparency of the appointment criteria
too-cosy relationships, leading to inade&uately rigorous
appointment criteria and this can degenerate into corruption.
-
7/24/2019 Procurement Approaches
7/18
COMPETITION
)ompetition is widely used in the construction industry as a
means of procurement. *esign competition is primarily used
when the conceptual &uality of the design solution is paramount.
-
7/24/2019 Procurement Approaches
8/18
The advantages of competition are that it:
generates opportunities for fresh competitors
brings transparency to the procurement process
encourages production efficiency.
#gainst these advantages, there are some important disadvantages:
only limited information on competitors is available for decision
some less important aspects of the offer may be over-assessed to the detriment
of possibly more important issues 'particularly in design competition(
procurement costs are high, both to the owners 'rewards, search and selection(
and to respondents to the competition 'in order to prepare the offer, which mayinclude creative work as in design competition(
re&uirements for high uncertainty transactions are difficult to prepare
underestimated winning tenders may lead to motivation problems during contract
delivery.
-
7/24/2019 Procurement Approaches
9/18
TRADITIONAL PROCUREMENT
RELATIONSHIPS
-
7/24/2019 Procurement Approaches
10/18
Traditional procurement assumes the separation of design and construction.
Typically, the owner first contracts design either to an architect for a building
project or to a consulting engineer for an engineering project, and they become
the owner!s agent during the design phase and act as the design team leader
+or small projects, the architect or the consultant engineer, as the case may be,
can take the role of contract administrator on behalf of the owner. #lternatively,a member of the owner!s staff can be appointed for this
)oordinators may be appointed to embrace the responsibility and authority of
part of the project team 'e.g. the design team, pre-construction team or the
construction team.
nder the traditional procurement approach, contractors are approached at the
pre-construction stage% eventually, a contractor is selected to carry out theworks. The main contractor must nominate a representative acting on the
contractor!s behalf, who tends to be called construction site manager, site
director, and contractor!s agent or even project manager, depending on the
countries.
-
7/24/2019 Procurement Approaches
11/18
DESIGN AND BUILD
PROCUREMENT RELATIONSHIPS
-
7/24/2019 Procurement Approaches
12/18
*esign and build arrangements aim at overcoming some of the
criticism of traditional procurement, namely the responsibility
chain, the need for complete design prior to signing the contract
and too late involvement of the
contractor in the project life-cycle.n order to develop the design, the contractor may use in-house
capabilities or outsource design to an independent team.
-
7/24/2019 Procurement Approaches
13/18
MANAGEMENT CONTRACTING
RELATIONSHIPS
-
7/24/2019 Procurement Approaches
14/18
nder this approach, the owner appoints a person or a company
to manage a set of work package subcontractors performing the
construction works on site
This approach allows for overlapping design and construction
because each work package may be launched only after thecorresponding design is sufficiently developed. This may result in
reduced contract period and lower construction costs.
the owner first contracts the design and then contracts the
management contractor. This allows the owner to keep control of
the design, while benefiting from the experience of themanagement contractor 'e.g. constructability and value
engineering( during the development of the design.
-
7/24/2019 Procurement Approaches
15/18
CONSTRUCTION MANAGEMENT
RELATIONSHIPS
-
7/24/2019 Procurement Approaches
16/18
nder the construction management approach, the owner directly
contracts each work package, and the construction manager
prepares the corresponding project execution and coordinates
works on site.
-
7/24/2019 Procurement Approaches
17/18
RELATIONAL
CONTRACTING
elational contracting embraces various approaches, such as
partnering, joint venturing, alliancing, integrated project delivery
and other collaborative working arrangements and risk sharing
mechanisms
-
7/24/2019 Procurement Approaches
18/18