Procurement Approaches

download Procurement Approaches

of 18

Transcript of Procurement Approaches

  • 7/24/2019 Procurement Approaches

    1/18

    PROCUREMENT

    APPROACHES

  • 7/24/2019 Procurement Approaches

    2/18

    Procurement is the process of selecting a team for successfully

    conducting a construction project.

    There are three main ways in which owners procure construction

    services: in-house capability, appointment and competition.

  • 7/24/2019 Procurement Approaches

    3/18

    IN-HOUSE

    The in-house capability is extensively used by owners who

    undertake large volumes of work, such as large private

    developers and state agencies. The functions usually handled in-

    house are related to design and facility management, because

    there has been a shift towards outsourcing most project functionsin recent years.

  • 7/24/2019 Procurement Approaches

    4/18

    There are a number of important advantages offered by the in-house

    capability option, including:

    no need for a complete contract prior to starting the project

    extensive administrative audit capability for the owner

    minimal risk of opportunistic profiteering at the owner!s expense.

    "owever, there are also important disadvantages of this option:

    possible diversion from the owner core business

    expensive to maintain in-house capability for small number of projects

    possible production inefficiencies because of lack of competition.

  • 7/24/2019 Procurement Approaches

    5/18

    APPOINTMENT

    #ppointment is often used for design and project management

    services.

    "owever, in many $uropean countries, appointment for public

    projects is limited to a pre-established maximum contract value%

    above that value a tender procedure is re&uired.

    #ppointment may also be used when the project re&uirements are

    so specific that only one entity can fulfil them or when the

    re&uirement to mobilise resources is so urgent that there is no

    time to go through a tendering process 'e.g. urgent repair of a

    wall at risk of collapsing(.

  • 7/24/2019 Procurement Approaches

    6/18

    The advantages of appointment are:

    restricted search of suppliers with lower costs and reduced risks

    high-trust relationships built up between the client and the

    supplier.

    Possible disadvantages are:

    lower levels of production efficiency and effectiveness due to

    the lack of competition

    lack of transparency of the appointment criteria

    too-cosy relationships, leading to inade&uately rigorous

    appointment criteria and this can degenerate into corruption.

  • 7/24/2019 Procurement Approaches

    7/18

    COMPETITION

    )ompetition is widely used in the construction industry as a

    means of procurement. *esign competition is primarily used

    when the conceptual &uality of the design solution is paramount.

  • 7/24/2019 Procurement Approaches

    8/18

    The advantages of competition are that it:

    generates opportunities for fresh competitors

    brings transparency to the procurement process

    encourages production efficiency.

    #gainst these advantages, there are some important disadvantages:

    only limited information on competitors is available for decision

    some less important aspects of the offer may be over-assessed to the detriment

    of possibly more important issues 'particularly in design competition(

    procurement costs are high, both to the owners 'rewards, search and selection(

    and to respondents to the competition 'in order to prepare the offer, which mayinclude creative work as in design competition(

    re&uirements for high uncertainty transactions are difficult to prepare

    underestimated winning tenders may lead to motivation problems during contract

    delivery.

  • 7/24/2019 Procurement Approaches

    9/18

    TRADITIONAL PROCUREMENT

    RELATIONSHIPS

  • 7/24/2019 Procurement Approaches

    10/18

    Traditional procurement assumes the separation of design and construction.

    Typically, the owner first contracts design either to an architect for a building

    project or to a consulting engineer for an engineering project, and they become

    the owner!s agent during the design phase and act as the design team leader

    +or small projects, the architect or the consultant engineer, as the case may be,

    can take the role of contract administrator on behalf of the owner. #lternatively,a member of the owner!s staff can be appointed for this

    )oordinators may be appointed to embrace the responsibility and authority of

    part of the project team 'e.g. the design team, pre-construction team or the

    construction team.

    nder the traditional procurement approach, contractors are approached at the

    pre-construction stage% eventually, a contractor is selected to carry out theworks. The main contractor must nominate a representative acting on the

    contractor!s behalf, who tends to be called construction site manager, site

    director, and contractor!s agent or even project manager, depending on the

    countries.

  • 7/24/2019 Procurement Approaches

    11/18

    DESIGN AND BUILD

    PROCUREMENT RELATIONSHIPS

  • 7/24/2019 Procurement Approaches

    12/18

    *esign and build arrangements aim at overcoming some of the

    criticism of traditional procurement, namely the responsibility

    chain, the need for complete design prior to signing the contract

    and too late involvement of the

    contractor in the project life-cycle.n order to develop the design, the contractor may use in-house

    capabilities or outsource design to an independent team.

  • 7/24/2019 Procurement Approaches

    13/18

    MANAGEMENT CONTRACTING

    RELATIONSHIPS

  • 7/24/2019 Procurement Approaches

    14/18

    nder this approach, the owner appoints a person or a company

    to manage a set of work package subcontractors performing the

    construction works on site

    This approach allows for overlapping design and construction

    because each work package may be launched only after thecorresponding design is sufficiently developed. This may result in

    reduced contract period and lower construction costs.

    the owner first contracts the design and then contracts the

    management contractor. This allows the owner to keep control of

    the design, while benefiting from the experience of themanagement contractor 'e.g. constructability and value

    engineering( during the development of the design.

  • 7/24/2019 Procurement Approaches

    15/18

    CONSTRUCTION MANAGEMENT

    RELATIONSHIPS

  • 7/24/2019 Procurement Approaches

    16/18

    nder the construction management approach, the owner directly

    contracts each work package, and the construction manager

    prepares the corresponding project execution and coordinates

    works on site.

  • 7/24/2019 Procurement Approaches

    17/18

    RELATIONAL

    CONTRACTING

    elational contracting embraces various approaches, such as

    partnering, joint venturing, alliancing, integrated project delivery

    and other collaborative working arrangements and risk sharing

    mechanisms

  • 7/24/2019 Procurement Approaches

    18/18