Page 1: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

Procurement 201Procurement 201

Page 2: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

2BRITE Procurement 201

Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!

Please turn off or silence cell phones and pagers

Please do not read or send email messages during class time

Respect those speaking and asking questions by keeping side discussions to a minimum

Please do not interrupt the person speaking We will start, break, and end on time All unanswered questions will be placed in

the “Parking Lot” and answers will be distributed later

Welcome and Ground RulesWelcome and Ground Rules

Page 3: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

3BRITE Procurement 201

LogisticsLogistics

Before we get started ...

Page 4: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

4BRITE Procurement 201

ConceptsConcepts

DemonstrationDemonstrationss

ExercisesExercisesBRITE BRITE

Classroom MaterialsClassroom Materials

(Let Me)(Let Me)

(Tell Me)(Tell Me)

(Show Me)(Show Me)

Page 5: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

5BRITE Procurement 201

At the end of this course, you should be able to:

Describe the requisition process

Create various types of requisitions

Describe the goods receipt/return process

Perform a goods receipt

Create a list of purchase requisitions based on your

own search criteria

Course ObjectivesCourse Objectives

Page 6: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

6BRITE Procurement 201

AgendaAgenda

Unit Time

Introduction 30 minutes

Unit One: Requisition Processing 3 hours

Unit Two: Goods Movement 1 hour

Unit Three: Purchasing Reporting 1 hour

Summary 30 minutes

Page 7: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

7BRITE Procurement 201

Requisition ProcessingRequisition Processing

Page 8: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

8BRITE Procurement 201

At the end of this Unit, you should be able to:

Define key terminology

Describe the various types of purchase requisitions

Display a purchase requisition

Identify the three sections of a purchase requisition

Create requisitions (standard, stock transport, and framework)

Describe the function of Catalog Content Management

Unit ObjectivesUnit Objectives

Page 9: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

9BRITE Procurement 201

At the end of this Unit, you should be able to:

Describe the process for procuring assets

Describe the process for creating requisitions against a grant

Describe the process for creating a textbook requisition

Display a purchase order for a given requisition

Unit Objectives (cont.) Unit Objectives (cont.)

Page 10: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

10BRITE Procurement 201

BRITE Key Terms BRITE Key Terms

Master Data Information that rarely changes. For example, Material Master Record or Vendor Master Record

Catalog Content Management

Online catalog of materials available for purchase both internally and externally that are on contract.

Document Type Used to identify the various types of purchasing documents (Standard Requisition, Framework Requisition, Stock Transport Requisition)

Business Area Used to identify an area of responsibility such as Food Services, Budget Office, or a specific school

Item Category A classification of the material or service being procured (standard, stock transport, service, etc.)

Page 11: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

11BRITE Procurement 201

BRITE Key Terms (cont.) BRITE Key Terms (cont.)

Account Assignment Category

Designates how the expense for a procurement will be charged (cost center, project, grant, etc.)

Material Group Category of materials; similar to a commodity code (classroom supplies, computer hardware, office supplies)

Cost Center/Fund Center

A unit of responsibility for capturing cost within a Business Area. Includes location number.

GL Account Number

Used to categorize expenses in the general ledger. For example, Consumable Materials or Computer Equipment (legacy system’s Class & Object Code)

Grant A source of funding against which materials and services may be procured

Invoicing Plan Used to schedule regular, periodic payments to a vendor

Page 12: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

12BRITE Procurement 201

Types of Purchase RequisitionsTypes of Purchase Requisitions

There are three types of Purchase Requisitions that will be discussed in this course:

Standard Requisitions Framework Requisitions

Stock Transport Requisitions

Are used for external procurements

Can be entered line-by-line or via Catalog Content Management (CCM)

Can be entered with or without reference to a Material Master Record

Are used for external procurements

Can be created using an attached list for orders of 25 or more line items

Cannot be used for assets

Invoicing Plan

Are used for internal procurements

Will always be entered via Catalog Content Management (CCM)

Page 13: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

13BRITE Procurement 201

Requisitions Requisitions

All Requisitions have three sections:

Header—Contains a Text tab where internal information can be entered

Item Overview—Shows an overview of all the line items on the Requisition

Item Details—Shows detailed procurement information about each line item on the requisition.

Page 14: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

14BRITE Procurement 201

Purchase RequisitionPurchase Requisition

Header

Item Overview

Item Details

Page 15: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

15BRITE Procurement 201

Account Assignment CategoriesAccount Assignment Categories

Each line item on a Requisition must have an Account Assignment Category. The following five account assignment categories will be covered in this course:

– <Blank> - Inventory (Warehouse)– Z – Asset (Use in Phase 1)– A – Asset (Use in Phase 2)– K - Cost Center– P - Project– Y - Grant

Page 16: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

16BRITE Procurement 201

Material GroupsMaterial Groups

The Material Group is a code used to group together materials with the same attributes (e.g., office supplies)

The Material Group will be the three-character National Institute of Governmental Purchasing (NIGP) code (e.g., 615 for “Office Supplies, General”

The Material Group will default for those items that have a Material Master Record

For those items that do not have a Material Master Record, the Material Group must be entered on the requisition

Page 17: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

17BRITE Procurement 201

Accounting DataAccounting Data

Accounting Object Number of Digits

Fund 3 or 4

Class 1

Function 4

Object 3

Phase 1

Sub-Object 2

Location 4

Type 1

Activity 5

Legacy Line of Coding

Accounting Object Composition

General Ledger (G/L) Account Number

Class + Object + Zeros

Eight Digits

Ex: 5 511 0000

Fund

Previous Fund # + 0 (if required)

Four Digits

Ex: 100 0

Functional Area

Function + Activity + Zeros

Sixteen Digits

Ex: 5101 00000 0000000

Cost Center

Business Area + Type

+ Location + 0

Ten Digits

Ex: 3307 1 1091 0

SAP Accounting String

Page 18: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

18BRITE Procurement 201

Demonstration and ExerciseDemonstration and Exercise

Scenario: Display a Purchase Requisition

Transaction Code: ME53N

Page 19: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

19BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

1

Page 20: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

20BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

3

Page 21: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

21BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

4

Page 22: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

22BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

5

6

Page 23: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

23BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

7

8

Page 24: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

24BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

9

10

Page 25: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

25BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

11

12

Page 26: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

26BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

13

Page 27: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

27BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

14

Page 28: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

28BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

15

Page 29: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

29BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

16

Page 30: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

30BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

17

Page 31: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

31BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

18

Page 32: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

32BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

19

21

20

Page 33: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

33BRITE Procurement 201

Display a Purchase RequisitionDisplay a Purchase Requisition

23

Page 34: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

34BRITE Procurement 201

Demonstration and ExerciseDemonstration and Exercise

Scenario: Create a Standard Purchase Requisition

Transaction Code: ME51N

Page 35: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

35BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

1

Page 36: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

36BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

3

Page 37: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

37BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

4

Page 38: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

38BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

5

6

Page 39: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

39BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

7

Page 40: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

40BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

9

8

Page 41: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

41BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

10

11

12

Page 42: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

42BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

15

13

14

Page 43: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

43BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

16

Page 44: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

44BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

17

18

Page 45: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

45BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

19

Page 46: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

46BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

2021

2223

24

Page 47: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

47BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

25

Page 48: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

48BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

27

28

29

30

Page 49: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

49BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

32

Page 50: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

50BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

34

35, 36

37

38

33

Page 51: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

51BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

4039

Page 52: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

52BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

41 42 44

Page 53: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

53BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

45

46

Page 54: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

54BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

47

Page 55: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

55BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

48

Page 56: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

56BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

50

Page 57: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

57BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

52

53

Page 58: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

58BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

54

Page 59: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

59BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

55

Page 60: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

60BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

56

57

Page 61: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

61BRITE Procurement 201

Create a Standard Purchase RequisitionCreate a Standard Purchase Requisition

58

Page 62: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

62BRITE Procurement 201

Demonstration and ExerciseDemonstration and Exercise

Scenario: Change a Standard Purchase Requisition

Transaction Code: ME52N

Change the requisition you created in the previous exercise.

Page 63: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

63BRITE Procurement 201

Change a Standard Purchase RequisitionChange a Standard Purchase Requisition

1

Page 64: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

64BRITE Procurement 201

Change a Standard Purchase RequisitionChange a Standard Purchase Requisition

3

Page 65: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

65BRITE Procurement 201

Change a Standard Purchase RequisitionChange a Standard Purchase Requisition

4

5

Page 66: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

66BRITE Procurement 201

Change a Standard Purchase RequisitionChange a Standard Purchase Requisition

97

Page 67: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

67BRITE Procurement 201

Change a Standard Purchase RequisitionChange a Standard Purchase Requisition

10

11

Page 68: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

68BRITE Procurement 201

Change a Standard Purchase RequisitionChange a Standard Purchase Requisition

11

Page 69: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

69BRITE Procurement 201

What is Catalog Content ManagementWhat is Catalog Content Management

Catalog Content Management (CCM):

Is a web-interface that allows end-users to search for and order standard catalog items from established suppliers with active contracts

Allows end-users to select materials by pointing and clicking on catalog items

Allows end-users to create a Requisition in SAP directly from an on-line shopping cart

Reduces data input errors and redundancy

Page 70: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

70BRITE Procurement 201

CCM RequisitionsCCM Requisitions

Click the “Catalog” icon to access the on-line catalog.

Page 71: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

71BRITE Procurement 201

Catalog Content ManagementCatalog Content Management

CCM allows “point and click” selection of materials to be purchased

Page 72: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

72BRITE Procurement 201

Demonstration and ExerciseDemonstration and Exercise

Scenario: Create a Standard Purchase Requisition Using CCM

Transaction Code: ME51N

Page 73: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

73BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

1

Page 74: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

74BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

3

4

Page 75: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

75BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

5

Page 76: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

76BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

6

Page 77: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

77BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

7

Page 78: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

78BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

8

9

10

Page 79: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

79BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

12

13

14

15

16

11

Page 80: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

80BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

18

Page 81: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

81BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

19

Page 82: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

82BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

20

21

Page 83: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

83BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

22

23

Page 84: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

84BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

24

25

Page 85: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

85BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

27

Page 86: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

86BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

28

29

Page 87: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

87BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

3031

32

Page 88: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

88BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

33

34

Page 89: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

89BRITE Procurement 201

Create a Standard Req Using CCMCreate a Standard Req Using CCM

35

Page 90: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

90BRITE Procurement 201

Assets (Interim Process – Wave 1)Assets (Interim Process – Wave 1)

A Requisition item is considered an asset if its value exceeds $1,000

The account assignment category on the requisition is coded as “Z” for asset

For assets ordered against a grant, a Work Breakdown Structure (WBS) element will also be required

- WBS contains details about who owns the grant and where the money is being spent

Asset tracking will continue to be performed in PROPS (Property & Inventory)

Page 91: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

91BRITE Procurement 201

Requisitions for GrantsRequisitions for Grants

Non-assets ordered against a grant will have an account assignment category of “Y”

Assets ordered against a grant will have an account assignment category of “Z” during Wave 1

A WBS element must be entered on the requisition

Page 92: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

92BRITE Procurement 201

Requisition Against a GrantRequisition Against a Grant

The WBS element for items ordered against a Grant appears on the “Account Assignment” tab.

Page 93: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

93BRITE Procurement 201

Stock Transport RequisitionsStock Transport Requisitions

Stock Transport Requisitions: Will have an Item Category of “U” (Stock Transfer) and an

Account Assignment Category of “K” (cost center) Will go through an approval process similar to external

requisitions Will be automatically converted to stock transport orders

after all budget checks and approvals have been accomplished

Can be used for B-stock as well as procurements from the central warehouse

Page 94: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

94BRITE Procurement 201

Stock LocationsStock Locations

Stock Transports can come from any of these locations

Page 95: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

95BRITE Procurement 201

Stock Transport Requisition Process FlowStock Transport Requisition Process Flow

Requisition entered by school or

department

Budget check performed

Requisition approved by principal or department

head

Stock transport order

created from requisition

Material delivered from

warehouse

Page 96: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

96BRITE Procurement 201

Demonstration and ExerciseDemonstration and Exercise

Scenario: Create a Stock Transport Requisition for Material from the Central Warehouse

Transaction Code: ME51N

Page 97: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

97BRITE Procurement 201

Create a Stock Transport Req Using CCMCreate a Stock Transport Req Using CCM

1

Page 98: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

98BRITE Procurement 201

Create a Stock Transport Req Using CCMCreate a Stock Transport Req Using CCM

3

4

5

Page 99: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

99BRITE Procurement 201

Create a Stock Transport Req Using CCMCreate a Stock Transport Req Using CCM

6

Page 100: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

100BRITE Procurement 201

Create a Stock Transport Req Using CCMCreate a Stock Transport Req Using CCM

7

Page 101: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

101BRITE Procurement 201

Create a Stock Transport Req Using CCMCreate a Stock Transport Req Using CCM

8

9

10

Page 102: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

102BRITE Procurement 201

Create a Stock Transport Req Using CCMCreate a Stock Transport Req Using CCM

11

Page 103: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

103BRITE Procurement 201

Create a Stock Transport Req Using CCMCreate a Stock Transport Req Using CCM

13

14

15

16

Page 104: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

104BRITE Procurement 201

Create a Stock Transport Req Using CCMCreate a Stock Transport Req Using CCM

18

20

21

Page 105: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

105BRITE Procurement 201

Create a Stock Transport Req Using CCMCreate a Stock Transport Req Using CCM

22

23

Page 106: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

106BRITE Procurement 201

Create a Stock Transport Req Using CCMCreate a Stock Transport Req Using CCM

24

Page 107: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

107BRITE Procurement 201

Framework RequisitionsFramework Requisitions

Framework Requisitions are created for: Items Ordered via Attached Lists

– Must be items that cannot be procured with a P-card– Must be 25 or more line items– Must be non-assets

Items for which pricing is unknown until invoice is received (for example, fuel, landscaping, utilities)

Items to be paid for via Automatic Payment (Invoicing Plan, ex: lease of a portable)

Page 108: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

108BRITE Procurement 201

Demonstration and ExerciseDemonstration and Exercise

Scenario: Create a Framework Requisition Using an Attached List

Transaction Code: ME51N

Page 109: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

109BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

1

Page 110: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

110BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

3

5 6

4

7, 8

9

10 11 12

13

Page 111: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

111BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

14

Page 112: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

112BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

15

16

Page 113: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

113BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

17

Page 114: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

114BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

18

Page 115: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

115BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

20

Page 116: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

116BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

22

23

2425

Page 117: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

117BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

27

28

Page 118: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

118BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

29

30

31

Page 119: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

119BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

32

33

Page 120: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

120BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

34

35

Page 121: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

121BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

36

37

Page 122: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

122BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

38

Page 123: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

123BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

39

Page 124: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

124BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

40

Page 125: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

125BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

41

42

Page 126: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

126BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

43

44

Page 127: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

127BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

4546

Page 128: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

128BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

48

47

Page 129: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

129BRITE Procurement 201

Create a Framework Req Using an AttachedCreate a Framework Req Using an AttachedListList

49

Page 130: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

130BRITE Procurement 201

Payments for Framework Purchase OrdersPayments for Framework Purchase Orders

A two-way match (purchase order to invoice) is required—no goods receipt

A copy of the invoice is routed to the receiving school or department for verification and signature

Accounts Payable pays the invoice after it is approved

Page 131: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

131BRITE Procurement 201

All Textbooks From FSBD (Core and Non-All Textbooks From FSBD (Core and Non-Core) – Elementary & Middle SchoolsCore) – Elementary & Middle Schools

Requisitions for textbooks are stock transport requisitions

Textbook Requisition Process:

Create a Stock Transport

Requisition to Textbook

Warehouse Non-Core Textbook

Warehouse bundles PR’s &

orders from FSBD

Non-Core Textbooks shipped to

warehouse or directly to school

Note: These Stock Transport requisitions are entered as text items.

Core Textbooks fulfilled from the

Warehouse

Core Textbooks shipped to

schools

Requisition Approved by Principal &

Instructional Materials Facilitator

Page 132: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

132BRITE Procurement 201

All Textbook Requisitions From FSBD – All Textbook Requisitions From FSBD – High Schools (Core and Non-Core)High Schools (Core and Non-Core)

Requisitions for textbooks are “framework requisitions”

Textbook Requisition Process:

Select books on FL School Book

Depository (FSBD) Website

Attach PDF File to Requisition

and Save

Requisition Approved by Principal &

Instructional Materials Facilitator

Purchase Order Created by

Buyer

Get Order Total from Website

Create & Hold Framework

Req w/Order Total

Enter Req # in FSBD Order on

Website and Save

PDF File is Automatically Printed From

FSBD Website

Page 133: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

133BRITE Procurement 201

You should now be able to:

Define key terminology

Describe the various types of purchase requisitions

Display a purchase requisition

Identify the three sections of a purchase requisition

Create requisitions (standard, stock transport, and framework)

Describe the function of Content Catalog Management

Unit ObjectivesUnit Objectives

Page 134: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

134BRITE Procurement 201

You should now be able to:

Describe the process for procuring assets

Describe the process for creating requisitions against a grant

Describe the process for creating a textbook requisition

Display a purchase order for a given requisition

Unit ObjectivesUnit Objectives

Page 135: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

135BRITE Procurement 201

Knowledge CheckpointKnowledge Checkpoint

Question: What three types of requisitions did you learn how to create in this unit?

Answer: Standard, Framework and Stock Transport

Page 136: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

136BRITE Procurement 201

AgendaAgenda

Unit Time

Introduction 30 minutes

Unit One: Requisition Processing 3 hours

Unit Two: Goods Movement 1 hour

Unit Three: Purchasing Reporting 1 hour

Summary 30 minutes

Page 137: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

137BRITE Procurement 201

Goods MovementGoods Movement

Page 138: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

138BRITE Procurement 201

At the end of this Unit, you should be able to: Describe the Goods Receipt and Return processes Perform a Goods Receipt Perform a Goods Return

Unit ObjectivesUnit Objectives

Page 139: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

139BRITE Procurement 201

Goods Receipts and Returns in SAPGoods Receipts and Returns in SAP

A Goods Receipt is executed in SAP any time material is received against a standard purchase order

When a Goods Receipt is executed, a material document is created in SAP that includes details of the transaction (date, quantity, storage location, etc.)

A Goods Return is executed to return material to a vendor

Goods Returns must be coordinated with Purchasing and Accounts Payable

Goods Receipt and Returns have different movement types in SAP, such as:

– 101: Goods Receipt for Purchase Order into Warehouse

– 122: Return Delivery to Vendor

Page 140: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

140BRITE Procurement 201

Demonstration and ExerciseDemonstration and Exercise

Scenario: Perform a Goods Receipt

Transaction Code: MIGO_GR

Page 141: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

141BRITE Procurement 201

Perform a Goods ReceiptPerform a Goods Receipt

1

Page 142: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

142BRITE Procurement 201

Perform a Goods ReceiptPerform a Goods Receipt

3

Page 143: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

143BRITE Procurement 201

Perform a Goods ReceiptPerform a Goods Receipt

4 5

Page 144: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

144BRITE Procurement 201

Perform a Goods ReceiptPerform a Goods Receipt

6

Page 145: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

145BRITE Procurement 201

Perform a Goods ReceiptPerform a Goods Receipt

7

9 8

10

Page 146: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

146BRITE Procurement 201

Perform a Goods ReceiptPerform a Goods Receipt

11

12

Page 147: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

147BRITE Procurement 201

Perform a Goods ReceiptPerform a Goods Receipt

13

Page 148: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

148BRITE Procurement 201

Perform a Goods ReceiptPerform a Goods Receipt

14

Page 149: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

149BRITE Procurement 201

Demonstration and ExerciseDemonstration and Exercise

Scenario: Perform a Goods Return

Transaction Code: MIGO

Page 150: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

150BRITE Procurement 201

Perform a Goods ReturnPerform a Goods Return

1

Page 151: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

151BRITE Procurement 201

Perform a Goods ReturnPerform a Goods Return

3

Page 152: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

152BRITE Procurement 201

Perform a Goods ReturnPerform a Goods Return

4

Page 153: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

153BRITE Procurement 201

Perform a Goods ReturnPerform a Goods Return

5

6

Page 154: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

154BRITE Procurement 201

Perform a Goods ReturnPerform a Goods Return

7

8

9

10

Page 155: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

155BRITE Procurement 201

Perform a Goods ReturnPerform a Goods Return

11

12

Page 156: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

156BRITE Procurement 201

Perform a Goods ReturnPerform a Goods Return

13

Page 157: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

157BRITE Procurement 201

Perform a Goods ReturnPerform a Goods Return

1415

16

Page 158: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

158BRITE Procurement 201

Perform a Goods ReturnPerform a Goods Return

17

18

Page 159: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

159BRITE Procurement 201

You should now be able to: Describe the Goods Receipt and Return

processes Perform a Goods Receipt Perform a Goods Return

Unit ObjectivesUnit Objectives

Page 160: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

160BRITE Procurement 201

Knowledge CheckpointKnowledge Checkpoint

Question: What type of Purchase Order requires a Goods Receipt?

Answer: Standard

Page 161: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

161BRITE Procurement 201

AgendaAgenda

Unit Time

Introduction 30 minutes

Unit One: Requisition Processing 3 hours

Unit Two: Goods Movement 1 hour

Unit Three: Purchasing Reporting 1 hour

Summary 30 minutes

Page 162: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

162BRITE Procurement 201

Purchasing ReportingPurchasing Reporting

Page 163: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

163BRITE Procurement 201

At the end of this Unit, you should be able to: Describe the use of List Displays in SAP Display a list of Purchase Requisitions

Unit ObjectivesUnit Objectives

Page 164: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

164BRITE Procurement 201

List Displays in SAPList Displays in SAP

A List Display in SAP is a powerful and flexible tool that allows End-Users to:

Generate a list of purchasing documents, materials, vendors, etc. that match a set of search criteria

Perform real-time, ad-hoc reporting

Change the content and layout of reports

Print hard copy reports or export them to other applications such as Excel

Page 165: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

165BRITE Procurement 201

Demonstration and ExerciseDemonstration and Exercise

Scenario: Display a List of Purchase Requisitions

Transaction Code: ME5A

Page 166: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

166BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

1

Page 167: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

167BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

3

4

5

Page 168: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

168BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

6

Page 169: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

169BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

7

8

Page 170: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

170BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

9

10

Page 171: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

171BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

1112

14

13

Page 172: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

172BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

15

Page 173: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

173BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

16

Page 174: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

174BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

18

Page 175: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

175BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

Page 176: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

176BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

19

Page 177: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

177BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

20

21

Page 178: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

178BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

22

23

Page 179: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

179BRITE Procurement 201

Display a List of Purchase RequisitionsDisplay a List of Purchase Requisitions

24

25

Page 180: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

180BRITE Procurement 201

You should now be able to: Describe the use of List Displays in SAP Display a list of Purchase Requisitions

Unit ObjectivesUnit Objectives

Page 181: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

181BRITE Procurement 201

Knowledge CheckpointKnowledge Checkpoint

Question: What are some advantages of using list displays in SAP?

Answer: Real-time information, ad-hoc reporting, ability to change content and layout, export to Excel.

Page 182: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

Follow-Up & Support OptionsFollow-Up & Support Options

Page 183: Procurement 201. 2 BRITE Procurement 201  Have fun and enjoy the opportunities we have to contribute to SBBC’s future success!  Please turn off or silence.

183BRITE Procurement 201

HELP DESK 754-321-8120 BRITE Website:

web/erp -or-

http://www.broward.k12.fl.us/erp/

e-Learning

Context Sensitive Help

CAB Conference

BRITE LITES (By Role)

User Support OptionsUser Support Options

ESS Appraisal

BlackboardFollow-UpFollow-Up