Process Based Restoration Approaches and Engineering Design Criteria · 2018. 10. 22. · Process...

46
Process Based Restoration Approaches and Engineering Design Criteria Tuesday October 23 rd 2018 Jared McKee Partners for Fish and Wildlife Program Hydrologist

Transcript of Process Based Restoration Approaches and Engineering Design Criteria · 2018. 10. 22. · Process...

  • Process Based Restoration Approaches and Engineering Design Criteria

    Tuesday October 23rd 2018

    Jared McKee Partners for Fish and Wildlife Program Hydrologist

  • Objectives

    • Learn Ecological Standards for restoration projects

    • Learn why it matters • Learn quantitative design criteria to ensure

    ecological standards are met

  • Outline

    • Background – Odum – Ecological Engineering and Self Design – Palmer and Beechie – Ecological Standards and

    Process Based Principles

    • Simplified Design Criteria for Ecological Process Based Engineering

    • Comparison to other approaches

  • Howard T. Odum As sometimes attributed to past cultures, people may again find glory in

    being an agent of the earth

    • American Ecologist (b. 1924, d. 2002) • Developed concept of “self design” • Defined Ecological Engineering

    – those cases where the energy supplied by man is small relative to the natural sources but sufficient to produce large effects in the resulting patterns and processes (Odum 1962)

  • Self Design

    • Integral to ecological engineering theory • Using Ecological Self Design is

    – Low energy – Sustainable – Composed of self regulating processes – Inexpensive – Different

  • Example – Port Aransas, Texas Wastewater Treatment

    • 1954 – 500 residents – Sewage plant with primary and secondary treatment released its

    nutritive waste waters on flat bare sands – Pond and freshwater marsh developed with salt adapted vegetation

    around outfall • 2000

    – 5000 residents – Outfall marsh spread and attracted wildlife including alligators,

    turtles, and waterfowl – Area adopted as an Audubon Wildlife sanctuary with boardwalk

    and observation tower

    Ecological engineering meant letting nature self organize a suitable tertiary treatment ecosystem and fitting human

    society to nature in a way that both prospered

  • Port Aransas Texas 1956

  • Time Lapse

    1956

  • 1979

  • 1990

  • 2003

  • 2017

  • 1956

    2017

  • Ecological Standards – Palmer et al. 2005

    Five Standards for Ecologically Success River Restoration 1. Guiding image of a dynamic state 2. Ecosystems are improved 3. Resilience is increased 4. No lasting harm 5. Ecological assessment is completed

  • Process Based Principles – Beechie et al. 2010

    Four Process-based Principles for Restoring River Ecosystems 1. Target root causes of habitat and ecosystem

    change 2. Tailor restoration actions to local potential 3. Match the scale of restoration to the scale of the

    problem 4. Be explicit about expected outcomes

  • Simplified Design Criteria

    • Space • Energy • Time

    • Matter

  • Space

    Fluvial process space is a widespread concept also known as: • Process Domain • Functional Process Zone • Freedom Space (Espace d’ Liberte) • Room for the River (Ruimte voor de Rivier) • Erodible Corridor

    We call it the Steam Evolution Corridor (SEC)

  • Space • Providing greater space for fluvial dynamics

    capitalizes on the ecosystem service of self system recovery (Bergen 2001)

    • Practitioners indirectly restore habitat by removing anthropogenic system disconnectivity, allowing for natural food disturbance and greater biodiversity (Junk 1989)

    • Criterion requires a project result in a net gain of dynamic fluvial process space where flooding, channel mobility, sediment conveyance

  • Space Process Space (𝑃𝑃𝑃𝑃) Stream Evolution Corridor (𝑃𝑃𝑆𝑆𝑆𝑆) Initial Process Space (𝑃𝑃𝑃𝑃𝑖𝑖) Final Process Space (𝑃𝑃𝑃𝑃𝑓𝑓)

    Pre Anthropogenic Influence 𝑃𝑃𝑃𝑃 ≤ 𝑃𝑃𝑆𝑆𝑆𝑆 Post Anthropogenic Influence 𝑃𝑃𝑃𝑃𝑖𝑖 ≪ 𝑃𝑃𝑆𝑆𝑆𝑆 Process Based Restoration Criteria 𝑃𝑃𝑃𝑃𝑓𝑓 > 𝑃𝑃𝑃𝑃𝑖𝑖

  • Space

    1. Map pre-disturbance extent of fluvial process space or SEC

    2. Map anthropogenic disconnections within the fluvial process space

    3. Map post-restoration extent of fluvial process space

    Restoration project meets the Space Criterion when the Final Process Space is greater than Initial Process Space

  • Space Process Space (𝑃𝑃𝑃𝑃) Stream Evolution Corridor (𝑃𝑃𝑆𝑆𝑆𝑆) Initial Process Space (𝑃𝑃𝑃𝑃𝑖𝑖) Final Process Space (𝑃𝑃𝑃𝑃𝑓𝑓)

    Pre Anthropogenic Influence 𝑃𝑃𝑃𝑃 ≤ 𝑃𝑃𝑆𝑆𝑆𝑆 Post Anthropogenic Influence 𝑃𝑃𝑃𝑃𝑖𝑖 ≪ 𝑃𝑃𝑆𝑆𝑆𝑆 Process Based Restoration Criteria 𝑃𝑃𝑃𝑃𝑓𝑓 > 𝑃𝑃𝑃𝑃𝑖𝑖

  • Space

    • Think about how this ties in with Stage 0, Stream Evolution Model, and beaver assisted restoration

    • Can Stage 0 conditions be met with a limited space (𝑃𝑃𝑃𝑃𝑖𝑖)?

    • Can beaver persist in a limited space (𝑃𝑃𝑃𝑃𝑖𝑖)?

  • • Process based approach takes time and flows • Restoration doesn’t occur during

    implementation • Restoration occurs through self design with

    inherent stream energy and biologic inputs • Requires patience • Guarantees long term success

    Time

    data

    StreamStats Output Report

    State/Region IDCA

    Workspace IDCA20180323205919842000

    Latitude38.93808

    Longitude-121.29271

    Time3/23/18 1:59:35 PM

    Basin Characteristics

    Parameter CodeParameter DescriptionValueUnit

    DRNAREAArea that drains to a point on a stream22.9square miles

    ELEVMean Basin Elevation596feet

    PRECIPMean Annual Precipitation28.4inches

    Peak-Flow Statistics Parameters100 Percent 2012 5113 Region 3 Sierra Nevada

    Parameter CodeParameter NameValueUnitsMin LimitMax Limit

    DRNAREADrainage Area22.9square miles0.072000

    ELEVMean Basin Elevation596feet9011000

    PRECIPMean Annual Precipitation28.4inches15100

    Peak-Flow Statistics Flow Report100 Percent 2012 5113 Region 3 Sierra Nevada

    PIl: Prediction Interval- Lower, PIu: Prediction Interval- Upper, SEp: Standard Error of Prediction, SE: Standard Error (other-- see report)

    StatisticValueUnitPIlPIuSEp

    2 Year Peak Flood697ft^3/s232210074.4

    5 Year Peak Flood1580ft^3/s674369054.4

    10 Year Peak Flood2200ft^3/s983494051.5

    25 Year Peak Flood2940ft^3/s1310662052.3

    50 Year Peak Flood3520ft^3/s1510820054.6

    100 Year Peak Flood4080ft^3/s1670994058

    200 Year Peak Flood4610ft^3/s18101180061.5

    500 Year Peak Flood5310ft^3/s19301460067.3

  • Time

    0200400600800

    1,0001,2001,4001,6001,8002,000

    Aug-10 Feb-11 Sep-11 Apr-12 Oct-12 May-13 Nov-13 Jun-14 Dec-14 Jul-15 Jan-16 Aug-16 Mar-17 Sep-17 Apr-18

    Levee Breach at beaver dam

    Beaver depredation ceased

    25 acre floodplain tree planting

    Beaver dam failure

    Levee removal and BDAs

    Beaver reactivate 25 acre floodplain Channel avulsion and formation

    3,200 cy sediment deposition on floodplain

    Lateral channel migration

    Levee removal and BDA

    0.2 acre mitigation pond constructed

    Habitat Creation Habitat Restoration

    2008 2018

  • Matter • Use geomorphically appropriate material for

    instream actions • Practitioners ask what would naturally occur,

    form habitat, or create base level control for the project reach

    • Boulder riffles rarely end up in low gradient reaches

    If projects are using material to form habitat that is not

    geomorphically appropriate then they are asking for trouble

  • Do we want anthropogenic habitat or naturally formed habitat?

    If we construct in this space we take away space for natural process formation (self design) and again we lower the return on our investment and risk further degrading to natural processes.

    “Rosgen” channel vs Stage Zero channel

    Matter

  • Examples and Economics

    • Log Jams and Woody Debris • Rock where appropriate

    • Sediment • Water

    • Common highest cost for implementation?

    Moving material (sediment) or importing rock

  • Energy

    Instream and floodplain restoration actions continue to use heavy machinery to achieve form-based goals in fluvial waterways, even the smallest streams and

    sensitive wet meadow habitats (Bernhardt 2005)

    Uvas Creek, California

  • Energy In A View of the River, Luna Leopold describes the

    river as a machine because like any machine it involves “the transformation of potential energy into kinetic form that accomplishes work in the

    process” (Leopold, 1994)

    Remember H.T. Odum and Ecological Engineering those cases where the energy supplied by man is small relative to the natural sources but sufficient to produce large effects in the resulting patterns and processes (Odum 1962)

  • Energy Prescriptive Based Tells practitioner HOW they have to implement project and ensures ecological approach

    1. “Net Zero Energy” Maximize use of stream energy for meeting form objective (aim for C neutral) unless you are modifying infrastructure

    2. Use geomorphically appropriate material (Pollock et al 2003, 2007, 2012; Manga and Kirchner 2000)

    This criteria is well established in Green Architecture

    Ecological Design is strongly rooted in Architecture

    Ecological design – “any form of design that minimizes environmentally destructive impacts by integrating itself with living processes”

    Sim Van der Ryn Architect/Ecologist

  • Energy Borrowing from Eco Architectural Design Eco Architecture Eco stream design

    1. Focus on energy available (solar and wind) to meet heating, cooling and space objectives over time

    2. Design optimizes passive strategies 3. Situate house to maximize energy need

    1. Focus on Stream energy hillslope/channel gradients, discharge and sediment supply to meet form and habitat objectives over time

    2. Design should optimize passive strategies 3. Modify infrastructure to maximize stream

    energy need

    Concept models on Energy Flow Home vs SEC

  • Do we want anthropogenic habitat or naturally formed habitat?

    If we construct in this space we take away space for natural process formation (self design) and again we lower the return on our investment and risk further degrading to natural processes.

    “Rosgen” channel vs Stage Zero channel

    Energy

  • This criteria is right out of Green Architecture Design

    Successional stages

    Maximize Stream Energy Minimize Fossil Fuel Input When working in the stream channel this prescriptive criteria places bounds on how the

    practitioner can work and requires them to:

    Exhaust all stream energy before using diesel energy • Doesn’t apply to infrastructure modification • Reduces habitat disturbance • Requires practitioner to build habitat using prevailing sediment and energy • Retain and encourage a shifting habitat mosiac • Very low risk of constructing forms that are overwhelmed or non compatible with

    system dynamic or scale

    Energy

  • Reduce Risk using Space and Energy Design Criteria

    1. Opening dynamic fluvial space is low risk

    2. Using stream energy to meet form objective is low risk

    Energy

  • Energy We will relate inherent stream energy through comparing energy in a flood event to energy in

    diesel fuel or,

    Inherent stream energy vs. fossil fuel energy

  • • The common unit of energy is the joule, so we will compare joules in diesel fuel and days of heavy equipment usage to joules in a flood event of a specific flow and duration.

    • Joule in SI base units 𝑘𝑘𝑘𝑘⋅𝑚𝑚2

    𝑠𝑠2

    Energy

  • Energy

    Bagnold (1966) defines stream power as “the available power supply, or time rate of energy supply, to unit length of a stream is clearly the time rate liberation in kinetic form of the liquid’s potential energy as it descends the gravity slope 𝑃𝑃. Denoting this power by 𝛺𝛺,

    𝛺𝛺 = 𝜌𝜌𝜌𝜌𝜌𝜌𝑃𝑃 Where 𝜌𝜌 is the whole discharge of the stream”, 𝜌𝜌 is density of water, and 𝜌𝜌 is gravity.

  • Energy By taking this available stream power and integrating over the length of the project (m) and the duration of a flow event (s), a total flow event energy can be estimated.

    Total flow event energy = available stream power * reach length * flow

    duration

    Units analysis of the available stream power equation multiplied by project length and flow duration is as follows

    ((𝑘𝑘𝑘𝑘𝑚𝑚3

    ) ∗ (𝑚𝑚𝑠𝑠2

    ) ∗ (𝑚𝑚3

    𝑠𝑠) ∗ (𝑚𝑚

    𝑚𝑚)) * (𝑚𝑚) * (𝑠𝑠) =𝑘𝑘𝑘𝑘⋅𝑚𝑚

    2

    𝑠𝑠2

  • Thus,

    Total flow event energy =𝑘𝑘𝑘𝑘⋅𝑚𝑚2

    𝑠𝑠2 and

    Joule =𝑘𝑘𝑘𝑘⋅𝑚𝑚2

    𝑠𝑠2

    Which leads to

    𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝑠𝑠 𝐺𝐺𝑜𝑜 𝑑𝑑𝑑𝑑𝑑𝑑𝑠𝑠𝑑𝑑𝐺𝐺 𝑜𝑜𝑓𝑓𝑑𝑑𝐺𝐺 𝑑𝑑𝐺𝐺 𝐺𝐺 𝑜𝑜𝐺𝐺𝐺𝐺𝑓𝑓 𝑑𝑑𝑒𝑒𝑑𝑑𝐺𝐺𝑒𝑒 =

    (𝐺𝐺𝑒𝑒𝐺𝐺𝑑𝑑𝐺𝐺𝐺𝐺𝑎𝑎𝐺𝐺𝑑𝑑 𝑠𝑠𝑒𝑒𝑠𝑠𝑑𝑑𝐺𝐺𝑚𝑚 𝑝𝑝𝐺𝐺𝑓𝑓𝑑𝑑𝑠𝑠 ∗ 𝑠𝑠𝑑𝑑𝐺𝐺𝑟𝑟𝑟 𝐺𝐺𝑑𝑑𝐺𝐺𝜌𝜌𝑒𝑒𝑟 ∗ 𝑜𝑜𝐺𝐺𝐺𝐺𝑓𝑓 𝑑𝑑𝑓𝑓𝑠𝑠𝐺𝐺𝑒𝑒𝑑𝑑𝐺𝐺𝐺𝐺)

    𝑗𝑗𝐺𝐺𝑓𝑓𝐺𝐺𝑑𝑑𝑠𝑠 𝑝𝑝𝑑𝑑𝑠𝑠 𝜌𝜌𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺 𝐺𝐺𝑜𝑜 𝑑𝑑𝑑𝑑𝑑𝑑𝑠𝑠𝑑𝑑𝐺𝐺 𝑜𝑜𝑓𝑓𝑑𝑑𝐺𝐺

    𝐻𝐻𝑑𝑑𝐺𝐺𝑒𝑒𝐻𝐻 𝑑𝑑𝑒𝑒𝑓𝑓𝑑𝑑𝑝𝑝𝑚𝑚𝑑𝑑𝐺𝐺𝑒𝑒 𝑑𝑑𝐺𝐺𝐻𝐻𝑠𝑠 = 𝜌𝜌𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝑠𝑠 𝐺𝐺𝑜𝑜 𝑑𝑑𝑑𝑑𝑑𝑑𝑠𝑠𝑑𝑑𝐺𝐺 𝑑𝑑𝐺𝐺 𝐺𝐺 𝑜𝑜𝐺𝐺𝐺𝐺𝑓𝑓 𝑑𝑑𝑒𝑒𝑑𝑑𝐺𝐺𝑒𝑒

    𝑜𝑜𝑓𝑓𝑑𝑑𝐺𝐺 𝑟𝑟𝐺𝐺𝐺𝐺𝑠𝑠𝑓𝑓𝑚𝑚𝑝𝑝𝑒𝑒𝑑𝑑𝐺𝐺𝐺𝐺 𝑝𝑝𝑑𝑑𝑠𝑠 𝑑𝑑𝐺𝐺𝐻𝐻

    Energy

  • • Doty Ravine Project Reach Length – 2333m Slope – 0.0024 Flows from USGS Streamstats

    Estimates of fuel consumption (3 𝑘𝑘𝑔𝑔𝑔𝑔ℎ𝑟𝑟

    ) and length of work days (10 ℎ𝑟𝑟𝑑𝑑𝑔𝑔𝑑𝑑

    )

    Energy

    Statistic Flow Rate (m3/s) Liters of Diesel Heavy Equipment Days

    2 Year Peak Flood 21 2604 22

    5 Year Peak Flood 48 5887 49

    10 Year Peak Flood 67 8235 69

    25 Year Peak Flood 88 10933 91

    50 Year Peak Flood 106 13071 109

    100 Year Peak Flood 122 15103 126

    200 Year Peak Flood 138 17066 142

    500 Year Peak Flood 158 19554 163

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    0

    5000

    10000

    15000

    20000

    25000

    0 50 100 150 200 250 300 350 400 450 500

    Heav

    y Eq

    upm

    ent D

    ays

    Lite

    rs o

    f Die

    sel

    x Year Peak Flood Statistic

    Intrinsic Stream Energy

    Equivalent Liters of Diesel Equivalent Heavy Equipment Days

    Statistic

    Flow Rate (m3/s)

    Liters of Diesel

    Heavy Equipment Days

    2 Year Peak Flood

    21

    2604

    22

    5 Year Peak Flood

    48

    5887

    49

    10 Year Peak Flood

    67

    8235

    69

    25 Year Peak Flood

    88

    10933

    91

    50 Year Peak Flood

    106

    13071

    109

    100 Year Peak Flood

    122

    15103

    126

    200 Year Peak Flood

    138

    17066

    142

    500 Year Peak Flood

    158

    19554

    163

  • Energy

  • Energy

  • Summary of Approaches Process Based Riverine Restoration

    Beechie et al., 2010; Palmer et al., 2005; Cluer and Thorne (2014); Pollock et al., 2014; Kondolf (2011)

    Design Standards Basis for Design

    Criteria Design Considerations Practices ● Address source ecological

    problems at appropriate spacio-temporal scale

    ● Articulated and measurable outcomes for restoring ecosystem dynamics

    ● Results in no lasting harm inflicted on ecosystem

    ● Increase space and connectivity for fluvial process

    ● Maximize site inherent energy to meet objectives

    ● Utilize ecologically appropriate material and structure to meet objectives

    Stability tolerance (High) Self-system design and organization (High) Data and analysis need (Low) Construction disturbance (Low) Energy efficiency (High) Public cost (Low) Adaptability (High) Dynamic outcome

    Wood placement, Beaver dam analogues Modifying land management practices e.g. adapt agriculture, urban parks or infrastructure to accommodate fluvial dynamics *Infrastructure criteria qualifies if net gain in dynamic space attained

    Infrastructure and Property Protection Seiweke (2013); DWR (2013); Sholtes et al., 2017; Copeland et al., 2001; Shields et. al., 2003

    Design Standards Basis for Design

    Criteria Design Considerations Practices ● Protect life, infrastructure, and

    property ● Consider impacts to amenities,

    economics, and ecosystem

    ● Space limit allowable for lateral spread and vertical fluctuation of flooding

    ● Space limit allowable for erosion and sedimentation process

    Stability tolerance (Low) Self-system design and organization (Low) Data and analysis need (High) Construction disturbance (High) Energy efficiency (Low) Public cost (High) Adaptability (Low) Static outcome

    Install, modify, or remove, culverts, bridges, levees, walls, channel bank or bed hardening, increasing channel capacity.

    Habitat Construction and Channel Design Copeland et al., 2001; Rosgen D.L. (2001); Shields et al., 2003

    Design Standards Basis for Design

    Criteria Design Considerations Example Practice ● Satisfy compensatory mitigation

    requirements ● Satisfy habitat structural

    components for focal species ● Applied when source problems

    cannot be addressed

    ● Channel geometry ● Vertical and lateral channel

    stability ● Floodplain geometry,

    elevation and form ● Stability of habitat

    structures

    Stability tolerance (Low) Self-system design and organization (Low) Data and analysis need (High) Construction disturbance (High) Energy efficiency (Low) Public cost (High) Adaptability (Low) Static outcome

    Filling of natural channels, channel reconstruction, riffle augmentation, grade controls and bank hardening (e.g. cross vanes, j-hooks, and toe wood)

    Process Based Riverine Restoration

    Beechie et al., 2010; Palmer et al., 2005; Cluer and Thorne (2014); Pollock et al., 2014; Kondolf (2011)

    Design Standards

    Basis for Design Criteria

    Design Considerations

    Practices

    · Address source ecological problems at appropriate spacio-temporal scale

    · Articulated and measurable outcomes for restoring ecosystem dynamics

    · Results in no lasting harm inflicted on ecosystem

    · Increase space and connectivity for fluvial process

    · Maximize site inherent energy to meet objectives

    · Utilize ecologically appropriate material and structure to meet objectives

    Stability tolerance (High)

    Self-system design and organization (High)

    Data and analysis need (Low)

    Construction disturbance (Low)

    Energy efficiency (High)

    Public cost (Low)

    Adaptability (High)

    Dynamic outcome

    Wood placement,

    Beaver dam analogues

    Modifying land management practices e.g. adapt agriculture, urban parks or infrastructure to accommodate fluvial dynamics *Infrastructure criteria qualifies if net gain in dynamic space attained

    Infrastructure and Property Protection

    Seiweke (2013); DWR (2013); Sholtes et al., 2017; Copeland et al., 2001; Shields et. al., 2003

    Design Standards

    Basis for Design Criteria

    Design Considerations

    Practices

    · Protect life, infrastructure, and property

    · Consider impacts to  amenities, economics, and ecosystem

    · Space limit allowable for lateral spread and vertical fluctuation of flooding

    · Space limit allowable for erosion and sedimentation process

    Stability tolerance (Low)

    Self-system design and organization (Low)

    Data and analysis need (High)

    Construction disturbance (High)

    Energy efficiency (Low)

    Public cost (High)

    Adaptability (Low)

    Static outcome

    Install, modify, or remove, culverts, bridges, levees, walls, channel bank or bed hardening, increasing channel capacity.

    Habitat Construction and Channel Design

    Copeland et al., 2001; Rosgen D.L. (2001); Shields et al., 2003

    Design Standards

    Basis for Design Criteria

    Design Considerations

    Example Practice

    · Satisfy compensatory mitigation requirements

    · Satisfy habitat structural components for focal species

    · Applied when source problems cannot be addressed

    · Channel geometry

    · Vertical and lateral channel stability

    · Floodplain geometry, elevation and form

    · Stability of habitat structures

    Stability tolerance (Low)

    Self-system design and organization (Low)

    Data and analysis need (High)

    Construction disturbance (High)

    Energy efficiency (Low)

    Public cost (High)

    Adaptability (Low)

    Static outcome

    Filling of natural channels, channel reconstruction, riffle augmentation, grade controls and bank hardening (e.g. cross vanes, j-hooks, and toe wood)

  • Design Pathways

    adapted from Fryirs et al., 2016 Assessing the Geomorphic Recovery Potential Rivers

  • Ecological Design Criteria

    • Matter • Energy • Time • Space

    Slide Number 1ObjectivesOutlineHoward T. Odum�As sometimes attributed to past cultures, people may again find glory in being an agent of the earthSelf DesignExample – Port Aransas, Texas Wastewater TreatmentSlide Number 7Time LapseSlide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Ecological Standards – Palmer et al. 2005Process Based Principles – Beechie et al. 2010Simplified Design CriteriaSpaceSpaceSpaceSpaceSlide Number 21SpaceSpaceTimeTimeMatterMatterExamples and EconomicsEnergyEnergyEnergyEnergyEnergyEnergyEnergyEnergySlide Number 37EnergyEnergySlide Number 40Slide Number 41Slide Number 42Slide Number 43Summary of ApproachesDesign PathwaysEcological Design Criteria