Probabilistic Risk Analysis
-
Upload
jordan-kirby -
Category
Documents
-
view
85 -
download
3
description
Transcript of Probabilistic Risk Analysis
Probabilistic Risk Analysis
Part 1Part 1
Topics to be discussed
The definition of a random variable The basic characteristics of
probability distributions Evaluation of projects with discrete
random variables Evaluation of projects with
continuous random variables
Risk The chance that the cash flow will fall short
or exceed the estimate – chance of loss. Sensitivity analysis questions the effect of
cash flow deviations and the cost of capital when risk is considered.
Risk analysis is appropriate when significant outcome variations are likely for different future states and meaningful probabilities can be assigned to those states.
Decision Making under Uncertainty vs. Risk
Under uncertainty There are only two or more
observable values; However, it is most difficult to assign
the probability of occurrence of the possible outcomes;
At times, no one is even willing to try to assign probabilities to the possible outcomes.
Decision Making under Uncertainty vs. Risk
Risk The process of incorporating explicitly
random variation in the estimates of measure of merit for an investment proposal
Initial investments, Operating expenses, Revenues, Useful life, and other economic factors are seen as random variables
Risk Analysis Risk is associated with knowing the
following about a parameter: The number of observable values and, The probability of each value occurring. The “state of nature” of the process is
known at hand.
Risk Analysis Approaches:
Expected value analysis Discrete or continuous? Must assign or assume
probabilities/probability distributions. Simulation Analysis
Assign relevant probability distributions: Generate simulated data by applying
sampling techniques from the assumed distributions
Before a Study Is Started
Must decide the following: Analysis under certainty (point
estimates); Analysis under risk:
Assign probability values or distributions to the specified parameters;
Account for variances; Which of the parameters are to be
probabilistic and which are to be treated as “certain” to occur?
Basic Probability and Statistics RANDOM VARIABLE
A rule that assigns a numerical outcome to a sample space.
Describes a parameter that can assume any one of several values over some range.
Random Variables (RV’s) can be: Discrete or, Continuous.
Discrete Probability Distributions
Continuous Distribution
Probability Distributions Individual probability values are stated
as:P(Xi) = probability that X = Xi “X” represents the random variable or rule
(math function, for example) Xi represents a specific value generated from
the random variable, X. Remember, the random variable, X, is most
likely a rule or function that assigns probabilities.
Probability Distributions
Probabilities are developed two ways:1. Listing the outcome and the
associated probability:2. From a mathematical function
that is a proper probability function.
Probability Concepts
Expected value or mean Discrete:
Continuous:
X
N
iii xpxXE
1
)()(
XdxxxfXE
)()(
Probability Concepts
Variance: the sum of squared deviations about the population mean. Var(X)= E{[X-E(X)]2}= E(X2)-[E(X)]2 Discrete:
Continuous:
N
iXii
N
iii xpxxpXExXVar
1
22
1
2 )()()]([)(
222 )()()]([)( XdxxfxdxxfXExXVar
Probability Concepts Standard deviation:
Multiplication of a random variable by a constant Expected value
Variance
)()( XVarXSD
)()( XcEcXE
)()( 2 XVarccXVar
Probability Concepts
Addition of two independent random variables Expected value
Variance
)()()( YEXEYXE
)()()( YVarXVarYXVar
Probability Concepts
Linear combination of two or more independent variables. Expected value
Variance
)()()( 2121 YEcXEcYcXcE
)()()( 22
211 2
YVarcXVarcYcXcVar
Probability Concepts
Multiplication of two independent random variables Expected value
Variance
)()()( YEXEXYE
)()()]()[()]()[(
)(22 YVarXVarXEYVarYEXVar
XYVar
Evaluation of Projects with Discrete Random Variables
Factors are modeled as discrete random variables.
Expected value and variance of equivalent measure of merit are investigated and used in the evaluation.
Example 1 A drainage channel in a community where flash
floods are experienced has a capacity sufficient to carry 700 cubic feet per second. Engineering studies produce the following data regarding the probability that a given water flow in any one year will be exceeded and the cost of enlarging the channel
Water FlowFt3/sec
Probability of a greater flow occurring in any one year
Capital investment to enlarge channel to carry
this flow
700 0.20 -
1,000 0.10 -$20,000
1,300 0.05 -$30,000
1,600 0.02 -$44,000
1,900 0.01 -$60,000
Example 1 (cont.)
The average property damage amounts to $20,000 when serious overflow occurs. Reconstruction of the channel would be financed by 40-year bonds bearing 8% interest per year.Solution:If nothing is done and the drainage’s maximum capacity stays at 700 ft3/sec,
Capital Recovery Amount = 0Expected AW(Property damage cost) = $20,000(0.2)+0(0.8)
= $4,000Total expected AW of this “do nothing” choice would be
$4,000
Example 1 (cont.)If decide to enlarge the drainage’s maximum capacity to 1,000 ft3/sec,
Capital Recovery Amount = $20,000(A/P,8%,40) = $20,000(0.0839) = $1,678
Expected AW(Property damage cost) = $20,000(0.10)+0(0.9)
= $2,000Total expected AW of this “do nothing” choice would be
$3,678
Example 1 (cont.)
Enlarge the
channel to
(ft3/sec)
Capital Recovery Amount
Expected Annual Property
Damage
Total Expected Equivalent Annual
Cost
700 0 -$4,000 -$4,000
1,000 -$1,678 -2,000 -3,678
1,300 -2,517 -1,000 -3,517
1,600 -3,692 -400 -4,092
1,900 -5,034 -200 -5,234
Example 1 (cont.)Enlarge the channel to(ft3/sec)
x P(x) Total Annual Cost(x)
Expected Total Annual
Cost
700 Flood 0.20 -20,000 -4,000
No flood 0.80 0
1000 Flood 0.10 -21,678 -3,678
No flood 0.90 -1,678
1300 Flood 0.05 -22,517 -3,517
No flood 0.95 -2,517
1600 Flood 0.02 -23,692 -4,092
No flood 0.98 -3,692
1900 Flood 0.01 -25,034 -5,234
No flood 0.99 -5,034
Example 2 The Heating, Ventilating, and Air-Conditioning (HVAC)
system in a commercial building has become unreliable and inefficient. Rental income is being hurt, and the annual expenses of the system continue to increase. Your engineering firm has been hired by the owners to
Perform a technical analysis of the system, Develop a preliminary design for rebuilding the
system, and Accomplish an engineering economic analysis to
assist the owners in making decision. The estimated capital investment cost and annual savings in O&M expenses, based on the preliminary design, are shown in the following table.
Example 2 (cont.)The estimated annual increase in rental income with a modern HVAC system has been developed by the owner’s marketing staff and is also provided in the following table. These estimates are considered reliable because of the extensive information available. The useful life of the rebuilt system, however, is quite uncertain. The estimated probabilities of various useful lives are provided. Assume that the MARR = 12% per year and the estimated market value of the rebuilt system at the end of its useful life is zero. Based on this information, what is the E(PW), V(PW), and SD(PW) of the project’s cash flows? Also, what is the probability of the PW >= 0? What decision would you make regarding the project, and how would you justify your decision using the available information?
Example 2 (cont.)
Economic Factor Estimate
Capital investment
-$521,000
Annual savings
48,600
Increases annual
revenue
31,000
Useful LifeYear (N)
p(N)
12 0.1
13 0.2
14 0.3
15 0.2
16 0.1
17 0.05
18 0.05
Example 2 (cont.)
Solution:The PW of the project’s cash flows, as a function of project life (N), is
PW(N) = - $521,000 + $79,600(P/A,12%,N)
Example 2 (cont.)Useful LifeYear (N)
(1)p(N)
(2)PW(N)
(3)(1) X (2)
12 0.1 -27,926 -2,793
13 0.2 -9,689 -1,938
14 0.3 6,605 1,982
15 0.2 21,148 4,230
16 0.1 34,130 3,413
17 0.05 45,720 2,286
18 0.05 56,076 2,804
E(PW) = $9,984
Example 2 (cont.)
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
-40,000 -20,000 0 20,000 40,000 60,000 80,000
E(PW) = $9,984 V(PW) = 477,847x106 SD(PW) = $21,859Pr{PW >= 0} = 0.3+0.2+0.1+0.05+0.05 = 0.7
Evaluation of Projects with Continuous Random Variables
Expected values and the variances of probabilistic factors are computed mathematically.
Simplifying assumptions are made about the distribution of the random variable and the statistical relationship among the values it takes on, for example, Cash flow amounts are normal distribution. Cash flow amounts are statistically independent.
When the situation is more complicated, Monte Carlo simulation is normally used.
Example 3 For the following annual cash flow estimates, find
the E(PW), V(PW), and SD(PW) of the project. Assume that the annual net cash flow amounts are normally distributed with the expected values and standard deviations as given and statistically independent, and that the MARR = 15% per year.
End of Year, k
Expected Value of Net Cash
Flow, Fk
SD of Net Cash Flow, Fk
0 -$7,000 0
1 3,500 $600
2 3,000 500
3 2,800 400
Example 3 (cont.) Solution:
Assume independency among cash flow amounts. Expected PW are then linear combination of cash
flow amounts.
3
0
)%,15,/()(k
k kFPFEPWE
153
)3%,15,/(800,2)2%,15,/(000,3
)1%,15,/(500,3000,7
FPFP
FP
)()%,15,/(3
0
k
kFEkFP
Example 3 (cont.)
)()%,15,/()(3
0
2k
k
FVkFPPWV
324,484
)3%,15,/(400)2%,15,/(500
)1%,15,/(600102222
2222
FPFP
FP
3
0
)%,15,/()(k
kFkFPVPWV
696)()( 2/1 PWVPWSD
Example 4 Refer to example 3. For this problem, what is the
probability that the IRR of the cash flow estimates is less than the MARR, Pr{IRR<MARR}? Assume that the PW of the project is a normally distributed random variable, with its mean and variance equal to the values calculated in example 3.
The probability that the IRR is less than the MARR is the same as the probability that PW is less than zero
22.0696
1530
)(
)(
PWSD
PWEPWZ
4129.022.0Pr0Pr ZPW