Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect...

16
Reserve Margins Building Block vs Probabilistic Matthew Elkins Manager – Performance Analysis

Transcript of Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect...

Page 1: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Reserve MarginsBuilding Block vs Probabilistic

Matthew Elkins

Manager – Performance Analysis

Page 2: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Resource Adequacy

• Study of a single “Peak” hour

• How much is the appropriate margin?

Demand

0 150

Resource Availability

180

GW

Margin

~20%

Page 3: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Building Block - Inception

• Methodology created by WECC’s Reliability Assessment Work Group

• Do not reflect a criteria‐based margin‐determination process and do not reflect any BA‐ or Load‐Serving Entity (LSE)‐level requirements

• Not intended to supplant any requirements that may have been established through other processes (e.g., state regulatory authorities).

Page 4: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Building Block - Components

• Contingency Reserves – An amount of operating reserve sufficient to reduce Area Control Error to zero in 10 minutes following loss of generating capacity, which would result from the most severe single contingency. (Standard)

• Regulating Reserves – The amount of spinning reserves responsive to automatic generation control that is sufficient to provide the normal regulating margin. (Survey)

• Forced Outages – The capacity lost to forced outages for both the summer (July) and winter (December) is added by subregion and divided by the total capacity reported for each subregion. (GADS)

• Temperature Adders – The MW/°C coefficient is determined by WECC staff based on five years of daily peak demand regressed on daily maximum temperature for every weekday in the season. (WECC’s Analytical Team)

Page 5: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Resource Availability

180175

Building Block - Hypothetical Example

• Contingency Reserves

• Regulating Reserves

• Forced Outages

• Temperature Adders

Demand

0

GW

150

Margin

~20%

Reference

Margin

~16.7%

Page 6: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Building Block Application

Demand

Resource Availability

January December

With Building Block

Resource AvailabilityDemand

Page 7: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Resource Adequacy - Variability

• Study of a single “Peak” hour

• How much is the appropriate margin?

Demand

0 150

Resource Availability

180

GW

Page 8: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Supply Variability*Historical Data

Hydro

Wind

Page 9: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Supply Variability

100%Availability0%

JanuaryFebruaryMarchAprilMayJuneJulyAugustSeptemberOctoberNovemberDecemberJanuary

*Historical Data

*Theoretical

Solar

Page 10: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Probabilistic Application

Demand

Resource Availability

January December

With Building Block

Page 11: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Probabilistic Application –Convolution

Demand Resource Availability

0 150 180

GW

Page 12: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Probabilistic Application –Convolution

LOSS OF LOAD PROBABILITY (LOLP)

Page 13: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Transmission Benefits

Demand

Resource Availability

January December

Page 14: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

WECC Footprint

• 329 Members

• 38 Balancing Authorities

• 1.8 million square miles

• 82.2 million people

Page 15: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Comparison

Page 16: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant

Questions

Matthew Elkins

Manager – Performance Analysis

[email protected]

801-819-7657