Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect...
Transcript of Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect...
![Page 1: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/1.jpg)
Reserve MarginsBuilding Block vs Probabilistic
Matthew Elkins
Manager – Performance Analysis
![Page 2: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/2.jpg)
Resource Adequacy
• Study of a single “Peak” hour
• How much is the appropriate margin?
Demand
0 150
Resource Availability
180
GW
Margin
~20%
![Page 3: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/3.jpg)
Building Block - Inception
• Methodology created by WECC’s Reliability Assessment Work Group
• Do not reflect a criteria‐based margin‐determination process and do not reflect any BA‐ or Load‐Serving Entity (LSE)‐level requirements
• Not intended to supplant any requirements that may have been established through other processes (e.g., state regulatory authorities).
![Page 4: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/4.jpg)
Building Block - Components
• Contingency Reserves – An amount of operating reserve sufficient to reduce Area Control Error to zero in 10 minutes following loss of generating capacity, which would result from the most severe single contingency. (Standard)
• Regulating Reserves – The amount of spinning reserves responsive to automatic generation control that is sufficient to provide the normal regulating margin. (Survey)
• Forced Outages – The capacity lost to forced outages for both the summer (July) and winter (December) is added by subregion and divided by the total capacity reported for each subregion. (GADS)
• Temperature Adders – The MW/°C coefficient is determined by WECC staff based on five years of daily peak demand regressed on daily maximum temperature for every weekday in the season. (WECC’s Analytical Team)
![Page 5: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/5.jpg)
Resource Availability
180175
Building Block - Hypothetical Example
• Contingency Reserves
• Regulating Reserves
• Forced Outages
• Temperature Adders
Demand
0
GW
150
Margin
~20%
Reference
Margin
~16.7%
![Page 6: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/6.jpg)
Building Block Application
Demand
Resource Availability
January December
With Building Block
Resource AvailabilityDemand
![Page 7: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/7.jpg)
Resource Adequacy - Variability
• Study of a single “Peak” hour
• How much is the appropriate margin?
Demand
0 150
Resource Availability
180
GW
![Page 8: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/8.jpg)
Supply Variability*Historical Data
Hydro
Wind
![Page 9: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/9.jpg)
Supply Variability
100%Availability0%
JanuaryFebruaryMarchAprilMayJuneJulyAugustSeptemberOctoberNovemberDecemberJanuary
*Historical Data
*Theoretical
Solar
![Page 10: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/10.jpg)
Probabilistic Application
Demand
Resource Availability
January December
With Building Block
![Page 11: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/11.jpg)
Probabilistic Application –Convolution
Demand Resource Availability
0 150 180
GW
![Page 12: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/12.jpg)
Probabilistic Application –Convolution
LOSS OF LOAD PROBABILITY (LOLP)
![Page 13: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/13.jpg)
Transmission Benefits
Demand
Resource Availability
January December
![Page 14: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/14.jpg)
WECC Footprint
• 329 Members
• 38 Balancing Authorities
• 1.8 million square miles
• 82.2 million people
![Page 15: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/15.jpg)
Comparison
![Page 16: Probabilistic Application Western Interconnection Margins... · 2018-10-09 · and do not reflect any A‐ or Load‐Serving Entity (LSE)‐level requirements •Not intended to supplant](https://reader033.fdocuments.us/reader033/viewer/2022042306/5ed2350d7dd16f3eb12d322d/html5/thumbnails/16.jpg)
Questions
Matthew Elkins
Manager – Performance Analysis
801-819-7657