Privatization of Electricity Generation Sector in Turkey Republic of Turkey Privatization Administration October 2011

Transcript of Privatization of Electricity Generation Sector in...

Page 1: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Privatization of Electricity

Generation Sector in

Turkey

Republic of Turkey

Privatization Administration

October 2011

Page 2: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Agenda

▪ Overview of Turkish Electricity Generation Sector

▪ Privatization Portfolio

-Priority Power Generation Plants

-Plants with Capasity Expansion Potential

-Design of Portfolio Groups

-Portfolio Groups

▪ Important Issues

▪ Conclusion

Overview of Electricity Generation Company

Page 3: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

EÜAŞ produced 46% of the electricity consumed in 2010

Distribution of the installed capacity in 2010

Source: EÜAŞ

Distribution of electric energy produced in 2010

100% = 49,5 GW 100% = 211.208 GWh

57,4%

Generation

Companies+TOR

21%

Built Own Operate

21%

Auto Producers

6%

Built Operate

Transfer

6%

EÜAŞ

46%

Built Operate

Transfer

5%

EÜAŞ

49%

Mobile

1%Auto Producers

6%Built Own Operate

12%

Generation

Companies+TOR

27%

Page 4: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

EÜAŞ has generated 57% of its output from thermal power plants which

constitute 52% of its installed capacity

Breakdown of installed capacity by fuel type

SOURCE: EÜAŞ

Thermal power plants represent 52%

of EÜAŞ installed capacity

Percent, 2010

Breakdown of energy production by fuel type

27%

40%

Thermal power plants represent 57% of

EÜAŞ generation

100% = 24,2 GW 100% = 95.532 GWh

Hydraulic

43%

Lignite

33%

Liquid Fuels

0%Hard Coal

2%

Natural Gas

22%

Hydraulic

48%

Lignite

31%

Natural Gas

17%

Hard Coal

1%

Liquid Fuels

3%

Page 5: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Total installed capacity of the plants that will be privatized, is over 16 GW

Installed Capacity

MW

Source: EÜAŞ, Privatization Administration

EÜAŞ Total

23,976

Not considered

for privatization

68%

32% 7,627

Total of plants

that will be

privatized

16,359

River

142

Hydro

3,687

Thermal

12,524

Number of

Plants

Minimum

ins.capacity

MW

Maksimum

ins.capacity

MW

18

50

1,440

27

26.2

702.6

53

<0.1

51.2

98

<0.1

1,440

21

6

2,405

119

<0.1

2,405

Going to be privatized

Atatürk

Karakaya

Keban

Berke

Borçka

Sır

Batman

Muratlı

Dicle

Torul

Kralkızı

Kadıncık 1

Seyhan 1

Kadıncık 2

Ş.Urfa

Manavgat

Karacaören 2

Kepez 1

Seyhan 2

Kepez 2

Yüreğir

▪ Total of plants that are going to

be privatized, makes up the

68% of EÜAŞ installed

capacity and 39% of total

installed capacity in Turkey

▪ Plants that are not planned to

be privatized:

2,405.0

1,800.0

1,330.0

510.0

300.0

283.5

198.0

115.0

110.0

103.2

94.5

70.0

60.0

56.0

51.0

48.0

46.4

26.4

7.5

6.0

6.0

Name

Installed Cap.

MW

Large Plants Small Plants

Page 6: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Agenda

▪ Overview of Electricity Generation Company

ion Assets Privatization Process

▪ Privatization Portfolio

-Priority Power Plants

-Plants with Capasity Expansion Potential

-Design of Portfolio Groups

-Portfolio Groups

▪ Important Issues

▪ Conclusion

Privatization Portfolio

Page 7: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Source: EÜAŞ -2010

278

189170169160159138128124120908576756969625654483832322726

703

500

Hirfa

nlı

Me

nze

let

Kılıç

ka

ya

klü

ce

rtün

Ke

sik

prü

Do

ğa

nke

nt

Su

at U

ğu

rlu

De

mirk

öprü

Ad

ıgü

ze

l

De

rbe

nt

ka

pu

luka

ya

Ke

me

r

Yenic

e

Ka

raca

öre

n-1

Ça

mlıg

öze

Alm

To

rtum

Ça

tala

n

Sa

rıya

r

Ge

ze

nd

e

Asla

nta

ş

Ha

san

urlu

kçe

kaya

Ka

rka

mış

Özlü

ce

Altın

ka

ya

Installed Capacity

MW

100 MW +

122 117 139149 128 122 150

300

129 138

434

261

171189

480488 658

274

763

53

366

497 650461

5051.722

2010 Gross Generation

GWh

12 hydroelectric power plants out of 27 have installed capacity over 100 MW

Page 8: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Source: EÜAŞ

Kürtün 85 MW

Almus 27 MW

Köklüce 90 MW

Çamlıgöze 32 MW

Kılıçkaya 120 MW

Karacaören-1 32 MW

Gökçekaya 278.4 MW

Sarıyar 160 MW

Kesikköprü 76 MW

Kemer 48 MW

Kapulukaya 54 MW Hasan Uğurlu 500 MW

Suat Uğurlu 69 MW

Derbent 56.4 MW

Altınkaya 702.5 MW

Adıgüzel 62 MW

Demirköprü 69 MW

Doğankent 74.5 MW

Tortum 26.2 MW

Menzelet 124 MW Hirfanlı 128 MW

Aslantaş138 MW Gezende 159.3 MW

Çatalan 168.9 MW

Özlüce 170 MW

Karkamış 189 MW

Yenice 37.8 MW

0-100 MW

100-200 MW

200 MW +

Kızılırmak

Yeşilırmak

Fırat Seyhan

Ceyhan

Aksu B. Menderes

Gediz

Göksu-

Ermenek

Sakarya

Peri çayı

Harşit çayı

High-capacity hydro plants are concentrated in central and eastern

regions of Turkey

Page 9: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Hopa 50 MW

Aliağa

180 MW

Orhaneli 210 MW

Bursa D.Gaz 1432 MW

Çatalağzı

300 MW

Çan

320 MW

Tunçbilek 365 MW

Seyitömer 600 MW

Yeniköy 420 MW

Kemerköy 630 MW

Yatağan 630 MW

Kangal

457 MW

Ambarlı F.Oil 630 MW

Ambarlı D.Gaz 1351 MW

Soma A 44 MW

Hamitabat

1156 MW

A. Elbistan A 1355 MW

A. Elbistan B 1440 MW

0-500 MW

500-1000 MW

1000 MW +

Soma B 990 MW

Most of the 18 thermal plants are located in western regions of Turkey

Source: EÜAŞ

Page 10: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

The largest thermal power plants are using natural gas.

50

180

210

300

320

365

420

457

600

630

630

630

1.034

A. ELBİSTAN A 1.355

BURSA D.GAZ

SOMA A+B

HAMİTABAT

1.432

A. ELBİSTAN B 1.440

YATAĞAN

SEYİTÖMER

KEMERKÖY

HOPA

ALİAĞA

ORHANELİ

1.120

AMBARLI-D.GAZ 1.351

AMBARLI-F.OİL

ÇATALAĞZI

ÇAN

TUNÇBİLEK

YENİKÖY

KANGAL

Total:

Installed Capacity

MW

Source: EÜAŞ

Lignite

Natural Gas

Fueloil

Hard Coal

283

0

279

4.802

6.804

7.769

7.788

4.178

3.159

1.543

1.246

2.071

1.977

3.587

3.525

2.121

2.278

2009-2010 average generation

GWh

2010 data was used 58.391 GWh

8.191

518

Page 11: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Generation Assets Privatization Process

Explanation

▪ 50 run-of-river plants have been tendered in

19 portfolio groups

Current status

▪ 9 portfolios have transferred to the private

sector. Rest of the portfolios are expected

to be transferred in the coming months.

53 small hydrolic

plants

▪ 4 priority power plants (all thermal) are to

be privatized before the portfolio groups Priority assets

privatization

▪ 12 thermal and 27 hydrolic power plants

are to be privatized in 9 portfolios

▪ Strategy has been determined and final

arrangements are in progress

Portfolio groups

▪ Generation assets of 141 MW have been

privatized for $510 million

▪ Completed

ADÜAŞ

▪ The privatization tender of Hamitabat

Combined Cycle Natural Gas Plant with

1,156 MW installed capacity was launched

on March 21, 2011. Six potential investors

had pre-qualified and the deadline for the

bids was September 23, 2011, but the

tender is cancelled. For the others; strategy

has been determined and final

arrangements are in progress.

1

2

3

4

Page 12: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Priority Power Generation Plants

Source: EÜAŞ.

(1) Installed capacity has been incresed from 1,120 MW to 1,156 MW followed by the rehabilitations works between 2007 and 2010.

These four power plants represent 29% of gross

generation of EÜAŞ thermal plants as of 2010

Plant Fuel Type Location

Installed Capacity

(MW)

2010 Gross

Generation

(GWh)

Hamitabat Natural Gas Lüleburgaz, Kırklareli

Kangal Lignite Kangal, Sivas

Seyitömer Lignite Seyitömer, Kütahya

Soma A-B Lignite Soma, Manisa

Total 3.247 15.583

1.034

600

457

1.156(1)

Priority Power Plants which will be privatised in advance are not included in the Portfolio Groups.

10

3.897

3.623

2.313

5.750

Page 13: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

210

600

365

1.034

100

150

400

500

Plant Name Fuel Type Location

Installed Capacity

(MW)

Feasible Additional

Capacity (MW)

Soma Lignite Soma, Manisa

Tunçbilek Lignite Tunçbilek, Kütahya

Seyitömer Lignite Seyitömer, Kütahya

Orhaneli Lignite Orhaneli, Bursa

Total 2,209 1,150

Plants With Capacity Expansion Potential

Lignite reserves to support additional capacity in Soma, Tunçbilek, Seyitömer and Orhaneli coal mines

A total of 1.150 MW additional capacity is feasible for these 4

thermal plants

SOURCE: McKinsey Strategy Report

Page 14: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Design of Portfolio Groups

Portfolios have been designed to accomodate different interests and attract a diverse group of

prospective investors

▪ Geographical location has been considered in order to preserve operational synergies and economies of

scale

▪ Certain power plants have to be grouped together due to some characteristics (common personnel, same

subsidiary, common mining field, etc.)

▪ Hydrolic power plants on the same river have been placed in the same portfolio to allow integrated

management and operational efficiencies

▪ 9 portfolios, 356 MW to 2.795 MW in size have been formed:

– 3 portfolios of themal power plants only

– 2 mixed portfolios of themal and hydrolic plants

– 4 portfolios of hydrolic power plants only

Page 15: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Geographical distribution of 9 portfolio groups

Kürtün 85 MW

Almus 27 MW

Köklüce 90 MW

Çamlıgöze 32 MW

Kılıçkaya 120 MW

Karacaören-1

32 MW

Gökçekaya

278 MW

Sarıyar

160 MW Kesikköprü

76 MW

Kemer

48 MW

Kapulukaya

54 MW Hasan Uğurlu 500 MW

Suat Uğurlu 69 MW

Derbent 56 MW

Altınkaya 703 MW

Adıgüzel 62 MW

Demirköprü

69 MW

Doğankent 75 MW

Tortum 26 MW

Menzelet

124 MW

Hirfanlı 128 MW

Aslantaş 138 MW

Gezende 159 MW

Çatalan 169 MW

Özlüce 170 MW

Karkamış

189 MW

Yenice

38 MW

Kızılırmak

Yeşilırmak

Fırat

Seyhan

Ceyhan

Aksu

B. Menderes

Gediz

Göksu -

Ermenek

Sakarya

Peri Çayı

Harşit Çayı

5

8

7

9

4

6

Aliağa

180 MW

Orhaneli

210 MW

Bursa D.Gaz

1432 MW

Çatalağzı

300 MW

Yeniköy 420 MW

Kemerköy 630 MW

Yatağan 630 MW

Kangal 457 MW

Ambarlı F.Oil 630 MW

Ambarlı D.Gaz 1351 MW

A. Elbistan A 1355 MW

A. Elbistan B 1440 MW

Tunçbilek

365 MW

1

3

2

3

3

Hidroelektrik

Santraller

Termik Santraller Portföy Grupları x Portföy Numarası

SOURCE: EÜAŞ.

Harşit

75 MW

Page 16: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Plant Fuel Type Location/River

Installed Capacity

(MW)

2010 Gross Generation

(GWh)

A. Elbistan A Lignite Afşin, K.Maraş

A. Elbistan B Lignite Afşin, K.Maraş

Ambarlı D.Gaz Natural Gas

Ambarlı, İstanbul

Ambarlı F.Oil Fuel-Oil Ambarlı, İstanbul

Aliağa Natural Gas Aliağa, İzmir

Çan Lignite Kangal, Sivas

Tunçbilek Lignite Tunçbilek, Kütahya

Bursa D.gaz Natural Gas Ovaakça, Bursa

Orhaneli Lignite Orhaneli, Bursa

Gökçekaya Hydro Sakarya

Sarıyar Hydro Sakarya

Yenice Hydro Sakarya

Kemerköy Lignite Milas, Muğla

Yatağan Lignite Yatağan, Muğla

Yeniköy Lignite Milas, Muğla

Demirköprü Hydro Gediz

Adıgüzel Hydro Büyük Menderes

Kemer Hydro Büyük Menderes

Karacaören-1 Hydro Aksu

Gezende Hydro Göksu, Ermenek

1.440

1.355

159

32

48

62

69

420

630

630

38

160

278

210

1.432

EÜAŞ Privatisation: Portfolio Groups (1)

1

2

3

4

5

630

1.351

300

365

320

180

Source: EÜAŞ.

(1) Four priority plants to be privatised in advance and Hopa, which is non-operational since 2003, are not represented in the above portfolios. Additionally, Çatalağzı, which to be privatized separately, is taken out of

Portfolio 3.

Total:

2,795

Total:

1,981

Total:

865

Total:

2,118

Total:

2,050

13

Total:

8,003

Total:

4.052

Total:

9.270

Total:

7.218

Total:

9.736

7.694

2.042

62

7.941

1.659

2.141

251

128

366

505

1.174

7.098

53

149

122

129

138

1.308

2.599

2.720

Page 17: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Plant Fuel Type Location/River

Installed Capacity

(MW)

2010 Gross Generation

(GWh)

Altınkaya Hydro Kızılırmak

Derbent Hydro Kızılırmak

Hirfanlı Hydro Kızılırmak

Kesikköprü Hydro Kızılırmak

Kapulukaya Hydro Kızılırmak

Hasan Uğurlu Hydro Yeşilırmak

Suat Uğurlu Hydro Yeşilırmak

Almuş Hydro Yeşilırmak

Köklüce Hydro Yeşilırmak

Kılıçkaya Hydro Yeşilırmak - Kelkit

Çamlıgöze Hydro Yeşilırmak - Kelkit

Çatalan Hydro Seyhan

Aslantaş Hydro Ceyhan

Menzelet Hydro Ceyhan

Karkamış Hydro Fırat

Doğankent Hydro Harşit Çayı

Kürtün Hydro Harşit Çayı

Tortum Hydro Tortum Gölü

Özlüce Hydro Peri Suyu

EUAŞ Privatisation: Portfolio Groups (1) (Cont’d)

6

7

8

9

Source: EÜAŞ.

(1) Four priority plants to be privatised in advance and Hopa, which is non-operational since 2003, are not represented in the above portfolios.

54

76

128

56

703

Total:

1,017

Total:

838

Total:

620

Total:

356

189

124

138

169

170

26

85

75

32

120

90

27

69

500

14

Total:

3.380

Total:

2.378

Total:

1.248

Total:

2.267 150

171

274

300

1.372

139

488

480

117

434

1.722

461

658

763

497

650

133

189

275

Page 18: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Agenda

▪ Overview of Electricity Generation Company

▪ Privatization Portfolio

-Priority Power Plants

-Plants with Capasity Expansion Potential

-Design of Portfolio Groups

-Portfolio Groups

▪ Conclusion

Important Issues

Page 19: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Important Issues

The Privatisation Administration and Ministry of Energy and Natural Resources are currently

working to address the following key considerations.

Natural gas is supplied by BOTAŞ,

It is planned that the power plants will handover with coal areas.

Share sale of Portfolio Companies to be incorporated

Portfolio Companies will have Operating Rights for HPPs and

ownership of the Thermal assets

Fuel Supply

Natural Gas

Lignite / Coal

Preparatork work ongoing for signing water usage agreements with

DSİ. Water

Transaction Structure

15

Environmental Compliance Investors will have enough time for completion of the

environmental investments.

Page 20: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Agenda

▪ Overview of Turkish Electricity Generation Company

▪ Privatization Portfolio

-Priority Power Plants

-Plants with Capasity Expansion Potential

-Design of Portfolio Groups

-Portfolio Groups

▪ Important Issues

▪ Conclusion

Page 21: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

542

469

334

309

281

169

147

134

111

86

Germany

France

United Kingdom

Italy

Spain

Turkey

Poland

Sweden

Netherlands

Finland

Attractive Market Fundamentals

Significant Market Size (2010)

Annual Consumption (TWh) (1)

High Growth Potential …

Consumption Growth Rate (2)

… From a Low Starting Point (2010)

Per Capita Power Consumption (3)

Expected to overtake UK

and become a top 3 market by

2020-2025

Given the size and current growth rate and potential, Turkish electricity market is one of the most attractive electricity markets in

Europe, expected to become a top 3 market by size in the next 10-15 years.

6.0

6.3

6.6

6.7

7.4

7.9

8.0

14.3

15.7

2.2Turkey

Denmark

Czech

Republic

Germany

Netherlands

France

Austria

Belgium

Sw eden

Finland

Average: 8.8

1

Source: EIU. (1) Net consumption for Turkey in 2010 is calculated by using 2009 net consumption figure and 2009-2010 gross consumption growth rate. For other countries EIU forecasts are used.

(2) Growtth rates are based on 2006 – 2010 period. (3) Net consumption for Turkey in 2010 is calculated by using 2009 net consumption figure and 2009-2010 gross consumption growth rate Per capita consumption

is calculated by dividing this number by population. For other countries EIU forecasts are used.

%4.6

%2.6

%1.8

%1.7

%1.6

%1.6

%1.2

%1.1

%0.6

%0.3

Turkey

Spain

Poland

Greece

Austria

Bulgaria

Czech Republic

Romania

Slovakia

Hungary

Average: %1,7

Page 22: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Conclusion

The Turkish Power Market represents a strong and sizeable growth opportunity for strategic and financial players. ▪ Turkey has one of the largest and fastest growing power markets in the CEEMEA * region ▪ Electricity demand growth is expected to outpace real GDP growth as a result of population growth,

urbanisation, industrialisation and economic growth ▪ Turkey, as the sixth largest electricity generating country in Europe, has a per capita power

consumption level well below Western European markets ▪ As well as enhancing competition and efficiency, the ongoing liberalisation process is also expected

to bring the Turkish power market in line with EU market structures ▪ Opportunities to create vertically-integrated operations in the sector are expected to increase ▪ Share of private players in the market is increasing ▪ EÜAŞ privatisation process is of critical importance due to the contribution it will make to

mobilise the growth potential of the sector .

▪ EÜAŞ generation assets’ privatisation process reflects a structure which will address the ongoing issues in the energy sector and serve the objectives of the privatisation. As such, EÜAŞ privatisation is an important opportunity for the investors

▪ With this perspective, we: – Have selected the priority assets of EÜAŞ and formed the portfolio groups, and – Have the determined the right strategy to tackle key issues

▪ We believe that the privatization process of EÜAŞ assets will be beneficial in ensuring supply security, enhancing efficiency and competition in the Turkish electricity market structure and activities

* CEEMEA: Central and Eastern Europe, Middle East, Africa

Page 23: Privatization of Electricity Generation Sector in Turkeyturkey-japan.com/business/category5/category5_412b.pdf · Privatization of Electricity Generation Sector in ... Certain power

Thank You